SlideShare a Scribd company logo
1 of 52
LECTURER:
ENG.HISHAM ALI, PMP
Project Management Processes (47)
 PROCESSES GROUP
Project Management Processes
 KNOWLEDGE AREA
• Time Management
 Plan Schedule management
 Define Activities
 Sequence Activities
 Estimate Activity Resources
 Estimate Activity Durations
 Develop Schedule
 Control Schedule
• 6.1 Plan Schedule Management
 the process of establishing the policies, procedures,
and documentation for planning, developing,
managing, executing, and controlling the project
schedule.
 it provides guidance and direction on how the project
schedule will be managed throughout the project
• Schedule Management Plan
 Project schedule model development
The scheduling methodology and the scheduling tool to be used
 Units of measure.
Each unit used in measurements (such as staff hours, staff days...)
 Level of accuracy.
The acceptable range used in determining realistic activity duration
 Control thresholds.
variation to be allowed before some action needs to be taken
 Rules of performance measurement
 Reporting formats.
The formats and frequency for the various schedule reports are
defined.
6.1 Plan Schedule Management
1. Project
management plan
1. Expert judgment
1. Schedule
Management Plan
2. Project Charter
2. Analytical
Technique
3. E.E.F
3. Meetings
4. O.P.A
• 6.2 Define Activities
 the process of identifying and documenting the specific
actions to be performed to produce the project deliverables
 to break down work packages into activities that provide
a basis for estimating, scheduling, executing, monitoring,
and controlling the project work
WBS Packages
Product Analysis
Product
Deliverables
WBS WBS WBS
Activity Activity
Deliverables
WBS
Activity Activity
• 6.2 Define Activities
 Activity List
The activity list is a comprehensive list that includes all
schedule activities required on the project.
 Activity Attributes
Activity attributes extend the description of the activity by
identifying the multiple components associated with each
activity.
 Milestone List
A milestone is a significant point or
event in a project
6.2 Define Activities
1. Schedule
management plan
1. Expert judgment
1. Activity List
2. Scope Baseline 2. Decomposition
2. Activity
Attributes
3. E.E.F
3. Rolling Wave
Planning 3. Milestone List
4. O.P.A
• 6.3 Sequence Activities
 the process of identifying and documenting relationships
among the project activities.
 it defines the logical sequence of work to obtain the
greatest efficiency given all project constraints.
How to make the sequence ??
 Precedence Diagramming Method (PDM)
 Finish-to-Start (FS)
 Finish-to-Finish (FF)
 Start-to-Start (SS)
 Start-to-Finish(SF)
 Types of Dependencies
 Mandatory Dependency(Hard Logic)
 Discretionary Dependency(Preferred-Soft Logic)
 External Dependency
 Internal Dependency
 Leads & Lags
 Lead : overlapping between activities
 Lags : waiting time between activities
Project Schedule Network Diagram
6.3 Sequence Activities
1. Schedule
management plan
1. Precedence
diagramming
method (PDM)
1. Project Schedule
Network Diagrams
2. Activity List
2. Dependency
Determination
2. Project
Documents Updates
3. Activity
Attributes
3. Leads & Lags
4. Milestone List
5. Project Scope
Statement
6. E.E.F
7. O.P.A
• 6.4 Estimate Activity Resources
 the process of estimating the type and quantities of
material, human resources, equipment, or supplies
required to perform each activity
 It identifies the type, quantity, and characteristics of
resources required to complete the activity
• Actions:
 Understand activities and their needs of resources.
 Review historical information and organization polices.
 Check availability of resources.
 Identify skills needed in resources.
 Review cost estimates and make alternative analysis.
 Review resources calendar.
 Quantify resources requirements for each activity.
 Create a resource breakdown structure (RBS).
Resource Breakdown Structure
6.4 Estimate Activity Resources
1. Schedule management
plan
1. Expert Judgment
1. Activity Resource
Requirements
2. Activity List 2. Alternative Analysis
2. Resource
Breakdown Structure
3. Activity Attributes
3. Published
Estimating Data
3. Project Documents
Updates
4. Resources Calendar
4. Bottom up
Estimating
5. Risk Register
5. Project Management
Software
6. Activity Cost
Estimates
6. E.E.F
7. O.P.A
• 6.5 Estimate Activity Durations
 the process of estimating the number of work periods
needed to complete individual activities with estimated
resources.
 it provides the amount of time each activity will take to
complete.
•Tools:
 One point estimating
coming from one source depending on expert or
historical information.
 Analogous Estimating
using historical data from a similar activity or project
to forecast for estimating our activities and used for
limited amount of information.
•Tools:
 Parametric Estimating
uses a statistical relationship between historical data
and other variables to calculate activity duration.
1) Regression Analysis (Scatter Diagram)
2) Learning Curve
depend on improvement of performance
3) Heuristics
depend on accepted rules or best practice
•Tools:
• Three Point Estimating (optimistic, pessimistic, most likely)
 Triangular Distribution
( simple Average )
 Beta Distribution
( weighted Average )
Tools Advantages & Disadvantages
6.5 Estimate Activity Durations
1. Schedule management plan 1. Expert Judgment
1. Activity Duration
Estimates
2. Activity List 2. Analogous Estimating
2. Project Documents
Updates
3. Activity Attributes 3. Parametric Estimating
4. Activity Resource
Requirements
4. Three Point Estimating
5. Resource Calendar
5.Group Decision Making
Technique
6. Project Scope Statement 6.Reserve Analysis
7. Risk Register
8.Resource Breakdown
Structure
9. E.E.F
10. O.P.A
• 6.6 Develop Schedule
 the process of analyzing activity sequences, durations,
resource requirements, and schedule constraints to
create the project schedule model.
 We entering schedule activities, durations, resources,
resource availabilities, and logical relationships into the
scheduling tool
Schedule Techniques
Critical Path Method (CPM)
 method used to estimate the minimum project
duration and determine the amount of scheduling
flexibility on the schedule model.
 Critical Path
the sequence of activities that represents the longest
path through a project, which determines the shortest
possible project duration.
Critical Path Method (CPM)
Critical path Benefits:
 Determine how long the project will take
 Helps the PM to focus his effort on critical activities
 Helps the PM to assign the best resources to critical path
 Shows the activities which have float to help PM
whenever have change.
 Helps to manage resources throughout the project
Float (slack):
 Free Float:
the time an activity can be delayed without delaying
Early start of Successor.
 Total Float:
the time an activity can be delayed without delaying
project end date.
 Project Float:
the time the project can be delayed without delaying
another project.
Critical Path Method (CPM)
Critical Path Method (CPM)
Schedule Compression
 Fast Tracking
By making activities on critical path in parallel not in
sequence. (discretionary dependency)
this technique will increase Risk
 Crashing
by adding or adjusting resources to activities to
compress the schedule.
this technique will increase costs and may increase risk
Critical Path Method (CPM)
Critical Chain Method
 method that allows the project team to place buffers
on any project schedule path to account for limited
resources and project uncertainties
Resource Leveling
 when a resource has been assigned to two or more
activities during the same time period we reallocate
this resources to be at constant level.
Modeling Techniques
 What if Scenario
the process of evaluating scenarios in order to predict
their effect, positively or negatively, on project objectives.
 Simulation
calculating multiple project durations with different sets
of activity assumptions, usually using probability
distributions (Monte Carlo analysis)
Project Schedule
 Network diagram.
showing dependencies
between activities each others.
 Milestone Chart
to show a summary status
to top management or key stakeholders.
 Bar chart (Gant chart)
to show progress between
project team
6.6 Develop Schedule
1. Schedule management
plan
1. Schedule Network
Analysis
1. Schedule baseline
2. Activity List 2. Critical Path Method 2. Project schedule
3. Activity Attributes 3. Critical chain method 3. Schedule data
4. Project schedule Network
Diagram
4. Resource optimization
techniques
4. Project calendars
5. Activity Resource
Requirements
5. Modeling techniques
5. Project management
plan Updates
6. Resource Calendar 6. Leads and lags
6. Project documents
updates
6.6 Develop Schedule
7. Activity Resource
Estimate
7. Schedule compression
8. Project Scope Statement 8. Scheduling tool
9. Risk Register
10. Project staff Assignment
11.Resource Breakdown
Structure
12. E.E.F
13. O.P.A
• 6.7 Control Schedule
 the process of monitoring the status of project activities
to update project progress and manage changes to the
schedule baseline to achieve the plan.
 it provides the means to recognize deviation from the
plan and take corrective and preventive actions.
Actions:
 Determining the current status of the project schedule,
 Influencing the factors that create schedule changes,
 Determining if the project schedule has changed,
 Managing the actual changes as they occur.
 Reprioritizing the remaining work plan
 Take a preventive or corrective action by creating change
requests.
6.7 Control Schedule
1. Project management plan 1. Performance reviews
1. Work performance
information
2. Project schedule
2. Project management
software
2. Schedule forecasts
3. Work performance data
3. Resource optimization
techniques
3. Change requests
4. Project calendars 4. Modeling techniques
4. Project management
plan
updates
5. Schedule data 5. Leads and lags
5. Project documents
updates
6. O.P.A 6. Schedule compression 6. O.P.A. Updates
7. Scheduling tool
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5

More Related Content

What's hot

Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updatedFarhana Rehman
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planningjosephb987
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptxWajihAnsari7
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecyclerlabsza
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Top 10 Agile Metrics
Top 10 Agile MetricsTop 10 Agile Metrics
Top 10 Agile MetricsXBOSoft
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Kickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesKickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesSlideTeam
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Kanchana Devi
 

What's hot (20)

Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planning
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Project management planning
Project management planningProject management planning
Project management planning
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecycle
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project management
Project managementProject management
Project management
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Top 10 Agile Metrics
Top 10 Agile MetricsTop 10 Agile Metrics
Top 10 Agile Metrics
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Kickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesKickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation Slides
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
Project time management
Project time managementProject time management
Project time management
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1
 

Viewers also liked

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryYudha Pratama, PMP
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementHisham Ali,PMP
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
PMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTPMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTHisham Ali,PMP
 
PMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder ManagementPMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder ManagementSudhanshu Singh MBA,PMP
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...GlobalSkillup
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...GlobalSkillup
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamGlobalSkillup
 

Viewers also liked (20)

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Pmp 3 chapter
Pmp  3 chapterPmp  3 chapter
Pmp 3 chapter
 
PMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTPMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENT
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
PMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder ManagementPMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder Management
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
 

Similar to TIME MANAGEMENT chapter(6), PMBOK5

Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.pptMohamadAGhareb
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 

Similar to TIME MANAGEMENT chapter(6), PMBOK5 (20)

Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
Time management
Time managementTime management
Time management
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
08 ch06
08 ch0608 ch06
08 ch06
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
L05 time management
L05 time managementL05 time management
L05 time management
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 

Recently uploaded

Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 

Recently uploaded (20)

Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 

TIME MANAGEMENT chapter(6), PMBOK5

  • 2. Project Management Processes (47)  PROCESSES GROUP
  • 4. • Time Management  Plan Schedule management  Define Activities  Sequence Activities  Estimate Activity Resources  Estimate Activity Durations  Develop Schedule  Control Schedule
  • 5. • 6.1 Plan Schedule Management  the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.  it provides guidance and direction on how the project schedule will be managed throughout the project
  • 6. • Schedule Management Plan  Project schedule model development The scheduling methodology and the scheduling tool to be used  Units of measure. Each unit used in measurements (such as staff hours, staff days...)  Level of accuracy. The acceptable range used in determining realistic activity duration  Control thresholds. variation to be allowed before some action needs to be taken  Rules of performance measurement  Reporting formats. The formats and frequency for the various schedule reports are defined.
  • 7. 6.1 Plan Schedule Management 1. Project management plan 1. Expert judgment 1. Schedule Management Plan 2. Project Charter 2. Analytical Technique 3. E.E.F 3. Meetings 4. O.P.A
  • 8. • 6.2 Define Activities  the process of identifying and documenting the specific actions to be performed to produce the project deliverables  to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work
  • 9. WBS Packages Product Analysis Product Deliverables WBS WBS WBS Activity Activity Deliverables WBS Activity Activity
  • 10.
  • 11.
  • 12. • 6.2 Define Activities  Activity List The activity list is a comprehensive list that includes all schedule activities required on the project.  Activity Attributes Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.  Milestone List A milestone is a significant point or event in a project
  • 13. 6.2 Define Activities 1. Schedule management plan 1. Expert judgment 1. Activity List 2. Scope Baseline 2. Decomposition 2. Activity Attributes 3. E.E.F 3. Rolling Wave Planning 3. Milestone List 4. O.P.A
  • 14. • 6.3 Sequence Activities  the process of identifying and documenting relationships among the project activities.  it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
  • 15. How to make the sequence ??  Precedence Diagramming Method (PDM)  Finish-to-Start (FS)  Finish-to-Finish (FF)  Start-to-Start (SS)  Start-to-Finish(SF)
  • 16.  Types of Dependencies  Mandatory Dependency(Hard Logic)  Discretionary Dependency(Preferred-Soft Logic)  External Dependency  Internal Dependency  Leads & Lags  Lead : overlapping between activities  Lags : waiting time between activities
  • 18. 6.3 Sequence Activities 1. Schedule management plan 1. Precedence diagramming method (PDM) 1. Project Schedule Network Diagrams 2. Activity List 2. Dependency Determination 2. Project Documents Updates 3. Activity Attributes 3. Leads & Lags 4. Milestone List 5. Project Scope Statement 6. E.E.F 7. O.P.A
  • 19. • 6.4 Estimate Activity Resources  the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity  It identifies the type, quantity, and characteristics of resources required to complete the activity
  • 20. • Actions:  Understand activities and their needs of resources.  Review historical information and organization polices.  Check availability of resources.  Identify skills needed in resources.  Review cost estimates and make alternative analysis.  Review resources calendar.  Quantify resources requirements for each activity.  Create a resource breakdown structure (RBS).
  • 22. 6.4 Estimate Activity Resources 1. Schedule management plan 1. Expert Judgment 1. Activity Resource Requirements 2. Activity List 2. Alternative Analysis 2. Resource Breakdown Structure 3. Activity Attributes 3. Published Estimating Data 3. Project Documents Updates 4. Resources Calendar 4. Bottom up Estimating 5. Risk Register 5. Project Management Software 6. Activity Cost Estimates 6. E.E.F 7. O.P.A
  • 23. • 6.5 Estimate Activity Durations  the process of estimating the number of work periods needed to complete individual activities with estimated resources.  it provides the amount of time each activity will take to complete.
  • 24. •Tools:  One point estimating coming from one source depending on expert or historical information.  Analogous Estimating using historical data from a similar activity or project to forecast for estimating our activities and used for limited amount of information.
  • 25. •Tools:  Parametric Estimating uses a statistical relationship between historical data and other variables to calculate activity duration. 1) Regression Analysis (Scatter Diagram) 2) Learning Curve depend on improvement of performance 3) Heuristics depend on accepted rules or best practice
  • 26. •Tools: • Three Point Estimating (optimistic, pessimistic, most likely)  Triangular Distribution ( simple Average )  Beta Distribution ( weighted Average )
  • 27. Tools Advantages & Disadvantages
  • 28. 6.5 Estimate Activity Durations 1. Schedule management plan 1. Expert Judgment 1. Activity Duration Estimates 2. Activity List 2. Analogous Estimating 2. Project Documents Updates 3. Activity Attributes 3. Parametric Estimating 4. Activity Resource Requirements 4. Three Point Estimating 5. Resource Calendar 5.Group Decision Making Technique 6. Project Scope Statement 6.Reserve Analysis 7. Risk Register 8.Resource Breakdown Structure 9. E.E.F 10. O.P.A
  • 29. • 6.6 Develop Schedule  the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.  We entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool
  • 31. Critical Path Method (CPM)  method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the schedule model.  Critical Path the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration.
  • 33. Critical path Benefits:  Determine how long the project will take  Helps the PM to focus his effort on critical activities  Helps the PM to assign the best resources to critical path  Shows the activities which have float to help PM whenever have change.  Helps to manage resources throughout the project
  • 34. Float (slack):  Free Float: the time an activity can be delayed without delaying Early start of Successor.  Total Float: the time an activity can be delayed without delaying project end date.  Project Float: the time the project can be delayed without delaying another project.
  • 37. Schedule Compression  Fast Tracking By making activities on critical path in parallel not in sequence. (discretionary dependency) this technique will increase Risk  Crashing by adding or adjusting resources to activities to compress the schedule. this technique will increase costs and may increase risk
  • 39. Critical Chain Method  method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties
  • 40. Resource Leveling  when a resource has been assigned to two or more activities during the same time period we reallocate this resources to be at constant level.
  • 41. Modeling Techniques  What if Scenario the process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives.  Simulation calculating multiple project durations with different sets of activity assumptions, usually using probability distributions (Monte Carlo analysis)
  • 42. Project Schedule  Network diagram. showing dependencies between activities each others.  Milestone Chart to show a summary status to top management or key stakeholders.  Bar chart (Gant chart) to show progress between project team
  • 43. 6.6 Develop Schedule 1. Schedule management plan 1. Schedule Network Analysis 1. Schedule baseline 2. Activity List 2. Critical Path Method 2. Project schedule 3. Activity Attributes 3. Critical chain method 3. Schedule data 4. Project schedule Network Diagram 4. Resource optimization techniques 4. Project calendars 5. Activity Resource Requirements 5. Modeling techniques 5. Project management plan Updates 6. Resource Calendar 6. Leads and lags 6. Project documents updates
  • 44. 6.6 Develop Schedule 7. Activity Resource Estimate 7. Schedule compression 8. Project Scope Statement 8. Scheduling tool 9. Risk Register 10. Project staff Assignment 11.Resource Breakdown Structure 12. E.E.F 13. O.P.A
  • 45. • 6.7 Control Schedule  the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.  it provides the means to recognize deviation from the plan and take corrective and preventive actions.
  • 46. Actions:  Determining the current status of the project schedule,  Influencing the factors that create schedule changes,  Determining if the project schedule has changed,  Managing the actual changes as they occur.  Reprioritizing the remaining work plan  Take a preventive or corrective action by creating change requests.
  • 47. 6.7 Control Schedule 1. Project management plan 1. Performance reviews 1. Work performance information 2. Project schedule 2. Project management software 2. Schedule forecasts 3. Work performance data 3. Resource optimization techniques 3. Change requests 4. Project calendars 4. Modeling techniques 4. Project management plan updates 5. Schedule data 5. Leads and lags 5. Project documents updates 6. O.P.A 6. Schedule compression 6. O.P.A. Updates 7. Scheduling tool