6. R-Squared Project Status Work stream Status Remarks Equipment Build Green High Level design complete, detailed design review session held Construction of Test Scripts Amber Cabling, power and installation guide in progress. Completing task planned next week (in workstream status) will make status green. Construction of String / Unit Test Scripts Green High Level design complete, detailed design review session held Construction of UTA Test Scripts Green All equipment ordered. 2 nd wave of blades to be ordered next week to leverage Core Trust Agreements discounted rates Legal Compliance Review and Acceptance Green Completed 1 st draft LMN/ Sabre Transfer: Processor v Controller document Configuration of Test Instance Green Build documents being drafted by tech teams Configuration of Production Instance Green Site architecture being drafted; Functional Testing Green 1 st draft of test plan reviewed. 5 FTE’s secured for 1 st March start UTA Testing Green Data migration workshop held with 3PAR and internal tech teams Project Turn -Over Green Approach agreed and 2 vendors contacted to assess suitability
7. Program Timelines JUL Contract New Space APR FEB MAR MAY JUN AUG SEP TODAY JAN App and env config Dry Run Testing Procurement Build out of New Site Design Legal OCT Equipment Build Exit UK Facility Cutover Contract expires