SlideShare una empresa de Scribd logo
1 de 47
Descargar para leer sin conexión
TSX: FM; LSE: FQM
May 2014
2
Cautionary Note Regarding Forward-Looking Statement
Some of the statements contained in the following material are
forward-looking statements and not statement of facts. Such
statements are based on the current beliefs of management, as
well as assumptions based on management information currently
available.
Forward-looking statements are subject to various risks,
uncertainties and other factors that could cause actual results to
differ materially from expected results.
Readers must rely on their own evaluation of these uncertainties.
Note: all dollar amounts in US dollars unless otherwise indicated
3
First Quantum Minerals – At a Glance
• A Global Company
– Operations and projects in 8 countries
• High-Quality, Stable, Efficient Operations
– 7 operations
– 2013 production:
 copper 412,281 tonnes
 nickel 47,066 tonnes
 gold 248,078 ounces
– Cash cost of production
 copper $1.30/lb; nickel $5.02/lb
• Strong Liquidity & Cash Flow
– Cash at March 31’14 = $747.2M
– Cash from operations = $370.1M
– Available & undrawn facilities of $1.3B
– Senior Notes = $850M
• Industry-Leading Growth
– 5 major projects under development
– Production capacities to rise to 1.1
Mtpa for copper and 110 ktpa for nickel
by 2018
• Unique Core Strength
– In-house project development team
– Delivered projects at an average of 40%
of the industry’s average capital per
tonne of capacity
• Strong Track Record
– Delivered over $2.4B in projects within
6% of budget
– Returned a compounded annual gain of
over 30% since listing
4
2013 – A Transformative Year
 Successfully acquired Inmet Mining Corporation
– Control of the Tier 1 Cobre Panama copper project
– Added 3 well-run, low-cost operations
 Restructured financing and capital structure
 Advanced projects under development
 Record production at Flagship Kansanshi mine;
Las Cruces; Guelb Moghrein; and Ravensthorpe
Main Areas of Focus
6
Cobre Panama – A Tier 1 Copper Project
• Acquired March 2013
• Critical review following acquisition
– Focused mainly on Engineering,
Contracts and Construction initially
– Copied major areas of the design of the
almost-complete Sentinel process plant
• Made significant changes
– Unwound ~US$1.7B of commitments
– Rectified multiple deficiencies
– Readied the site for construction
– Connected mine site to port site
– Changed to an in-house, self-perform
arrangement
7
Cobre Panama – A Tier 1 Copper Project
• A larger, more robust project
– Installed capacity Yrs 1-10 = ~70 Mtpa
 17% higher than prior
 Expansion up to 100 Mtpa beyond
Yr 10
– Average annual LOM* copper production
of 320,000 tonnes
 ~ 20% higher than prior
– Average annual LOM by-product
production
 100,000 ounces gold; 1,800,000 ounces
silver and 3,500 tonnes molybdenum
• Mine life of 34 years
* On the basis of the current Resource estimate and the planned installed capacity of about 70 Mtpa
8
Cobre Panama – A Tier 1 Copper Project
• Capex estimate of $6.4 billion
– inclusive of $913 million incurred prior
to acquisition
• Capital per installed tonne of capacity of
$17,125
– ~25% lower than prior
• A realistic and well-defined timeframe
– 230 KV overland power line – Q4 ’15
– 300 MW powerstation – Q1 ‘17
– Tailings management facility – Q2 ’17
– Process plant construction – Q3 ‘17
– Commissioning & 1st concentrate
production – Q4 ‘17
9
COBRE PANAMA PROJECT – PROCESS PLANT SITE EARTHWORKS
10
COBRE PANAMA PROJECT – MILL PAD EARTHWORKS
11
COBRE PANAMA PROJECT – PROCESS PLANT STOCKPILE PAD
12
COBRE PANAMA PROJECT – POWER STATION AREA
13
COBRE PANAMA PROJECT – BREAKWATER AND MATERIAL OFFLOADING
FACILITY
14
Advanced Projects
Copper Smelter Complex, Zambia
• Phase 1
– Processing capacity of 1.2 Mtpa
– Combination of concentrate
from Kansanshi & Sentinel
– Average copper grade 26%
• Copper production 300,000 Tpa;
acid production 1.0 Mtpa
• Commissioning from 2H2014
• Estimated savings:
– US$340M - US$510M/year
• Phase 2 being planned to increase processing
capacity to between 2 to 2.4 Mtpa in 2017
15
Phase 1 Smelter - Overview
16
Phase 1 Smelter – Cold Box Lifts – April 2014
17
Advanced Projects
Sentinel, Zambia
• Located ~ 140 km northwest of
Solwezi, northern Zambia
• M&I resource of 1,027 Mt at 0.51% Cu
grade, containing 5.2 Mt Cu
• Estimates:
– 2.2:1 LOM strip ratio
– >15 years mine life
– Annual production up to 300,000
tonnes
– US$2.0B capex (incl. Enterprise nickel
project)
– Completion targeted for mid-2014
• Includes 4 Mtpa nickel facility; flexibility
to augment copper capacity
18
Sentinel Cu project, Zambia
• 55 Mtpa target throughput
• 3 semi-mobile in pit crushers and assembly
of large scale mining equipment
• Largest operating SAG/Ball mill trains in
the world (100MW milling power)
• 265,000t of freight = 14,500 truckloads
of materials
• 2 rivers to be dammed/diverted
• Life of mine TSF
• 600 km of 330kV power transmission lines from
Lumwana – Kalumbila – Lusaka West
• 690 staff houses plus 590 houses in resettlement
• Development of a new town, airport, clinic, school etc….
Advanced Projects
19
Sentinel – 80 Meter Feed Shuttle Conveyor Truss - April 2014
20
Sentinel – 80 Meter Feed Shuttle Conveyor Truss - April 2014
21
Advanced Projects – Sentinel
100MW Milling – 2 x 40’SAG Mills + 2 x 28’Ball Mills
22
SPORTS FACILITY 04-NOV-2013
TRIDENT PREPARATORY SCHOOL 05-NOV-2013
SENIOR HOUSING - SINGLES 31-MAR-2013
SENIOR HOUSING AREA 28-FEB-2013
Advanced Projects – Sentinel Senior Housing
23
TRUST SCHOOL 05-NOV-2013
AFFORDABLE HOUSING LAYOUT TEACHER’S HOME 3-JAN-2014
COMPLETED 4-BEDROOM HOUSE 3-JAN-2014
Advanced Projects – Sentinel Affordable Housing
24
Optimized Capital Structure & Financial Flexibility
 Refinanced the short-term US$2.5B revolver at FQM (Akubra) with a $1.2 billion Term Loan
Facility five-year Term and and a $1.8 billion Revolving Credit Facility
 Exchanged the FQM (Akubra) Inc. US$1.49B 8.75% 2020 and US$500M 7.50% 2021 notes
for new 6.75% 6-year notes and new 7.00% 7-year notes
 In conjunction with the Exchange Offer, made covenant changes to better match the
Company's needs going forward
 Made certain amendments to the existing indentures of the US$350M 7.25% Senior Notes
due 2019 through a consent solicitation offer to bondholders
 Retired the project financing at Kevitsa and Kansanshi and put in place a $350M unsecured
facility at Kansanshi
 Launched Senior Notes Offering - original amount of $650M increased to $850M on strong
response
25
Illustrative Pro Forma Corporate Structure Chart
As at March 31, 2014
One of the Few Mining Companies
Investing in Building Capacity
27
Current State of the Copper Industry
• EXPLORATION
–Majors have cut back on exploration and juniors are mainly un-financeable
–It takes 12-15 years to get from discovery to production
• BROWN FIELD EXPANSIONS
–Should be lower capital intensity but are not
–Capital projects cancelled or deferred from shareholder pressure
• GREENFIELD PROJECTS
–High capital intensity
–Capital projects cancelled or deferred as above
–Very poor track record of developing projects efficiently
A Small Copper Surplus Now, But…..
28
Current State of the Copper Industry
Results in a Looming Deficit
29
Lack of Supply Response to Price Was Staggering Over 2006-2012 Period
Global copper mine supply growth and price
0%
0%
1%
0%
-1%
7%
9%
4%
7%
5%
4%
3%
-1%
1%
7%
2% 2%
3%
1%
2%
0%
0%
3%
7%
-2%
0%
2%
4%
6%
8%
10%
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
Copperminesupplygrowth%YoY
0
50
100
150
200
250
300
350
400
Copperprice,cents/lb
Mine supply growth Price
Source: Wood Mackenzie, Macquarie Research, February 2014
30
So The Seeds of The Next Copper Price Bubble are Already Sown
AND it is Coming Soon
• Pressure from shareholders who have a much shorter time horizon than miners
This is not going to change
• There is not much out there that the majors want
With the cut-back in exploration, this is unlikely to change
• The capital intensity of new projects is rising rapidly
Why is this so?
So why is the industry cutting investment?
31
Why is Capital Intensity Rising?
• Falling grades
• Difficult geographies
• Geopolitics
Source: Brook Hunt, Freeport McMoRan
Average Copper Grades
32
Source: Wood Mackenzie, CRU, Macquarie Research, February 2014
Weighted average copper project by year of delivery
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 5000 10000 15000 20000 25000 30000 35000 40000
Life of mine capital intensity
Averageheadgrade
2000-2011
2012-2018f
2000
2001
2002
2004
2005
2006
2007
2008 2009
2010
2011
2012
2013f
2014f
2015f
2016f
2017f
2018f
As Head Grades Fall, Capital Intensity Rises Rapidly
33
0 5,000 10,000 15,000 20,000 25,000 30,000
Kansanshi (First Quantum)
Kansanshi Expansion (First Quantum)
Sentinel (First Quantum)
Buenavista DC (Southern Copper)
Antapaccay (Xstrata)
Antamina (BHP)
Guelb Moghrein (First Quantum)
Canariaco (Candente)
Las Cruces (Inmet)
Los Bronces (Anglo American)
Oyu Tolgoi (Rio Tinto)
Ministro Mina Hales (Codelco)
Sierra Gorda (KGHM)
Toromocho (Chinalco)
Tampakan (Xstrata)
Las Bambas (Xstrata)
Cobre Panama (First Quantum)
Galeno (Minmetals)
But it is Possible to Build Projects Efficiently
Capital Intensity
(US$ / t)
Source: First Quantum, Broker Research
33
A producing First Quantum mine
A current First Quantum project
34
Source: Wood Mackenzie, CRU, Macquarie Research, February 2014
Weighted average copper project by year of delivery
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 5000 10000 15000 20000 25000 30000 35000 40000
Life of mine capital intensity
Averageheadgrade
2000-2011
2012-2018f
2000
2001
2002
2004
2005
2006
2007
2008 2009
2010
2011
2012
2013f
2014f
2015f
2016f
2017f
2018f
COBRE PANAMA
Cobre Panama Has Substantially Lower Capital Intensity Compared to
Other Projects with Similar Start-Up Horizons
35
High-Quality, Stable Operations
36
High-Quality, Stable Operations
Kansanshi Cu-Au mine, Zambia
• Located near Solwezi in the north
western Province of Zambia
• First production in 2005
• Open pit mining
• Flexible ore treatment to allow for
variation in ore type :
– sulphide circuit; oxide circuit; gold
facility
• As at December 31, 2013, the
estimated mine life was ~17 years
• Workforce = ~1,937
37
High-Quality, Stable Operations
Kansanshi Cu-Au mine, Zambia
• Q1 2014
– 71 kt of copper
– 40 kozs of gold
– $1.57/lb copper C1 cash cost
• 2014 outlook
– 255 to 270 kt of copper
– 145 to 160 kozs of gold
• Multi-phase capacity expansion
project
– 2012 – 2017
60% increase in overall production capacity
– 2012 – 2014
130% increase in oxide production capacity
– 2017
90% increase in sulphide production capacity
Expansion
Project Capacity Completion
Estimate
Cost
Production
Impact
(US$M)
Oxide 7.2 Mtpa Complete 34 Copper: 10,000 - 15,000 Tpa
Oxide 14.5 Mtpa Complete 280 Copper: 60,000 - 75,000 Tpa
Sulphide 25 Mtpa 2017 565 Copper: 60,000 - 70,000 Tpa
38
High-Quality, Stable Operations
Guelb Moghrein Cu-Au mine, Mauritania
• 100% ownership
• Located 250 kilometres northeast of
the nation’s capital, Nouakchott
• As at December 31, 2013, the
estimated mine life was ~ 8 years
(including stockpiles) based on current
operations
• First production in 2006
• Workforce = ~1,170
39
High-Quality, Stable Operations
Guelb Moghrein Cu-Au mine, Mauritania
• Q1 ‘14
– 9 kt tonnes of copper
– 14 kozs of gold
– $1.56/lb copper C1 cash cost
• 2014 Outlook
– 36 to 39 kt of copper
– 55 to 60 k ozs of gold
• Magnetite plant project:
– In detailed design stage
– Estimated capex of $50M
– Expected annual production of 1M - 2M tonnes
of 69% Fe magnetite concentrate
– Expected start up in mid-2014
– Expected to extend mine life through retreatment of tailings dam
40
High-Quality, Stable Operations
Ravensthorpe Ni mine, Australia
• Acquired as a decommissioned plant
in 2010
• First production within 20 months
of purchase
• Estimated mine life of 32 years
• Commercial production declared
Dec 2011
• Workforce = ~428
• Q1 ’14
– 9 kt of nickel @ $4.02/lb C1 cash cost
• 2014 Outlook = 33 to 37 kt of nickel
41
High-Quality, Stable Operations
Kevitsa Ni-Cu-PGE mine, Finland
• Built, commissioned and started
commercial operations within
36 months of board approval
• Estimated mine life of 29 years
• Commercial production declared
August 2012
• Workforce = ~337
• Further potential
– Process optimization
– Approval to increase throughput to a
maximum of 10 Mtpa from 5.5 Mtpa
• Q1 ’14 = 4 kt of copper @ $1.52/lb C1 cash cost ; 2 kt of nickel @ $5.19/lb nickel C1 cash cost
• 2014 Outlook = 69 to 72 kt of copper; 9 to 10 kt of nickel
42
High-Quality, Stable Operations
Las Cruces Cu mine, Spain
• Acquired in March 2013
• Estimated mine life of 9 years;
potential for extension
• Current average reserve grade of 5.4%
copper
• Workforce = ~254
• Q1 ’14
– 19 Kt of copper; $0.98/lb copper C1
cash cost
• 2014 Outlook
– 69 to 72 kt of copper
43
High-Quality, Stable Operations
Çayeli Cu-Zn mine, Turkey
• Acquired in March 2013
• Estimated mine life of 6 years with
potential for an additional 3 years
• Average grade of 3.1% copper and
3.6% zinc
• Workforce = ~520 employees
• Q1 ’14
– 7 kt of copper; 10 kt of zinc
– $0.76/lb copper C1 cash cost
• 2014 Outlook
– 27 to 29 kt of copper
– 38 to 42 kt of zinc
44
High-Quality, Stable Operations
Pyhäsalmi Cu-Zn mine, Finland
• Acquired in March 2013
• One of the most efficient underground
mines in the world
• Estimated mine life of 6 years
• Average grade of 1.05% copper and 1.79%
zinc
• Workforce = ~228 employees
• Q1 ’14
– 4 kt of copper; 5 kt of zinc
– $0.52/lb copper C1 cash cost
• 2014 Outlook
– 14 to 15 kt of copper; 21 to 23 kt of zinc
45
Strong Q1 2014 Results
• Production up
– Copper up 43% to 113,118 tonnes
– Nickel up 7% to 11,838 tonnes
– Gold up 8% to 60,164 ounces
– Platinum and palladium up 22% to 15,342 ounces
• Cash cost lowered
– Copper down 9% to $1.38 per pound
– Nickel down 18% to $4.37 per pound
• Comparative net earnings of $126.8 million or $0.22 per share inclusive of:
– $26.7 million or $0.05 per share of unfavorable, recurring acquisition-related adjustments.
– Unfavorable impact of $152 million from lower commodity prices and the build-up in
concentrate inventory at Kansanshi
Copper Production
000’s tonnes
Nickel Production
000’s tonnes
Gold Production
000’s ounces
Copper C1 Cost
US$/lb
Q1 '13Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2 '13 Q3'13 Q4'13 Q1'14
46
Full Year 2014 Guidance
• Production
- Copper between 418,000 - 444,000 tonnes
- Nickel between 42,000 - 47,000 tonnes
- Gold between 221,000 - 246,000 ounces
- Zinc between 59,000 - 65,000 tonnes
- Palladium and platinum between 22,000 - 24,000 ounces each
• C1 cash cost
- Copper between $1.32 - $1.48/lb.
- Nickel between $4.40 - $4.90/lb.
• Capital expenditures
- $2.1B to $2.2B
May 2014

Más contenido relacionado

Similar a First Quantum Minerals Corporate Presentation - May 2014

Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - finalFirstQuantum
 
Corporate Presentation - February 2014
Corporate Presentation - February 2014Corporate Presentation - February 2014
Corporate Presentation - February 2014FirstQuantum
 
First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014FirstQuantum
 
Corporate Presentation December 2013
Corporate Presentation December 2013Corporate Presentation December 2013
Corporate Presentation December 2013FirstQuantum
 
First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014FirstQuantum
 
Corporate Presentation - November 2013
Corporate Presentation - November 2013Corporate Presentation - November 2013
Corporate Presentation - November 2013FirstQuantum
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate PresentationFirstQuantum
 
Corporate Presentation - September 2013
Corporate Presentation - September 2013Corporate Presentation - September 2013
Corporate Presentation - September 2013FirstQuantum
 
Corporate Presentation - August 2013
Corporate Presentation - August 2013Corporate Presentation - August 2013
Corporate Presentation - August 2013FirstQuantum
 
Investor Presentation - October 2014
Investor Presentation - October 2014Investor Presentation - October 2014
Investor Presentation - October 2014CobreDelMayo
 
Sept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - EnglishSept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - EnglishChampionMines
 
KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...
KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...
KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...Symposium
 
Oct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - EnglishOct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - EnglishChampionMines
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - finalFirstQuantum
 
KBL Mining | ASX:KBL | RIS2014 Broken Hill Investor Presentation
KBL Mining | ASX:KBL | RIS2014 Broken Hill Investor PresentationKBL Mining | ASX:KBL | RIS2014 Broken Hill Investor Presentation
KBL Mining | ASX:KBL | RIS2014 Broken Hill Investor PresentationSymposium
 
Feb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - EnglishFeb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - EnglishChampionMines
 
Corporate Presentation February 2015
Corporate Presentation February 2015Corporate Presentation February 2015
Corporate Presentation February 2015FirstQuantum
 
Presentation february - final
Presentation   february - finalPresentation   february - final
Presentation february - finalFirstQuantum
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - finalFirstQuantum
 
Information Memorandum: Capital Raise, Three Rivers Prospecting
Information Memorandum: Capital Raise, Three Rivers ProspectingInformation Memorandum: Capital Raise, Three Rivers Prospecting
Information Memorandum: Capital Raise, Three Rivers ProspectingAshley Mangano
 

Similar a First Quantum Minerals Corporate Presentation - May 2014 (20)

Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - final
 
Corporate Presentation - February 2014
Corporate Presentation - February 2014Corporate Presentation - February 2014
Corporate Presentation - February 2014
 
First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014
 
Corporate Presentation December 2013
Corporate Presentation December 2013Corporate Presentation December 2013
Corporate Presentation December 2013
 
First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014
 
Corporate Presentation - November 2013
Corporate Presentation - November 2013Corporate Presentation - November 2013
Corporate Presentation - November 2013
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Corporate Presentation - September 2013
Corporate Presentation - September 2013Corporate Presentation - September 2013
Corporate Presentation - September 2013
 
Corporate Presentation - August 2013
Corporate Presentation - August 2013Corporate Presentation - August 2013
Corporate Presentation - August 2013
 
Investor Presentation - October 2014
Investor Presentation - October 2014Investor Presentation - October 2014
Investor Presentation - October 2014
 
Sept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - EnglishSept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - English
 
KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...
KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...
KBL Mining (ASX:KBL) Company Presentation, Symposium Investor Roadshow April ...
 
Oct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - EnglishOct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - English
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
KBL Mining | ASX:KBL | RIS2014 Broken Hill Investor Presentation
KBL Mining | ASX:KBL | RIS2014 Broken Hill Investor PresentationKBL Mining | ASX:KBL | RIS2014 Broken Hill Investor Presentation
KBL Mining | ASX:KBL | RIS2014 Broken Hill Investor Presentation
 
Feb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - EnglishFeb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - English
 
Corporate Presentation February 2015
Corporate Presentation February 2015Corporate Presentation February 2015
Corporate Presentation February 2015
 
Presentation february - final
Presentation   february - finalPresentation   february - final
Presentation february - final
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
Information Memorandum: Capital Raise, Three Rivers Prospecting
Information Memorandum: Capital Raise, Three Rivers ProspectingInformation Memorandum: Capital Raise, Three Rivers Prospecting
Information Memorandum: Capital Raise, Three Rivers Prospecting
 

Más de FirstQuantum

Presentation may 3 final
Presentation may 3   finalPresentation may 3   final
Presentation may 3 finalFirstQuantum
 
Presentation may-3
Presentation may-3Presentation may-3
Presentation may-3FirstQuantum
 
Presentation bmo - final
Presentation   bmo - finalPresentation   bmo - final
Presentation bmo - finalFirstQuantum
 
Presentation january 2018 - final
Presentation   january 2018 - finalPresentation   january 2018 - final
Presentation january 2018 - finalFirstQuantum
 
Presentation november final
Presentation   november finalPresentation   november final
Presentation november finalFirstQuantum
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - finalFirstQuantum
 
February 2017 Corporate Presentation
February 2017 Corporate PresentationFebruary 2017 Corporate Presentation
February 2017 Corporate PresentationFirstQuantum
 
Presentation november - final
Presentation   november - finalPresentation   november - final
Presentation november - finalFirstQuantum
 
Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - finalFirstQuantum
 
Presentation june - final
Presentation   june - finalPresentation   june - final
Presentation june - finalFirstQuantum
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - finalFirstQuantum
 
Presentation april - final
Presentation   april - finalPresentation   april - final
Presentation april - finalFirstQuantum
 
Presentation december - final
Presentation   december - finalPresentation   december - final
Presentation december - finalFirstQuantum
 
Presentation september - fina lv2
Presentation   september - fina lv2Presentation   september - fina lv2
Presentation september - fina lv2FirstQuantum
 
Corporate Presentation September 2015
Corporate Presentation September 2015Corporate Presentation September 2015
Corporate Presentation September 2015FirstQuantum
 
First Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirst Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirstQuantum
 
Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013FirstQuantum
 

Más de FirstQuantum (17)

Presentation may 3 final
Presentation may 3   finalPresentation may 3   final
Presentation may 3 final
 
Presentation may-3
Presentation may-3Presentation may-3
Presentation may-3
 
Presentation bmo - final
Presentation   bmo - finalPresentation   bmo - final
Presentation bmo - final
 
Presentation january 2018 - final
Presentation   january 2018 - finalPresentation   january 2018 - final
Presentation january 2018 - final
 
Presentation november final
Presentation   november finalPresentation   november final
Presentation november final
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - final
 
February 2017 Corporate Presentation
February 2017 Corporate PresentationFebruary 2017 Corporate Presentation
February 2017 Corporate Presentation
 
Presentation november - final
Presentation   november - finalPresentation   november - final
Presentation november - final
 
Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - final
 
Presentation june - final
Presentation   june - finalPresentation   june - final
Presentation june - final
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
Presentation april - final
Presentation   april - finalPresentation   april - final
Presentation april - final
 
Presentation december - final
Presentation   december - finalPresentation   december - final
Presentation december - final
 
Presentation september - fina lv2
Presentation   september - fina lv2Presentation   september - fina lv2
Presentation september - fina lv2
 
Corporate Presentation September 2015
Corporate Presentation September 2015Corporate Presentation September 2015
Corporate Presentation September 2015
 
First Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirst Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor Presentation
 
Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013
 

Último

Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalayResources
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024CollectiveMining1
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd
 
Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Probe Gold
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 

Último (12)

Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR Presentation
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
Korea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment ReportKorea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment Report
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
 
Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 

First Quantum Minerals Corporate Presentation - May 2014

  • 1. TSX: FM; LSE: FQM May 2014
  • 2. 2 Cautionary Note Regarding Forward-Looking Statement Some of the statements contained in the following material are forward-looking statements and not statement of facts. Such statements are based on the current beliefs of management, as well as assumptions based on management information currently available. Forward-looking statements are subject to various risks, uncertainties and other factors that could cause actual results to differ materially from expected results. Readers must rely on their own evaluation of these uncertainties. Note: all dollar amounts in US dollars unless otherwise indicated
  • 3. 3 First Quantum Minerals – At a Glance • A Global Company – Operations and projects in 8 countries • High-Quality, Stable, Efficient Operations – 7 operations – 2013 production:  copper 412,281 tonnes  nickel 47,066 tonnes  gold 248,078 ounces – Cash cost of production  copper $1.30/lb; nickel $5.02/lb • Strong Liquidity & Cash Flow – Cash at March 31’14 = $747.2M – Cash from operations = $370.1M – Available & undrawn facilities of $1.3B – Senior Notes = $850M • Industry-Leading Growth – 5 major projects under development – Production capacities to rise to 1.1 Mtpa for copper and 110 ktpa for nickel by 2018 • Unique Core Strength – In-house project development team – Delivered projects at an average of 40% of the industry’s average capital per tonne of capacity • Strong Track Record – Delivered over $2.4B in projects within 6% of budget – Returned a compounded annual gain of over 30% since listing
  • 4. 4 2013 – A Transformative Year  Successfully acquired Inmet Mining Corporation – Control of the Tier 1 Cobre Panama copper project – Added 3 well-run, low-cost operations  Restructured financing and capital structure  Advanced projects under development  Record production at Flagship Kansanshi mine; Las Cruces; Guelb Moghrein; and Ravensthorpe
  • 6. 6 Cobre Panama – A Tier 1 Copper Project • Acquired March 2013 • Critical review following acquisition – Focused mainly on Engineering, Contracts and Construction initially – Copied major areas of the design of the almost-complete Sentinel process plant • Made significant changes – Unwound ~US$1.7B of commitments – Rectified multiple deficiencies – Readied the site for construction – Connected mine site to port site – Changed to an in-house, self-perform arrangement
  • 7. 7 Cobre Panama – A Tier 1 Copper Project • A larger, more robust project – Installed capacity Yrs 1-10 = ~70 Mtpa  17% higher than prior  Expansion up to 100 Mtpa beyond Yr 10 – Average annual LOM* copper production of 320,000 tonnes  ~ 20% higher than prior – Average annual LOM by-product production  100,000 ounces gold; 1,800,000 ounces silver and 3,500 tonnes molybdenum • Mine life of 34 years * On the basis of the current Resource estimate and the planned installed capacity of about 70 Mtpa
  • 8. 8 Cobre Panama – A Tier 1 Copper Project • Capex estimate of $6.4 billion – inclusive of $913 million incurred prior to acquisition • Capital per installed tonne of capacity of $17,125 – ~25% lower than prior • A realistic and well-defined timeframe – 230 KV overland power line – Q4 ’15 – 300 MW powerstation – Q1 ‘17 – Tailings management facility – Q2 ’17 – Process plant construction – Q3 ‘17 – Commissioning & 1st concentrate production – Q4 ‘17
  • 9. 9 COBRE PANAMA PROJECT – PROCESS PLANT SITE EARTHWORKS
  • 10. 10 COBRE PANAMA PROJECT – MILL PAD EARTHWORKS
  • 11. 11 COBRE PANAMA PROJECT – PROCESS PLANT STOCKPILE PAD
  • 12. 12 COBRE PANAMA PROJECT – POWER STATION AREA
  • 13. 13 COBRE PANAMA PROJECT – BREAKWATER AND MATERIAL OFFLOADING FACILITY
  • 14. 14 Advanced Projects Copper Smelter Complex, Zambia • Phase 1 – Processing capacity of 1.2 Mtpa – Combination of concentrate from Kansanshi & Sentinel – Average copper grade 26% • Copper production 300,000 Tpa; acid production 1.0 Mtpa • Commissioning from 2H2014 • Estimated savings: – US$340M - US$510M/year • Phase 2 being planned to increase processing capacity to between 2 to 2.4 Mtpa in 2017
  • 15. 15 Phase 1 Smelter - Overview
  • 16. 16 Phase 1 Smelter – Cold Box Lifts – April 2014
  • 17. 17 Advanced Projects Sentinel, Zambia • Located ~ 140 km northwest of Solwezi, northern Zambia • M&I resource of 1,027 Mt at 0.51% Cu grade, containing 5.2 Mt Cu • Estimates: – 2.2:1 LOM strip ratio – >15 years mine life – Annual production up to 300,000 tonnes – US$2.0B capex (incl. Enterprise nickel project) – Completion targeted for mid-2014 • Includes 4 Mtpa nickel facility; flexibility to augment copper capacity
  • 18. 18 Sentinel Cu project, Zambia • 55 Mtpa target throughput • 3 semi-mobile in pit crushers and assembly of large scale mining equipment • Largest operating SAG/Ball mill trains in the world (100MW milling power) • 265,000t of freight = 14,500 truckloads of materials • 2 rivers to be dammed/diverted • Life of mine TSF • 600 km of 330kV power transmission lines from Lumwana – Kalumbila – Lusaka West • 690 staff houses plus 590 houses in resettlement • Development of a new town, airport, clinic, school etc…. Advanced Projects
  • 19. 19 Sentinel – 80 Meter Feed Shuttle Conveyor Truss - April 2014
  • 20. 20 Sentinel – 80 Meter Feed Shuttle Conveyor Truss - April 2014
  • 21. 21 Advanced Projects – Sentinel 100MW Milling – 2 x 40’SAG Mills + 2 x 28’Ball Mills
  • 22. 22 SPORTS FACILITY 04-NOV-2013 TRIDENT PREPARATORY SCHOOL 05-NOV-2013 SENIOR HOUSING - SINGLES 31-MAR-2013 SENIOR HOUSING AREA 28-FEB-2013 Advanced Projects – Sentinel Senior Housing
  • 23. 23 TRUST SCHOOL 05-NOV-2013 AFFORDABLE HOUSING LAYOUT TEACHER’S HOME 3-JAN-2014 COMPLETED 4-BEDROOM HOUSE 3-JAN-2014 Advanced Projects – Sentinel Affordable Housing
  • 24. 24 Optimized Capital Structure & Financial Flexibility  Refinanced the short-term US$2.5B revolver at FQM (Akubra) with a $1.2 billion Term Loan Facility five-year Term and and a $1.8 billion Revolving Credit Facility  Exchanged the FQM (Akubra) Inc. US$1.49B 8.75% 2020 and US$500M 7.50% 2021 notes for new 6.75% 6-year notes and new 7.00% 7-year notes  In conjunction with the Exchange Offer, made covenant changes to better match the Company's needs going forward  Made certain amendments to the existing indentures of the US$350M 7.25% Senior Notes due 2019 through a consent solicitation offer to bondholders  Retired the project financing at Kevitsa and Kansanshi and put in place a $350M unsecured facility at Kansanshi  Launched Senior Notes Offering - original amount of $650M increased to $850M on strong response
  • 25. 25 Illustrative Pro Forma Corporate Structure Chart As at March 31, 2014
  • 26. One of the Few Mining Companies Investing in Building Capacity
  • 27. 27 Current State of the Copper Industry • EXPLORATION –Majors have cut back on exploration and juniors are mainly un-financeable –It takes 12-15 years to get from discovery to production • BROWN FIELD EXPANSIONS –Should be lower capital intensity but are not –Capital projects cancelled or deferred from shareholder pressure • GREENFIELD PROJECTS –High capital intensity –Capital projects cancelled or deferred as above –Very poor track record of developing projects efficiently A Small Copper Surplus Now, But…..
  • 28. 28 Current State of the Copper Industry Results in a Looming Deficit
  • 29. 29 Lack of Supply Response to Price Was Staggering Over 2006-2012 Period Global copper mine supply growth and price 0% 0% 1% 0% -1% 7% 9% 4% 7% 5% 4% 3% -1% 1% 7% 2% 2% 3% 1% 2% 0% 0% 3% 7% -2% 0% 2% 4% 6% 8% 10% 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Copperminesupplygrowth%YoY 0 50 100 150 200 250 300 350 400 Copperprice,cents/lb Mine supply growth Price Source: Wood Mackenzie, Macquarie Research, February 2014
  • 30. 30 So The Seeds of The Next Copper Price Bubble are Already Sown AND it is Coming Soon • Pressure from shareholders who have a much shorter time horizon than miners This is not going to change • There is not much out there that the majors want With the cut-back in exploration, this is unlikely to change • The capital intensity of new projects is rising rapidly Why is this so? So why is the industry cutting investment?
  • 31. 31 Why is Capital Intensity Rising? • Falling grades • Difficult geographies • Geopolitics Source: Brook Hunt, Freeport McMoRan Average Copper Grades
  • 32. 32 Source: Wood Mackenzie, CRU, Macquarie Research, February 2014 Weighted average copper project by year of delivery 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 0 5000 10000 15000 20000 25000 30000 35000 40000 Life of mine capital intensity Averageheadgrade 2000-2011 2012-2018f 2000 2001 2002 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013f 2014f 2015f 2016f 2017f 2018f As Head Grades Fall, Capital Intensity Rises Rapidly
  • 33. 33 0 5,000 10,000 15,000 20,000 25,000 30,000 Kansanshi (First Quantum) Kansanshi Expansion (First Quantum) Sentinel (First Quantum) Buenavista DC (Southern Copper) Antapaccay (Xstrata) Antamina (BHP) Guelb Moghrein (First Quantum) Canariaco (Candente) Las Cruces (Inmet) Los Bronces (Anglo American) Oyu Tolgoi (Rio Tinto) Ministro Mina Hales (Codelco) Sierra Gorda (KGHM) Toromocho (Chinalco) Tampakan (Xstrata) Las Bambas (Xstrata) Cobre Panama (First Quantum) Galeno (Minmetals) But it is Possible to Build Projects Efficiently Capital Intensity (US$ / t) Source: First Quantum, Broker Research 33 A producing First Quantum mine A current First Quantum project
  • 34. 34 Source: Wood Mackenzie, CRU, Macquarie Research, February 2014 Weighted average copper project by year of delivery 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 0 5000 10000 15000 20000 25000 30000 35000 40000 Life of mine capital intensity Averageheadgrade 2000-2011 2012-2018f 2000 2001 2002 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013f 2014f 2015f 2016f 2017f 2018f COBRE PANAMA Cobre Panama Has Substantially Lower Capital Intensity Compared to Other Projects with Similar Start-Up Horizons
  • 36. 36 High-Quality, Stable Operations Kansanshi Cu-Au mine, Zambia • Located near Solwezi in the north western Province of Zambia • First production in 2005 • Open pit mining • Flexible ore treatment to allow for variation in ore type : – sulphide circuit; oxide circuit; gold facility • As at December 31, 2013, the estimated mine life was ~17 years • Workforce = ~1,937
  • 37. 37 High-Quality, Stable Operations Kansanshi Cu-Au mine, Zambia • Q1 2014 – 71 kt of copper – 40 kozs of gold – $1.57/lb copper C1 cash cost • 2014 outlook – 255 to 270 kt of copper – 145 to 160 kozs of gold • Multi-phase capacity expansion project – 2012 – 2017 60% increase in overall production capacity – 2012 – 2014 130% increase in oxide production capacity – 2017 90% increase in sulphide production capacity Expansion Project Capacity Completion Estimate Cost Production Impact (US$M) Oxide 7.2 Mtpa Complete 34 Copper: 10,000 - 15,000 Tpa Oxide 14.5 Mtpa Complete 280 Copper: 60,000 - 75,000 Tpa Sulphide 25 Mtpa 2017 565 Copper: 60,000 - 70,000 Tpa
  • 38. 38 High-Quality, Stable Operations Guelb Moghrein Cu-Au mine, Mauritania • 100% ownership • Located 250 kilometres northeast of the nation’s capital, Nouakchott • As at December 31, 2013, the estimated mine life was ~ 8 years (including stockpiles) based on current operations • First production in 2006 • Workforce = ~1,170
  • 39. 39 High-Quality, Stable Operations Guelb Moghrein Cu-Au mine, Mauritania • Q1 ‘14 – 9 kt tonnes of copper – 14 kozs of gold – $1.56/lb copper C1 cash cost • 2014 Outlook – 36 to 39 kt of copper – 55 to 60 k ozs of gold • Magnetite plant project: – In detailed design stage – Estimated capex of $50M – Expected annual production of 1M - 2M tonnes of 69% Fe magnetite concentrate – Expected start up in mid-2014 – Expected to extend mine life through retreatment of tailings dam
  • 40. 40 High-Quality, Stable Operations Ravensthorpe Ni mine, Australia • Acquired as a decommissioned plant in 2010 • First production within 20 months of purchase • Estimated mine life of 32 years • Commercial production declared Dec 2011 • Workforce = ~428 • Q1 ’14 – 9 kt of nickel @ $4.02/lb C1 cash cost • 2014 Outlook = 33 to 37 kt of nickel
  • 41. 41 High-Quality, Stable Operations Kevitsa Ni-Cu-PGE mine, Finland • Built, commissioned and started commercial operations within 36 months of board approval • Estimated mine life of 29 years • Commercial production declared August 2012 • Workforce = ~337 • Further potential – Process optimization – Approval to increase throughput to a maximum of 10 Mtpa from 5.5 Mtpa • Q1 ’14 = 4 kt of copper @ $1.52/lb C1 cash cost ; 2 kt of nickel @ $5.19/lb nickel C1 cash cost • 2014 Outlook = 69 to 72 kt of copper; 9 to 10 kt of nickel
  • 42. 42 High-Quality, Stable Operations Las Cruces Cu mine, Spain • Acquired in March 2013 • Estimated mine life of 9 years; potential for extension • Current average reserve grade of 5.4% copper • Workforce = ~254 • Q1 ’14 – 19 Kt of copper; $0.98/lb copper C1 cash cost • 2014 Outlook – 69 to 72 kt of copper
  • 43. 43 High-Quality, Stable Operations Çayeli Cu-Zn mine, Turkey • Acquired in March 2013 • Estimated mine life of 6 years with potential for an additional 3 years • Average grade of 3.1% copper and 3.6% zinc • Workforce = ~520 employees • Q1 ’14 – 7 kt of copper; 10 kt of zinc – $0.76/lb copper C1 cash cost • 2014 Outlook – 27 to 29 kt of copper – 38 to 42 kt of zinc
  • 44. 44 High-Quality, Stable Operations Pyhäsalmi Cu-Zn mine, Finland • Acquired in March 2013 • One of the most efficient underground mines in the world • Estimated mine life of 6 years • Average grade of 1.05% copper and 1.79% zinc • Workforce = ~228 employees • Q1 ’14 – 4 kt of copper; 5 kt of zinc – $0.52/lb copper C1 cash cost • 2014 Outlook – 14 to 15 kt of copper; 21 to 23 kt of zinc
  • 45. 45 Strong Q1 2014 Results • Production up – Copper up 43% to 113,118 tonnes – Nickel up 7% to 11,838 tonnes – Gold up 8% to 60,164 ounces – Platinum and palladium up 22% to 15,342 ounces • Cash cost lowered – Copper down 9% to $1.38 per pound – Nickel down 18% to $4.37 per pound • Comparative net earnings of $126.8 million or $0.22 per share inclusive of: – $26.7 million or $0.05 per share of unfavorable, recurring acquisition-related adjustments. – Unfavorable impact of $152 million from lower commodity prices and the build-up in concentrate inventory at Kansanshi Copper Production 000’s tonnes Nickel Production 000’s tonnes Gold Production 000’s ounces Copper C1 Cost US$/lb Q1 '13Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2 '13 Q3'13 Q4'13 Q1'14
  • 46. 46 Full Year 2014 Guidance • Production - Copper between 418,000 - 444,000 tonnes - Nickel between 42,000 - 47,000 tonnes - Gold between 221,000 - 246,000 ounces - Zinc between 59,000 - 65,000 tonnes - Palladium and platinum between 22,000 - 24,000 ounces each • C1 cash cost - Copper between $1.32 - $1.48/lb. - Nickel between $4.40 - $4.90/lb. • Capital expenditures - $2.1B to $2.2B