Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017

CROSSTOWN LRT
Construction Liaison
Committee
August 8, 2017
Agenda
• Fairbank Station
• Oakwood Station
Fairbank Station Aerial View
Main
Entrance
Service
Building
Secondary
Entrance
How We’re Building Fairbank Station:
Support of Excavation – Top Down
• Also known as ‘shoring’ or ‘piling’, support of
excavation is a common step in the process of
constructing a building.
• An area the size of the station’s footprint
(about 100m x 20m) called the ‘station box’ is
cut, steel piles are installed around the
perimeter, a shallow area is excavated, and
braces and tie-backs are installed at the sides
to support excavation.
• A concrete roof slab is constructed and placed
over top of the excavated area, restoring
traffic while crews work safely underground.
• Support of excavation at Fairbank Station will
take approximately 1.5 years to complete
Fairbank Station Construction Update
Complete
 Demolition at the Service Building
 Installation of geotechnical monitoring equipment
 Telecommunication utilities relocation
 Piling at the Main Entrance and Service Building
 Hydro utilities relocation
2017
• Continue piling on the north side of Eglinton Ave W
• Continue wet utilities relocation work on Eglinton Ave W
• Implement traffic staging on the south side of Eglinton Ave W and commence piling
Current Construction Staging
Construction Progress Pictures
Construction Progress Pictures
Construction Progress Pictures
WATERMAIN
CUT-AND-CAP
WORK
Construction Progress Pictures
GUIDEWALL
CONSTRUCTION
Construction Progress Pictures
PILING
NORTHEAST
STATION BOX
Oakwood Station Concept: Aerial View
Main
Entrance
Secondary
Entrance
*60% rendering
Accessible Entrance
The main entrance and
technical box are
designed with an art
feature to animate and
highlight the view from
Oakwood Avenue.
Oakwood Station Concept: Main Entrance
Outdoor
bicycle parking
On-street
connections to
TTC Buses
Oakwood Station Concept: Secondary Entrance
Outdoor
bicycle parking
How We’re Building Oakwood Station:
Support of Excavation
• Oakwood Station is being constructed using a
mined method known as Sequential Excavation
Method or SEM. The first stage is support of
excavation.
• Support of excavation (shoring) is a common step in
the process of installing the foundation of a
building.
• In the first stage, crews will install
steel piles around the perimeter
of the entrance. This has been
completed at both entrances.
• In the second stage, crews
excavate the area level by level,
installing braces and tie-backs as
they progress. This work is
underway at the main entrance.
• Mining occurs from inside of the excavated main
entrance after the support of excavation is
complete.
• The underground area to be excavated is divided
into manageable segments and the segments are
excavated in a planned sequence.
How We’re Building Oakwood Station:
Sequential Excavation Mining Method
• Within the mined area, the
station box is constructed
accommodating the rail
tunnels, associated
platform and rail
infrastructure.
Oakwood Station Construction Summary
2016
 Geotechnical Investigation completed
 Demolition 1578-1584 and 1611-1619 Eglinton Ave W completed
 Stage one of long-term closure (main entrance)
 Support of excavation (shoring) work started at Main and Secondary entrances
 Temporary traffic signals installations
 60% design completion
2017
 Piling operations completed at both entrances
 Temporary power works completed (Civil works completed, energization pending
crane assembly)
2016 Progress
Oakwood Station Construction Lookahead
August/September 2017
• Excavation at main entrance - underway
• Geotechnical Instrumentation and Monitoring Plan (phase 2 installations ) –
ongoing periodically
• Overhead crane assembly at main entrance - underway
• Site service connections (water & sewer) - upcoming
– Starting August 14st
– Some overnight work to reduce impacts at intersection
• Stage 3A set up late August/early September 2017 (Staging under review)
• Dewatering wells installation on the sidewalk along Eglinton (south and north
side)
2017
• Utilities Protection (Sewer lining and replacement, work on the watermain)
• Mining work late 2017 (from main entrance)
Site Service Connections
Dewatering System Installation & Operation
• The term “dewatering” means pumping from the ground water at a site where
there will be excavation.
• Wells will be drilled in the ground and will be connected above ground in the area
required.
• System will operate for the duration of construction (2020).
Oakwood Stage 3A Revised
2017 - 2020
Progress Picture
Progress Picture
Progress Picture
Local Area Map
1 de 26

Recomendados

Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017 por
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017Crosstown TO
2K vistas11 diapositivas
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017 por
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
3K vistas35 diapositivas
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017 por
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
2.7K vistas24 diapositivas
Community Information Meeting of parkette design plan at Fairbank Station por
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
531 vistas34 diapositivas
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017 por
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Crosstown TO
1.7K vistas13 diapositivas
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017 por
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
2.3K vistas17 diapositivas

Más contenido relacionado

La actualidad más candente

Eglinton & Mount Pleasant Construction Liaison Committee - November 2017 por
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
2.9K vistas19 diapositivas
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017 por
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Crosstown TO
1.9K vistas9 diapositivas
Mount Pleasant Station Open House - April 2017 por
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Crosstown TO
1.8K vistas37 diapositivas
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017 por
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Crosstown TO
2.4K vistas16 diapositivas
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ... por
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Crosstown TO
3.1K vistas23 diapositivas
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017 por
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
1.4K vistas22 diapositivas

La actualidad más candente(20)

Eglinton & Mount Pleasant Construction Liaison Committee - November 2017 por Crosstown TO
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Crosstown TO2.9K vistas
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017 por Crosstown TO
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Crosstown TO1.9K vistas
Mount Pleasant Station Open House - April 2017 por Crosstown TO
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
Crosstown TO1.8K vistas
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017 por Crosstown TO
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Crosstown TO2.4K vistas
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ... por Crosstown TO
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Crosstown TO3.1K vistas
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017 por Crosstown TO
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Crosstown TO1.4K vistas
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018 por Crosstown TO
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Crosstown TO1.2K vistas
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017 por Crosstown TO
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Crosstown TO2.3K vistas
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017 por Crosstown TO
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Crosstown TO1.8K vistas
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017 por Crosstown TO
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Crosstown TO1.9K vistas
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ... por Crosstown TO
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Crosstown TO2.4K vistas
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint... por Crosstown TO
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Crosstown TO591 vistas
Leaside & Laird Construction Liaison Committee Meeting - September 2017 por Crosstown TO
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Crosstown TO2.3K vistas
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017 por Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Crosstown TO4.1K vistas
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J... por Crosstown TO
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Crosstown TO2.3K vistas
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017 por Crosstown TO
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
Crosstown TO2K vistas
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017 por Crosstown TO
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Crosstown TO2.1K vistas
Forest Hill Station Open House - June 2017 por Crosstown TO
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO1.6K vistas
Leaside & Laird Stations Construction Liaison Committee - October 2017 por Crosstown TO
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
Crosstown TO225 vistas
Chaplin & Avenue CLC - Construction Update - February 7, 2018 por Brittany Maxwell
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Brittany Maxwell1.3K vistas

Destacado

Stations Presentation - Corridor Wide por
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
99.9K vistas42 diapositivas
Caledonia Station, West Portal and Elevated Guideway Open House por
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
2.3K vistas49 diapositivas
Science Centre Station Open House - June 2017 por
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Crosstown TO
346 vistas36 diapositivas
Science Centre Station and West At-Grade Surface Stops Open House - November ... por
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Crosstown TO
841 vistas40 diapositivas
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017 por
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Crosstown TO
1.5K vistas25 diapositivas
Chaplin station open house por
Chaplin station open houseChaplin station open house
Chaplin station open houseCrosstown TO
2.7K vistas55 diapositivas

Destacado(20)

Stations Presentation - Corridor Wide por Crosstown TO
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
Crosstown TO99.9K vistas
Caledonia Station, West Portal and Elevated Guideway Open House por Crosstown TO
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO2.3K vistas
Science Centre Station Open House - June 2017 por Crosstown TO
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
Crosstown TO346 vistas
Science Centre Station and West At-Grade Surface Stops Open House - November ... por Crosstown TO
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Crosstown TO841 vistas
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017 por Crosstown TO
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Crosstown TO1.5K vistas
Chaplin station open house por Crosstown TO
Chaplin station open houseChaplin station open house
Chaplin station open house
Crosstown TO2.7K vistas
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017 por Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Crosstown TO2.5K vistas
Mount Dennis Station and EMSF Open House - March 2017 por Crosstown TO
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO2.6K vistas
Western Works - Construction Liaison Committee Meeting - May 2017 por Crosstown TO
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO2.2K vistas
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017 por Crosstown TO
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Crosstown TO1.7K vistas
Leaside Station Open House - March 2017 por Crosstown TO
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
Crosstown TO3.4K vistas
Eglinton Station Open House - March 2017 por Crosstown TO
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO2.3K vistas
Leaside - Laird Construction Liaison Committee Meeting - July 2017 por Crosstown TO
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO1.7K vistas
Laird Station Open House - April 2017 por Crosstown TO
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
Crosstown TO1.7K vistas
Fairbank & Oakwood Stations Open House - April 2017 por Crosstown TO
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
Crosstown TO2.1K vistas
Forest hill station open house por Crosstown TO
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO3.4K vistas
Surface Section and Kennedy Station Open House - April 2017 por Crosstown TO
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
Crosstown TO2.7K vistas
Fairbank and Oakwood stations open house por Crosstown TO
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house
Crosstown TO4.1K vistas
Cedarvale Station Open House - March 2017 por Crosstown TO
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
Crosstown TO2.2K vistas
Avenue Station Open House - May 2017 por Crosstown TO
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO1.2K vistas

Similar a Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017

Leaside - Laird Construction Liaison Committee Meeting - June 2017 por
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
1.3K vistas27 diapositivas
Western works final por
Western works final Western works final
Western works final Crosstown TO
5.5K vistas43 diapositivas
Brentcliffe - Victoria Park Construction Liaison Committee Meeting por
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
4.3K vistas28 diapositivas
Central Eastern Works Open House - October 2019 por
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Crosstown TO
4.5K vistas28 diapositivas
Brentcliffe - Victoria Park Construction Liaison Committee Meeting por
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
5.4K vistas22 diapositivas
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January... por
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Crosstown TO
2.6K vistas11 diapositivas

Similar a Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017(17)

Leaside - Laird Construction Liaison Committee Meeting - June 2017 por Crosstown TO
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO1.3K vistas
Western works final por Crosstown TO
Western works final Western works final
Western works final
Crosstown TO5.5K vistas
Brentcliffe - Victoria Park Construction Liaison Committee Meeting por Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO4.3K vistas
Central Eastern Works Open House - October 2019 por Crosstown TO
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
Crosstown TO4.5K vistas
Brentcliffe - Victoria Park Construction Liaison Committee Meeting por Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO5.4K vistas
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January... por Crosstown TO
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Crosstown TO2.6K vistas
West Open House - Progress Update Sept 2014 por Crosstown TO
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
Crosstown TO23.5K vistas
Cedarvale station open house for website final2 por Crosstown TO
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
Crosstown TO4.3K vistas
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018 por Crosstown TO
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO351 vistas
Avenue & Chaplin CLC - Construction Update: July 8, 2020 por Crosstown TO
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Crosstown TO2.3K vistas
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting por Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO3.3K vistas
Leaside open house sep 2014 Slides por Crosstown TO
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
Crosstown TO27.1K vistas
Leaside open house sep 2014 slides por Crosstown TO
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
Crosstown TO322 vistas
Final central east open house oct282020 por Crosstown TO
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
Crosstown TO3.7K vistas
Brentcliffe - Victoria Park Construction Liaison Committee Meeting por Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO5.6K vistas
Chaplin & Avenue CLC - Construction Update - April 4, 2018 por Crosstown TO
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Crosstown TO1.4K vistas

Más de Crosstown TO

Western Works CLC - January 17, 2023.pdf por
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
36 vistas22 diapositivas
Western Works CLC - May 16, 2023 por
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
147 vistas23 diapositivas
Western Works CLC - March, 21 2023 por
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
143 vistas23 diapositivas
Leaside-Laird CLC - May 8, 2023.pdf por
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
919 vistas15 diapositivas
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf por
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
1.5K vistas11 diapositivas
Chaplin-Avenue CLC - May 3 2023 Updated.pptx por
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
985 vistas14 diapositivas

Más de Crosstown TO(20)

Western Works CLC - January 17, 2023.pdf por Crosstown TO
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO36 vistas
Western Works CLC - May 16, 2023 por Crosstown TO
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO147 vistas
Western Works CLC - March, 21 2023 por Crosstown TO
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO143 vistas
Leaside-Laird CLC - May 8, 2023.pdf por Crosstown TO
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO919 vistas
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf por Crosstown TO
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO1.5K vistas
Chaplin-Avenue CLC - May 3 2023 Updated.pptx por Crosstown TO
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO985 vistas
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx por Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO1.1K vistas
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx por Crosstown TO
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO1.5K vistas
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx por Crosstown TO
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO1.8K vistas
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx por Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO2K vistas
Chaplin-Avenue CLC - March 1, 2023.pptx por Crosstown TO
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO1.7K vistas
Leaside-Laird CLC - March 13, 2023.pdf por Crosstown TO
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO6.1K vistas
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx por Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO171 vistas
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf por Crosstown TO
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO3.6K vistas
Chaplin-Avenue CLC - November 2 2022 compressed.pptx por Crosstown TO
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO1.4K vistas
Chaplin-Avenue CLC - January 11 2023 (002).pptx por Crosstown TO
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO2.5K vistas
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx por Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO3.2K vistas
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf por Crosstown TO
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO4.8K vistas
Leaside-Laird CLC - January 9, 2023.pdf por Crosstown TO
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO3K vistas
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf por Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO192 vistas

Último

Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th... por
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...India Water Portal
10 vistas19 diapositivas
PPT - SIGMA-GIZ Academies - Topic 4 - Azerbaijan - Public Service Design.pdf por
PPT - SIGMA-GIZ Academies - Topic 4 - Azerbaijan - Public Service Design.pdfPPT - SIGMA-GIZ Academies - Topic 4 - Azerbaijan - Public Service Design.pdf
PPT - SIGMA-GIZ Academies - Topic 4 - Azerbaijan - Public Service Design.pdfSupport for Improvement in Governance and Management SIGMA
49 vistas37 diapositivas
Atlas of Military Compensation por
Atlas of Military CompensationAtlas of Military Compensation
Atlas of Military CompensationCongressional Budget Office
675 vistas5 diapositivas
Cover Letter for Canada VISITOR visa.pdf por
Cover Letter for Canada VISITOR visa.pdfCover Letter for Canada VISITOR visa.pdf
Cover Letter for Canada VISITOR visa.pdfAriful Saimon
8 vistas2 diapositivas
Job Posting - Fire Inspector, PT.pdf por
Job Posting - Fire Inspector, PT.pdfJob Posting - Fire Inspector, PT.pdf
Job Posting - Fire Inspector, PT.pdfNorthwestBOCA
15 vistas1 diapositiva
WCAG 2.2 - An Overview of the New Accessibility Guidelines.pptx por
WCAG 2.2 - An Overview of the New Accessibility Guidelines.pptxWCAG 2.2 - An Overview of the New Accessibility Guidelines.pptx
WCAG 2.2 - An Overview of the New Accessibility Guidelines.pptxAbilityNet
72 vistas20 diapositivas

Último(20)

Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th... por India Water Portal
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...
India Water Portal10 vistas
Cover Letter for Canada VISITOR visa.pdf por Ariful Saimon
Cover Letter for Canada VISITOR visa.pdfCover Letter for Canada VISITOR visa.pdf
Cover Letter for Canada VISITOR visa.pdf
Ariful Saimon8 vistas
Job Posting - Fire Inspector, PT.pdf por NorthwestBOCA
Job Posting - Fire Inspector, PT.pdfJob Posting - Fire Inspector, PT.pdf
Job Posting - Fire Inspector, PT.pdf
NorthwestBOCA15 vistas
WCAG 2.2 - An Overview of the New Accessibility Guidelines.pptx por AbilityNet
WCAG 2.2 - An Overview of the New Accessibility Guidelines.pptxWCAG 2.2 - An Overview of the New Accessibility Guidelines.pptx
WCAG 2.2 - An Overview of the New Accessibility Guidelines.pptx
AbilityNet72 vistas
Mapping location and co-location of industries at the neighborhood level - A... por OECD CFE
Mapping location and co-location of industries at the neighborhood level  - A...Mapping location and co-location of industries at the neighborhood level  - A...
Mapping location and co-location of industries at the neighborhood level - A...
OECD CFE7 vistas
Managing drinking water infrastructure in West Bengal Gram Panchayats_Sujata ... por India Water Portal
Managing drinking water infrastructure in West Bengal Gram Panchayats_Sujata ...Managing drinking water infrastructure in West Bengal Gram Panchayats_Sujata ...
Managing drinking water infrastructure in West Bengal Gram Panchayats_Sujata ...
India Water Portal10 vistas
Advancing and democratizing business data in Canada- Patrick Gill & Stephen Tapp por OECD CFE
Advancing and democratizing business data in Canada- Patrick Gill & Stephen TappAdvancing and democratizing business data in Canada- Patrick Gill & Stephen Tapp
Advancing and democratizing business data in Canada- Patrick Gill & Stephen Tapp
OECD CFE7 vistas
COP 28 GHANA DELEGATES.docx por Kweku Zurek
COP 28 GHANA DELEGATES.docxCOP 28 GHANA DELEGATES.docx
COP 28 GHANA DELEGATES.docx
Kweku Zurek6.6K vistas
Project Nexus Regional Rail por Lee Haber
Project Nexus Regional RailProject Nexus Regional Rail
Project Nexus Regional Rail
Lee Haber6 vistas
Monitoring and Evaluation Plan (Theory of change, results framework, Logframe... por Scoffy Wangang
Monitoring and Evaluation Plan (Theory of change, results framework, Logframe...Monitoring and Evaluation Plan (Theory of change, results framework, Logframe...
Monitoring and Evaluation Plan (Theory of change, results framework, Logframe...
Scoffy Wangang5 vistas
Support Girl students with Education por SERUDS INDIA
Support Girl students with EducationSupport Girl students with Education
Support Girl students with Education
SERUDS INDIA7 vistas

Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017

  • 3. Fairbank Station Aerial View Main Entrance Service Building Secondary Entrance
  • 4. How We’re Building Fairbank Station: Support of Excavation – Top Down • Also known as ‘shoring’ or ‘piling’, support of excavation is a common step in the process of constructing a building. • An area the size of the station’s footprint (about 100m x 20m) called the ‘station box’ is cut, steel piles are installed around the perimeter, a shallow area is excavated, and braces and tie-backs are installed at the sides to support excavation. • A concrete roof slab is constructed and placed over top of the excavated area, restoring traffic while crews work safely underground. • Support of excavation at Fairbank Station will take approximately 1.5 years to complete
  • 5. Fairbank Station Construction Update Complete  Demolition at the Service Building  Installation of geotechnical monitoring equipment  Telecommunication utilities relocation  Piling at the Main Entrance and Service Building  Hydro utilities relocation 2017 • Continue piling on the north side of Eglinton Ave W • Continue wet utilities relocation work on Eglinton Ave W • Implement traffic staging on the south side of Eglinton Ave W and commence piling
  • 12. Oakwood Station Concept: Aerial View Main Entrance Secondary Entrance *60% rendering Accessible Entrance
  • 13. The main entrance and technical box are designed with an art feature to animate and highlight the view from Oakwood Avenue. Oakwood Station Concept: Main Entrance Outdoor bicycle parking
  • 14. On-street connections to TTC Buses Oakwood Station Concept: Secondary Entrance Outdoor bicycle parking
  • 15. How We’re Building Oakwood Station: Support of Excavation • Oakwood Station is being constructed using a mined method known as Sequential Excavation Method or SEM. The first stage is support of excavation. • Support of excavation (shoring) is a common step in the process of installing the foundation of a building. • In the first stage, crews will install steel piles around the perimeter of the entrance. This has been completed at both entrances. • In the second stage, crews excavate the area level by level, installing braces and tie-backs as they progress. This work is underway at the main entrance.
  • 16. • Mining occurs from inside of the excavated main entrance after the support of excavation is complete. • The underground area to be excavated is divided into manageable segments and the segments are excavated in a planned sequence. How We’re Building Oakwood Station: Sequential Excavation Mining Method • Within the mined area, the station box is constructed accommodating the rail tunnels, associated platform and rail infrastructure.
  • 17. Oakwood Station Construction Summary 2016  Geotechnical Investigation completed  Demolition 1578-1584 and 1611-1619 Eglinton Ave W completed  Stage one of long-term closure (main entrance)  Support of excavation (shoring) work started at Main and Secondary entrances  Temporary traffic signals installations  60% design completion 2017  Piling operations completed at both entrances  Temporary power works completed (Civil works completed, energization pending crane assembly)
  • 19. Oakwood Station Construction Lookahead August/September 2017 • Excavation at main entrance - underway • Geotechnical Instrumentation and Monitoring Plan (phase 2 installations ) – ongoing periodically • Overhead crane assembly at main entrance - underway • Site service connections (water & sewer) - upcoming – Starting August 14st – Some overnight work to reduce impacts at intersection • Stage 3A set up late August/early September 2017 (Staging under review) • Dewatering wells installation on the sidewalk along Eglinton (south and north side) 2017 • Utilities Protection (Sewer lining and replacement, work on the watermain) • Mining work late 2017 (from main entrance)
  • 21. Dewatering System Installation & Operation • The term “dewatering” means pumping from the ground water at a site where there will be excavation. • Wells will be drilled in the ground and will be connected above ground in the area required. • System will operate for the duration of construction (2020).
  • 22. Oakwood Stage 3A Revised 2017 - 2020

Notas del editor

  1. Support of Excavation (Shoring) Shoring is a common step in the process of installing the foundation of a building. This will support the surrounding loads until the underground levels of the building are constructed.