SlideShare una empresa de Scribd logo
1 de 54
Descargar para leer sin conexión
2015Craig R Horne – All Rights Reserved 2015 0
Long-Duration Energy Storage and PV:
Renewable Energy’s BFFs
Craig R. Horne, Ph.D.
Santa Clara Valley IEEE PV Society
May 13, 2015
content within this presentation is provided
courtesy of EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
Outline
!  Markets & Drivers
!  Illustrative Projects
!  Configuring Storage Systems
!  Storage Architectures
!  Impact on PV Projects
1
Craig R Horne – All Rights Reserved 2015
What this talk is (mostly) about –
MW-scale, Long-Duration Energy Storage for Electricity Supply
(Wholesale Markets)
What this talk is (mostly) not about –
kW-scale Energy Storge for Residential or Commercial Applications
MW-scale, Short-Duration Energy Storage for Wholesale Markets
Craig R Horne – All Rights Reserved 2015
Energy Storage Markets Are Global
Entity Size (Power) Duration (Energy) Description
CA 1,360 MW 2-4 hrs
!  California procurement decision AB
2514 (October 2013)
SCE 260 MW ≥ 4 hrs
!  RFP issued (October 2013)
!  > 5x awarded (November 2014)
LIPA
150 MW –
650 MW
12 hrs !  RFP issued (November 2013)
Hokkaido
12 MW 5 hrs !  Contract awarded (July 2013)
Terna 130 MW 6 hrs !  Contract awarded (May 2013)
SDG&E
25 MW –
800 MW
≥ 4 hrs !  RFP issued (September 2014)
ConEd
59 MW
2 MW
12 hrs
!  RFI for 12 hour load deferral (July 2014)
!  RFQ issued (September 2014)
IESO 16.5 MW ≥ 4 hrs !  RFP initiated (October 2014)
3
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
Energy Storage Markets Are Global
http://www.energystorageexchange.org/projects
4
Craig R Horne – All Rights Reserved 2015
A)  The Head
[MW]
B) The Neck
[MW/hr]
C) The Belly
[- MW or MWidle]
Three Challenges
5
Craig R Horne – All Rights Reserved 2015
Energy Storage vs. Conventional Peaker
More than 2X the Flexible Ramp Resource
ChargingDischarging
Idle Power
CT Flexible
Resource
Value
BESS
Flexible
Resource
Value
Interconnect
Rating
Interconnect
Rating
Throttle
Courtesy EnerVault Corporation
Adapated from P. Kathpal,“Energy Storage in Resource Planning
and Procurement”, ESA Annual Meeting, June 2014
6
Craig R Horne – All Rights Reserved 2015
Energy Storage vs. Conventional Peaker
But in CA more than 4X the Flexible Ramp Resource
ChargingDischarging
Idle Power
@ 50%
(NOx standards)
CT Flexible
Resource
Value
BESS
Flexible
Resource
Value
7
Interconnect
Rating
Interconnect
Rating
Throttle
Courtesy EnerVault Corporation
Adapated from P. Kathpal,“Energy Storage in Resource Planning
and Procurement”, ESA Annual Meeting, June 2014
Craig R Horne – All Rights Reserved 2015
AB 2514 – 1.325 GW Mandate for Storage
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M078/K912/78912194.PDF
8
Craig R Horne – All Rights Reserved 2015
Many Ways To Store Energy
Electrochemical
Flow
Batteries
Redox Flow Battery
Non-Redox Flow Battery
Supercapacitors
Other
Sodium-Sulfur
Lead-Acid
Lithium-based
Sodium-NiCI2
Aqueous-other
Metal/air
Molten metal
Metal-based Flow Battery
Non-Metal Flow Battery
Regenerative Fuel Cell
Chemical
ThermalChilled Water
Ice
Heat
Molten Salt
Pumped
Hydro
Power
Energy
Non-Traditional
Traditional
Cavern
Containerized
Non-Cavern
Compressed
Air
Electromagnetic
Integrated Cell
Battery
Energy Storage
Mechanical
Flywheel
SMES
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
Fairbanks, AK
27 Megawatt UPS
(Nickel Cadmium)
Craig R Horne – All Rights Reserved 2015
Dublin, CA
2 Megawatt Micro-Grid
(BYD, Li-Ion)
11
Craig R Horne – All Rights Reserved 2015
Stephenstown NY
20 Megawatt Fast Frequency Response
(Flywheel Energy Storage)
Miller,Western Oregon U.
Craig R Horne – All Rights Reserved 2015
Laurel Mountain,WV
32 Megawatt wind integration
(AES Energy Storage, Li-ion)
Craig R Horne – All Rights Reserved 2015
Notrees, TX
36 Megawatt wind management
(Younicos, lead-acid)
Craig R Horne – All Rights Reserved 2015
Rokkasho JapanWind Farm
15
Okimoto, NGK – ESA 2009
Craig R Horne – All Rights Reserved 2015
Turlock, CA
250 Kilowatt, 4 hr Load Management
(EnerVault, Fe/Cr-RFB)
16
Craig R Horne – All Rights Reserved 2015
Gila Bend, AZ
280 Megawatt, 6 hours
(Abengoa, molten salt)
Craig R Horne – All Rights Reserved 2015
Northwestern PA
435 Megawatt Peak Load Management
(Pumped Hydro Energy Storage)
wikipedia
Craig R Horne – All Rights Reserved 2015
McIntosh, AL
110 Megawatt Peak Load Management
(Cavern Compressed Air Energy Storage)
PG&E
Craig R Horne – All Rights Reserved 2015
Moraine, OH
20 Megawatt Peaker
(AES, Li-Ion)
20
Craig R Horne – All Rights Reserved 2015
City of Industry, CA
479 MW Peaker - 5 x 100 MW
(Edison Mission Group, NGGT)
21
Craig R Horne – All Rights Reserved 2015
City of Industry, CA
5 x 100 MW GT (GE) " 479 MW(AC) for
capacity payments & bids into CAISO (EMG)
22
power capability power capacity
Craig R Horne – All Rights Reserved 2015
!  Duration at rated power: Day 1 AND Day N
•  N = 3,650 for 10 year project,
or 7,300 for 20 year project
time
NetPower,MW(AC)
4
-4
charge
discharge
40 8 12 16 20
What is Required of A Grid Storage Asset
26
!  Total project cost requires storage
capacity allotments for...
•  Capacity utilization
(“Depth of Discharge” or
“State-of-Charge Range” (SoCR) )
•  Losses (inefficiency)
•  Capacity fade
26
Craig R Horne – All Rights Reserved 2015
!  Duration at rated power: Day 1 AND Day N
•  N = 3,650 for 10 year project,
or 7,300 for 20 year project
What is Required of A Grid Storage Asset
29
!  Total project cost requires storage
capacity allotments for...
•  Capacity utilization
(“Depth of Discharge” or
“State-of-Charge Range” (SoCR) )
•  Losses (inefficiency)
•  Capacity fade
Power DurationX
= Energy
time
NetPower,MW(AC)
4
-4
charge
discharge
40 8 12 16 20
29
Craig R Horne – All Rights Reserved 2015
System Configuration
!  SCE Tehachapi Project (Li-ion)
• 8 MW(AC)/32 MW-hr
30
Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project 2014 ESA Annual Meeting, June 4-6 2014
Craig R Horne – All Rights Reserved 2015
Two Components to LiB Aging (per Saft)
31
Craig R Horne – All Rights Reserved 2015
0 6 12 18 24
Power
Time of Day
Saft Data on LiB Aging: Impact on Configuration
" SOH factors = calendar X cycling
4 hr
11 hr 3 hr
6 hr
0%
25%
50%
75%
100%
0 6 12 18 24
Stateof
Charge
Time of Day
idle time/day @
top of charge
SystemChargeLevel
(notcell)
project design
1 MWAC for 4 hours, 20-30oC &
75% SOC at top of charge,
15% SOC at bottom of cycle
(discharged state)
" 60% utilization &
44 to 31 year calendar life
15 year project
1 cycle/day
11 hrs/day idle @ full charge
means:
11 hrs/day * 365 days/year *
15 year project life = 60,225
hrs
60,225 hrs/8,760 hrs per year
"
7 equivalent years at idle
Analysis
adapted from:
~ 10-20% impact
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
Properly Configuring a Grid Storage Asset
33
$125/kWh
?SoCR
capacity fade
losses
system integration
installation
grid connection
Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project
2014 ESA Annual Meeting, June 4-6 2014
Craig R Horne – All Rights Reserved 2015
Properly Configuring a Grid Asset
34
$125/kWh
?SoCR
capacity fade
losses
system integration
installation
grid connection
Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project
2014 ESA Annual Meeting, June 4-6 2014
can deliver MW(AC) capacitycapability to store MWh(DC)
Craig R Horne – All Rights Reserved 2015 35
Properly Configuring a Grid Storage Asset
Energy Storage Capability
!  kWh: ability to deliver MW(DC) until
storage media is fully utilized
!  ability to store MWh(DC)
!  based on the quantity of storage
media or factory acceptance test of
the article
!  provided by storage vendor
Energy Storage Capacity
!  kW-hr: ability to deliver MW(AC) for
required # hours throughout project
lifetime
!  ability to deliver MW(AC)
!  based on fully installed system
!  provided by storage project
developer
$$ this is what is monetized $$
It is important to distinguish the capability from the capacity!
Craig R Horne – All Rights Reserved 2015
Properly Configuring a Grid Storage Asset
36
$125/kWh
$400-600/kW-hrSoCR
capacity fade
losses
system integration
installation
grid connection
storage capability
storage capacity
Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project
2014 ESA Annual Meeting, June 4-6 2014
Craig R Horne – All Rights Reserved 2015
!  Duration at rated power: Day 1 AND Day N
•  N = 3,650 for 10 year project,
or 7,300 for 20 year project
What is Required of A Grid Storage Asset
37
!  Total project cost requires storage
capacity allotments for...
•  Capacity utilization
(“Depth of Discharge” or
“State-of-Charge Range” (SoCR) )
•  Losses (inefficiency)
•  Capacity fade
Power DurationX
= Energy
4 MWAC for 4 hrs = 16 MW-hr storage capacity;
$/kW-hr = TTL Installed $/16,000 kW-hr
time
NetPower,MW(AC)
4
-4
charge
discharge
40 8 12 16 20
37
the actual installed unit will have > 16 MWh of storage capability, how
much more depends on storage product & project conditions
Craig R Horne – All Rights Reserved 2015
Key for Individual Project: Stacking Benefits
B. Kaun (2013)
Craig R Horne – All Rights Reserved 2015
But Reality Can Be A Bummer
B. Kaun (2013)
Craig R Horne – All Rights Reserved 2015
Configurations
System DesignVolume
TotalEnergyOutput
Rate-AdjustedEnergyOutput
Configuration
BESSASP
RESize
REPrice
Project Modeling Overview
1) Operational
Model
2) Pricing
Model
4) Pro Forma Model
FixedO&M
Variable
O&M
MajorRefurb
3) O&M Model
Project IRR, NPV, B/E, $
Craig R Horne – All Rights Reserved 2015
Project Model Inputs
!  Performance Model
•  BESS: MW, MW-hr, ramp up, ramp down, start time, self-discharge, degradation,
operational efficiency
•  project setting: charging power,TOU rates/premiums, boundary conditions (e.g. IX limit)
•  dispatch method: charge priorities, benefit maximization, etc.
!  Pricing Model
•  subsystem cost as function of time
•  system cost basis for configuration variations
!  O&M Model
•  component lifetimes/replacement intervals, service requirements, subsystem costs at
replacement time
!  Pro Forma Model
•  discount rate, depreciation, PPA/tariff structure, subsidies/offsets, other values (e.g. $/
tonne-C avoided)
Craig R Horne – All Rights Reserved 2015
A Look Inside Efficiency
Echarge
Pcharge,
direct
Edisch.
Pout
Eout
Pparsitic load, charge
PPCS loss, charge
PECC loss, charge
Echarged
Pstdby load
Pdisch
Pcharge
Estdby
Pparsitic load, discharge
PPCS loss, discharge
PECC loss, discharge
/tcharge
*tcharge
/tdisch
*tdisch
*tstdby
Pcont load
Econt load
/tcycle!
Ein
Overall
Efficiency
η=Ein/Eout
II
IV
I
III
I)  Continous Load: Occur the whole
time
•  controller, HMI, lights, etc.
II)  Charging Losses: during tcharge
•  Energy Conversion:
charging efficiency
•  Power Conditioning System:
charging efficiency
•  Parasitic Load (BOP,Therm.
Mgmt, etc)
III)  Standby Load: during tstdby
•  Standby Load 1
•  Standby Load 2
IV)  Discharging Losses: during tdisch
•  Energy Conversion:
discharging efficiency
•  Power Condintioning
System: discharging
efficiency
•  Parasitic Load (BOP,Therm.
Mgmt, etc)
Requires Use Case-Based Operational Analysis of System Over FullYear/Life of Project
Craig R Horne – All Rights Reserved 2015 43
Storage Architectures
Coupled Power & Energy Decoupled Power & Energy
๏  energy stored & conversion/power
delivery intimately coupled
“cans of soda”
๏  energy stored decoupled from
conversion/power delivery
“soda fountain drink”
Electrochemical
Flow
Batteries
Redox Flow Battery
Non-Redox Flow Battery
Supercapacitors
Other
Sodium-Sulfur
Lead-Acid
Lithium-based
Sodium-NiCI2
Aqueous-other
Metal/air
Molten metal
Metal-based Flow Battery
Non-Metal Flow Battery
Regenerative Fuel Cell
Chemical
ThermalHeat
Molten Salt
Chilled Water
Ice
Pumped
Hydro
Power
Energy
Non-Traditional
Traditional
Cavern
Containerized
Non-Cavern
Compressed
Air
Electromagnetic
Integrated Cell
Battery
Energy Storage
Mechanical
Flywheel
SMES
Craig R Horne – All Rights Reserved 2015
Abengoa’s Solano Generating Station
280 MW(AC) for 6 hours " 1,280 MW-hrs
Craig R Horne – All Rights Reserved 2015
EnerVault’s Turlock Demonstration
250 kW(AC) for 4 hours " 1 MW-hr
45
Craig R Horne – All Rights Reserved 2015 46
An Example in Battery System Architectures
Integrated Cell Redox Flow
๏  energy stored & conversion/power
delivery intimately coupled
๏  energy stored decoupled from
conversion/power delivery
+
-
cell
3.3 V
3 Ah
10 V
48 Ah
480 Wh
battery: 48 cells
+
-
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
RFB System Building Blocks
A: Energy Block
Main components: tanks, electrolyte
Function: stores energy
B: Power Block
Main components: cell stacks (cascades),
stack module, rebalance system (DRSTM
unit), State-of-Health (eSOH) monitors
Function: absorbs and releases power
C: Hydraulic Block
Main components: main hydraulics, flow
meters, filtration
Function: distributes electrolyte from A to B
D: Controls Block
Main components: controls/user interface,
battery management system, DC
conditioning, AC/DC inverter
Function: controls system and monitors overall
system State-of-Health; conditions power;
grid interface
47
A
B
D C
NE PE
eSOH
eSOH
DRS™
BMS
stacks
B
C
A
D
–
~
user
interface
D
B –
stack
module
C
A
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
50
B
D C
eSOH
eSOH
DRS™
BMS
stacks
B
C
D
–
~
user
interface
Power
RFB System Building Blocks – Decoupled P & E
A NE PE
A
Energy
(duration)
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
EnerVault System Building Blocks – Decoupled P & E
51
Power
Energy
Craig R Horne – All Rights Reserved 2015
EnerVault System Building Blocks – Decoupled P & E
52
Power Energy
Craig R Horne – All Rights Reserved 2015
Another Way to Think About Decoupled P & E
53
Power
Energy
acknowledgement: Bret Adams
Craig R Horne – All Rights Reserved 2015
Another Way to Think About Decoupled P & E
Power Energy
acknowledgement: Bret Adams
Craig R Horne – All Rights Reserved 2015
Decoupled Power & Energy Storage Systems
Unique advantages in long-duration applications
Decoupled Storage Systems
(RFBs, CAES, Molten Salt, RFCs, etc)
hr or E/P
$/kW-hr
hr or E/P
O&MCost
hr or E/P
O&MCost
hr or E/P
$/kW-hr
CapEx
OpEx
Coupled Storage Systems
(Li-ion, NAS, Pb-acid, flywheel, etc.)
Craig R Horne – All Rights Reserved 2015
Hawaii Project Case Study
57
Time-shifted production from PV plant
!  PV used to charge 1 MW EnerVault Fe/Cr RFB Battery Energy Storage System (BESS)
•  Optimized size of PV dedicated to BESS charging
to nearest 0.1 MW as function of storage duration
•  No ITC applied to the PV & Battery
!  Priority for PV is to charge battery
•  PV optimized to maximize amount of Shifted PV
•  LCOE determined for Shifted PV; project expenses
normalized to Shifted PV Energy Delivered
•  PV production > 1 MW or after BESS reaches 100%
SoC can be sold as Direct PV to improve project economics
!  Results scale with BESS size
•  e.g. 3 MW BESS has same LCOE & trends (% change) but 3X PV size, CapEx $
= ~X MWdc
PV
Single Axis
Tracking
X MWp
~ =
Shifted PV
1 MWac,Y hrs
Energy Unit
Y MW-hrs
Power Unit
1 MWac
1 MWac
X’ MWac Direct PV
X’ MWac, ? hrs
KIUC Grid Status
!  Conventional generation is mix of oil & hydro (~ 5 MW)
•  cost of oil generation ~ $230/MWh (translates to
~ $1/liter at 40% generator efficiency and no O&M)
!  PV meets almost 50% of daytime Summer load
!  KIUC current and projected PV satisfies daytime loads
•  deploying short-duration storage for voltage stability,
frequency regulation, and ramp support
•  high interest in increasing % RE and more PV
!  KIUC open to offers for time-shifted PV to supplant lower
efficiency generators
Source: B. Rockwell (Power Supply Mgr) KIUC Energy
Storage RFP UpdateWebinar August 28, 2014
Craig R Horne – All Rights Reserved 2015
+0%
+10%
+20%
+30%
+40%
+50%
+60%
+70%
+80%
+90%
+100%
+110%
$80
$100
$120
$140
$160
$180
$200
$220
$240
$260
$280
$300
2 3 4 5 6 7 8 9 10
Change(vs.4hourduartion)
$/MWh
Storage Duration, hours
LCOE Shifted $/MWh LCOE Shifted & Direct $/MWh Shifted PV MWh/yr PV $M BESS $M
Impact of Storage Duration
Low marginal cost of additional storage capacity with Fe/Cr reduces LCOE by a third,
approx. doubles dispatched energy & increases PV revenue by more than 80%!
LCOE - Shifted PV
LCOE - Shifted & Direct PV
Annual Shifted PV
Energy Delivered
PV CapEx
Fe/Cr RFB BESS CapEx
Project results have no ITC or other subsidy applied
1.0
MW
1.4
MW
1.8
MW
PV Size
@ $1.25/Wp 2.0
MW
58
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
!  To Achieve 100% RE island
•  PV + BESS + Bio-diesel
!  EPC/PV mfg
⇒  4 to 5X larger PV installation
⇒  e.g.: 22 MWdc vs. max 4 to 6 MWac
allowed w/o storage
!  EnerVault system
•  approx. 1/3 of TTL project
•  w/ full 24 hour backup
(+96 MW-hr)
•  adding energy ~ 2.5X more cost-
effective than adding power (PV +
BESS chg.)
!  Benefit of system to rate payers
⇒  40% reduction in generation costs
vs. incumbent diesel gen sets
⇒  Controllable future costs
⇒  Market sustainable tourism
Project Example: Island µGrid
59
“lean” storage
full 24 hrs storage
oversized PV
basic configuration
= ~
~ =
Energy Unit
90 MW-hrs
(5.5 hrs backup)
Power Unit
15 MWac
EnerVault BESS
22 MWdc
4 – 6 MWac Direct PV
4 MWac, 7 hrs
BESS
4 MWac, 17 hrs
18.7 MWac
14.7 MWac 4 MWac
Diesel Gen Set
6.6 MWac
~
PV
Single Axis Tracking
22 MWp
53 Acres
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
Long-Duration, Decoupled Power & Energy Storage Systems
Provide multiple benefits to PV
PV System
๏  enhanced capacity factors
๏  enable TOD premiums -
compete with fossils 24/7
๏  reduce penalties, losses from
curtailment
๏  impart resiliency into weak
grids
๏  enable capacity payments
๏  3 to 10X more PV per project!
hr or E/P
O&MCost
hr or E/P
$/kW-hr
Decoupled Storage Systems
(RFBs, CAES, RFCs, etc)
Source: EnerVault Corporation
Craig R Horne – All Rights Reserved 2015
Want To Know More?
http://www.energystorage.org
61

Más contenido relacionado

La actualidad más candente

5 kw solar solution implementation for telecom site
5 kw solar solution implementation for telecom site5 kw solar solution implementation for telecom site
5 kw solar solution implementation for telecom sitecoaltech
 
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUCFlinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUCjames hamilton
 
Session 3A - Samuel Sanchez
Session 3A - Samuel SanchezSession 3A - Samuel Sanchez
Session 3A - Samuel SanchezReenergize
 
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...ScottMadden, Inc.
 
GreenLight CENIC Award
GreenLight CENIC AwardGreenLight CENIC Award
GreenLight CENIC AwardJerry Sheehan
 
Flinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDARFlinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDARjames hamilton
 
Flinders Island Isolated Power System (IPS) Connect 2016 H MERKEL ACEP
Flinders Island Isolated Power System (IPS) Connect 2016  H MERKEL ACEPFlinders Island Isolated Power System (IPS) Connect 2016  H MERKEL ACEP
Flinders Island Isolated Power System (IPS) Connect 2016 H MERKEL ACEPjames hamilton
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanIBRAR AHMAD
 
New base march 10 2022 energy news issue - 1493 by khaled al awadi
New base march 10 2022  energy news issue - 1493  by khaled al awadiNew base march 10 2022  energy news issue - 1493  by khaled al awadi
New base march 10 2022 energy news issue - 1493 by khaled al awadiKhaled Al Awadi
 
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Engineering Limited
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsSanman Rajput
 
A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...EG TECHNOLOGIES
 
Solar Energy Applications
Solar Energy ApplicationsSolar Energy Applications
Solar Energy ApplicationsAvish Thakral
 
A study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in indiaA study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in indiaKetan Vador
 
Sierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local PowerSierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local PowerRhys Gerholdt
 
Designing Next Generation Data Centres
Designing Next Generation Data CentresDesigning Next Generation Data Centres
Designing Next Generation Data CentresSam Wood
 

La actualidad más candente (20)

Market Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaMarket Outlook for Energy Storage in India
Market Outlook for Energy Storage in India
 
5 kw solar solution implementation for telecom site
5 kw solar solution implementation for telecom site5 kw solar solution implementation for telecom site
5 kw solar solution implementation for telecom site
 
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUCFlinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
 
Session 3A - Samuel Sanchez
Session 3A - Samuel SanchezSession 3A - Samuel Sanchez
Session 3A - Samuel Sanchez
 
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
 
GreenLight CENIC Award
GreenLight CENIC AwardGreenLight CENIC Award
GreenLight CENIC Award
 
National Solar Mission Status (July'17)
National Solar Mission Status (July'17)National Solar Mission Status (July'17)
National Solar Mission Status (July'17)
 
Flinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDARFlinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDAR
Flinders Island Isolated Power System (IPS) Connect 2016 J CARUSO MASDAR
 
Flinders Island Isolated Power System (IPS) Connect 2016 H MERKEL ACEP
Flinders Island Isolated Power System (IPS) Connect 2016  H MERKEL ACEPFlinders Island Isolated Power System (IPS) Connect 2016  H MERKEL ACEP
Flinders Island Isolated Power System (IPS) Connect 2016 H MERKEL ACEP
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistan
 
New base march 10 2022 energy news issue - 1493 by khaled al awadi
New base march 10 2022  energy news issue - 1493  by khaled al awadiNew base march 10 2022  energy news issue - 1493  by khaled al awadi
New base march 10 2022 energy news issue - 1493 by khaled al awadi
 
Converteam presentation
Converteam presentationConverteam presentation
Converteam presentation
 
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projects
 
Floating Solar PV - An Introduction
Floating Solar PV -  An Introduction Floating Solar PV -  An Introduction
Floating Solar PV - An Introduction
 
A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...
 
Solar Energy Applications
Solar Energy ApplicationsSolar Energy Applications
Solar Energy Applications
 
A study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in indiaA study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in india
 
Sierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local PowerSierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local Power
 
Designing Next Generation Data Centres
Designing Next Generation Data CentresDesigning Next Generation Data Centres
Designing Next Generation Data Centres
 

Similar a Long-Duration Energy Storage and PV: Renewable Energy’s BFFs

Battery Integration & Technology Compare 7-7-15
Battery Integration & Technology Compare 7-7-15Battery Integration & Technology Compare 7-7-15
Battery Integration & Technology Compare 7-7-15Jacob McKee
 
David Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET Power
David Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET PowerDavid Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET Power
David Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET PowerELEEP Network
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
Sgs all presentations_8-30-2011
Sgs all presentations_8-30-2011Sgs all presentations_8-30-2011
Sgs all presentations_8-30-2011Melanie Brandt
 
Grid Level Battery Storage
Grid Level Battery StorageGrid Level Battery Storage
Grid Level Battery Storageswapnil_energy
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements Iceland Geothermal
 
What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?Cedric Christensen
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptsomnathmahapatra6
 
Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]Tomo Kalaba
 
Value of CSP with TES november 2014
Value of CSP with TES november 2014Value of CSP with TES november 2014
Value of CSP with TES november 2014Daniel Schwab
 
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentationEnergy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentationBritish Embassy Paris
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winnerDave Bryant
 
Aat Overview 2 9 2010 Jj Handout Copy
Aat Overview 2 9 2010 Jj Handout CopyAat Overview 2 9 2010 Jj Handout Copy
Aat Overview 2 9 2010 Jj Handout Copymls1964
 
Latest in energy storage
Latest in energy storageLatest in energy storage
Latest in energy storageLoic Charmoille
 
Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...
Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...
Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...larkly
 

Similar a Long-Duration Energy Storage and PV: Renewable Energy’s BFFs (20)

Battery Integration & Technology Compare 7-7-15
Battery Integration & Technology Compare 7-7-15Battery Integration & Technology Compare 7-7-15
Battery Integration & Technology Compare 7-7-15
 
David Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET Power
David Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET PowerDavid Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET Power
David Freed (8 Rivers Capital), ELEEP Virtual Discussion on NET Power
 
Arena presentation for State of Solar breakfast
Arena presentation for State of Solar breakfastArena presentation for State of Solar breakfast
Arena presentation for State of Solar breakfast
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
Sgs all presentations_8-30-2011
Sgs all presentations_8-30-2011Sgs all presentations_8-30-2011
Sgs all presentations_8-30-2011
 
2010 jun14 fast presentation
2010 jun14 fast presentation2010 jun14 fast presentation
2010 jun14 fast presentation
 
Grid Level Battery Storage
Grid Level Battery StorageGrid Level Battery Storage
Grid Level Battery Storage
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements
 
What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?
 
NMRESGI_Energy Storage Trends and Challenges_Willard
NMRESGI_Energy Storage Trends and Challenges_WillardNMRESGI_Energy Storage Trends and Challenges_Willard
NMRESGI_Energy Storage Trends and Challenges_Willard
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
 
Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]Concept of the Hagersvalle Energy ParkF[1]
Concept of the Hagersvalle Energy ParkF[1]
 
Value of CSP with TES november 2014
Value of CSP with TES november 2014Value of CSP with TES november 2014
Value of CSP with TES november 2014
 
Amber kinetics intro non nda 06-16-2017
Amber kinetics intro non nda 06-16-2017Amber kinetics intro non nda 06-16-2017
Amber kinetics intro non nda 06-16-2017
 
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentationEnergy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winner
 
Aat Overview 2 9 2010 Jj Handout Copy
Aat Overview 2 9 2010 Jj Handout CopyAat Overview 2 9 2010 Jj Handout Copy
Aat Overview 2 9 2010 Jj Handout Copy
 
Latest in energy storage
Latest in energy storageLatest in energy storage
Latest in energy storage
 
Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...
Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...
Teslas JB Straubel at SCES2014 - Future of EVS gigafactories, battery storage...
 
Poster
PosterPoster
Poster
 

Último

Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxJohnree4
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...Henrik Hanke
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.KathleenAnnCordero2
 
Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEMCharmi13
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this periodSaraIsabelJimenez
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptxogubuikealex
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxnoorehahmad
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGYpruthirajnayak525
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSebastiano Panichella
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRachelAnnTenibroAmaz
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...漢銘 謝
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationNathan Young
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Escort Service
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRRsarwankumar4524
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comsaastr
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 

Último (20)

Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptx
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
 
Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEM
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this period
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptx
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation Track
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism Presentation
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 

Long-Duration Energy Storage and PV: Renewable Energy’s BFFs

  • 1. 2015Craig R Horne – All Rights Reserved 2015 0 Long-Duration Energy Storage and PV: Renewable Energy’s BFFs Craig R. Horne, Ph.D. Santa Clara Valley IEEE PV Society May 13, 2015 content within this presentation is provided courtesy of EnerVault Corporation
  • 2. Craig R Horne – All Rights Reserved 2015 Outline !  Markets & Drivers !  Illustrative Projects !  Configuring Storage Systems !  Storage Architectures !  Impact on PV Projects 1
  • 3. Craig R Horne – All Rights Reserved 2015 What this talk is (mostly) about – MW-scale, Long-Duration Energy Storage for Electricity Supply (Wholesale Markets) What this talk is (mostly) not about – kW-scale Energy Storge for Residential or Commercial Applications MW-scale, Short-Duration Energy Storage for Wholesale Markets
  • 4. Craig R Horne – All Rights Reserved 2015 Energy Storage Markets Are Global Entity Size (Power) Duration (Energy) Description CA 1,360 MW 2-4 hrs !  California procurement decision AB 2514 (October 2013) SCE 260 MW ≥ 4 hrs !  RFP issued (October 2013) !  > 5x awarded (November 2014) LIPA 150 MW – 650 MW 12 hrs !  RFP issued (November 2013) Hokkaido 12 MW 5 hrs !  Contract awarded (July 2013) Terna 130 MW 6 hrs !  Contract awarded (May 2013) SDG&E 25 MW – 800 MW ≥ 4 hrs !  RFP issued (September 2014) ConEd 59 MW 2 MW 12 hrs !  RFI for 12 hour load deferral (July 2014) !  RFQ issued (September 2014) IESO 16.5 MW ≥ 4 hrs !  RFP initiated (October 2014) 3 Source: EnerVault Corporation
  • 5. Craig R Horne – All Rights Reserved 2015 Energy Storage Markets Are Global http://www.energystorageexchange.org/projects 4
  • 6. Craig R Horne – All Rights Reserved 2015 A)  The Head [MW] B) The Neck [MW/hr] C) The Belly [- MW or MWidle] Three Challenges 5
  • 7. Craig R Horne – All Rights Reserved 2015 Energy Storage vs. Conventional Peaker More than 2X the Flexible Ramp Resource ChargingDischarging Idle Power CT Flexible Resource Value BESS Flexible Resource Value Interconnect Rating Interconnect Rating Throttle Courtesy EnerVault Corporation Adapated from P. Kathpal,“Energy Storage in Resource Planning and Procurement”, ESA Annual Meeting, June 2014 6
  • 8. Craig R Horne – All Rights Reserved 2015 Energy Storage vs. Conventional Peaker But in CA more than 4X the Flexible Ramp Resource ChargingDischarging Idle Power @ 50% (NOx standards) CT Flexible Resource Value BESS Flexible Resource Value 7 Interconnect Rating Interconnect Rating Throttle Courtesy EnerVault Corporation Adapated from P. Kathpal,“Energy Storage in Resource Planning and Procurement”, ESA Annual Meeting, June 2014
  • 9. Craig R Horne – All Rights Reserved 2015 AB 2514 – 1.325 GW Mandate for Storage http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M078/K912/78912194.PDF 8
  • 10. Craig R Horne – All Rights Reserved 2015 Many Ways To Store Energy Electrochemical Flow Batteries Redox Flow Battery Non-Redox Flow Battery Supercapacitors Other Sodium-Sulfur Lead-Acid Lithium-based Sodium-NiCI2 Aqueous-other Metal/air Molten metal Metal-based Flow Battery Non-Metal Flow Battery Regenerative Fuel Cell Chemical ThermalChilled Water Ice Heat Molten Salt Pumped Hydro Power Energy Non-Traditional Traditional Cavern Containerized Non-Cavern Compressed Air Electromagnetic Integrated Cell Battery Energy Storage Mechanical Flywheel SMES Source: EnerVault Corporation
  • 11. Craig R Horne – All Rights Reserved 2015 Fairbanks, AK 27 Megawatt UPS (Nickel Cadmium)
  • 12. Craig R Horne – All Rights Reserved 2015 Dublin, CA 2 Megawatt Micro-Grid (BYD, Li-Ion) 11
  • 13. Craig R Horne – All Rights Reserved 2015 Stephenstown NY 20 Megawatt Fast Frequency Response (Flywheel Energy Storage) Miller,Western Oregon U.
  • 14. Craig R Horne – All Rights Reserved 2015 Laurel Mountain,WV 32 Megawatt wind integration (AES Energy Storage, Li-ion)
  • 15. Craig R Horne – All Rights Reserved 2015 Notrees, TX 36 Megawatt wind management (Younicos, lead-acid)
  • 16. Craig R Horne – All Rights Reserved 2015 Rokkasho JapanWind Farm 15 Okimoto, NGK – ESA 2009
  • 17. Craig R Horne – All Rights Reserved 2015 Turlock, CA 250 Kilowatt, 4 hr Load Management (EnerVault, Fe/Cr-RFB) 16
  • 18. Craig R Horne – All Rights Reserved 2015 Gila Bend, AZ 280 Megawatt, 6 hours (Abengoa, molten salt)
  • 19. Craig R Horne – All Rights Reserved 2015 Northwestern PA 435 Megawatt Peak Load Management (Pumped Hydro Energy Storage) wikipedia
  • 20. Craig R Horne – All Rights Reserved 2015 McIntosh, AL 110 Megawatt Peak Load Management (Cavern Compressed Air Energy Storage) PG&E
  • 21. Craig R Horne – All Rights Reserved 2015 Moraine, OH 20 Megawatt Peaker (AES, Li-Ion) 20
  • 22. Craig R Horne – All Rights Reserved 2015 City of Industry, CA 479 MW Peaker - 5 x 100 MW (Edison Mission Group, NGGT) 21
  • 23. Craig R Horne – All Rights Reserved 2015 City of Industry, CA 5 x 100 MW GT (GE) " 479 MW(AC) for capacity payments & bids into CAISO (EMG) 22 power capability power capacity
  • 24. Craig R Horne – All Rights Reserved 2015 !  Duration at rated power: Day 1 AND Day N •  N = 3,650 for 10 year project, or 7,300 for 20 year project time NetPower,MW(AC) 4 -4 charge discharge 40 8 12 16 20 What is Required of A Grid Storage Asset 26 !  Total project cost requires storage capacity allotments for... •  Capacity utilization (“Depth of Discharge” or “State-of-Charge Range” (SoCR) ) •  Losses (inefficiency) •  Capacity fade 26
  • 25. Craig R Horne – All Rights Reserved 2015 !  Duration at rated power: Day 1 AND Day N •  N = 3,650 for 10 year project, or 7,300 for 20 year project What is Required of A Grid Storage Asset 29 !  Total project cost requires storage capacity allotments for... •  Capacity utilization (“Depth of Discharge” or “State-of-Charge Range” (SoCR) ) •  Losses (inefficiency) •  Capacity fade Power DurationX = Energy time NetPower,MW(AC) 4 -4 charge discharge 40 8 12 16 20 29
  • 26. Craig R Horne – All Rights Reserved 2015 System Configuration !  SCE Tehachapi Project (Li-ion) • 8 MW(AC)/32 MW-hr 30 Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project 2014 ESA Annual Meeting, June 4-6 2014
  • 27. Craig R Horne – All Rights Reserved 2015 Two Components to LiB Aging (per Saft) 31
  • 28. Craig R Horne – All Rights Reserved 2015 0 6 12 18 24 Power Time of Day Saft Data on LiB Aging: Impact on Configuration " SOH factors = calendar X cycling 4 hr 11 hr 3 hr 6 hr 0% 25% 50% 75% 100% 0 6 12 18 24 Stateof Charge Time of Day idle time/day @ top of charge SystemChargeLevel (notcell) project design 1 MWAC for 4 hours, 20-30oC & 75% SOC at top of charge, 15% SOC at bottom of cycle (discharged state) " 60% utilization & 44 to 31 year calendar life 15 year project 1 cycle/day 11 hrs/day idle @ full charge means: 11 hrs/day * 365 days/year * 15 year project life = 60,225 hrs 60,225 hrs/8,760 hrs per year " 7 equivalent years at idle Analysis adapted from: ~ 10-20% impact Source: EnerVault Corporation
  • 29. Craig R Horne – All Rights Reserved 2015 Properly Configuring a Grid Storage Asset 33 $125/kWh ?SoCR capacity fade losses system integration installation grid connection Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project 2014 ESA Annual Meeting, June 4-6 2014
  • 30. Craig R Horne – All Rights Reserved 2015 Properly Configuring a Grid Asset 34 $125/kWh ?SoCR capacity fade losses system integration installation grid connection Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project 2014 ESA Annual Meeting, June 4-6 2014 can deliver MW(AC) capacitycapability to store MWh(DC)
  • 31. Craig R Horne – All Rights Reserved 2015 35 Properly Configuring a Grid Storage Asset Energy Storage Capability !  kWh: ability to deliver MW(DC) until storage media is fully utilized !  ability to store MWh(DC) !  based on the quantity of storage media or factory acceptance test of the article !  provided by storage vendor Energy Storage Capacity !  kW-hr: ability to deliver MW(AC) for required # hours throughout project lifetime !  ability to deliver MW(AC) !  based on fully installed system !  provided by storage project developer $$ this is what is monetized $$ It is important to distinguish the capability from the capacity!
  • 32. Craig R Horne – All Rights Reserved 2015 Properly Configuring a Grid Storage Asset 36 $125/kWh $400-600/kW-hrSoCR capacity fade losses system integration installation grid connection storage capability storage capacity Source: L. Gaillac, SCE - Tehachapi Wind Energy Storage Project 2014 ESA Annual Meeting, June 4-6 2014
  • 33. Craig R Horne – All Rights Reserved 2015 !  Duration at rated power: Day 1 AND Day N •  N = 3,650 for 10 year project, or 7,300 for 20 year project What is Required of A Grid Storage Asset 37 !  Total project cost requires storage capacity allotments for... •  Capacity utilization (“Depth of Discharge” or “State-of-Charge Range” (SoCR) ) •  Losses (inefficiency) •  Capacity fade Power DurationX = Energy 4 MWAC for 4 hrs = 16 MW-hr storage capacity; $/kW-hr = TTL Installed $/16,000 kW-hr time NetPower,MW(AC) 4 -4 charge discharge 40 8 12 16 20 37 the actual installed unit will have > 16 MWh of storage capability, how much more depends on storage product & project conditions
  • 34. Craig R Horne – All Rights Reserved 2015 Key for Individual Project: Stacking Benefits B. Kaun (2013)
  • 35. Craig R Horne – All Rights Reserved 2015 But Reality Can Be A Bummer B. Kaun (2013)
  • 36. Craig R Horne – All Rights Reserved 2015 Configurations System DesignVolume TotalEnergyOutput Rate-AdjustedEnergyOutput Configuration BESSASP RESize REPrice Project Modeling Overview 1) Operational Model 2) Pricing Model 4) Pro Forma Model FixedO&M Variable O&M MajorRefurb 3) O&M Model Project IRR, NPV, B/E, $
  • 37. Craig R Horne – All Rights Reserved 2015 Project Model Inputs !  Performance Model •  BESS: MW, MW-hr, ramp up, ramp down, start time, self-discharge, degradation, operational efficiency •  project setting: charging power,TOU rates/premiums, boundary conditions (e.g. IX limit) •  dispatch method: charge priorities, benefit maximization, etc. !  Pricing Model •  subsystem cost as function of time •  system cost basis for configuration variations !  O&M Model •  component lifetimes/replacement intervals, service requirements, subsystem costs at replacement time !  Pro Forma Model •  discount rate, depreciation, PPA/tariff structure, subsidies/offsets, other values (e.g. $/ tonne-C avoided)
  • 38. Craig R Horne – All Rights Reserved 2015 A Look Inside Efficiency Echarge Pcharge, direct Edisch. Pout Eout Pparsitic load, charge PPCS loss, charge PECC loss, charge Echarged Pstdby load Pdisch Pcharge Estdby Pparsitic load, discharge PPCS loss, discharge PECC loss, discharge /tcharge *tcharge /tdisch *tdisch *tstdby Pcont load Econt load /tcycle! Ein Overall Efficiency η=Ein/Eout II IV I III I)  Continous Load: Occur the whole time •  controller, HMI, lights, etc. II)  Charging Losses: during tcharge •  Energy Conversion: charging efficiency •  Power Conditioning System: charging efficiency •  Parasitic Load (BOP,Therm. Mgmt, etc) III)  Standby Load: during tstdby •  Standby Load 1 •  Standby Load 2 IV)  Discharging Losses: during tdisch •  Energy Conversion: discharging efficiency •  Power Condintioning System: discharging efficiency •  Parasitic Load (BOP,Therm. Mgmt, etc) Requires Use Case-Based Operational Analysis of System Over FullYear/Life of Project
  • 39. Craig R Horne – All Rights Reserved 2015 43 Storage Architectures Coupled Power & Energy Decoupled Power & Energy ๏  energy stored & conversion/power delivery intimately coupled “cans of soda” ๏  energy stored decoupled from conversion/power delivery “soda fountain drink” Electrochemical Flow Batteries Redox Flow Battery Non-Redox Flow Battery Supercapacitors Other Sodium-Sulfur Lead-Acid Lithium-based Sodium-NiCI2 Aqueous-other Metal/air Molten metal Metal-based Flow Battery Non-Metal Flow Battery Regenerative Fuel Cell Chemical ThermalHeat Molten Salt Chilled Water Ice Pumped Hydro Power Energy Non-Traditional Traditional Cavern Containerized Non-Cavern Compressed Air Electromagnetic Integrated Cell Battery Energy Storage Mechanical Flywheel SMES
  • 40. Craig R Horne – All Rights Reserved 2015 Abengoa’s Solano Generating Station 280 MW(AC) for 6 hours " 1,280 MW-hrs
  • 41. Craig R Horne – All Rights Reserved 2015 EnerVault’s Turlock Demonstration 250 kW(AC) for 4 hours " 1 MW-hr 45
  • 42. Craig R Horne – All Rights Reserved 2015 46 An Example in Battery System Architectures Integrated Cell Redox Flow ๏  energy stored & conversion/power delivery intimately coupled ๏  energy stored decoupled from conversion/power delivery + - cell 3.3 V 3 Ah 10 V 48 Ah 480 Wh battery: 48 cells + - Source: EnerVault Corporation
  • 43. Craig R Horne – All Rights Reserved 2015 RFB System Building Blocks A: Energy Block Main components: tanks, electrolyte Function: stores energy B: Power Block Main components: cell stacks (cascades), stack module, rebalance system (DRSTM unit), State-of-Health (eSOH) monitors Function: absorbs and releases power C: Hydraulic Block Main components: main hydraulics, flow meters, filtration Function: distributes electrolyte from A to B D: Controls Block Main components: controls/user interface, battery management system, DC conditioning, AC/DC inverter Function: controls system and monitors overall system State-of-Health; conditions power; grid interface 47 A B D C NE PE eSOH eSOH DRS™ BMS stacks B C A D – ~ user interface D B – stack module C A Source: EnerVault Corporation
  • 44. Craig R Horne – All Rights Reserved 2015 50 B D C eSOH eSOH DRS™ BMS stacks B C D – ~ user interface Power RFB System Building Blocks – Decoupled P & E A NE PE A Energy (duration) Source: EnerVault Corporation
  • 45. Craig R Horne – All Rights Reserved 2015 EnerVault System Building Blocks – Decoupled P & E 51 Power Energy
  • 46. Craig R Horne – All Rights Reserved 2015 EnerVault System Building Blocks – Decoupled P & E 52 Power Energy
  • 47. Craig R Horne – All Rights Reserved 2015 Another Way to Think About Decoupled P & E 53 Power Energy acknowledgement: Bret Adams
  • 48. Craig R Horne – All Rights Reserved 2015 Another Way to Think About Decoupled P & E Power Energy acknowledgement: Bret Adams
  • 49. Craig R Horne – All Rights Reserved 2015 Decoupled Power & Energy Storage Systems Unique advantages in long-duration applications Decoupled Storage Systems (RFBs, CAES, Molten Salt, RFCs, etc) hr or E/P $/kW-hr hr or E/P O&MCost hr or E/P O&MCost hr or E/P $/kW-hr CapEx OpEx Coupled Storage Systems (Li-ion, NAS, Pb-acid, flywheel, etc.)
  • 50. Craig R Horne – All Rights Reserved 2015 Hawaii Project Case Study 57 Time-shifted production from PV plant !  PV used to charge 1 MW EnerVault Fe/Cr RFB Battery Energy Storage System (BESS) •  Optimized size of PV dedicated to BESS charging to nearest 0.1 MW as function of storage duration •  No ITC applied to the PV & Battery !  Priority for PV is to charge battery •  PV optimized to maximize amount of Shifted PV •  LCOE determined for Shifted PV; project expenses normalized to Shifted PV Energy Delivered •  PV production > 1 MW or after BESS reaches 100% SoC can be sold as Direct PV to improve project economics !  Results scale with BESS size •  e.g. 3 MW BESS has same LCOE & trends (% change) but 3X PV size, CapEx $ = ~X MWdc PV Single Axis Tracking X MWp ~ = Shifted PV 1 MWac,Y hrs Energy Unit Y MW-hrs Power Unit 1 MWac 1 MWac X’ MWac Direct PV X’ MWac, ? hrs KIUC Grid Status !  Conventional generation is mix of oil & hydro (~ 5 MW) •  cost of oil generation ~ $230/MWh (translates to ~ $1/liter at 40% generator efficiency and no O&M) !  PV meets almost 50% of daytime Summer load !  KIUC current and projected PV satisfies daytime loads •  deploying short-duration storage for voltage stability, frequency regulation, and ramp support •  high interest in increasing % RE and more PV !  KIUC open to offers for time-shifted PV to supplant lower efficiency generators Source: B. Rockwell (Power Supply Mgr) KIUC Energy Storage RFP UpdateWebinar August 28, 2014
  • 51. Craig R Horne – All Rights Reserved 2015 +0% +10% +20% +30% +40% +50% +60% +70% +80% +90% +100% +110% $80 $100 $120 $140 $160 $180 $200 $220 $240 $260 $280 $300 2 3 4 5 6 7 8 9 10 Change(vs.4hourduartion) $/MWh Storage Duration, hours LCOE Shifted $/MWh LCOE Shifted & Direct $/MWh Shifted PV MWh/yr PV $M BESS $M Impact of Storage Duration Low marginal cost of additional storage capacity with Fe/Cr reduces LCOE by a third, approx. doubles dispatched energy & increases PV revenue by more than 80%! LCOE - Shifted PV LCOE - Shifted & Direct PV Annual Shifted PV Energy Delivered PV CapEx Fe/Cr RFB BESS CapEx Project results have no ITC or other subsidy applied 1.0 MW 1.4 MW 1.8 MW PV Size @ $1.25/Wp 2.0 MW 58 Source: EnerVault Corporation
  • 52. Craig R Horne – All Rights Reserved 2015 !  To Achieve 100% RE island •  PV + BESS + Bio-diesel !  EPC/PV mfg ⇒  4 to 5X larger PV installation ⇒  e.g.: 22 MWdc vs. max 4 to 6 MWac allowed w/o storage !  EnerVault system •  approx. 1/3 of TTL project •  w/ full 24 hour backup (+96 MW-hr) •  adding energy ~ 2.5X more cost- effective than adding power (PV + BESS chg.) !  Benefit of system to rate payers ⇒  40% reduction in generation costs vs. incumbent diesel gen sets ⇒  Controllable future costs ⇒  Market sustainable tourism Project Example: Island µGrid 59 “lean” storage full 24 hrs storage oversized PV basic configuration = ~ ~ = Energy Unit 90 MW-hrs (5.5 hrs backup) Power Unit 15 MWac EnerVault BESS 22 MWdc 4 – 6 MWac Direct PV 4 MWac, 7 hrs BESS 4 MWac, 17 hrs 18.7 MWac 14.7 MWac 4 MWac Diesel Gen Set 6.6 MWac ~ PV Single Axis Tracking 22 MWp 53 Acres Source: EnerVault Corporation
  • 53. Craig R Horne – All Rights Reserved 2015 Long-Duration, Decoupled Power & Energy Storage Systems Provide multiple benefits to PV PV System ๏  enhanced capacity factors ๏  enable TOD premiums - compete with fossils 24/7 ๏  reduce penalties, losses from curtailment ๏  impart resiliency into weak grids ๏  enable capacity payments ๏  3 to 10X more PV per project! hr or E/P O&MCost hr or E/P $/kW-hr Decoupled Storage Systems (RFBs, CAES, RFCs, etc) Source: EnerVault Corporation
  • 54. Craig R Horne – All Rights Reserved 2015 Want To Know More? http://www.energystorage.org 61