SlideShare a Scribd company logo
1 of 17
Ganapati PMP(I Dip NEBOSH)
Substation Construction Safety Aspect
Foundation/ back filling Excavation Safety
Walls & Columns Scaffolding , WAH
Slab & Precast Erection Lifting Operations
Transformer Erection Jack & Slide Operations
Electrical Cabling Electrical & WAH Safety
Utility Installation Safe work practices & WP
GIS installation Lifting ops & work permit
Asphalting Hot work MEPI
Underground cable work - Safety Aspect
Duct banks Excavation & Confined Space
Cable Pulling Lifting operations, Mech hdlg
Road work Traffic Management ,Road
Safety , Permits
HDD HDD Operational safety
The Plan for Safety is
Step 1 Hazard Identification - STARRT, RA
Step 2 Stress on house keeping – Daily ½ Hour EOD
Step 3 Tool box talks & Training Induction ,RMGM
Step 4 Daily Observations area wise - Safety officers
Step 5 Access Egress Traffic management ,MEPI
Step 6 Work Permit System & Job rotation
Step 7 Internal & External Audits -CAPA
Step 8 Enforcement of PPE Glove selection MSDS
Step 9 Daily Weekly & Monthly review meetings
Major Safety Consideration with the column and
retaining wall work is work at height and
Scaffolding .
All work above 1.8 meters height shall be based on
height work permit procedures and as per
standard 214.
All ladders shall be inspected and issued through
stores ,a register/ log book shall be maintained .
All scaffolds shall be erected as per standard 215.
The scaffolding shall be used for building up the
rebars , form work and the concreting operations.
All and each individual activity shall not proceed
without STARRTalk being conducted by the
foreman.
Scaffolds shall be extended in height at strategic
locations and these shall be used as anchorage
for Personal fall protection where lifelines cannot
be erected or are not reasonably practicable
Mobile scaffold and ladders shall be available for
rescue work incase of a fall as the person using
fall protection is hung for more than 15 minutes .
The Male nurse is the head of the Initial emergency
response team.
Strict Adherence to precautions mentioned in the
height work permit, 100% hook up using twin
lanyard of the personal fall protection / FBH
Major safety consideration for slab casting is work
at height and scaffolding as discussed in previous
slides.
Precast erection is primarily a lifting operation
HHC transfers this risk to an approved Contractor
EPC the operations shall not commence without
an approved method statement and Risk
assessment.
The double tee erection which is the single largest
of the operation as well as all other lifts shall be
as per standard 221
The crane operator , lifting competent person shall
all meet the requirements as specified in the
standard 221.
The lift calculations shall be submitted well in
advance at least 3 weeks in advance to
Commencement of operations as per standard 221.
All the sub contractor personnel shall be provided
induction and tool box talk apart from STARRT
prior to operations.
All rigging equipment shall be issued from store after
Inspection &verification of validity of TPC
 Excavation safety - care to obtain permit to dig ,
excavation work permit , trail pits
 Protect employees from cave-ins
 Barricades , spoil distance maintained
 Competent person in place
 Excavation Log
 TMP showing excavations , MEPI
 Confined Space Training
 HHC chooses to transfer the risk associated with
Jack and slide operation to the sub contractor
who is a specialist in the field .
 The Road safety aspect of the movement of the
low boy trailer shall be as per the approved RC
procedure this will be preceded by a route
survey
 The use of beams dun nage hydraulic jacks and
power packs Present hazards of crushing &
falling objects this hall be taken care of by
restricting the access to the work area, proper
 Blocked roads provided with appropriate signage.
 Flag man at each end of the blocked roads.(shifts &
supervision )
 Concrete barricades for safety.
 Night lighting to prevent accidents.
 Dedicadeted banks men for controlling the movement of
construction plant such as dumper, excavator etc.,
 Flags man, blanks men training.(shifts & supervision )
 Red man & green man training.
 Emergency initial response team.
 Arabic & English signage showing the detour route.
 Provision of Arabic speaking supervisor.
 Provision of appropriate paddles flags ,PPE to flags man
& banks man etc.,
 Excavation competent person & supervisor to handle
the excavation process and the work to proceed under
the permit to work system.
 Reference to as laid drawings where available if not,
use of trail pits for detection of buried services.
 Site inspection and survey and identification of over
head or buried services prior to issue of work permit.
 Protection of workers by ensuring correct design of
sloping and shoring systems, use of trench boxes as
required.
 Prevention of cave in by ensuring that spoil is kept
away by a minimum distance equal to depth of the
excavation, barricades at a minimum of 6 feet from
the edge of the excavation and dewatering done
where required.
 Restricting the movement of vehicles around the
excavation to avoid surcharging, use of stop blocks
for preventing plant from falling into excavation.
 Appropriate handling of material and equipment.
 Red man and green man training to all involved in
the work.
 STARRT talk on excavation and hazards involved
prior to start of work.
 Risk assessment and method statement approval
prior to issue of permit to work.
 Arrangement of access and egress such that a worker
will walk a maximum of 25 feet to access exits.
 Ladders to extend 1m above the excavation edge.
 Regular inspection of excavation by supervisor and
excavation competent person.
Excavation safety management for ug works contd….
CONFINED SPACE MANAGEMENT
FOR UG WORKS
 Any enclosed or partially enclosed space located either
above or below ground or deck level where entry is
possible and where is a risk of oxygen deficiency or
enrichment the accumulation of dust or gases which are
flammable or hazardous.
 Large enough to enter and work but has limited access or
egress.
 Not designed for human occupancy.
 Where required by method statement
and risk assessment RPE and local
exhaust ventilation shall be arranged.
 All entrants into the confined space shall
be trained and certified prior to work.
 All confined spaces shall have a
dedicated confined space attendant.
 Gas testing shall take place prior to start
of work and gases in the confined space
monitored at 15 minute intervals.
 A proper communication plan in place.
 Emergency response team and
ambulance availability.
 Fire watch incase of hot works.
Confined space management for UG works contd…
Construction  safety at 071C20R new

More Related Content

What's hot

LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1Sreenath Pokkadavath
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessmentSimba Zhao
 
Lifting Equipment
Lifting Equipment Lifting Equipment
Lifting Equipment Manish Yadav
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Yousif Fikry
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2Sergio Augusto Esteves
 
Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IAtlantic Training, LLC.
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetyAtlantic Training, LLC.
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputGaurav Singh Rajput
 
Michael lynn welch resume
Michael lynn welch resumeMichael lynn welch resume
Michael lynn welch resumemichael welch
 
CV.James Swearengin.3-2015
CV.James Swearengin.3-2015CV.James Swearengin.3-2015
CV.James Swearengin.3-2015James Swearengin
 

What's hot (20)

LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
Lifting Equipment
Lifting Equipment Lifting Equipment
Lifting Equipment
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
Overhead Crane Safety Course
Overhead Crane Safety CourseOverhead Crane Safety Course
Overhead Crane Safety Course
 
Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&I
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Michael lynn welch resume
Michael lynn welch resumeMichael lynn welch resume
Michael lynn welch resume
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Preventing and Protecting Against OSHA’s Top 10 Workplace Accidents
Preventing and Protecting Against OSHA’s Top 10 Workplace AccidentsPreventing and Protecting Against OSHA’s Top 10 Workplace Accidents
Preventing and Protecting Against OSHA’s Top 10 Workplace Accidents
 
Rigging
RiggingRigging
Rigging
 
CV.James Swearengin.3-2015
CV.James Swearengin.3-2015CV.James Swearengin.3-2015
CV.James Swearengin.3-2015
 

Viewers also liked

Substance abuse in the workplace ppt (sflpp version)
Substance abuse in the workplace ppt (sflpp version)Substance abuse in the workplace ppt (sflpp version)
Substance abuse in the workplace ppt (sflpp version)oliviaenny
 
The major TQM and SCM Practices
The major TQM and SCM PracticesThe major TQM and SCM Practices
The major TQM and SCM PracticesVishal jawanjal
 
Do you ask the right questions when getting in contractors?
Do you ask the right questions when getting in contractors?Do you ask the right questions when getting in contractors?
Do you ask the right questions when getting in contractors?Programmed
 
Practical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and TechniciansPractical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and TechniciansLiving Online
 
Cresatech Substation Safety Mitigation and Outage Management
Cresatech  Substation Safety Mitigation and Outage ManagementCresatech  Substation Safety Mitigation and Outage Management
Cresatech Substation Safety Mitigation and Outage ManagementCatherine Fulton
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safetyDebajit Roy
 
Drugs power point
Drugs power pointDrugs power point
Drugs power pointMATTY_666
 

Viewers also liked (9)

Substance abuse in the workplace ppt (sflpp version)
Substance abuse in the workplace ppt (sflpp version)Substance abuse in the workplace ppt (sflpp version)
Substance abuse in the workplace ppt (sflpp version)
 
The major TQM and SCM Practices
The major TQM and SCM PracticesThe major TQM and SCM Practices
The major TQM and SCM Practices
 
Do you ask the right questions when getting in contractors?
Do you ask the right questions when getting in contractors?Do you ask the right questions when getting in contractors?
Do you ask the right questions when getting in contractors?
 
Daily excavation cheklist.
Daily excavation cheklist.Daily excavation cheklist.
Daily excavation cheklist.
 
Practical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and TechniciansPractical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and Technicians
 
Excavation & Trench Safety by NUCA
Excavation & Trench Safety by NUCAExcavation & Trench Safety by NUCA
Excavation & Trench Safety by NUCA
 
Cresatech Substation Safety Mitigation and Outage Management
Cresatech  Substation Safety Mitigation and Outage ManagementCresatech  Substation Safety Mitigation and Outage Management
Cresatech Substation Safety Mitigation and Outage Management
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safety
 
Drugs power point
Drugs power pointDrugs power point
Drugs power point
 

Similar to Construction safety at 071C20R new

JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJESUSBASILIOANTONIO
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Safety in construction site
Safety in construction siteSafety in construction site
Safety in construction siteakshaykathalkar
 
FARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxFARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxssuser10f6ca
 
Construction site safety (FINAL).pptx
Construction site safety (FINAL).pptxConstruction site safety (FINAL).pptx
Construction site safety (FINAL).pptxRutvikChabhadiya1
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...Dwarika Bhushan Sharma
 
VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00Varadharajalu Gopal
 
Glenn Ross CV .doc 1
Glenn Ross CV .doc 1Glenn Ross CV .doc 1
Glenn Ross CV .doc 1Glenn Ross
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...MohammedAliQazi
 
Glenn Ross CV .doc 1
Glenn Ross CV .doc 1Glenn Ross CV .doc 1
Glenn Ross CV .doc 1Glenn Ross
 
Excavation & Back filling work 02.docx
Excavation & Back filling work 02.docxExcavation & Back filling work 02.docx
Excavation & Back filling work 02.docxnrphsebarauni
 
MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxSyed Neyaz Ahmad
 

Similar to Construction safety at 071C20R new (20)

JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
 
Safety in construction site
Safety in construction siteSafety in construction site
Safety in construction site
 
FARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxFARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docx
 
Construction site safety (FINAL).pptx
Construction site safety (FINAL).pptxConstruction site safety (FINAL).pptx
Construction site safety (FINAL).pptx
 
Liffting supervisor
Liffting supervisorLiffting supervisor
Liffting supervisor
 
Safety plan
Safety planSafety plan
Safety plan
 
Paul CV 2017-2
Paul CV  2017-2Paul CV  2017-2
Paul CV 2017-2
 
MEWP TRAINING.pptx
MEWP TRAINING.pptxMEWP TRAINING.pptx
MEWP TRAINING.pptx
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...
 
VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00
 
Glenn Ross CV .doc 1
Glenn Ross CV .doc 1Glenn Ross CV .doc 1
Glenn Ross CV .doc 1
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
Glenn Ross CV .doc 1
Glenn Ross CV .doc 1Glenn Ross CV .doc 1
Glenn Ross CV .doc 1
 
Excavation & Back filling work 02.docx
Excavation & Back filling work 02.docxExcavation & Back filling work 02.docx
Excavation & Back filling work 02.docx
 
MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptx
 
Hira
HiraHira
Hira
 

Construction safety at 071C20R new

  • 2. Substation Construction Safety Aspect Foundation/ back filling Excavation Safety Walls & Columns Scaffolding , WAH Slab & Precast Erection Lifting Operations Transformer Erection Jack & Slide Operations Electrical Cabling Electrical & WAH Safety Utility Installation Safe work practices & WP GIS installation Lifting ops & work permit Asphalting Hot work MEPI
  • 3. Underground cable work - Safety Aspect Duct banks Excavation & Confined Space Cable Pulling Lifting operations, Mech hdlg Road work Traffic Management ,Road Safety , Permits HDD HDD Operational safety
  • 4. The Plan for Safety is Step 1 Hazard Identification - STARRT, RA Step 2 Stress on house keeping – Daily ½ Hour EOD Step 3 Tool box talks & Training Induction ,RMGM Step 4 Daily Observations area wise - Safety officers Step 5 Access Egress Traffic management ,MEPI Step 6 Work Permit System & Job rotation Step 7 Internal & External Audits -CAPA Step 8 Enforcement of PPE Glove selection MSDS Step 9 Daily Weekly & Monthly review meetings
  • 5. Major Safety Consideration with the column and retaining wall work is work at height and Scaffolding . All work above 1.8 meters height shall be based on height work permit procedures and as per standard 214. All ladders shall be inspected and issued through stores ,a register/ log book shall be maintained .
  • 6. All scaffolds shall be erected as per standard 215. The scaffolding shall be used for building up the rebars , form work and the concreting operations. All and each individual activity shall not proceed without STARRTalk being conducted by the foreman. Scaffolds shall be extended in height at strategic locations and these shall be used as anchorage for Personal fall protection where lifelines cannot be erected or are not reasonably practicable
  • 7. Mobile scaffold and ladders shall be available for rescue work incase of a fall as the person using fall protection is hung for more than 15 minutes . The Male nurse is the head of the Initial emergency response team. Strict Adherence to precautions mentioned in the height work permit, 100% hook up using twin lanyard of the personal fall protection / FBH
  • 8. Major safety consideration for slab casting is work at height and scaffolding as discussed in previous slides. Precast erection is primarily a lifting operation HHC transfers this risk to an approved Contractor EPC the operations shall not commence without an approved method statement and Risk assessment. The double tee erection which is the single largest of the operation as well as all other lifts shall be as per standard 221
  • 9. The crane operator , lifting competent person shall all meet the requirements as specified in the standard 221. The lift calculations shall be submitted well in advance at least 3 weeks in advance to Commencement of operations as per standard 221. All the sub contractor personnel shall be provided induction and tool box talk apart from STARRT prior to operations. All rigging equipment shall be issued from store after Inspection &verification of validity of TPC
  • 10.  Excavation safety - care to obtain permit to dig , excavation work permit , trail pits  Protect employees from cave-ins  Barricades , spoil distance maintained  Competent person in place  Excavation Log  TMP showing excavations , MEPI  Confined Space Training
  • 11.  HHC chooses to transfer the risk associated with Jack and slide operation to the sub contractor who is a specialist in the field .  The Road safety aspect of the movement of the low boy trailer shall be as per the approved RC procedure this will be preceded by a route survey  The use of beams dun nage hydraulic jacks and power packs Present hazards of crushing & falling objects this hall be taken care of by restricting the access to the work area, proper
  • 12.  Blocked roads provided with appropriate signage.  Flag man at each end of the blocked roads.(shifts & supervision )  Concrete barricades for safety.  Night lighting to prevent accidents.  Dedicadeted banks men for controlling the movement of construction plant such as dumper, excavator etc.,  Flags man, blanks men training.(shifts & supervision )  Red man & green man training.  Emergency initial response team.  Arabic & English signage showing the detour route.  Provision of Arabic speaking supervisor.  Provision of appropriate paddles flags ,PPE to flags man & banks man etc.,
  • 13.  Excavation competent person & supervisor to handle the excavation process and the work to proceed under the permit to work system.  Reference to as laid drawings where available if not, use of trail pits for detection of buried services.  Site inspection and survey and identification of over head or buried services prior to issue of work permit.  Protection of workers by ensuring correct design of sloping and shoring systems, use of trench boxes as required.  Prevention of cave in by ensuring that spoil is kept away by a minimum distance equal to depth of the excavation, barricades at a minimum of 6 feet from the edge of the excavation and dewatering done where required.
  • 14.  Restricting the movement of vehicles around the excavation to avoid surcharging, use of stop blocks for preventing plant from falling into excavation.  Appropriate handling of material and equipment.  Red man and green man training to all involved in the work.  STARRT talk on excavation and hazards involved prior to start of work.  Risk assessment and method statement approval prior to issue of permit to work.  Arrangement of access and egress such that a worker will walk a maximum of 25 feet to access exits.  Ladders to extend 1m above the excavation edge.  Regular inspection of excavation by supervisor and excavation competent person. Excavation safety management for ug works contd….
  • 15. CONFINED SPACE MANAGEMENT FOR UG WORKS  Any enclosed or partially enclosed space located either above or below ground or deck level where entry is possible and where is a risk of oxygen deficiency or enrichment the accumulation of dust or gases which are flammable or hazardous.  Large enough to enter and work but has limited access or egress.  Not designed for human occupancy.
  • 16.  Where required by method statement and risk assessment RPE and local exhaust ventilation shall be arranged.  All entrants into the confined space shall be trained and certified prior to work.  All confined spaces shall have a dedicated confined space attendant.  Gas testing shall take place prior to start of work and gases in the confined space monitored at 15 minute intervals.  A proper communication plan in place.  Emergency response team and ambulance availability.  Fire watch incase of hot works. Confined space management for UG works contd…

Editor's Notes

  1. Reference 29 CFR 1926.652. This section will discuss, risk, prevention, factors At the conclusion of the training, you should be able to: State the greatest risk that is present at an excavation. 2. Briefly describe the three main methods for protecting employees from cave-ins. 3. Name at least three factors that pose a hazard to employees working in excavations, and at least one way to eliminate or reduce each of the hazards. 4. Describe the role of a competent person at an excavation site.