SlideShare a Scribd company logo
1 of 15
Download to read offline
November 4, 2020
Eglinton Crosstown LRT
Chaplin-Avenue CLC
Chaplin Station
CHAPLIN STATION UPDATE
3
Activity Location Approx. Date & Duration What to Expect
Tertiary Entrance Construction
Wall construction, rebar and
formwork
South side of Eglinton Ave,
east of Chaplin Cres and
adjacent Toronto Fire Station
135
Underway into spring 2021
• Noise from construction
equipment
• Laneway closure
Main Entrance Construction
Waterproofing, rebar, formwork
North side of Eglinton Ave
between Chaplin Cres and
Gilgorm Rd
Underway into spring 2021
• Noise from construction
equipment
• Chipping
Station Box Construction
Rebar, concrete, formwork
Beneath Eglinton Ave Underway into spring 2021
• Noise from associated
surface works, such as use of
crane and trucks
Watermain Works
Connections and reinstatement
Intersection of Eglinton Ave
and Chaplin Cres
Beginning mid-November 2020
into mid-January 2021
• Lane reductions
• Chaplin Cres and Eglinton
Ave intersection closure
• Overnight work
• Noise from construction
equipment
CURRENT TRAFFIC CONFIGURATION
4
Until mid-November 2020
CONSTRUCTION PROGRESS PHOTOS
5CENTRAL WEST WORKS MONTHLY MEETING
STATION BOXTERTIARY ENTRANCE
Avenue Station
AVENUE STATION UPDATE
7INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Final lining (waterproofing,
rebar installation, and
mechanical electrical works)
Throughout all station areas Underway through to late-2020
• Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 – 18 hours through to 2021
• Concrete truck activity
• Occupation of the westbound
curb lane during some pours
Eglinton Connects Streetscape
and Cycle Track
Overnight Utility Works & Water
Shut-off for fire hydrant relocation
Eglinton Ave between Lascelles Blvd
and Duplex Ave
Affected properties:
• 174 Eglinton Ave W
• 200 Eglinton Ave W
Underway through to early 2021
Utility works: Thursday November 5,
2020; beginning at 10:00 p.m. for
approx. seven (7) hours
• Eglinton reduced to one lane in
each direction between
Lascelles Blvd & Duplex Ave
• Use of excavator, hydro-vac
and concrete trucks
• Overnight noise can be expected
during utility works
Dewatering Well Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. – 4:00 p.m.
• Road occupancy around well
• Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 • Short-term road occupancy
CURRENT TRAFFIC CONFIGURATION
8
Through September 2021
INSERT FOOTER
CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE
9INSERT FOOTER
Through Winter 2020
EGLINTON AVE FUTURE CONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD
10INSERT FOOTER
EGLINTON AVE FUTURE CONFIGURATION – LASCELLES BLVD – DUPLEX AVE
11INSERT FOOTER
EGLINTON CONNECTS CONSTRUCTION OVERVIEW
12
Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will
continue into 2021.
The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of
Toronto’s Streetscape and Cycle Track Design.
Construction Hours:
• Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work
Construction Activities:
• Excavation
• Utility Reinstatement
• Concrete Work
• Compaction and Paving
• Landscaping – installation of street furnishings, light poles, trees etc.
To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be
removed. Notice will be provided in advance of removals.
Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.
INSERT FOOTER
CONSTRUCTION PROGRESS PHOTOS
13INSERT FOOTER
REBAR INSTALLATION –
MAIN ENTRANCE
WATERPROOFING –
SECONDARY ENTRACE HEADWALL
CONSTRUCTION PROGRESS PHOTOS
14INSERT FOOTER
REBAR INSTALLATION
- STATION BOX CONCOURSE LEVEL
Avenue & Chaplin CLC - Construction Update: November 4, 2020

More Related Content

What's hot

CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Crosstown TO
 

What's hot (20)

Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
 

Similar to Avenue & Chaplin CLC - Construction Update: November 4, 2020

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
 

Similar to Avenue & Chaplin CLC - Construction Update: November 4, 2020 (20)

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 

More from Crosstown TO

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 

Recently uploaded

VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
sonatiwari757
 
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
sonatiwari757
 

Recently uploaded (20)

Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 

Avenue & Chaplin CLC - Construction Update: November 4, 2020

  • 1. November 4, 2020 Eglinton Crosstown LRT Chaplin-Avenue CLC
  • 3. CHAPLIN STATION UPDATE 3 Activity Location Approx. Date & Duration What to Expect Tertiary Entrance Construction Wall construction, rebar and formwork South side of Eglinton Ave, east of Chaplin Cres and adjacent Toronto Fire Station 135 Underway into spring 2021 • Noise from construction equipment • Laneway closure Main Entrance Construction Waterproofing, rebar, formwork North side of Eglinton Ave between Chaplin Cres and Gilgorm Rd Underway into spring 2021 • Noise from construction equipment • Chipping Station Box Construction Rebar, concrete, formwork Beneath Eglinton Ave Underway into spring 2021 • Noise from associated surface works, such as use of crane and trucks Watermain Works Connections and reinstatement Intersection of Eglinton Ave and Chaplin Cres Beginning mid-November 2020 into mid-January 2021 • Lane reductions • Chaplin Cres and Eglinton Ave intersection closure • Overnight work • Noise from construction equipment
  • 5. CONSTRUCTION PROGRESS PHOTOS 5CENTRAL WEST WORKS MONTHLY MEETING STATION BOXTERTIARY ENTRANCE
  • 7. AVENUE STATION UPDATE 7INSERT FOOTER Activity Location Approx. Date & Duration What to Expect Final lining (waterproofing, rebar installation, and mechanical electrical works) Throughout all station areas Underway through to late-2020 • Deliveries at the main and secondary entrances Concrete Pours Between the Main and Secondary Entrances Three times per week for approx. 12 – 18 hours through to 2021 • Concrete truck activity • Occupation of the westbound curb lane during some pours Eglinton Connects Streetscape and Cycle Track Overnight Utility Works & Water Shut-off for fire hydrant relocation Eglinton Ave between Lascelles Blvd and Duplex Ave Affected properties: • 174 Eglinton Ave W • 200 Eglinton Ave W Underway through to early 2021 Utility works: Thursday November 5, 2020; beginning at 10:00 p.m. for approx. seven (7) hours • Eglinton reduced to one lane in each direction between Lascelles Blvd & Duplex Ave • Use of excavator, hydro-vac and concrete trucks • Overnight noise can be expected during utility works Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9:00 a.m. – 4:00 p.m. • Road occupancy around well • Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 • Short-term road occupancy
  • 8. CURRENT TRAFFIC CONFIGURATION 8 Through September 2021 INSERT FOOTER
  • 9. CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE 9INSERT FOOTER Through Winter 2020
  • 10. EGLINTON AVE FUTURE CONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD 10INSERT FOOTER
  • 11. EGLINTON AVE FUTURE CONFIGURATION – LASCELLES BLVD – DUPLEX AVE 11INSERT FOOTER
  • 12. EGLINTON CONNECTS CONSTRUCTION OVERVIEW 12 Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will continue into 2021. The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of Toronto’s Streetscape and Cycle Track Design. Construction Hours: • Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work Construction Activities: • Excavation • Utility Reinstatement • Concrete Work • Compaction and Paving • Landscaping – installation of street furnishings, light poles, trees etc. To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be removed. Notice will be provided in advance of removals. Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave. INSERT FOOTER
  • 13. CONSTRUCTION PROGRESS PHOTOS 13INSERT FOOTER REBAR INSTALLATION – MAIN ENTRANCE WATERPROOFING – SECONDARY ENTRACE HEADWALL
  • 14. CONSTRUCTION PROGRESS PHOTOS 14INSERT FOOTER REBAR INSTALLATION - STATION BOX CONCOURSE LEVEL