SlideShare una empresa de Scribd logo
1 de 39
Descargar para leer sin conexión
CROSSTOWN LRT TOWN HALL
April 2019
2
Agenda
7:00 to 7:30 – View Deck
7:30 to 8:00 – Presentation
8:00 to 8:30 – Question & Answer
3
Eglinton Crosstown Overview
• 19 km route separated from regular traffic
• 10-kilometres underground; 9-kilometres at surface east of Laird
• 15 underground stations and 10 surface stops
• 20,000 m2 maintenance and storage facility to maintain and house 76
vehicles
• Transit communications system
• Links to 54 bus routes, 3 subway stations, GO Transit, UP Express
station
4
Eglinton Avenue East
- Final Configuration
O’Connor Stop at Victoria
Park and Eglinton Avenue
5
Eglinton Avenue East - At-Grade
Construction
• Major work will be occurring at intersection between Leslie and Ionview
throughout 2019
• LRT guideway will be constructed in the middle of Eglinton and track will be
installed
• The work takes place in two stages – paving, followed by guideway
construction and track installation
6
2019 Construction Schedule
– Leslie to Ionview Road
7
Sunnybrook Park Stop – Leslie/Eglinton
8
July-August Traffic Restriction - Leslie/Eglinton
8
• Crosslinx is seeking city permits for a temporary eight week restriction
on vehicles travelling between Leslie Street & Eglinton Avenue East
• Allows for LRT guideway construction & track installation.
• Eglinton Avenue will remain open in both directions at all times.
• Leslie Street will otherwise function normally.
• Traffic lanes will open up & turn restrictions will be lifted at
Bayview/Eglinton & Don Mills/Eglinton before the Leslie work starts.
• Proposed timeline is during the lowest traffic volume months.
9
July-August Traffic Restriction - Leslie/Eglinton
9
• Emergency services access to and from Eglinton Avenue will be
maintained at all times.
• Pedestrian & cyclist access between Leslie Street and Eglinton Avenue
will be maintained throughout the closure.
• The entry to Sunnybrook Park off Leslie Street north of Eglinton Avenue
is outside the work zone and will be open.
10
Leslie Street Intersection July-August 2019
11
Bayview and Eglinton Intersection
June 30th 2019
12
Don Mills and Eglinton Intersection
Mid-May 2019
13
Traffic Movements at Adjacent Intersections
14
Why Restrict Some Traffic and Transit Access at Leslie?
• Keeping the intersection open for all traffic and transit access would
require carrying the work out in a minimum of four stages resulting
in:
– Extended disruption from construction from two to six months,
including periods where traffic volume is greater than summer
months.
– At least four (4) major changes in how traffic gets through the
area; each stage of construction would be disruptive.
– Additional off-peak lane closures and intermediate traffic setups
with associated restrictions required.
– Reduced quality of road when work is completed due to joints
and higher future maintenance costs, with future road work
required earlier or more frequently.
15
Prior to the Closure
• A comprehensive advertising campaign will be launched.
• Canvasses will be scheduled for residences and businesses in the immediate
area.
• Advanced Signage:
– Portable Variable Message Signs (PVMS) at York Mills/Leslie, Don
Mills/Lawrence, Bayview/Eglinton, Laird/Eglinton and Don Mills/Eglinton
– Local traffic only signs at Lawrence and Leslie
– Additional construction-grade signage will be placed in key locations:
• East and west of Leslie on Eglinton Ave
• North of Eglinton at Lawrence and York Mills
• South of Eglinton
• TTC will provide advance information to impacted transit riders.
• The 24/7 Crosstown call centre will be available to provide information and
respond to issues.
• During the closure, Crosslinx will continually monitor the situation and make
adjustments as required.
16
TTC Detours
17
Communications & Engagement
17
• On-street activations & info booths leading up to works
- Eglinton Square Mall, Smart Centre Plaza, Golden Mile Plaza, Eglinton
Town Centre, Don Montgomery Community Centre, residential lobbies,
activations on TTC and on street ambassadors at stops
• Distribution of construction notices and wayfinding postcards to
businesses and residents
• Open House – April 10th
• Advertising – radio, print, digital, TTC locations
• Digital – social media, Metrolinx & TTC websites
• Advanced signage – informing road users of the status of the intersections
far upstream of Eglinton and leading up to date of works
18
Business support
1
2
3
4
5
1. Shop Local Campaign 2. Spring Newsletter
3. Business Profile 4. BlogTO Post 5. Signage
19
Community Benefits
20
416-782-8118 or 416-482-7411
24 hours/7days a week
www.thecrosstown.ca
crosstown@metrolinx.com
facebook.com/thecrosstown
twitter.com/crosstownTO
instagram.com/eglinton_crosstown
Crosstown West Office
1848 Eglinton Ave W (at Dufferin)
Crosstown East Office
660 Eglinton Ave E (at Bayview)
Stay in Touch
21
QUESTIONS?
22
Traction Power Substations
22
• Eglinton Crosstown LRT requires 12 traction power substations (TPSS) to power
vehicles across the 19 km alignment.
• TPSS takes power from THESL, converts it to the voltage required to run the LRT
and distributes it to LRT system.
• Engineering study completed prior to the RFP determined number and location of
TPSS.
– Proximity to Eglinton Avenue reduces the total number required
• On the underground alignment, eight TPSS will be located inside stations or
service buildings.
• At-grade, four TPSS will be free-standing structures on City of Toronto approved
sites.
– Building underground or lowering the grade does not meet regulatory requirements.
– It would not be compliant with Toronto Hydro’s ‘Requirements for Customer Owned Sub-
Stations’ or the City of Toronto’s storm water management guidelines: ‘Wet Weather
Management Flow Guidelines.’
23
TPSS Key Facts
23
• Common to LRT projects
• Prefab unit approximately 20 metres X 10 metres X 4 metres
– Surrounded by architectural screen
– In discussions with City Urban Design
– Exploring public art option which could include community engagement
• Meets all electrical regulations and safety requirements
– Secured inside locked building
– Electrical equipment also in locked units within the building
• Only noise is from air conditioning units:
– Maximum 60 decibels - equivalent to residential central air condenser
– Noise level less than ambient noise from Eglinton Avenue and surrounding
streets
• No vibration
• Security lighting for building will be installed behind screen
• TPSS pose no public health risks
24
• TPSS 9:
Eglinton East of Don Mills near Science Centre
Stop
• TPSS 10:
Eglinton at Victoria Park near O’Connor Stop
• TPSS 11:
Warden south of Eglinton near Golden Mile Stop
• TPSS 12:
Eglinton at Birchmount near Birchmount Stop
TPSS 9
TPSS 10
TPSS 11TPSS 12
Location of At-Grade TPSS
4
25
TPSS - Unscreened
5
26
TPSS Proposed Architectural Screen
• 4m height to visually screen TPSS unit from
street
• Modular design panels
• Heavy gauge aluminum
• Painted or embossed graphic image
• Concealed posts
• Frame and fastening systems to match fence
panel
• 30% to 40% porosity (TBD)
• Anti Graffiti Coated
Graphic of Perforated Metal Fence Panels – Based on Design Guidelines
6
27
TPSS 9 – Before & After
- Eglinton Avenue West of Don Mills
8
28
TPSS 10 – Before & After
- Eglinton and Victoria Park
12
29
TPSS 11- Before & After
- Warden and Eglinton
SITE
WARDEN
15
30
TPSS 12 – Before & After
- Eglinton & Birchmount
18
31
Existing Examples
23
Before After
Copeland site (in downtown Toronto) on Bremner next to Roundhouse Park is
the second transformer station to be built underground in Canada
Hydro One Electrical Substation (John St. and Wellington St.)
32
• Perforated fence design allows for
the creation of dynamic imagery.
• Above images provide examples
showing the level of image detail that
can be illustrated as part of an art
installation.
• Potential opportunity to engage community in development of public art
• TPSS screens are a ‘blank canvas’
• Could be used to celebrate the interesting and rich history of the Golden Mile
and/or other aspects of the community
• CTS consulting Scarborough Arts and local counsellors
Option for Public Art and Community
Engagement
33
Sunnybrook Park Stop Rendering
AERIAL VIEW PLATFORM VIEW
CROSSWALK VIEW CROSSWALK VIEW
34
Eglinton Avenue East Renderings
34
SCIENCE CENTRE MAIN ENTRANCE
HAKIMI/LEBOVIC SIDEWALK
IONVIEW STOP AERIAL VIEW
PHARMACY STOP AERIAL VIEW
35
East Portal at Brentcliffe Rendering
36
- ASPHALT REMOVAL
- EXCAVATION
- OVERHEAD CATENARY SYSTEM
(OCS) FOUNDATION
- DUCT BANK
- SAND LAYER
- INSULATION LAYER
- BACKFILL
- BARRIER WALLS
- TRACK SLAB
- RAILWAY
- TRAFFIC SHIFTING
Excavation depth is 2 to 6 metres; width 8 metres.
How we build the guideway
8
37
Intersection operations during construction
- Paving & Guideway Construction
37
• CTS requires temporary changes to intersections operations from Leslie to
Ionview for road paving and guideway construction:
– Eglinton must be widened for LRT; road must be paved prior to guideway
installation
– Paving is completed in 2 weekends per intersection from Victoria Park to
Ionview
– Paving is completed in 12 weeks per intersection for concrete base
intersections (Credit Union/Swift, Sloane/Bermondsey)
– Guideway work in centre of intersection; no through north/south traffic for six
weeks at each intersection; includes rail installation
• Restrictions are not full intersection closures.
– Eglinton remains open in both directions at all times
– Work will not take place at adjacent intersections
– Emergency services access maintained
– Signal timing will be optimized at the main and adjacent intersections to benefit
operations
38
Intersection operations during construction
- Paving
Paving work for concrete road intersections require approximately six (6)
weeks of work per side. For other intersections two (2) weekends of work
is required.
39
Intersection operations during construction
- Guideway
39
No through north/south traffic and no left turns for six weeks to construct guideway
and install rail.

Más contenido relacionado

La actualidad más candente

Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022Crosstown TO
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 Crosstown TO
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Crosstown TO
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsCrosstown TO
 

La actualidad más candente (20)

Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 

Similar a CROSSTOWN LRT TOWN HALL DISCUSSION

East At-Grade Town Hall Meeting
East At-Grade Town Hall MeetingEast At-Grade Town Hall Meeting
East At-Grade Town Hall MeetingCrosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house Crosstown TO
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House Crosstown TO
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Crosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Crosstown TO
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Crosstown TO
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open houseCrosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCrosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment WorksCrosstown TO
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House SlidesCrosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 

Similar a CROSSTOWN LRT TOWN HALL DISCUSSION (20)

East At-Grade Town Hall Meeting
East At-Grade Town Hall MeetingEast At-Grade Town Hall Meeting
East At-Grade Town Hall Meeting
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 

Más de Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

Más de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Último

call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...narwatsonia7
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...ResolutionFoundation
 
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfIf there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfKatrina Sriranpong
 
Yellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdfYellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdfAmir Saranga
 
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...saminamagar
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfCharlynTorres1
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Sonam Pathan
 
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...
NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...
NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...Amil baba
 
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...yalehistoricalreview
 
Angels_EDProgrammes & Services 2024.pptx
Angels_EDProgrammes & Services 2024.pptxAngels_EDProgrammes & Services 2024.pptx
Angels_EDProgrammes & Services 2024.pptxLizelle Coombs
 
PEO AVRIL POUR LA COMMUNE D'ORGERUS INFO
PEO AVRIL POUR LA COMMUNE D'ORGERUS INFOPEO AVRIL POUR LA COMMUNE D'ORGERUS INFO
PEO AVRIL POUR LA COMMUNE D'ORGERUS INFOMAIRIEORGERUS
 

Último (20)

call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...
 
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfIf there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
 
Yellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdfYellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdf
 
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170
 
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...
NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...
NO1 Certified kala jadu Love Marriage Black Magic Punjab Powerful Black Magic...
 
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
 
Angels_EDProgrammes & Services 2024.pptx
Angels_EDProgrammes & Services 2024.pptxAngels_EDProgrammes & Services 2024.pptx
Angels_EDProgrammes & Services 2024.pptx
 
PEO AVRIL POUR LA COMMUNE D'ORGERUS INFO
PEO AVRIL POUR LA COMMUNE D'ORGERUS INFOPEO AVRIL POUR LA COMMUNE D'ORGERUS INFO
PEO AVRIL POUR LA COMMUNE D'ORGERUS INFO
 

CROSSTOWN LRT TOWN HALL DISCUSSION

  • 1. CROSSTOWN LRT TOWN HALL April 2019
  • 2. 2 Agenda 7:00 to 7:30 – View Deck 7:30 to 8:00 – Presentation 8:00 to 8:30 – Question & Answer
  • 3. 3 Eglinton Crosstown Overview • 19 km route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface east of Laird • 15 underground stations and 10 surface stops • 20,000 m2 maintenance and storage facility to maintain and house 76 vehicles • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
  • 4. 4 Eglinton Avenue East - Final Configuration O’Connor Stop at Victoria Park and Eglinton Avenue
  • 5. 5 Eglinton Avenue East - At-Grade Construction • Major work will be occurring at intersection between Leslie and Ionview throughout 2019 • LRT guideway will be constructed in the middle of Eglinton and track will be installed • The work takes place in two stages – paving, followed by guideway construction and track installation
  • 6. 6 2019 Construction Schedule – Leslie to Ionview Road
  • 7. 7 Sunnybrook Park Stop – Leslie/Eglinton
  • 8. 8 July-August Traffic Restriction - Leslie/Eglinton 8 • Crosslinx is seeking city permits for a temporary eight week restriction on vehicles travelling between Leslie Street & Eglinton Avenue East • Allows for LRT guideway construction & track installation. • Eglinton Avenue will remain open in both directions at all times. • Leslie Street will otherwise function normally. • Traffic lanes will open up & turn restrictions will be lifted at Bayview/Eglinton & Don Mills/Eglinton before the Leslie work starts. • Proposed timeline is during the lowest traffic volume months.
  • 9. 9 July-August Traffic Restriction - Leslie/Eglinton 9 • Emergency services access to and from Eglinton Avenue will be maintained at all times. • Pedestrian & cyclist access between Leslie Street and Eglinton Avenue will be maintained throughout the closure. • The entry to Sunnybrook Park off Leslie Street north of Eglinton Avenue is outside the work zone and will be open.
  • 10. 10 Leslie Street Intersection July-August 2019
  • 11. 11 Bayview and Eglinton Intersection June 30th 2019
  • 12. 12 Don Mills and Eglinton Intersection Mid-May 2019
  • 13. 13 Traffic Movements at Adjacent Intersections
  • 14. 14 Why Restrict Some Traffic and Transit Access at Leslie? • Keeping the intersection open for all traffic and transit access would require carrying the work out in a minimum of four stages resulting in: – Extended disruption from construction from two to six months, including periods where traffic volume is greater than summer months. – At least four (4) major changes in how traffic gets through the area; each stage of construction would be disruptive. – Additional off-peak lane closures and intermediate traffic setups with associated restrictions required. – Reduced quality of road when work is completed due to joints and higher future maintenance costs, with future road work required earlier or more frequently.
  • 15. 15 Prior to the Closure • A comprehensive advertising campaign will be launched. • Canvasses will be scheduled for residences and businesses in the immediate area. • Advanced Signage: – Portable Variable Message Signs (PVMS) at York Mills/Leslie, Don Mills/Lawrence, Bayview/Eglinton, Laird/Eglinton and Don Mills/Eglinton – Local traffic only signs at Lawrence and Leslie – Additional construction-grade signage will be placed in key locations: • East and west of Leslie on Eglinton Ave • North of Eglinton at Lawrence and York Mills • South of Eglinton • TTC will provide advance information to impacted transit riders. • The 24/7 Crosstown call centre will be available to provide information and respond to issues. • During the closure, Crosslinx will continually monitor the situation and make adjustments as required.
  • 17. 17 Communications & Engagement 17 • On-street activations & info booths leading up to works - Eglinton Square Mall, Smart Centre Plaza, Golden Mile Plaza, Eglinton Town Centre, Don Montgomery Community Centre, residential lobbies, activations on TTC and on street ambassadors at stops • Distribution of construction notices and wayfinding postcards to businesses and residents • Open House – April 10th • Advertising – radio, print, digital, TTC locations • Digital – social media, Metrolinx & TTC websites • Advanced signage – informing road users of the status of the intersections far upstream of Eglinton and leading up to date of works
  • 18. 18 Business support 1 2 3 4 5 1. Shop Local Campaign 2. Spring Newsletter 3. Business Profile 4. BlogTO Post 5. Signage
  • 20. 20 416-782-8118 or 416-482-7411 24 hours/7days a week www.thecrosstown.ca crosstown@metrolinx.com facebook.com/thecrosstown twitter.com/crosstownTO instagram.com/eglinton_crosstown Crosstown West Office 1848 Eglinton Ave W (at Dufferin) Crosstown East Office 660 Eglinton Ave E (at Bayview) Stay in Touch
  • 22. 22 Traction Power Substations 22 • Eglinton Crosstown LRT requires 12 traction power substations (TPSS) to power vehicles across the 19 km alignment. • TPSS takes power from THESL, converts it to the voltage required to run the LRT and distributes it to LRT system. • Engineering study completed prior to the RFP determined number and location of TPSS. – Proximity to Eglinton Avenue reduces the total number required • On the underground alignment, eight TPSS will be located inside stations or service buildings. • At-grade, four TPSS will be free-standing structures on City of Toronto approved sites. – Building underground or lowering the grade does not meet regulatory requirements. – It would not be compliant with Toronto Hydro’s ‘Requirements for Customer Owned Sub- Stations’ or the City of Toronto’s storm water management guidelines: ‘Wet Weather Management Flow Guidelines.’
  • 23. 23 TPSS Key Facts 23 • Common to LRT projects • Prefab unit approximately 20 metres X 10 metres X 4 metres – Surrounded by architectural screen – In discussions with City Urban Design – Exploring public art option which could include community engagement • Meets all electrical regulations and safety requirements – Secured inside locked building – Electrical equipment also in locked units within the building • Only noise is from air conditioning units: – Maximum 60 decibels - equivalent to residential central air condenser – Noise level less than ambient noise from Eglinton Avenue and surrounding streets • No vibration • Security lighting for building will be installed behind screen • TPSS pose no public health risks
  • 24. 24 • TPSS 9: Eglinton East of Don Mills near Science Centre Stop • TPSS 10: Eglinton at Victoria Park near O’Connor Stop • TPSS 11: Warden south of Eglinton near Golden Mile Stop • TPSS 12: Eglinton at Birchmount near Birchmount Stop TPSS 9 TPSS 10 TPSS 11TPSS 12 Location of At-Grade TPSS 4
  • 26. 26 TPSS Proposed Architectural Screen • 4m height to visually screen TPSS unit from street • Modular design panels • Heavy gauge aluminum • Painted or embossed graphic image • Concealed posts • Frame and fastening systems to match fence panel • 30% to 40% porosity (TBD) • Anti Graffiti Coated Graphic of Perforated Metal Fence Panels – Based on Design Guidelines 6
  • 27. 27 TPSS 9 – Before & After - Eglinton Avenue West of Don Mills 8
  • 28. 28 TPSS 10 – Before & After - Eglinton and Victoria Park 12
  • 29. 29 TPSS 11- Before & After - Warden and Eglinton SITE WARDEN 15
  • 30. 30 TPSS 12 – Before & After - Eglinton & Birchmount 18
  • 31. 31 Existing Examples 23 Before After Copeland site (in downtown Toronto) on Bremner next to Roundhouse Park is the second transformer station to be built underground in Canada Hydro One Electrical Substation (John St. and Wellington St.)
  • 32. 32 • Perforated fence design allows for the creation of dynamic imagery. • Above images provide examples showing the level of image detail that can be illustrated as part of an art installation. • Potential opportunity to engage community in development of public art • TPSS screens are a ‘blank canvas’ • Could be used to celebrate the interesting and rich history of the Golden Mile and/or other aspects of the community • CTS consulting Scarborough Arts and local counsellors Option for Public Art and Community Engagement
  • 33. 33 Sunnybrook Park Stop Rendering AERIAL VIEW PLATFORM VIEW CROSSWALK VIEW CROSSWALK VIEW
  • 34. 34 Eglinton Avenue East Renderings 34 SCIENCE CENTRE MAIN ENTRANCE HAKIMI/LEBOVIC SIDEWALK IONVIEW STOP AERIAL VIEW PHARMACY STOP AERIAL VIEW
  • 35. 35 East Portal at Brentcliffe Rendering
  • 36. 36 - ASPHALT REMOVAL - EXCAVATION - OVERHEAD CATENARY SYSTEM (OCS) FOUNDATION - DUCT BANK - SAND LAYER - INSULATION LAYER - BACKFILL - BARRIER WALLS - TRACK SLAB - RAILWAY - TRAFFIC SHIFTING Excavation depth is 2 to 6 metres; width 8 metres. How we build the guideway 8
  • 37. 37 Intersection operations during construction - Paving & Guideway Construction 37 • CTS requires temporary changes to intersections operations from Leslie to Ionview for road paving and guideway construction: – Eglinton must be widened for LRT; road must be paved prior to guideway installation – Paving is completed in 2 weekends per intersection from Victoria Park to Ionview – Paving is completed in 12 weeks per intersection for concrete base intersections (Credit Union/Swift, Sloane/Bermondsey) – Guideway work in centre of intersection; no through north/south traffic for six weeks at each intersection; includes rail installation • Restrictions are not full intersection closures. – Eglinton remains open in both directions at all times – Work will not take place at adjacent intersections – Emergency services access maintained – Signal timing will be optimized at the main and adjacent intersections to benefit operations
  • 38. 38 Intersection operations during construction - Paving Paving work for concrete road intersections require approximately six (6) weeks of work per side. For other intersections two (2) weekends of work is required.
  • 39. 39 Intersection operations during construction - Guideway 39 No through north/south traffic and no left turns for six weeks to construct guideway and install rail.