TopicsforDiscussion
•Third-PartyOwnershipofDERsinVirginia
•CleanPowerPlan
•Permitting/CPCNRequirements
•CommunitySolarConsiderations
•CompetitiveBiddingRequirementsforUtility-ScaleProjects
(Self-Buildv.PPAs)
•BiomassConversionProject
•WindPermitbyRule/SolarPermitbyRule
Third-PartyRenewableRetailSalesinVirginia
-Overview:
-WhileVirginiadoesnotprovideawhollycompetitiveenergymarket,optionsexistinVirginiaforalternativeenergysupply.
-ExistingVirginiaStatutes:
oVa.CodeSection§56-577(CompetitiveSupply)
“OnlyindividualretailcustomersofelectricenergywithintheCommonwealth,regardlessofcustomerclass,whosedemandduringthemost
recentcalendaryearexceededfivemegawattsbutdidnotexceedonepercentofthecustomer'sincumbentelectricutility'speakloadduringthe
mostrecentcalendaryearunlesssuchcustomerhadnoncoincidentpeakdemandinexcessof90megawattsincalendaryear2006oranyyear
thereafter,shallbepermittedtopurchaseelectricenergyfromanysupplierofelectricenergylicensedtosellretailelectricenergywithinthe
Commonwealth…”
“…IndividualretailcustomersofelectricenergywithintheCommonwealth,regardlessofcustomerclass,shallbepermitted…topurchase
electricenergyprovided100percentfromrenewableenergyfromanysupplierofelectricenergylicensedtosellretailelectricenergywithinthe
Commonwealth,otherthananyincumbentelectricutilitythatisnottheincumbentelectricutilityservingtheexclusiveserviceterritoryinwhich
suchacustomerislocated,iftheincumbentelectricutilityservingtheexclusiveserviceterritorydoesnotofferanapprovedtariffforelectric
energyprovided100percentfromrenewableenergy...”
oVa.CodeSection56-594(NetMetering)
Legislativeupdate(July1,2015):Increasedfrom500kWhto1MW,themaximumgeneratingcapacityofanelectricalgeneratingfacilityowned
oroperatedbyanelectricutility’snonresidentialcustomerthatmaybeeligibletoparticipateintheutility’snetmeteringprogram.
“Eligiblecustomer-generator”meansacustomerthatownsandoperates,orcontractswithotherpersonstoown,operate,orboth,an
electricalgeneratingfacilitythathasacapacityofnotmorethan20kilowattsforresidentialcustomersandnotmorethanone
megawattfornonresidentialcustomersonanelectricalgeneratingfacilityplacedinserviceafterJuly1,2015…”
Third-PartyRenewableRetailSalesinVirginia
-ExistingVirginiaPrograms:
-DominionPilotProgram–AllowsqualifiedcustomerstoenterintoaPowerPurchaseAgreementwithathirdparty
renewableenergysupplier.Theenergysuppliedmustcomefromawindorsolargeneratorlocatedonthecustomer’s
premise.
-TechnologyLimits
-Sizelimits
-Customerlimits
-SCCRegulatoryproceedings
-APCOPPARider(PUE-2015-00040)
-2016Legislation:
-HouseBillNo.1286wasintroducedonJanuary20,2016.
-Theproposedchangesprovideconsumersfullaccesstothirdpartyownedfinancingforon-siterenewableenergy,
andeliminatesbarrierstomatchingon-sitegenerationwithon-sitedemand.
-TheBillprovidesthesameaccesstofinancingasfoundin23otherstates.
-TheBilldoesnotimpacttheexistingeconomicsorvaluefortheconsumerorfortheutility.
-TheBillalsodoesNOTimpacttheutilities’operationsorinterconnectionproceduresinexistingstatutesand
regulations.
Third-PartyRenewableRetailSalesinVirginia
-2016DriversofThirdPartySales:
-UserGroupRFP’s:
-CouncilofIndependentCollegesinVirginia’sRFP:
-IssuedNovember16,2015,responsesdueJanuary22,2016.
-Goalofinstalling30MWofdistributedsolargenerationby2020atthecampusesofsomeofitsmembercolleges.
-ITCExtension:
-OnDecember18,2015,CongresspassedanextensionoftheSolarInvestmentTaxCredit.
-Extendsthe30%ITCforbothresidentialandcommercialprojectsthroughtheendof2019;dropsthecreditto26%in
2020;dropsto22%in2021;dropspermanentlyto10%forcommercialprojectsand0%forresidentialprojects.
-CleanPowerPlanImplementationinVirginia:
-EmissionsStandardPlanv.StateMeasuresPlan
-EmissionsStandardPlan:BasedonthesourceperformancestandardestablishedinthefinalEPAruleforaffectedcoal
andnaturalgasunits.Renewableenergycouldsupplement.
-StateMeasuresPlan:RelyonstateadoptedorsupportedmechanismssuchasRPSand/orenergyefficiencystandards
tomeetthestategoal.
GuidelinesRegardingNoticeInformationfora
ThirdPartyPPA
OnMarch14,2013,theVirginiaGeneralAssemblyapprovedChapter382
requiringtheVirginiaStateCorporationCommissiontoconductarenewable
energypilotprogramforthird-partypowerpurchaseagreementsandto
establishcertainguidelinesregardingitsimplementation.
PURPOSE
SCCmustestablishguidelinesconcerning(i)informationtobeprovidedin
writtennoticesand(ii)proceduresforcollectingandpostinginformation
derivedfromsuchnoticestotheCommission’swebsite.
APPLICABILITY
Applicabletoanyowneroroperatorofasolar-poweredorwind-powdered
electricgenerationfacilitylocatedonpremisesownedorleasedbyaneligible
customer-generator.Suchafacilityshallhavegenerationcapacityof50kWto
1MW.Aneligiblefacilityshallprovideelectricitytoonlyonecustomer.
Theowner-operatorshallbepermittedtoselltheelectricitygeneratedfrom
suchfacilityexclusivelytosucheligiblecustomer-generatorunderapower
purchaseagreementtoprovidesucheligiblecustomer-generatorthird-party
financingofthecostsofsucharenewablegenerationfacility.
Thepilotprogramislimitedto50MW.
GuidelinesRegardingNoticeInformationfora
ThirdPartyPPA(cont’d)
CONTENTSOFFILING
Theowner-operatorshallprovidewrittennoticetotheCommissionandthePilot
Utilitynotlessthan30calendardaysbeforetheeffectivedateofsuchagreement
andshallinclude,butnotbelimitedto,thefollowinginformation:
Identityofowner-operatoroftherenewableelectricgenerationfacility;
Thename,address,andundersealas“confidential”or“extraordinarily
sensitive”information,thePilotUtilityelectricaccountnumberofthe
eligiblecustomer-generator;
Locationofthepremise(s)uponwhichtherenewableelectricgeneration
facilitywillbeinstalled;
Renewablesourceoftheelectricgenerationfacility;
Generationcapacityoftherenewableelectricgenerationfacility
expressedtintermsofkWsavailablefordeliverytotheend-under
statedinalternatingcurrent(AC);
Expecteddatethattheelectricgenerationfacilitywillbeplacedin
service(“placedinservice”accordingto26U.S.C.§48)
GuidelinesRegardingNoticeInformationfora
ThirdPartyPPA(cont’d)
POSTINGANDTRACKINGVIASCCWEBSITE
PROGRAMCAPMANAGEMENT
TheCommissionbeganreviewofthepilotprogramin2015andwillcontinueeverytwoyears
thereafter.
Currently,thepilotisavailableonlyinDominion’sserviceterritory.
DOMINIONPPAsUNDERCURRENTPROGRAM
Since2013,notasinglefacilityhasgoneonline.Thereareseveralprojectsinthequeue.
VASCCCaseNo.PUE-2011-00107PetitionforDeclaratoryJudgment
GuidelinesRegardingNoticeInformationfora
ThirdPartyPPA(cont’d)
Virginia:Proposedv.FinalTargetRates
(poundspermegawatt-hour)
884
810
1047
934
0
200
400
600
800
1000
1200
InterimAverage(Pre-2030)Final(2030)
Proposed
Final
Virginia:Proposedv.FinalMassLimits(milliontons,
existingunitsonly)
22.8
20.9
29.5
27.4
0
5
10
15
20
25
30
35
InterimAverage(Pre-2030)Final(2030)
Proposed
Final
Rate-BasedOptions
National
Subcategory
EmissionRates
•Coal:
1,6071,305
•Gas:
877771
(2022)(2030)
StateEmission
Rates
•VirginiaCoal
andGas:
1,120934
(2022)(2030)
VariedEmission
RatesAmongUnits
•Overall,theState
muststillachieve
equivalentof
eitherthestate
ornational
subcategory
rates
Mass-BasedOptions
ExistingVirginia
UnitsOnly
•VirginiaCoal
andGas:
31.3million
(2022)
27.4million
(2030)
•Less“leakage”
adjustment
ExistingandNew
VirginiaUnits
•Bringinginnew
unitswould
increase
Virginia’smass
limitbyless
than0.5million
“complement”
StateMeasures
•Mustachieve
EPA’slimits;but,
todoso,canuse
measures
implemented
andenforceable
onlyunderstate
law
CPP-SixComplianceOptions
Rate-Based(Intensity)Compliance#CO2/MWh
1.Stateaverageemissionsperformancerate(VA=934#/MWh)
2.Subcategorizedperformancerates(dualrate)TradingReady
771#/MWhgasCCunits
1305#/MWhsteamunits(coal,gasboiler,heavyoil)
3.Uniqueemissionperformancerates(nottoexceedstatelimit)
Mass-BasedComplianceTonCap
1.EmissionsCap(existingunitsonly)TradingReady
Leakage
2.EmissionCap(allunits)TradingReady
IncludesnewCCs
Approx1.4%increaseintotalcap(notperyearbuttotalentireperiod)
3.Statemeasuredapproach(uniqueapproach)
CPP-VirginiaBestComplianceOptions
Rate-Based(Intensity)Compliance(#CO2/MWh)
Subcategorizednationalperformancerates(dualrate)
AllowsforgrowthwithinVirginia
Tradingready
CanearnGasShiftERCs
BeneficialtoRenewableGeneratorsandEnergyEfficiency
Helpspreserveoptionofnewnuclear
Stakeholderscanplan
Implementation:EM&Vandunittracking
Mass-BasedCompliance(TonCap)
EmissionsCap:existingunitsonly
AllowsforgrowthwithinVirginia
Tradingready
CanearnGasShiftAllowances(assumingsetaside)
Implementation:LessEM&VbutSetAsidesandLeakage
CPP-VirginiaBestComplianceOptions
Arate-basedapproachmaybebetterforeconomic
growth,betterforpromotingrenewablesandenergy
efficiency,andbetterforcustomersandVA'seconomy.
CurrentlyworkingaspartofastakeholderteamwithDEQ
whoisevaluatingalloptions.Thismaychangeoncethefinal
tradingrulesareknown.Anystate’spreferencewill
dependonmanyfactors,includinggeneratingmix.
Dominion’sIRPofferedleast-cost“non-complaint”planthatreliedsolelyonnaturalgas-
firedgeneration,aswellasfouralternateresourceplans–eachdesignedtocomplywiththe
CleanPowerPlan–whichsomecalltheCarbonRule.
Asoftheendoflastyear,Dominionhadsolarfacilitiesinserviceinsevenstates–from
CaliforniatoConnecticut–withmoreindevelopment.
Alltold,Dominionexpectstoinvestabout$3billioninvarioussolarprojects–inVirginia
andbeyond–with$700millionslatedforprojectsthatwillgeneratepowerforitscustomers.
Planscallfordevelopingmultiple,large-scalesolarprojectstotaling400megawattsof
generatingcapacity.Theseprojectsshouldbeoperationalby2020andbecapableof
producingenoughpowertosupplyabout100,000homes.
CPP-VirginiaBestComplianceOptions
162
VirginiaLegislation–
•Chapter771ofthe2011VirginiaActsofAssembly
•Chapter382ofthe2013VirginiaActsofAssembly
•Chapters431and432ofthe2015VirginiaActsof
Assembly
RenewableDistributedEnergy
163
VirginiaStateCorporationCommissionDockets–
•PUE-2011-00117:DVPDGSolarPartnershipProgram
•PUE-2012-00064:DVPDGSolarPurchaseProgram
•PUE-2012-00142:DVPRenewableGenerationPilotProgram
•PUE-2013-00045:3rdPartyRenewableGenerationPPAPilot
Program
•PUE-2015-00005:DVPDCSPilotProgram
•PUE-2015-00006:DVPRemingtonSolarCPCN
•PUE-2015-00040:APCoRenewableGenerationPilotProgram
•PUE-2015-00057:AmendedNetMeteringRules
•PUE-2015-00104:DVPSolarProjectsCPCN
RenewableDistributedEnergy
CommunitySolarConsiderations
-OverviewofCommunitySolar:
-Anarrangementwhichallowsnumerouscustomerstoinvestinonesolarprojectandsharethebenefits
(powerand/orfinancial)inreturn.Communitysolarallowsaccesstosolarenergybycustomerswhomay
otherwiselacksufficientcapitaltoinstalltheirownsolarprojectsorwhosepropertymaybeunsuitablefor
solarinstallation.
-Models:
-UtilitySponsoredModel:autilityprovidestheircustomerswiththeoptionofpurchasingrenewableenergy
fromasharedgeneratingfacility.
-On-BillCrediting:asharedgeneratingfacilityenablescustomerstoinvestinaportionofthesolarfacilityand
receiveacreditforthatportionoftheenergyproductionfromthesolarfacilityontheirutilitybill.
-SPEModel:customerscreateabusinessentitytodevelopasharedsolarfacility.
CommunitySolarConsiderations
-Minnesota’sCommunitySolarProgram:
-Enactedin2005,andsubsequentlyamended,theCommunity-BasedEnergyDevelopment(C-BED)Tariff(Minn.Stat.
§216B.1612)providesthatatariffistobeestablishedto“optimizelocal,regional,andstatebenefitsfromrenewable
energydevelopmentandtofacilitatewidespreaddevelopmentofcommunity-basedrenewnableenergyprojects
throughoutMinnesota.”
-TheC-BEDTariffprovidesthateachpublicutilityinMinnesotaisrequiredtofilewiththeMinnesotaPublicUtilities
Commissiontocreatea20-yearpowerpurchaseagreementforcommunity-ownedrenewableenergyprojects.
-TheC-BEDtariffratemustbehigherinthefirst10yearsofthePPAthanthefinal10years.
-2009legislationrequiresallutilitiestofilestandardcontractswiththeCommissionforthepurchaseofelectricityfrom
projectswitharatedcapacityof5MWorless.
-Inorderforarenewableenergyprojecttobeconsideredcommunity-basedandeligibleforC-BEDtariffs:
-(1)51%oftherevenuesfromthePPAmustflowtoMinnesota-basedownersandotherqualifyinglocalentities;
-(2)nosinglewindprojectinvestorcanownmorethan15%ofaprojectconsistingoftwoormorewindturbines,exceptforlocal
governmentswhichmaybethesoleownersofcommunity-basedprojects;
-(3)theprojectmusthavearesolutionofsupportadoptedbythecountyboardofeachcountyinwhichtheprojectistobelocated,
orinthecaseofaprojectlocatedwithintheboundariesofareservation,thetribalcouncilforthatreservation;and
-(4)allownersofpropertytraversedbytransmissionlinesservingtheprojectmustbegiventheopportunitytoinvest.
-[AsofSeptember2011,266.30MWofC-BEDprojectshadbeencompleted.]
CommunitySolarConsiderations
-NewYork’sCommunitySolarProgram:
-AspartoftheNYSUNInitiative,aimedatstimulatingNewYork’ssolarmarket,theNewYorkPublicService
CommissionintroducedtheNY-SUNIncentiveProgramtohelpreducethecostsofinstallingsolarsystemsin
NewYork.
-Aspartofsuchefforts,theNYCommissionrecentlylaunchedCommunitySolarNY,aprogramwhichseeks
tomakesolareasierandmoreaffordablethroughcommunity-driveninitiatives.Moreparticularly,the
SharedRenewablesinitiative(alsoknownasCommunityDistributedGenerationorCommunityDG)provides
opportunitiesforcustomerstoparticipatedirectlyinoff-siterenewableprojectsthroughnetmetering.
-CommunityDGwasenabledbytheNYCommissionthroughitsJuly2015Order(Case15-E-0082).
-Phase1ofCommunityDGbeganonOctober19,2015andallowsprojectstointerconnectifthey:
-ArelocatedinthenewCommunityDGOpportunityZonesdesignedbytheutilities;or
-Includelow-incomeresidentialcustomers,definedasacustomerparticipatinginaStateorutilityenergyassistance
program,asatleast20%oftheprojectmembership.
-CommunityDGprojectsmayinterconnectstatewidebeginningonMay1,2016.
CommunitySolarConsiderations
-NewYork’sCommunitySolarProgram,continued:
-Eachprojectmusthaveasponsor,whoownsoroperatestheproject,organizesthemembershipandcollaborates
withtheutility.
-Thesponsorwillprovidetheutilitywithalistofthemembersandtheirpercentallocationoftheproject’snet
meteringcreditspriortointerconnection.
-Eachprojectmusthaveatleast10members,andeachmembermustbeallocatedatleast1,000kWhperyear(not
toexceedtheirhistoricaverageannualconsumption);provided,however,nomorethan40%oftheCommunityDG
host’sexcessgenerationmayservememberswithanaveragemonthlypeakdemandof25kWorgreater.
-ThetermsoftheCommunityDGmembership(e.g.,paymentstructure)aregovernedbytheagreementbetweenthe
sponsorandmembers.
-Netmeteringcreditsareallocatedtomemberseachmonthbasedonthepercentageprovidedtotheutilitybythe
sponsor.
Diagram:file:///C:/Users/bwortham/Downloads/Community-
Distributed-Generation-Project-Developers.pdf
CommunitySolarConsiderations
-Virginia’s2016CommunitySolarLegislation:
-HouseBillNo.1285wasintroducedonJanuary20,2016.
-Authorizesinvestor-ownedelectricutilitiesandelectriccooperativestoestablishacommunityenergyprogram.
-Asubscriberacquiresasubscriptionthatentitlesthemtoaproportionalinterestinarenewableenergygenerationfacility
andtheyreceivesacreditontheirelectricutilitybill.
-SolarCo-OpsinVirginia:
-Asolarco-opisagroupofhomeownersinadefinedgeographicareawhousetheircombinedbulkbuyingpowertoreceive
discountsonthehomeowner’sindividualpurchaseofasolarsystemfortheirresidence.Theco-opgroupwillputoutarequest
forproposalsfromsolarinstallers.Eachbidfromthesolarinstallerwillcontainasetpricepertheamountofsolartheinstaller
wouldinstallontheindividualresidence’shome.Inotherwords,thisallowstheinstallerstomakeindividualizedproposalsto
eachoftheco-opmembers.Theco-opmemberswillselectaninstallertoinstallthesystemsoneachofthehomes,pursuant
towhicheachmemberwillenterintotheirowncontractwiththeinstaller.Inaddition,co-opmembershavethebenefitof
workingwithagrouptopooleducationandguidancethroughouttheinstallationprocess.
-Examples:
-RichmondSolarCo-Op
-MassanuttenSolarCo-Op
-RockbridgeAreaSolarCo-Op
CompetitiveBiddingRequirementsforUtility-ScaleProjects
-ExistingStatutoryRequirementstoAssessThird-PartyAlternatives:
-Va.Code§56-585.1A6
-Va.Code§56-585.1D
-What’shappenedrecently?
-Dominion’s2015SolarRFP
-ODECSolarRFP
-Recentregulatoryproceedings?
-RemingtonCase(PUE-2015-00006)
-NewCPCNfilings(PUE-2015-00104)
-WholesalePPAactivityinVirginia
-Amazon’sfacilityinAccomackCounty
-Clusterofprojects(250,000solarpanels)overapproximately900acresinAccomackCounty
-80MW(AC)enoughtopower15,000homesayear(representsmorethan5timesofallthesolarenergycurrentlyinstalledin
theCommonwealth)
-AmazontopurchasetheenergygeneratedfromthefacilityaspartofAmazon’splantouserenewableenergyforallits
infrastructure,includingmanydatacentersinNorthernVA
-TobecompletedbyOctober2016
Biomass
SUMMARY
InJune2011,DominionfiledwiththeSCCanapplicationtoamendandreissue
certificatesofpublicconvenienceandnecessityforapprovaltoconvertthreeelectric
coal-firedgenerationfacilitiesintobiomass-burningfacilities.Theconversionwould
decreasethenetcapacityratingforeachfacilityfrom63MWto51MW,but
increaseexpectedenergyproduction.
TheestimatedconstructioncostoftheConversionsisapproximately$165.8million,
excludingfinancingcosts.Pursuantto§56-585.1A6oftheCodeofthe
Commission’sRulesGoverningUtilityRateApplicationsandAnnualInformational
Filings,theCompanyseeksapprovalofarateadjustmentclause,designatedRider
B,fortherecoveryofcostsassociatedwiththeConversions.
Altavista,Hopewell,andSouthamptonPowerStationwereconventionalsteam
unitswithcoalstokerboilersandassociatedequipment.Thestationswere
convertedtoburnvirginbiomass,requiringmajorconversions:
Thestationfuelhandlingequipmentwaschangedoutinitsentiretyto
accommodatethedelivery,processing,anddistributionoffueltothe
boilerstobeburned.
Combustionsystemsandcomponentswerechanged/convertedto
accommodatethenewfuel.
AltavistabecameoperationalJuly12,2013,HopewellOctober18,2013,and
SouthamptonNovember28,2013.Postcommissioning,Dominioncontinuesto
identify,analyze,andresolveissuestooptimizeoperationofthesefacilities.
Biomass(cont’d)
ParallelGeneration:
InterconnectionwiththeGrid
ParallelGenerationwiththeGrid
•UtilityConsiderations
–Safety
–Reliabilityofthegridforallcustomers
–Gridmodificationsneededtoaccommodategenerator
interconnection
•RegulatedInterconnectionProcedures
–Chapter314oftheVirginiaAdministrativeCode
(distributionvoltage)
–PJMOpenAccessTransmissionTariff(transmission
voltage)
HighLevelViewofInterconnectProcess
Chapter314&PJM
-135BusinessDays
Multiplestudiesmayberequired
•CompletedRequest
Form
•ProofofSite
Control
•Fee/Deposit
•Reviewapplication
•Discusspotential
scope
•Determinescope,
protection
requirements,cost
estimatesand
constructiontime
estimates
•Interconnection
Agreementexecution
•Paymentofcharges
•Constructionofrequired
utilityupgrades
•Utilitywitnessingof
OperationalTeststo
enableoperationof
generationfacility
ApproximateTimeFrames(inmonths)
Interconnectionrequesttoexecutionofagreement7-12
Construction(dependingonrequirements
determinedbystudies)
9-24
Totaltimefromrequesttocompletion16-36
Generator
Interconnect
Request&
Analysis
Customer
Meeting
StudyAgreement
Execution&
Payment
Constructionof
Interconnection
Facilities
InterconnectionandNetMetering
-ExistingRegulations:
-20VAC-5-315(NetMeteredSystems)
-TimingandNoticeissues
-20VAC5-314(Non-NetMeteredSystems)
-TimingandNoticeissues
-2016Legislation:
-HouseBillNo.1286wasintroducedonJanuary20,2016.
-WouldcreatenewNet-Meteringclassificationof“eligiblemulti-metercustomer-generator.”
-Facilitatenetmeteringforcustomerswithmultiplemetersthatarelocatedatseparatebutcontiguoussites
toaggregateinasingleaccountfornetmeteringpurposes.
WindPermitbyRule/SolarPermitbyRule
-VADEQPermitbyRuleOverview:
-TheVirginiaDepartmentofEnvironmentalQuality(“DEQ”)wasinstructedbytheVirginiaGeneralAssemblytodeveloppermitbyrule
(“PBR”)regulationstoimplementVirginia’s2009“SmallRenewableEnergyProjects”legislation(Va.Code§10.1-1197.6).
-ThestatutemovedauthorityfromtheStateCorporationCommission(“SCC”)toDEQoverprotectionofnaturalresources(specifically
wildlifeandhistoricresources)withrespecttorenewableenergyprojects.
-DEQhasjurisdictiontoapprovePBRapplicationsforsolarprojectswitharatedcapacityof100megawattsorless,whiletheSCCretains
jurisdictionforprojectswitharatedcapacityover100megawatts(i.e.alternativetoCPCNprocess).
-Procedure:
-9VAC15-60setsforththeprocedureandrequirementsforanowneroroperatorofasmallsolarenergyprojecttoapply
foraPBR.
-Theregulationprovides14basicapplicationrequirements.
-Thesecriteriaincluderequirementssuchascertificationbythegoverningbodyofthelocalitywheretheprojectwillbelocatedthat
theprojectcomplieswithallapplicablelanduseordinances,acopyofthefinalinterconnectionagreement,acertificationsignedby
aprofessionalengineerlicensedinVirginiathatthemaximumgenerationcapacityoftheprojectdoesnotexceed100megawatts,an
analysisofthebeneficialandadverseimpactsoftheproposedprojectonnaturalresources,acertificationthattheapplicanthas
appliedforallnecessaryenvironmentalpermits,etc.
-Theregulationsfurtherprovidethatwithin90daysofreceivingalloftherequireddocumentsandtheappropriatefee,
DEQshalldetermine(afterconsultationwithotheragenciesintheSecretariatofNaturalResources)whetherthe
applicationiscompleteandwhetheritmeetstherequirementsoftheregulations.IfDEQdeterminesthatitdoes,then
DEQ“shallnotifytheapplicantinwritingthatheisauthorizedtoconstructandoperateasmallsolarenergyproject.”
WindPermitbyRule/SolarPermitbyRule
-DEQ’sOverviewofProcedure:
-RecentExample:Amazon’sFacilityinAccomackCounty
-Timing
-FinalPermit

More Related Content

Viewers also liked (8)

Science Sources of Energy
Science Sources of Energy Science Sources of Energy
Science Sources of Energy
 
Sources of Energy
Sources of EnergySources of Energy
Sources of Energy
 
WASTE TO ENERGY
WASTE TO ENERGYWASTE TO ENERGY
WASTE TO ENERGY
 
Renewable Energy Resources
Renewable Energy ResourcesRenewable Energy Resources
Renewable Energy Resources
 
Renewable Energy Resourses
Renewable Energy ResoursesRenewable Energy Resourses
Renewable Energy Resourses
 
Renewable non-renewable-energy-resources
Renewable non-renewable-energy-resourcesRenewable non-renewable-energy-resources
Renewable non-renewable-energy-resources
 
Renewable Energy Power Point
Renewable Energy Power PointRenewable Energy Power Point
Renewable Energy Power Point
 
Renewable Energy Sources
Renewable Energy SourcesRenewable Energy Sources
Renewable Energy Sources
 

Similar to Raleigh Slides

A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...
A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...
A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...
Jill Kirkpatrick
 
Electricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docxElectricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docx
toltonkendal
 
Electricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docxElectricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docx
gidmanmary
 

Similar to Raleigh Slides (9)

New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
 
Hawaii Microgrid Solutions Update.pdf
Hawaii Microgrid Solutions Update.pdfHawaii Microgrid Solutions Update.pdf
Hawaii Microgrid Solutions Update.pdf
 
Trail By Fire: Rana Plaza and Transnational Legal Orders
Trail By Fire: Rana Plaza and Transnational Legal Orders Trail By Fire: Rana Plaza and Transnational Legal Orders
Trail By Fire: Rana Plaza and Transnational Legal Orders
 
Increasing Friction in Jurisdiction: Interplay Between State Subsidies and th...
Increasing Friction in Jurisdiction: Interplay Between State Subsidies and th...Increasing Friction in Jurisdiction: Interplay Between State Subsidies and th...
Increasing Friction in Jurisdiction: Interplay Between State Subsidies and th...
 
A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...
A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...
A World Full of Possibilities: Integrating DERs into Wholesale Markets – Outl...
 
Community Microgrids: A resilient clean energy solution for cities
Community Microgrids: A resilient clean energy solution for citiesCommunity Microgrids: A resilient clean energy solution for cities
Community Microgrids: A resilient clean energy solution for cities
 
Electricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docxElectricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docx
 
Electricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docxElectricity Restructuringand Competition.docx
Electricity Restructuringand Competition.docx
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power Policy
 

Raleigh Slides