1. TIME DELAY DETERMINATION SUMMARY
PROJECT : CASH CENTRE BUILDING BRANCH 11304
CONSULTANT: CONSULTING
CONTRACTOR :
APPROVED BL
FINISH DATE Total float
Approved BL
wt/ float
FINISH DATE
ACTUAL FINISH
DATE
CRITICAL DELAY
IMPACT
CONTRACTOR
RESP. JUSTIFIED DELAY
1 BOUNDARY RELOCATION FOR THE INTIRE LOT 4/7/13 0 4/7/13 6/30/2013 84 N/A 84
ACTUAL NOT AS PER THE
DOCUMENTS GIVEN BY
THE CLIENT
2
RESOLVED CONFLICT TO CCB FOUNDATION AGAINST OPERATION
BLDG RET. WALL BASEMENT
4/14/13 0 4/14/13 8/27/2013 135 N/A 135
RET.WALL BASEMENT
AFFECTED THE
FOUNDATION OF CCB GRID
A
3 STRUCTURAL WORK 1/0/00 0 1/0/00 1/0/1900 0 N/A 0
4
MAIN BUILDING SUB STRUCTURE FOUNDATION
10/27/13 105 2/9/14 8/30/14 202 N/A 202
DELAY CAUSE BY THE
CONFLICT OF
FOUNDATION
S/N
BASELINE & ACTUAL DATES
NOTES
DELAY IMPACT ANALYSIS
SCECO ACTIVITY IMPACTED TIME DELAY SCHEDULE
ACTIVITIES
5
GROUND FLOOR STRUCTURAL
12/3/13 105 3/18/14 9/10/14 176 N/A 176
DELAY CAUSE BY THE
CONFLICT OF
FOUNDATION
6
FIRST FLOOR STRUCTURAL
2/4/14 105 5/20/14 9/22/14 125 N/A 125
DELAY CAUSE BY THE
CONFLICT OF
FOUNDATION
7
PENTHOUSE STRUCTURAL
3/2/14 92 6/2/14 10/8/14 128 N/A 128
DELAY CAUSE BY THE
CONFLICT OF
FOUNDATION
8 ARCHITECTURAL WORK 60 0
9 APPROVAL OF FINISHING 1/7/14 92 4/9/14 4/7/2015 363 N/A 363
CLIENT DELAY OF FINAL
APPROVAL.
10 ELECTROMECHANICAL WORKS 1/21/14 0 1/21/14 9/24/14 246 N/A 0
11 LOW CURRENT SYSTEM 7/21/14 72 10/1/14 10/15/14 14 N/A 14
NEW CLIENT
REQUIREMENTS
12
13
TOTAL DELAY AS affected 0 11/1/14 4/7/2015 157 DAYS