Earned Value Analysis
 EVA is a system for planning and controlling project
cost performance.
 It establishes a work package earned value baseline by
integrating project scope, time , schedule and cost
objectives. This baseline is called control account is
used for performance evaluation on a given date.
 Analysis of variance from baseline provides cost
related information for problem identification, trend
analysis and corrective action.
Earned Value Analysis
 Earned value analysis serve 2 main purposes-
 1. To analyze the cost changes resulting in time and
cost over-runs or under-runs for taking timely
corrective actions such as modifying cash flow, and
updating financial forecasts and project profitability
expectations.
 2.To update key personnel on anticipated cost changes
in their field of responsibility, so as to create cost
consciousness for exploring means of minimizing
wastage and reducing costs.
Earned Value Analysis
 Consider a project with projected cost at completion of
Rs 1,60,000 and completion period of 20 weeks. When
reviewed at the end of 10th week, it shows that as
against the planned cost of Rs 92000/- at the end of 10
the week provided all the work is done as planned; it
has incurred expenditure of Rs 90,000.
 It raises many question such as how well is the project
actually performing; is it nor performing well as actual
expenses spent are less than budgeted, is the project
behind the schedule work or could be that the work
has been done nicely and project may be completed at
a cost that is below budget.
Earned Value Analysis
 Analysis of variance from baseline using EVA yields
variety of variances that are analyzed to determine the
current status, initiate corrective actions and forecast
the future trends.
 EVM is the process of measuring performance of
project work against a baseline plan. The application
of EVM enables better integration of cost and time
schedule control with responsibility defined in OBS.
 It provides better overall picture of performance and
gives better forecast of the final costs at completion.
 Thus EV represents a translation of project cost into
work progress.
Earned Value Analysis
 Planned Value(PV): It is the cumulative planned
value of the authorized work, scheduled for
completion to date at contract rate. It represents time-
phased cost projections of planned value in the
budget. For example, if a project has budget of Rs
1,00,000 and 5 month schedule shows that 40 % of the
value of project work should be completed at the end
oof 5th month, then PV at the end of 5th month is Rs
4,00,000/-. The planned value is also called as
Budgeted Cost of Work Scheduled(BCWS).
Earned Value Analysis
 Earned Value (EV) : It is the cumulative value of the
authorized work completed to date at contract rate.
 For example, if a project has budget of Rs 1,00,000 and
work completed to date represents 25 % of the value of
entire project work as against the 40 % planned, then
EV at the end of 5th month is Rs 2,50,000/-. The
Earned value is also called as Budgeted Cost of Work
Performed.(BCWP).
Earned Value Analysis
 Actual Cost (AC) : It is the cumulative actual expenses
including apportioned management reserve incurred
in the project to date..
 For example, if a project has budget of Rs 10,00,000
and Rs 5,00,000 has been spent on the project to date,
the AC of the project would be Rs 5,00,000 . Actual
Cost is also known as Actual Cost of Work
Performed.(ACWP).
Earned Value Analysis
 If a project progresses exactly as per cost and time integrated plan, the
3 parameters will be identical. But this rarely happens.
 The difference (EV-AC) and (EV-PV) during implementation phases
generates variances.
 Cost Variance: Cost Variance is computed by comparing actual
performance (AC) with the budgeted cost of work performed (EV).
 Cost Variance(CV)= EV-AC.
 =2,50,000-500000
 =-250000/-
 If CV is positive the project has under-run, i.e. the cost incurred is less
than planned or budgeted cost.
 If CV is negative the project has over-run, i.e. the cost incurred is more
than planned or budgeted cost.
 If CV is zero, then the project is proceeding according to the budgeted
cost.
Earned Value Analysis
 Schedule Variance(SV): Schedule Variance is computed by
comparing planned performance (PV) with the budgeted cost of
work performed (EV).
 Schedule Variance(SV)= EV-PV.
 =250000-400000
 =-150000
 If SV is positive then the project is ahead of its planned cost or
planned schedule, i.e. earned value of the work performed is
higher than planned or scheduled earned value.
 If SV is negative, then the project is behind its planned cost or
planned schedule, i.e. earned value of the work performed is less
than planned or scheduled earned value.
 If SV is zero, then the project is proceeding according to the
planned schedule.
Earned Value Analysis
 Performance Indices:- It determines how efficiently the
task was done and what its implications will be on future
trends. The future trends in productivity, cost and time
performance can be predicted as under
 Cost Performance Index (CPI)= EV/AC
 =250000/500000
 =0.5
 Schedule Performance Index(SPI)=EV/PV
 =250000/400000
 =0.625
 An index of 1.0 or greater indicates a favorable performance
and less than 1.0 implies an unfavorable trend.
Earned Value Analysis
 Estimate at completion- The project manager
should prepare a to-complete forecast, which is an
estimate of time and cost needed to complete the
project.
 This forecast plus the current status of the project
provide a forecast of the date and cost of the project at
completion.
 Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI
 Where BAC is the budgeted cost at completion for the project (the
same as the total planned value as of the target completion date)
 ETC= (1000000-250000)/0.5
 = 1500000/-
Earned Value Analysis
 EAC (Estimated cost at completion)=AC+ ETC
 =500000+1500000
 =2000000
Earned Value Analysis
Problem from tutorial
Solution
 1.Planned Value(BCWS)= 4 robots x 100000
 = Rs 400000 /-
 2.Earned Value (BCWP)=3 robots x 100000
 =Rs 300000/-
 3.Actual Cost(ACWP) =3 robots x 150000
 =Rs 450000
 4.Cost Variance(CV)= EV-AC
 = 300000-450000
 =-150000
 The project has overrun by Rs 150000 till date
Solution
 5. Cost Performance Index (CPI)= EV/AC
 =300000/450000
 =2/3=0.667
 6. Schedule Variance(SV)= EV-PV.
 =300000-400000
 =-100000
 The project is behind schedule by Rs 100000 work
 7. Schedule Performance Index(SPI)=EV/PV
 =300000/400000
 =0.75
 The project is behind schedule by 25 % time.
Solution
 8. Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI
 =(400000-300000)/0.667
 =Rs 150000
 The project will require additional Rs 150000 to complete.
 9. EAC (Estimated cost at completion)=AC+ ETC
 =450000+150000
 =Rs 600000
 The estimated project cost will be Rs 600000 as against the budgeted
cost of Rs 400000 if it continues in the same way.
Earned value analysis (1)

More Related Content

What's hot

Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
ssuserb4074f
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
haroldtaylor1113
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
Nicola2903
 
Earned value management
Earned value managementEarned value management
Earned value management
Ashif AR
 

What's hot (20)

CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Project Planning and Management
Project Planning and Management Project Planning and Management
Project Planning and Management
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project controls
Project controlsProject controls
Project controls
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Pert
PertPert
Pert
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
WBS presentation
WBS presentationWBS presentation
WBS presentation
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Earned value management
Earned value managementEarned value management
Earned value management
 

Similar to Earned value analysis (1)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 

Similar to Earned value analysis (1) (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned value management
Earned value managementEarned value management
Earned value management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value Analysis
 
Earned value management
Earned value managementEarned value management
Earned value management
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 

Recently uploaded (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 

Earned value analysis (1)

  • 1. Earned Value Analysis  EVA is a system for planning and controlling project cost performance.  It establishes a work package earned value baseline by integrating project scope, time , schedule and cost objectives. This baseline is called control account is used for performance evaluation on a given date.  Analysis of variance from baseline provides cost related information for problem identification, trend analysis and corrective action.
  • 2. Earned Value Analysis  Earned value analysis serve 2 main purposes-  1. To analyze the cost changes resulting in time and cost over-runs or under-runs for taking timely corrective actions such as modifying cash flow, and updating financial forecasts and project profitability expectations.  2.To update key personnel on anticipated cost changes in their field of responsibility, so as to create cost consciousness for exploring means of minimizing wastage and reducing costs.
  • 3. Earned Value Analysis  Consider a project with projected cost at completion of Rs 1,60,000 and completion period of 20 weeks. When reviewed at the end of 10th week, it shows that as against the planned cost of Rs 92000/- at the end of 10 the week provided all the work is done as planned; it has incurred expenditure of Rs 90,000.  It raises many question such as how well is the project actually performing; is it nor performing well as actual expenses spent are less than budgeted, is the project behind the schedule work or could be that the work has been done nicely and project may be completed at a cost that is below budget.
  • 4. Earned Value Analysis  Analysis of variance from baseline using EVA yields variety of variances that are analyzed to determine the current status, initiate corrective actions and forecast the future trends.  EVM is the process of measuring performance of project work against a baseline plan. The application of EVM enables better integration of cost and time schedule control with responsibility defined in OBS.  It provides better overall picture of performance and gives better forecast of the final costs at completion.  Thus EV represents a translation of project cost into work progress.
  • 5. Earned Value Analysis  Planned Value(PV): It is the cumulative planned value of the authorized work, scheduled for completion to date at contract rate. It represents time- phased cost projections of planned value in the budget. For example, if a project has budget of Rs 1,00,000 and 5 month schedule shows that 40 % of the value of project work should be completed at the end oof 5th month, then PV at the end of 5th month is Rs 4,00,000/-. The planned value is also called as Budgeted Cost of Work Scheduled(BCWS).
  • 6. Earned Value Analysis  Earned Value (EV) : It is the cumulative value of the authorized work completed to date at contract rate.  For example, if a project has budget of Rs 1,00,000 and work completed to date represents 25 % of the value of entire project work as against the 40 % planned, then EV at the end of 5th month is Rs 2,50,000/-. The Earned value is also called as Budgeted Cost of Work Performed.(BCWP).
  • 7. Earned Value Analysis  Actual Cost (AC) : It is the cumulative actual expenses including apportioned management reserve incurred in the project to date..  For example, if a project has budget of Rs 10,00,000 and Rs 5,00,000 has been spent on the project to date, the AC of the project would be Rs 5,00,000 . Actual Cost is also known as Actual Cost of Work Performed.(ACWP).
  • 8. Earned Value Analysis  If a project progresses exactly as per cost and time integrated plan, the 3 parameters will be identical. But this rarely happens.  The difference (EV-AC) and (EV-PV) during implementation phases generates variances.  Cost Variance: Cost Variance is computed by comparing actual performance (AC) with the budgeted cost of work performed (EV).  Cost Variance(CV)= EV-AC.  =2,50,000-500000  =-250000/-  If CV is positive the project has under-run, i.e. the cost incurred is less than planned or budgeted cost.  If CV is negative the project has over-run, i.e. the cost incurred is more than planned or budgeted cost.  If CV is zero, then the project is proceeding according to the budgeted cost.
  • 9. Earned Value Analysis  Schedule Variance(SV): Schedule Variance is computed by comparing planned performance (PV) with the budgeted cost of work performed (EV).  Schedule Variance(SV)= EV-PV.  =250000-400000  =-150000  If SV is positive then the project is ahead of its planned cost or planned schedule, i.e. earned value of the work performed is higher than planned or scheduled earned value.  If SV is negative, then the project is behind its planned cost or planned schedule, i.e. earned value of the work performed is less than planned or scheduled earned value.  If SV is zero, then the project is proceeding according to the planned schedule.
  • 10. Earned Value Analysis  Performance Indices:- It determines how efficiently the task was done and what its implications will be on future trends. The future trends in productivity, cost and time performance can be predicted as under  Cost Performance Index (CPI)= EV/AC  =250000/500000  =0.5  Schedule Performance Index(SPI)=EV/PV  =250000/400000  =0.625  An index of 1.0 or greater indicates a favorable performance and less than 1.0 implies an unfavorable trend.
  • 11. Earned Value Analysis  Estimate at completion- The project manager should prepare a to-complete forecast, which is an estimate of time and cost needed to complete the project.  This forecast plus the current status of the project provide a forecast of the date and cost of the project at completion.  Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI  Where BAC is the budgeted cost at completion for the project (the same as the total planned value as of the target completion date)  ETC= (1000000-250000)/0.5  = 1500000/-
  • 12. Earned Value Analysis  EAC (Estimated cost at completion)=AC+ ETC  =500000+1500000  =2000000
  • 15. Solution  1.Planned Value(BCWS)= 4 robots x 100000  = Rs 400000 /-  2.Earned Value (BCWP)=3 robots x 100000  =Rs 300000/-  3.Actual Cost(ACWP) =3 robots x 150000  =Rs 450000  4.Cost Variance(CV)= EV-AC  = 300000-450000  =-150000  The project has overrun by Rs 150000 till date
  • 16. Solution  5. Cost Performance Index (CPI)= EV/AC  =300000/450000  =2/3=0.667  6. Schedule Variance(SV)= EV-PV.  =300000-400000  =-100000  The project is behind schedule by Rs 100000 work  7. Schedule Performance Index(SPI)=EV/PV  =300000/400000  =0.75  The project is behind schedule by 25 % time.
  • 17. Solution  8. Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI  =(400000-300000)/0.667  =Rs 150000  The project will require additional Rs 150000 to complete.  9. EAC (Estimated cost at completion)=AC+ ETC  =450000+150000  =Rs 600000  The estimated project cost will be Rs 600000 as against the budgeted cost of Rs 400000 if it continues in the same way.