2. There are many benefits and solutions
BIM is used for visualizations, quantity takeoffs, and design validation. These can be done
without the need for BIM, but BIM allows it to be done with very little error, more precession,
and more importantly much much quicker.
Secondly, BIM is great for Virtual Rehearsals. Where we build the job on the computer first,
logistics included, and make sure the schedule makes sense.
3. What does BIM do currently?
•PreConstruction
• Quantity Takeoffs
• Visualizations
• Schedule Validation
• Media – 4D (3D Model + Schedule) videos
• Logistics Plans
4. Quantity Takeoff
Complete takeoff for Marlins Ballpark
was achieved in 17 minutes.
All-Aboard Florida, Jade Signature,
1000 Museum, and SkyRise Miami just
to name a few.
Due to limited resources we only
provide quantities where traditional
takeoff is inadequate for complex
designs.
8. Logistics Planning
Cranes, temporary structures, safety equipment, from systems, dirt, heavy equipment, and access are all issues that are easier to
resolve in 3D than they are in someone's head.
9. Logistics Planning
Not only figuring out where to put cranes, but displaying that information in context with other useful information like pours or
buildings, and quantities, on paper.
14. What does BIM do currently?
•Operations
• Line Drawings
• Backgrounds for Engineering
• Visualizations
• Logistics Planning
• Spatial Coordination
• Schedule Validation
• Design Validation
• Quantity Takeoff
15. Design
Validation
This is where BIM provides the most
value. Design Validation reduces Baker’s
exposure by making sure that the design
is complete when our line and grade gets
there.
There are just some design issues that
can’t be realized until they are modeled
in BIM or laid out in the field.
How much could this have cost Baker if it
wasn’t discovered until we started laying
it out?
• Would an official RFI be asked?
• Would a change order ensue?
• How much carpenter time would
have been lost?
• How much line and grade time would
be lost?
• Does rebar need to be changed?
16. Line Drawings
These are provided to jobs for one or
more reasons:
• Required by contract for submittal
• Design Validation to get RFIs out
ahead of the construction team
• Needs to be done for Line & Grade,
it’s a byproduct of model creation,
why do the same work twice?
17. Engineering
Support
Engineering needs a reliable, accurate,
and up-to-date backgrounds to work
with. Especially when it comes to cross
sections of buildings.
These backgrounds are merely a bi-
product of model creation. Virtually no
extra time is needed to bring these to
the table.
18. Logistics & Spatial Coordination
Figuring out what cranes to use and where to place them. For the Miami Science Museum we literally only had 5ft to spare until
using a Truck pump would not be feasible. It was so tight, we had to layout precisely where the pumps would be placed, and
painted the ground where the outriggers had to sit.
19. Pour Planning
We didn’t realize a lot of things about
the Gulf Stream Tanks until we
modeled it. We found the slopes via
the BIM Model. Would have been
impossible otherwise.
Baker determined that the Top form,
which needed to be used for slopes of
33° or more, did not cover enough of
the tank.
20. Pour Planning &
Quantity Takeoff
Another thing that would have been
almost impossible to do without
modeling was figuring out how much
concrete was going into the tank.
In the next video, you’ll see a study of
how gravity works with this shape. We
found that the real challenge was at
the ring beam, which also happened to
be where the Architectural finish was.
21.
22. Schedules
1. 90% of construction schedules that weren’t validated using BIM have 5 or more logical
errors.
2. This is fine because 90% of construction schedules are so long and complicated that no one
bothers to look at them.
3. BIM can solve that with 4D (3D + time).
23. Scheduling (4D)
On Surf Club, we’ve combined the
schedule with the BIM Model. The
blue represents shoring, although one
day we hope to replace this with
actual shoring tables and formwork.
For now, this schedule is just used by
the Project Manager, though the
project managers tend to be
intimidated by the software, and they
don’t use it much if at all. This is due
to several reasons, we believe include:
• Intimidation by seemingly complex
software
• Hardware limitations
• Input limitations; Software (license
costs $6,500)
• No direction from management
24. By failing to prepare, you are preparing to fail.
– Benjamin Franklin
25. Where we are going
Engineering is the logical next step. However, there are several hurdles to tackle before we can do so. Things like catalog creation
and training/hiring capable staff are imperative, costly, and take time. The huge benefit here would be total resource
management, our logistics plan would be more realistic, and we could have a more complete “virtual rehearsal”.
26. Line & Grade
Not yet implemented, providing points
for robotic total station we can
potentially reduce Line & Grade Labor
while simultaneously providing greater
accuracy, speed, and reliability.
BEAM already owns the total stations
needed. We just need to train and
implement to get it going.
Learn more about Autodesk® Point
Layout here
27. Lean Construction
Scheduling (4D)
With Synchro, its very easy to practice
Lean Construction Principles® on all our
jobsites.
1. Two-Week & Six-Week Look Aheads
can easily be communicated even
with tradesman who cannot read
construction drawings.
2. The practice of linking our BIM with
our Construction schedule makes it
necessary to include a “backlog of
ready work”.
3. Seeing upcoming work in context of
surrounding work helps identify
constraints, detail methods for
execution, and identifying pre-
requisites.
4. Using Project Management software
the way it was meant allows for
matching work flow & capacity. 4D BIM helps us quickly define
constraints as identified by the
Lean Construction Institute®
28. 5D BIM +
Scheduling +
Money
This is where the most benefit can be
had.
Currently, we are working on getting
the estimate for Biscayne Beach into
our schedule, this gives us our
baseline cost. We know how many
man hours are required for each
activity, and tracking that, as well as
heavy equipment rentals, rebar
materials/installation etc., can allow us
to see how our project is doing in all
aspects.
However, this is something we are
exploring, and it will most likely
require more staff to implement.