Publicidad
Publicidad

Más contenido relacionado

Similar a Innovative solution for line uprating(20)

Publicidad
Publicidad

Innovative solution for line uprating

  1. INNOVATIVE SOLUTION FOR LINE UPRATING
  2. • It is becoming increasingly difficult to obtain ROW to install new transmission line to cater the increased loads on existing lines. • It may be noted inevitable concomitant of load increase is geographical congestion. • Geographical congestion would mean that the extra load can be catered through smart solution of line uprating. • This would require reconductoring of lines using High Performance Conductor. However, this exercise is problematic as the shutdown required for reconductoring cannot be provided as those lines which are already critical. • Use of ERS proved to be a vital solution for reducing the shutdown time during reconductoring. INTRODUCTION
  3. • Sections (600 x 600 x 3000 mm) made of High Strength Steel are both modular as well as portable. • The columns are made of High Strength Steel instead of Aluminium. • High strength steel has three times the specific gravity and yield strength of more than 2 times when compared with High Strength Aluminium alloy. • High Strength Steel make sure that there is no permanent deformation on the structure due to compression. ERS – EMERGENCY RESTORATION SYSTEM
  4. • While designing, direct stress due to Vertical load, bending moment due to transverse loading and broken wire conditions are considered. • Overturning moments due to lateral loads will result in tension responses at the anchoring level. • These are effectively resisted with the help of ground anchors. • Depending upon the soil condition, different types of anchors shall be used. LOADING
  5. ANCHORING CROSS PLATE ANCHOR Suitable for Normal Soil (dry) SCREW ANCHOR Suitable for loose soil ROCK ANCHORING Suitable for hard rock RAY TYPE ANCHOR Suitable for soft soil LARGE PLATE ANCHOR Suitable for Marshy soil
  6. • Steel plates supported by I-Beam on each corner provides enough strength and support to maintain a lighter section and support GIN pole. • Sections are modular and does not require any heavy machineries for erection. With skilled manpower, the tower can be erected within 3-4 hours. • Use of guy wires takes the lateral load and negates the need of civil foundation. • Tower positions & Guy placements are pre-determined with the use of design software PLS LINE ANALYSIS
  7. Experience obtained during two projects executed in Ghaziabad will be discussed in the following sections.
  8. CASE STUDY 1 GHAZIABAD: 132 kV LINE BETWEEN VAISHALI AND SAHIBABAD
  9. • Ghaziabad Development Authority requested UPPTCL to re-route their 132 kV Transmission Line from Vaishali to Sahibabad which was a hindrance for completing their flyover project. • UPPTCL decided to shift the line and construct a multi circuit tower in place of existing tower and also uprate the line by changing the conductor from ACSR to ACCC. CASE STATEMENT
  10. • Initial and detailed survey were made before and after the award of contract. • After detailed survey, the technical team concluded that 3 ERS tower of 30M high will be required in view of the multi storey mansions and residential apartments. • Erection works began on 21st April and was finished by 27th April. SURVEY
  11. • After erection, we waited for the shutdown of 33kV Line that was crossing the section between ERS 1 and Multi circuit as well as a 11kV Line that was crossing the section between ERS 1 & ERS 2. • In the meantime, stringing works were carried out between ERS 2 and ERS 3. • On 30th April, UPPTCL provided a shutdown of 33 kV Line for 2 hours within which the stringing work between the Multi Circuit tower and ERS 1 was done. CHALLENGES 33 kV Line Crossing
  12. • Later on, 1st May, shutdown on 11kV Line was provided for 2 hours to complete the stringing between ERS 1 & ERS 2. • Stringing between ERS 3 and 132 kV tower was delayed by 5 days due to non- availability of shutdown. • After the line is shifted to ERS, UPPTCL dismantled the existing 132 kV Towers and replaced them with Multi Circuit Towers. CHALLENGES 11 kV Line Crossing
  13.  Even after installing the ERS, we were not able to string the line as UPPTCL could not provide shutdown on the 132kV Line.  This shows how critical that particular line is and it would have taken years to complete the project without ERS.  Both the flyover project and line uprating would have been on hold. IMPACT
  14. • No heavy machinery or earth movers were introduced for execution of above, other than for transportation. • It is worthwhile to mention that, after shifting the line to ERS, there was a severe hailstorm but the tower withstood the same without any damage to it. • The bypass line is in charged state since then serving utility customers who didn’t have to undergo suspension of service. OUTCOME
  15. Live line from existing to ERS tower Live Line between two ERS Towers Tower with cross arm & insulator
  16. GHAZIABAD: 400 kV ATUR – INDRA PURAM LINE CASE STUDY 2
  17. • A 400 kV Transmission Line between Atur and Indira Puram, abandoned since March 2017 and was likely to remain idle for at least three months, due to a line crossing over 132 kV Single Circuit Transmission Line between Loni and Mohan Nagar in Uttar Pradesh. • The bottom crossarm of 132 kV Tower was at a height of 53m which didn’t provide the necessary clearance required for stringing the 400kV line. • The situation was that the height of 132kV tower has to be reduced and it required a shutdown for 5 to 7 days which was not possible. CASE STATEMENT
  18. • Our engineering team conducted a survey and made a detailed report. • This project was a huge challenge as the particular corridor contains a Highway crossing, River crossing and a Flyover Crossing. • After analyzing the detailed report, three locations were chosen for ERS erection. SURVEY
  19. • Based on the experience from previous project, new techniques were followed in order to fasten the erection time. • Also as the crew was experienced, the entire erection was done in 3 days whereas the previous work took 6 days. • We did a challenging feat of taking the bypass line across the highway without any disruption of highway traffic even for a minute EXPERIENCE Flyover Crossing
  20. • On 7th June, UPPTCL provided a shutdown for 3 hours within which we carried out the stringing on ERS and destringing of 132 kV Line. • Again after installing the tower, there was heavy rain and stormy wind but no damage was made to the ERS. • No heavy machinery or earth movers were introduced for execution of above, other than for transportation. OUTCOME River Crossing
  21. OUTCOME
  22. • This exercise helped in completing a project which would evacuate 580 MW line where substantial investment was already made on 98% stretch of the line and associated substation would have remained idle for indefinite period. • Benefits of this exercise was higher than cost by exponential proportions.
  23. THANK YOU SUPREME & CO. PVT. LTD. P-200, BENARAS ROAD, HOWRAH -711108, WEST BENGAL, INDIA Phone : +91-033-26516701 TO 05 Fax : +91-033-26516706 Email : sales@supreme.in & info@supreme.in Website : www.supreme.in
Publicidad