SlideShare a Scribd company logo
1 of 18
Project R-Squares:  Weekly Update March 1 , 2010
Project Objectives ,[object Object],[object Object]
Major Accomplishments ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Top Issues being worked on ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],Legend White Not Started Red Delay or overspend will occur beyond project tolerances Amber Risk of delay or overspend but mitigation is possible to keep the project within tolerances  Green On track for delivery within time, quality and budget Blue Complete
R-Squared Project Status Work stream Status Remarks Equipment Build Green High Level design complete, detailed design review session held Construction of Test Scripts Amber Cabling, power and installation guide in progress. Completing task planned next week (in workstream status) will make status green.  Construction of String / Unit Test Scripts Green High Level design complete, detailed design review session held Construction of UTA Test Scripts Green All equipment ordered. 2 nd  wave of blades to be ordered next week to leverage Core Trust Agreements discounted rates Legal Compliance Review and Acceptance Green Completed 1 st  draft LMN/ Sabre Transfer: Processor v Controller document Configuration of Test Instance Green Build documents being drafted by tech teams Configuration of Production Instance Green Site architecture being drafted; Functional Testing Green 1 st  draft of test plan reviewed. 5 FTE’s secured for 1 st  March start UTA Testing Green Data migration workshop held with 3PAR and internal tech teams Project Turn -Over Green Approach agreed and 2 vendors contacted to assess suitability
Program Timelines JUL Contract New Space APR FEB MAR MAY JUN AUG SEP TODAY JAN App and env config Dry Run Testing Procurement Build out of New Site Design Legal OCT Equipment Build Exit UK Facility Cutover Contract  expires
Hardware – Dan Gabrieison  ,[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],Objective :  Complete Data Centre build  capable of supporting the lastminute.com environment Progress to Date Milestone From To % complete Sign contract complete 100% Take possession complete 100% Receive  equipment complete 100% Setup cabling complete 100% Configure patching complete 100% Allocate rack numbering complete 100% Cutover in agreed outage window complete 100%
Server – Dan Gabrielson Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Build and deploy the server environment necessary to run  R-Squared applications : Test &  Production Progress to Date Milestone From To % complete Define  inventory of servers requiring migration 1/Jan 31/Jan 100% Define Servers specifications and order 1/Feb 28/Feb 80% Install servers in R- Squared 1/Mar 31/Mar 0% Setup Infrastructure services 15/Mar 31/Mar 0% Build OS w/ unit testing 15/Mar 15/Apr 0% Migrate cloned servers 1/Apr 30/Apr 0% Start deploying applications 1/Apr 30/Apr 0%
Network – Wole Taiwo ,[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Build and deploy the network environment to support applications and services Progress to Date Milestone From To % complete Design new solution 1/Jan 28/Feb 100% Receive equipment 1/Mar 15/Mar 0% Setup WAN/LAN 15/Feb 15/Mar 30% Test Network 15/Mar 15/May 0% Model connectivity changes 15/Mar 15/July 0% Pre-cutover testing 15/July 15/Aug 0% Cutover in agreed outage window 15/Aug 15/Aug 0%
Storage/Backups – Andy Mora/Tony Ives Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Establish enterprise  storage /backup environment capable of supporting multiple platforms Progress to Date Milestone From To % complete Define  existing storage configuration 1/Jan 31/Jan 100% Design Solution 1/Feb 28/Feb 80% Order equipment 1/Feb 14/Feb 80% Receive, install and configure equipment 1/Mar 15/Mar 0% Replicate all data 15/Mar 31/Mar 0% Start testing applications 1/Apr 1/Apr 0% Cutover in agreed outage window 15/Aug 15/Aug 0%
Databases – Steve Lewis ,[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Migrate Databases without data loss Progress to Date Milestone From To % complete Document database architecture 1/Jan 31/Jan 0% Determine migration method for each db 1/Feb 28/Feb 25% Determine synch method 28/Feb 14/Mar 10% Migrate data 15/Mar 31/Mar 0% Fix bugs 1/Apr 15/Jul 0% Perform dry-runs 16/Jul 15/Aug 0% Cutover in agreed outage window 15/Aug Aug 0%
Applications – Martin Bianco ,[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Migrate applications to the new infrastructure Progress to Date Milestone From To % complete Document application architecture 1/Jan 12/Mar 30% Determine deployment method for each app 1/Feb 31/Mar 25% Build Kick-start script 14/Feb 14/Mar 25% Deploy Applications 1/Mar 31/Mar 0% Fix bugs 1/Apr 15/Jul 0% Perform dry-runs 16/Jul 15/Aug 0% Cutover in agreed outage window 15/Aug Aug 0%
Testing – Rachel Pilgrim ,[object Object],[object Object],[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Build and execute a Quality Assurance methodology to ensure functionality works upon  migration Progress to Date Milestone From To % complete Gap analysis of test scripts 1/Jan 31/Jan 90% Define test approach for non-standard items 1/Feb 28/Feb 80% Define cut-over test plan 1/Mar 31/Mar 10% Write test scripts 1/Feb 31/Mar 20% Execute test scripts 1/Apr 15/Jul 0% Execute Dry-runs 16/Jul 15/Aug 0% Cutover in agreed outage window 15/Aug 15/Aug 0%
End User Computing – David Kent ,[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],Objective :  Migrate End User Computing (including call centre support & applications) to Cyrus One and HP Progress to Date Milestone From To % complete Define  inventory of servers requiring migration 1/Jan 31/Jan 100% Define Servers specifications and order 1/Feb 28/Feb 80% Setup End User Computing environment 1/Mar 31/Mar 0% Setup Call Centre Support services 1/Mar 31/Mar 0% Test and bug fix 1/Apr 15/Jul 0% Perform dry-runs 16/Jul 15/Aug 0% Cutover in agreed outage window 15/Aug Aug 0%
Cutover – Peter Raftery  ,[object Object],[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],Objective :  Flip the site from London to CyrusOne in agreed outage window Progress to Date Milestone From To % complete Define cutover approach 1/Feb 31/Mar 50% Define roll-back approach 1/Mar 30/Apr 10% Test Storage replication 15/Mar 30/Apr 0% Test Data migration 15/Mar 30/Apr 0% Test NAS migration 15/Mar 30/Apr 0% Perform dry-runs 16/Jul 15/Aug 0% Cutover in agreed outage window 15/Aug 15/Aug 0%
Legal – Emma Warwick ,[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],Objective :  Ensure legal compliance with data centre move to US Progress to Date Milestone From To % complete Agree contract with CyrusOne 1/Jan 15/Feb 100% Assess impact of licensing with move 1/Jan 31/Mar 75% Assess impact of Data Protection & PII 1/Jan 31/Mar 50% Assess impact of PCI 1/Jan 31/Mar 50% Sign Data Controller agreement 31/Mar 31/May 20% Ensure no legal/compliance breach with cutover 30/Jun 15/Aug 0%
Exit UK Facilities – Ken Lee ,[object Object],[object Object],[object Object],Key Accomplishments this week Issues / Risks Key Activities Next Week Historical Log: Changes / Decisions  ,[object Object],[object Object],[object Object],[object Object],[object Object],Objective :  Decommission and exit COLT facilities in PWG and PCT by 30th September Progress to Date Milestone From To % complete Contract disposal 3 rd  party 1 st  Mar 15 th  Aug 5% Remove all equipment in line with COLT contractual obligations 1 st  Sep 21 st  Sep 0% Format data on disks to ensure  data protection 1 st  Sep 21 st  Sep 0% Transfer equipment to Sabre 1 st  Sep 30 th  Sep 0% Sale of equipment 1 st  Sep 30 th  Sep 0%

More Related Content

What's hot

Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Stationchetlapally balakrishna
 
HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15Euan Pirie
 
Engineering process flow
Engineering process flowEngineering process flow
Engineering process flowPurnendu Jha
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Processd_mackay
 
PMP and Planning Process Equivalents
PMP and Planning Process EquivalentsPMP and Planning Process Equivalents
PMP and Planning Process EquivalentsKevin Pannell
 
2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...
2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...
2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...GIS in the Rockies
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status reportTom Evans
 
Logic tree eo t methods
Logic tree eo t methodsLogic tree eo t methods
Logic tree eo t methodsfaizrasul
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Final presentation
Final presentationFinal presentation
Final presentationRauf Virk
 

What's hot (16)

Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15
 
Engineering process flow
Engineering process flowEngineering process flow
Engineering process flow
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
PMP and Planning Process Equivalents
PMP and Planning Process EquivalentsPMP and Planning Process Equivalents
PMP and Planning Process Equivalents
 
Integration Golden Rules
Integration Golden RulesIntegration Golden Rules
Integration Golden Rules
 
CV-ANIL
CV-ANILCV-ANIL
CV-ANIL
 
Qa plan1
Qa plan1Qa plan1
Qa plan1
 
2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...
2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...
2012 URISA Track, How to Conduct Geographic Information Systems (GIS) Work wi...
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status report
 
Logic tree eo t methods
Logic tree eo t methodsLogic tree eo t methods
Logic tree eo t methods
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Energy Efficiency Quality Assurance
Energy Efficiency Quality AssuranceEnergy Efficiency Quality Assurance
Energy Efficiency Quality Assurance
 
Final presentation
Final presentationFinal presentation
Final presentation
 
The Six March 19th
The Six March 19thThe Six March 19th
The Six March 19th
 

Viewers also liked

MSN Consumer Packages July Sept 2010
MSN Consumer Packages July   Sept 2010MSN Consumer Packages July   Sept 2010
MSN Consumer Packages July Sept 2010Will Lynch
 
MSN Ireland Homepage Takeover Summer Packages 2010
MSN Ireland Homepage Takeover Summer Packages 2010MSN Ireland Homepage Takeover Summer Packages 2010
MSN Ireland Homepage Takeover Summer Packages 2010Will Lynch
 
MSN Consumer Packages 2010
MSN Consumer Packages 2010MSN Consumer Packages 2010
MSN Consumer Packages 2010Will Lynch
 
How to post photos using firefox
How to post photos using firefoxHow to post photos using firefox
How to post photos using firefoxCoffeeClub Network
 

Viewers also liked (7)

MSN Consumer Packages July Sept 2010
MSN Consumer Packages July   Sept 2010MSN Consumer Packages July   Sept 2010
MSN Consumer Packages July Sept 2010
 
RECREACIÓN
RECREACIÓNRECREACIÓN
RECREACIÓN
 
How to create a community
How to create a communityHow to create a community
How to create a community
 
MSN Ireland Homepage Takeover Summer Packages 2010
MSN Ireland Homepage Takeover Summer Packages 2010MSN Ireland Homepage Takeover Summer Packages 2010
MSN Ireland Homepage Takeover Summer Packages 2010
 
MSN Consumer Packages 2010
MSN Consumer Packages 2010MSN Consumer Packages 2010
MSN Consumer Packages 2010
 
How to post photos using firefox
How to post photos using firefoxHow to post photos using firefox
How to post photos using firefox
 
Generator
GeneratorGenerator
Generator
 

Similar to R squared weekly-status_03012010[1]

Stakeholder update 4 14 data center outage
Stakeholder update 4 14 data center outageStakeholder update 4 14 data center outage
Stakeholder update 4 14 data center outagekevin_donovan
 
General Performance Testing Overview
General Performance Testing OverviewGeneral Performance Testing Overview
General Performance Testing Overviewjsb1976
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...p6academy
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...p6academy
 
Arokia Raj RM Resume
Arokia Raj RM  ResumeArokia Raj RM  Resume
Arokia Raj RM Resumearokiagetz
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0Mark S. Mahre
 
Data center outage project update
Data center outage project updateData center outage project update
Data center outage project updatekevin_donovan
 
Afcom Relocation Pres V4
Afcom   Relocation Pres V4Afcom   Relocation Pres V4
Afcom Relocation Pres V4kestephensjr
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt projectSamehTeleb
 
DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...
DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...
DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...Deltares
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeTheodore Van Patten, Jr.
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptxsharpan
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Duke, Brian_MDSupportServicesProfessional
Duke, Brian_MDSupportServicesProfessionalDuke, Brian_MDSupportServicesProfessional
Duke, Brian_MDSupportServicesProfessionalBrian Duke
 
James Jackson Reume T1
James Jackson Reume T1James Jackson Reume T1
James Jackson Reume T1James Jackson
 
My resume 2016 07 14 v 12
My resume 2016 07 14 v 12My resume 2016 07 14 v 12
My resume 2016 07 14 v 12Jeff Abrahamson
 

Similar to R squared weekly-status_03012010[1] (20)

Stakeholder update 4 14 data center outage
Stakeholder update 4 14 data center outageStakeholder update 4 14 data center outage
Stakeholder update 4 14 data center outage
 
General Performance Testing Overview
General Performance Testing OverviewGeneral Performance Testing Overview
General Performance Testing Overview
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
 
Douglas Carlesco Resume
Douglas Carlesco ResumeDouglas Carlesco Resume
Douglas Carlesco Resume
 
Arokia Raj RM Resume
Arokia Raj RM  ResumeArokia Raj RM  Resume
Arokia Raj RM Resume
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0
 
Data center outage project update
Data center outage project updateData center outage project update
Data center outage project update
 
Afcom Relocation Pres V4
Afcom   Relocation Pres V4Afcom   Relocation Pres V4
Afcom Relocation Pres V4
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...
DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...
DSD-INT 2014 - Delft-FEWS Users Meeting - Challenges related to extending, te...
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptx
 
EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3
 
Nataraj Krishnaswamy Profile
Nataraj Krishnaswamy ProfileNataraj Krishnaswamy Profile
Nataraj Krishnaswamy Profile
 
Docweb Milestone 2 Report
Docweb Milestone 2 ReportDocweb Milestone 2 Report
Docweb Milestone 2 Report
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Duke, Brian_MDSupportServicesProfessional
Duke, Brian_MDSupportServicesProfessionalDuke, Brian_MDSupportServicesProfessional
Duke, Brian_MDSupportServicesProfessional
 
James Jackson Reume T1
James Jackson Reume T1James Jackson Reume T1
James Jackson Reume T1
 
My resume 2016 07 14 v 12
My resume 2016 07 14 v 12My resume 2016 07 14 v 12
My resume 2016 07 14 v 12
 

Recently uploaded

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 

Recently uploaded (20)

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 

R squared weekly-status_03012010[1]

  • 1. Project R-Squares: Weekly Update March 1 , 2010
  • 2.
  • 3.
  • 4.
  • 5.
  • 6. R-Squared Project Status Work stream Status Remarks Equipment Build Green High Level design complete, detailed design review session held Construction of Test Scripts Amber Cabling, power and installation guide in progress. Completing task planned next week (in workstream status) will make status green. Construction of String / Unit Test Scripts Green High Level design complete, detailed design review session held Construction of UTA Test Scripts Green All equipment ordered. 2 nd wave of blades to be ordered next week to leverage Core Trust Agreements discounted rates Legal Compliance Review and Acceptance Green Completed 1 st draft LMN/ Sabre Transfer: Processor v Controller document Configuration of Test Instance Green Build documents being drafted by tech teams Configuration of Production Instance Green Site architecture being drafted; Functional Testing Green 1 st draft of test plan reviewed. 5 FTE’s secured for 1 st March start UTA Testing Green Data migration workshop held with 3PAR and internal tech teams Project Turn -Over Green Approach agreed and 2 vendors contacted to assess suitability
  • 7. Program Timelines JUL Contract New Space APR FEB MAR MAY JUN AUG SEP TODAY JAN App and env config Dry Run Testing Procurement Build out of New Site Design Legal OCT Equipment Build Exit UK Facility Cutover Contract expires
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.

Editor's Notes

  1. 04/13/08