IBM Global Business Services

IBM Institute for Business Value


                                   Chemicals and
                                     Petroleum
A high-stakes
race against
time
Are investors prepared
to capture the liquefied
natural gas opportunity
that emerges from the
recession?
IBM Institute for Business Value
   IBM Global Business Services, through the IBM Institute for Business Value,
develops fact-based strategic insights for senior business executives around critical
  industry-specific and cross-industry issues. This executive brief is based on an
in-depth study by the Institute’s research team. It is part of an ongoing commitment
   by IBM Global Business Services to provide analysis and viewpoints that help
companies realize business value. You may contact the authors or send an e-mail to
                      iibv@us.ibm.com for more information.
A high-stakes race against time
Are investors prepared to capture the liquefied natural gas opportunity that
emerges from the recession?
By Steve Edwards, David Haake and Omar Ishaq



                        Despite the current global financial crisis, which has led to a fall in energy
                        demand and prices, the market for liquefied natural gas is expected to regain
                        its steep growth trajectory in the mid and long terms, spurred by anticipated
                        increases in demand, particularly in emerging markets. In this update to our
                        2007 study, we find the exact extent of this surge in demand and related
                        investments in infrastructure is difficult to project, however, given complex risk
                        management issues, volatility of natural gas prices and availability of competing
                        fuels. To capitalize on opportunity when it arises, investors must be prepared to
                        mobilize quickly and establish flexible business and operational models for an
                        unpredictable, high-stakes future.
                        The liquefied natural gas (LNG) industry has         Indeed, from 2006-2015, the global market for
                        developed slowly over the last half century          LNG is expected to increase by 70 percent
                                                                                                           2
                        because, in most heavy-consuming nations,            and more than triple by 2030. Not surprisingly,
                        the domestic energy supply has been suffi-           investors are anxious to grab their share of this
                        cient to meet demand. However, as energy             opportunity.
                        consumption has continued to increase
                        around the world (most dramatically in               The rise in energy demand led to a peak in
                        emerging nations), it has become more diffi­         energy prices around mid-2008, followed
                        cult for many nations to satisfy their energy        by a recession-generated steep decline. As
                        needs locally. Complicating the situation            the short-term impact of the global reces­
                        further, more than a third of the world’s natural    sion subsides, however, natural gas prices
                        gas reserves are located in low-consumption          are expected to stabilize again through
                        countries, far from where energy demand is           2011 and then increase for the foreseeable
                                                                                    3
                                 1
                        highest. Increasingly, nations are turning to the    future. These higher gas prices will make
                        mobility and flexibility of LNG to resolve these 
   it economically feasible for businesses and
                        imbalances.





                    1   A high-stakes race against time
nations to again invest in LNG. The cumulative     the fact that modern renewable technologies
      2007-2030 investment in gas supply infra­          may well overtake gas to become the second-
      structure is expected to be US$ 5.5 trillion (in   largest source of electricity, behind coal, soon
                     4                                              6
      2007 dollars). Out of this, US$440 billion is      after 2010.
      expected to be made specifically in LNG infra­
      structure.
                5                                        The question is: will investors be able to scale
                                                         their LNG infrastructure quickly enough to
      However, the same high prices that spur            capitalize on this bubble of opportunity? And
      frenzied investment in LNG could eventu­           equally important, how can they make their
      ally become detrimental to the industry. The       businesses flexible enough to withstand the
      International Energy Agency forecasts suggest      cyclic nature of this industry?
      that high natural gas prices may prompt
      consumers to turn to other fuels, reflected in




22   IBM Global Business Services
       IBM Global Business Services
A high-stakes race against time
Are investors prepared to capture the liquefied natural gas opportunity that
emerges from the recession?

           Because of its     LNG: The opportunity…                                                     regional natural gas trade will rise from 52
                                                                                                                                                 11
                              Driven by population and economic growth,                                 percent in 2006 to 69 percent in 2030.
     “mobility,” LNG will
                              global primary energy demand is expected
       play a critical role                                                                             Not surprisingly, investors are anxious to
                              to increase by 45 percent between 2006 and
      in satisfying rising    2030, with 87 percent of projected growth
                                                                                                        capture their share of this revenue oppor­
 energy demand around                                              7                                    tunity. Many were rushing to establish the
                              coming from non-OECD countries. As a
                                                                                                        infrastructure necessary to capitalize on this
    the world. But global     result, their share of world primary energy
                                                                                                        upswing in LNG demand before the reces­
economic conditions are       demand is expected to rise from 51 percent
                                              8                                                         sion shocked the world energy market, halting
                              to 62 percent. China and India are expected
 forcing a re-evaluation                                                                                a great number of these projects (see Figure
                              to account for 51 percent of incremental world
of investment priorities.                                               9                               1). The industry was considering proposals to
                              primary energy demand in 2006-2030. Even
                                                                                                        more than double the world’s 2008 regasifica­
                              established nations such as the United States
                                                                                                        tion (regas) capacity by 2013, with more than
                              are likely to see energy use rise by more than
                                                                     10                                 100 new plants under planning or construc­
                              11 percent between 2007 and 2030.                                                       12
                                                                                                        tion globally. On the production side, 30
                              Most of the world’s known gas reserves are                                new liquefaction plants were in some stage
                              concentrated in just a few regions – far from                             of planning or construction to start operation
                                                                                                                 13
                              where energy is needed most – and so LNG,                                 by 2013. Investors are no doubt urgently
                              as a means of delivery, has become a more                                 re-evaluating their portfolio of LNG invest­
                              attractive alternative in recent years. Industry                          ments, trying to decide which to reactivate,
                              analysts anticipate LNG’s share of inter-                                 which to mothball and which to accelerate
                                                                                                        going forward.


                               FIGURE 1.
                               An investment of US$440 billion is expected over 2007-2030 in expansion of LNG infrastructure.

                                           30 new liquefaction
                                           plants planned or under
                                           construction to start by 2013
                                                                                              Pipeline


                                                                                                         Doubling globally
                                                                                                         by 2013
                                                                                                                                                       Point of
                                Production          Processing and export                                                                            consumption




                                                                                    Transport LNG                      Import and regas

                              Source: “World Energy Outlook 2008,” International Energy Agency; “Natural Gas Market Review 2008,” International Energy Agency.




                         3    A high-stakes race against time
…and the unpredictability                                                                          Often, governmental control of the supply of
     Yet, the demand for LNG – perhaps more than                                                        natural gas is used as political leverage on the
     other energy sources – is characterized by                                                         world stage. Complicating the situation further,
     unpredictability. There are inherent uncertain­                                                    many of the particularly gas-rich areas of the
     ties in any industry based on constrained                                                          world are fraught with political instability. The
     natural resources. New natural gas sources                                                         facilities and infrastructure that produce and
     are increasingly difficult and expensive to find                                                   transport LNG are prime targets for terrorism.
     and develop, more and more remote, and                                                             In some cases labor strife, trade embargoes –
     production volumes are harder to anticipate                                                        and even piracy – threaten LNG shipments.
     and realize.
                                                                                                        The most volatile factor influencing demand
     Geopolitical issues also aggravate the                                                             for LNG is alternative fuel prices. LNG is inher­
     economics of LNG supply and demand.                                                                ently caught up in a tug-of-war between the
     Most nations strive for energy self-sufficiency,                                                   price of natural gas and that of oil, with coal
     but for many, this desire for independence                                                         emerging to dominate in the not-too-distant
     is outpaced by GDP growth and its corre­                                                           future. Lower natural gas prices tend to raise
     sponding energy demands (see Figure 2).                                                            overall demand for gas. The price must also


      FIGURE 2.
      Most economies are becoming increasingly energy dependent.
                                         125%

                                         100%
                                                                                      Australia
                                          75%                                                                                          Vietnam
             Total energy independence




                                          50%
                                                                                                                     Venezuela
                                          25%
                                                      Independence                                                  Argentina
                                           0%                                     New Zealand
                                                      Dependence          UK                                                                       China
                                         -25%                                              Brazil
                                                           Netherlands
                                         -50%                  France                 U.S.                                            India
                                                                                                  Czech Republic
                                                         Germany
                                         -75%                                    Finland
                                                          Italy          Japan                 Israel      Turkey                       2010 GDP
                                         -100%
                                                                                                                                        2005 GDP
                                         -125%
                                                 0%        1%        2%             3%            4%         5%        6%        7%           8%       9%

                                                                                             2010 GDP growth

      Notes: The size of the two bubbles for each nation represent the size of the country’s gross domestic product in 2005 as compared to 2010. The
      position of the bubbles represent their energy independence in those same two years. The energy independence percentage is calculated as the
      amount of domestic production in excess of consumption divided by overall consumption. A positive value indicates a measure of independence,
      while a negative value represents the degree of dependence on energy imports.
      Sources: IBM Corporate Economics analysis; “Annual Energy Outlook 2006,” U.S. Department of Energy, Energy Information Administration.




4   IBM Global Business Services
LNG must contend      remain high enough to support the higher                                  remained tight overall), LNG shipments to the
                         costs of LNG delivery, but not increase too                               United States plummeted, as domestic gas
 with the uncertainty
                         much or consumers will switch to alternative                              proved a cheaper alternative.
       of constrained
                         fuels. The threat of substitution is substantial:
  natural resources,     nearly 20 percent of today’s current natural                              For LNG, this competition among fuels creates
  geopolitical issues    gas usage in the United States can be easily                              a window of opportunity. But the extent and
                                                                                                   duration of this opportunity are difficult to
and, most of all, fuel   switched to other fuels (primarily through dual-
                         fired power plants that can use either coal or                            project precisely. The International Energy
  prices, making the                                                                               Agency predicts that high natural gas prices
                         gas).14

   precise window of                                                                               would ultimately lead to a shift in demand
 opportunity difficult   As the most “mobile” form of natural gas                                  towards coal. The U.S. Department of Energy
                                                                                                                 15



           to predict.   supply, LNG imports are particularly vulnerable                           forecasts that high LNG prices will spur
                         to regional and even local price shifts. When                             domestic supply, leading to a decline in U.S.
                         higher natural gas prices decrease overall                                imports over the long run (see Figure 3).16 As a
                         demand, LNG imports tend to be the first cut.                             result, LNG industry participants face difficult
                         When unexpected spikes in demand occur,                                   choices about how much to invest, where, and
                         buyers often close the gap with LNG. When                                 how fast.
                         Asian demand spiked in 2008 (while supply


                           FIGURE 3.
                           High LNG prices are expected to increase domestic production of natural gas in the United States, leading
                           to a fall in imports over the long run.

                                                              4              History Projections
                            Net U.S. natural gas imports by




                                                              3
                              source (trillion cubic feet)




                                                              2
                                                                                                                     Overseas LNG
                                                              1
                                                                                                                     Canada
                                                              0
                                                                                                                     Mexico
                                                              -1

                                                              -2
                                                               1990   2000              2010                     2020               2030

                          Source: “Annual Energy Outlook 2009,” U.S. Department of Energy, Energy Information Administration.




                     5   A high-stakes race against time
Complexity and risk                                                 As the supply network expands and importers
     As the LNG supply chain becomes larger and                          demand more purchasing flexibility, the indus­
     more flexible – with more globally distributed                      try’s historical long-term contracts are steadily
     liquefaction and regas facilities – the nature of                   giving way to commodity marketplaces. In the
     the LNG business is changing, with commen­                          1990s, less than 2 percent of all natural gas
     surate increases in complexity and risk.                            transactions were spot trades; by 2007 that
                                                                                                                  ,
                                                                                                            17
                                                                         figure had grown to 11 percent. We expect
     The supply chain – or more precisely, the LNG                       this trend to accelerate as existing long-term
     value chain network – has become inordi­                            contracts expire. The industry impact could
     nately more complex to manage. Historical                           be substantial, given that contracts for a large
     point-to-point delivery has evolved into an                         amount of gas sold each year to Asian coun­
     intricate network of origination points, trans­                     tries will be up for renewal over the coming
     portation partners and shipping destinations.                       decade.A commodity-like market structure
     Each player must manage a complex value                             is quickly falling into place, with LNG pricing
     chain of new assets, joint ventures, invest­                        mechanisms already established in both the
     ments, purchase/supply agreements and                               Atlantic and Pacific Basins.
     logistics – constantly monitoring both physical
     and transactional flows in order to react in real­                  In addition to the financial complexity intro­
     time as situations change (see Figure 4).                           duced by the expanding commodity market,
                                                                         LNG ventures face another possible side


      FIGURE 4.
      This example illustrates the major physical and transactional movements that must be managed as
      part of an LNG value network.



                                                                                  Japan
                                      China

                                                                                                   Physical movements
                                                                                                   Information and transac­
                                                                                                   tional movements
                                                                                                   Global/regional decision
                                                                                                   support center
                                                                                                   Reservoir
                                                                                                   LNG terminal
                                                           Malaysia
                                                                                                   Integrated downstream
                                                                                                   operations
                                                                                                   Customers and
                                                                                                   consumers
                                                                      Australia
                                                                                                   LNG tanker


      Source: IBM Institute for Business Value analysis.




6   IBM Global Business Services
It’s important for     effect. The thinner margins that often accom­        venture its own business practices and tech­
                            pany commodity trades will likely expose             nology standards, making holistic assessment
       LNG ventues to
                            operational inefficiencies in the supply chain       and management of the business extremely
focus on actions that
                            previously hidden by higher-margin, long-term        challenging.
  facilitate long-term      contracts.
             flexibility.                                                        Early readiness, enduring flexibility
                            As always, production, storage and trans­            So how can industry players and nations
                            port of a fuel such as natural gas requires          protect the investments they are making to
                            the utmost attention to safety, reliability and      meet global energy demand? How can they
                            regulatory compliance. The general public            mitigate risk amid ever-increasing complexity?
                            and the governments that represent them are
                            understandably concerned about protecting            It is important for new LNG ventures to focus
                            the environment. Even with superior safety           on actions that can accelerate successful
                            records, LNG ventures face a daunting image          scale-up, while positioning themselves for
                            challenge, given the magnitude and visibility of     long-term flexibility. We believe investment
                            their projects.                                      partners should consider four key actions
                                                                                 early in the joint venture process:
                            The scale and complexity of the LNG busi­
                                                                                 •	Focus constrained joint venture resources on
                            ness is matched only by the financial stakes
                                                                                   differentiated areas of the new business.
                            involved. By almost any measure, LNG
                            ventures are massive, encompassing thou­             •	Instill a culture of safety.
                            sands of acres of shoreline, thousands of            •	Increase visibility for improved decision
                            employees to build and operate, millions of            making.
                            design documents and often billions of invest­
                                                                                 •	Establish a reusable business model and
                            ment dollars. Constructing a regas terminal,           associated infrastructure.
                            for example, typically costs about US$900
                            million – and the price tag for a gas liquefac­      Focus constrained joint venture resources
                                                              18
                            tion plant begins in the billions. Consider also     By nature, most joint ventures operate with
                            that these investments usually have a five-year      limited staff. Adding to the challenge, most of
                            lag for engineering and construction before          the specialized skills required by new LNG
                            payback begins and are based on a 30-year            ventures are in short supply. These ventures
                            business case.                                       are often competing with the petroleum and
                                                                                 utilities industries for a shrinking pool of talent
                            Because of the magnitude of the invest­              and expertise.
                            ment (and the risk), most LNG projects are
                            accomplished through joint ventures. These           Thus, it is crucial for investors to focus their
                            capital projects involve a complex collabora­        scarce resources on areas of the business
                            tion among engineering firms, equipment              that are most strategic, as well as those that
                            suppliers, producers, pipelines, liquefaction        carry the highest stakes because of safety
                            plants, shippers, regas facilities, and storage      risks or the degree of capital involved. Equally
                            and distribution networks. However, the joint        important, investors should consider turning
                            venture structure, in turn, complicates visibility   low-risk, low-investment functions over to
                            of investments, assets, inventory and finan­         external specialists that can often perform
                            cials. Each investment partner brings to the         those activities more economically and at a
                                                                                 higher level of quality.




                        7   A high-stakes race against time
Instill a culture of safety                         must make a commitment to safety to the
     In the LNG industry, safety must be a core          public, employees and regulators. Early hiring
     value, designed into the business from the          and professional training of operations staff is
     start. This can be institutionalized through        critical to success.
     the implementation of formal, enterprise-wide
     safety practices and broadly communicated           Increase visibility for improved decision
     expectations of safety performance. Where
                                                         making
                                                         The sponsors and owners of LNG ventures
     possible, the expected level of performance
                                                         often lack access to operational, financial,
     should be explicitly stated and measured
                                                         logistical and asset management information
     using standard, industry-accepted metrics.
                                                         associated with the new business. Conflicting
     Clear communication channels – up and down          business practices, incompatible processes
     the management chain – must be established          and technologies, and different information
     to surface and correct potential safety issues      standards can make it difficult to share infor­
     as they arise. Leaders must continuously rein­      mation across corporate boundaries.
     force an environment where the disclosure of
                                                         It is critically important to flatten these hurdles
     problems is encouraged and employees are
                                                         early in the venture. All investment part­
     motivated to do the right thing, even when it
                                                         ners need a common view of information to
     might seem difficult.
                                                         facilitate decision making and more timely
     Practically every decision a joint venture          responses to business changes. As they work
     makes – from where facilities are located to        to improve visibility, investors should implement
     whom they partner with – should involve a           processes and infrastructure that can transi­
     safety element. Achieving a positive return on      tion smoothly from design and construction
     investment is inexorably linked to safe and reli­   phases to ongoing operations.
     able operations. For LNG ventures, safety is
     not a cost; it’s an investment.
                                                         Establish a reusable business model and
                                                         associated infrastructure
     A key example of instilling safety is through       New joint ventures present partners with
     operator training. Many LNG ventures are            a fresh start, an entrepreneurial environ­
     essentially start-ups, with no operations history   ment where they can adopt industry-leading
     and few experienced staff. Using design             processes, practices and technologies.
     data from process equipment, automation             Partners can bring the best from their respec­
     and information technology, sophisticated           tive companies, while escaping ineffective
     operator training simulators can be developed       processes and current infrastructure limita­
     to support comprehensive training for new           tions.
     hires – long before they must help commission
                                                         The goal should be to merge diverse partner
     new LNG facilities. Would an airline allow pilots
                                                         interests into a flexible business model with
     to fly a jet on which they had not been simu­
                                                         components that can be reused in future
     lator trained and certified? The LNG industry




8   IBM Global Business Services
Standarization early in   ventures. Standardization – of processes,                           operations. These key steps in handover of the
                            business practices, technology platforms                            facility from the engineering, procurement and
a venture helps mitigate
                            and such – lays the groundwork for reuse.                           construction provider to the owner/operator
     risk and accelerate
                            Standardization early in the venture is even                        can be streamlined and enhanced if technolo­
        implementation.     more beneficial, as it helps mitigate risk and                      gies are in place early enough to leverage.
                            accelerate implementation timelines. Too often,
                            new ventures postpone process, technology                           In low-risk, low-investment areas of the busi­
                            and measurement standardization decisions                           ness, investors should consider using a
                            until forced by the construction schedule.                          centralized services approach or possibly
                            Agreeing upfront on key processes, infrastruc­                      outsourcing to speed implementation and
                            ture and metrics helps prevent delays that                          reduce risk (see Figure 5). In strategic areas,
                            might otherwise occur.                                              investors will also want to invest in infrastruc­
                                                                                                ture for standardization and automation.
                            Using today’s digital technologies for example,                     Financial information sharing, asset manage­
                            it is possible to electronically exploit facility                   ment and procurement are some of the key
                            design data within its new operational systems                      areas to evaluate for standardization opportu­
                            even before factory acceptance testing,                             nities.
                            helping smooth site acceptance testing, plant
                            commissioning and both initial and long-term


                             FIGURE 5.
                             Early investment in standardized aspects of the business model reduces variability and focuses efforts on
                             accelerating implementation without compromising safety.

                                                                                                                              Focus investments on
                                                                                                                              strategic and/or high-
                                                          Consolidate                        Achieve superiority              risk areas
                                                          •	 Increase	efficiency             •	 Focus	the	business	on	
                                    High investment          and consistency                    becoming best-in-class
                                                          •	 Customization	and	              •	 Invest	to	gain	unique	
                                                             integration with other             competitive advantage
                                                             business activities may
                                                             limit outsourcing

                                                          Manage as utility                  Leverage specialists
                                                          •	 Operate	on	specific	service-    •	 Use	best-in-class	partners	
                                                             level agreements and usage         in areas where internal
                                     Low investment                                             capability is not unique
                                                          •	 Use	partners	with	low	cost	
                                                             of entry and high reliability   •	 Seek	tightly	integrated,	
                             Use standard business                                              exclusive relationships
                             practice templates/
                             partners to simplify
                             and facilitate                         Low risk                         High risk
                             implementation.
                             Source: IBM Institute for Business Value.




                        9   A high-stakes race against time
Ready for the race?                                •	 In which areas of our business could stan­
      In those very early stages, when a LNG joint          dardization and established governance
      venture is initially forming, investors make          processes help reduce costs and risk?
      critical decisions that impact their long-term        Where could we use partners to accelerate
      odds of success. Delaying those important             start-up, improve performance or share
      decisions simply piles risk onto an already           risk?
      risky endeavor.                                    •	 How modular and reusable are our
                                                            processes and business practices? What
      As a participant in a new LNG venture, here           specifically do we plan to redeploy in our
      are some questions to help you assess your            next LNG venture?
      level of preparedness:
                                                         •	 Overall, how confident are we that our
      •	 How quickly can we adapt to changing               current LNG project will achieve its
         conditions? Are we locked into an inflex­          expected return on investment?
         ible business infrastructure that cannot be
         scaled easily or hard-wired processes that      Given the inherent volatility of this business, it
         constrain innovation?                           is uncertain how long the present upswing in
                                                         LNG demand will last. We believe focusing on
      •	 What specific steps are we taking to
         manage the safety risks involved in our         the four key action areas we’ve outlined can
         project? Do our employees understand the        help investors move quickly enough to capture
         safety-related aspects of their roles and the   the current LNG opportunity, while remaining
         decisions they are making?                      flexible enough to thrive amid a chaotic and
                                                         cyclic industry.
      •	 Do all of our investment partners have
         access to the information they need? Do
         we have the necessary information to make
         fast and accurate decisions as situations
         change?




10   IBM Global Business Services
DPLNG: Preparing for scale-up from start-up
       In 2006, the Guangdong Dapeng (DPLNG) regas terminal received its inaugural shipment: 66,000 tons of LNG
       arriving from Australia. The terminal is part of a US$3.6 billion investment that also includes the LNG transpor­
       tation infrastructure and pipeline system that connects several fast-growing cities and five new power plants
       in Southeast China. DPLNG has 11 shareholders, including the China National Offshore Oil Corporation, which
       owns 33 percent of the venture, and BP, the lone foreign shareholder, which controls a 30-percent stake.
       DPLNG is China’s first LNG regas terminal. It is a government-endorsed pilot that will serve as a template for
       other future facilities. Being first has presented the business with some unique challenges: it had no precedents
       for forming a Chinese LNG joint venture or designing appropriate management practices and business
       processes. It has been a pioneering effort in almost every way.
       In addition to facing first-of-its-kind pressures, the venture must also be capable of scaling operations in
       step with the region’s ever-increasing energy needs. Its strategy for achieving this objective has centered on
       standardization, optmization and reuse. It selected business processes and technology standards strategi­
       cally – not only to support the complexity of its current business, but also to facilitate replication in future regas
       terminal projects.
       During construction, business practices were created based on business templates so that when the physical
       infrastructure was ready, the business infrastructure was available too. This approach allowed the business to
       move more seamlessly from construction to operations.
       The choice of standardized business processes and supporting technologies made it easier to integrate and
       coordinate with the facilities’ myriad upstream and downstream partners. But perhaps more importantly,
       designing the business with reuse in mind from the start has led to standard, industry-leading practices that can
       be repeated in subsequent ventures.




11   A high-stakes race against time
About the authors                                 Omar Ishaq is the IBM Institute for Business
      Steve Edwards is the IBM Global Industry          Value leader for the Chemicals & Petroleum
      Leader for the Chemicals and Petroleum            Industry. He has extensive experience in
      industries. He has been consulting for over       Strategy & Change consulting from the Nordic,
      25 years with his recent focus involving          and has worked with a number of large
      cross-border business transformation and          global Chemicals & Petroleum clients. Omar
      associated technologies for super major           has a dual Master of Science in Strategy/
      and national oil companies. Recently, he has      Organizational Psychology and Business/
      devoted significant time in key oil and gas       Economics, and he is considered a subject
      territories including Russia, China and India,    matter expert on future energy. He can be
      as well as in Central and Eastern Europe, Latin   contacted at omar.ishaq@no.ibm.com.
      America, North America, Australia and the
                                                        Contributor
      Middle East. Mr. Edwards is a Fellow of the
                                                        Krishna Kaushik, strategy consultant, IBM
      Institute of Management Consultants and an
                                                        Global Business Services
      affiliated member of the Institute of Chartered
      Accountants in England and Wales. He is a         The right partner for a changing
      frequent speaker at conferences including the
                                                        world
      Oil and Money Conference in London, China
                                                        At IBM Global Business Services, we
      Business Forum Beijing, and Oil and Gas
                                                        collaborate with our clients, bringing together
      World Economic Forum Moscow.
                                                        business insight, advanced research and tech­
      David Haake is a Chemicals and Petroleum          nology to give them a distinct advantage in
      Industry Solutions Executive in IBM Global        today’s rapidly changing environment. Through
      Business Services focusing on asset               our integrated approach to business design
      management solutions and value network            and execution, we help turn strategies into
      management for the LNG industry. Mr. Haake’s      action. And with expertise in 17 industries and
      career background includes more than a            global capabilities that span 170 countries, we
      decade in process automation with ABB             can help clients anticipate change and profit
      and The Foxboro Company (now Invensys)            from new opportunities.
      focused on capital projects worldwide. He has
      spent the past ten years working with business
      transformation and technology projects in the
      global Oil and Gas Industry. Mr. Haake recently
      participated in a panel discussion at the LNG
      San Antonio 2007 conference.




12   IBM Global Business Services
References
                                                        11	
                                                              “World Energy Outlook 2008.” International
     1	
           “World Energy Outlook 2008.” International         Energy Agency.
           Energy Agency.                               12	
                                                              “Natural Gas Market Review 2008.”
     2
           Ibid.                                              International Energy Agency.
                                                        13	
     3
           “Annual Energy Outlook 2009.” U.S.                 Ibid.
           Department of Energy, Energy Information     14	
                                                              “World Energy Outlook 2008.” International
           Administration.                                    Energy Agency.
     4
           “World Energy Outlook 2008.” International   15	
                                                              Ibid.
           Energy Agency.                               16	
                                                              “Annual Energy Outlook 2009.” U.S.
     5	
           Ibid.                                              Department of Energy, Energy Information
     6	
           Ibid.                                              Administration.
                                                        17	
     7	
           Ibid                                               “Natural Gas Market Review 2008.”
     8	                                                       International Energy Agency.
           Ibid.
                                                        18	
     9	                                                       Ibid.
           Ibid.
     10	
           “Annual Energy Outlook 2009.” U.S.
           Department of Energy, Energy Information
           Administration.




13   A high-stakes race against time
© Copyright IBM Corporation 2009

  IBM Global Services

  Route 100

  Somers, NY 10589

  U.S.A.

  Produced in the United States of America

  July 2009

  All Rights Reserved


  IBM, the IBM logo and ibm.com are trademarks
  or registered trademarks of International
  Business Machines Corporation in the United
  States, other countries, or both. If these and
  other IBM trademarked terms are marked
  on their first occurrence in this information
  with a trademark symbol (® or ™), these
  symbols indicate U.S. registered or common
  law trademarks owned by IBM at the time this
  information was published. Such trademarks
  may also be registered or common law
  trademarks in other countries. A current list
  of IBM trademarks is available on the Web at
  “Copyright and trademark information” at
  ibm.com/legal/copytrade.shtml

  Other company, product and service names
  may be trademarks or service marks of others.

  References in this publication to IBM products
  and services do not imply that IBM intends to
  make them available in all countries in which
  IBM operates.




   GBE03239-USEN-01

Más contenido relacionado

La actualidad más candente

New base 687 special 15 september 2015
New base 687 special  15 september 2015New base 687 special  15 september 2015
New base 687 special 15 september 2015Khaled Al Awadi
 
New base 700 special 05 october 2015
New base 700 special  05 october 2015New base 700 special  05 october 2015
New base 700 special 05 october 2015Khaled Al Awadi
 
New base 558 special 11 march 2015
New base 558 special 11 march  2015New base 558 special 11 march  2015
New base 558 special 11 march 2015Khaled Al Awadi
 
African Energy Project Development Challenges Power Gen Africa 092012
African Energy Project Development Challenges   Power Gen Africa 092012African Energy Project Development Challenges   Power Gen Africa 092012
African Energy Project Development Challenges Power Gen Africa 092012ronmiller74
 
New base 23 december 2019 energy news issue 1304 by khaled al awadi -compr...
New base 23 december 2019 energy news issue   1304  by khaled al awadi -compr...New base 23 december 2019 energy news issue   1304  by khaled al awadi -compr...
New base 23 december 2019 energy news issue 1304 by khaled al awadi -compr...Khaled Al Awadi
 
New base 1033 special 23 may 2017 energy news
New base 1033 special 23 may 2017 energy newsNew base 1033 special 23 may 2017 energy news
New base 1033 special 23 may 2017 energy newsKhaled Al Awadi
 
Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...
Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...
Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...mimariner
 
New base 486 special 25 november 2014
New base 486 special  25 november  2014New base 486 special  25 november  2014
New base 486 special 25 november 2014Khaled Al Awadi
 
NewBase April 04-2022 Energy News issue - 1501 by Khaled Al Awadi.pdf
NewBase April 04-2022  Energy News issue - 1501  by Khaled Al Awadi.pdfNewBase April 04-2022  Energy News issue - 1501  by Khaled Al Awadi.pdf
NewBase April 04-2022 Energy News issue - 1501 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Microsoft word new base 994 special 02 february 2017 energy news
Microsoft word   new base 994 special 02 february 2017 energy newsMicrosoft word   new base 994 special 02 february 2017 energy news
Microsoft word new base 994 special 02 february 2017 energy newsKhaled Al Awadi
 
Ne base 07 march 2018 energy news issue 1148 by khaled al awadi
Ne base 07 march 2018 energy news issue   1148  by khaled al awadiNe base 07 march 2018 energy news issue   1148  by khaled al awadi
Ne base 07 march 2018 energy news issue 1148 by khaled al awadiKhaled Al Awadi
 
E&P partnership for India’s energy security
E&P partnership for India’s energy securityE&P partnership for India’s energy security
E&P partnership for India’s energy securityIndEnergySecure
 
2019 Election| LNG| Natural Resources| Canada| August 2019
2019 Election| LNG| Natural Resources| Canada| August 20192019 Election| LNG| Natural Resources| Canada| August 2019
2019 Election| LNG| Natural Resources| Canada| August 2019paul young cpa, cga
 
New base 1185 special 09 july 2018 energy news 22
New base 1185 special 09 july  2018 energy news 22New base 1185 special 09 july  2018 energy news 22
New base 1185 special 09 july 2018 energy news 22Khaled Al Awadi
 
New base 11 may 2021 energy news issue 1431 by khaled al awadi
New base 11 may 2021 energy news issue   1431  by khaled al awadiNew base 11 may 2021 energy news issue   1431  by khaled al awadi
New base 11 may 2021 energy news issue 1431 by khaled al awadiKhaled Al Awadi
 
New base 826 special 10 april 2016
New base 826 special 10 april  2016New base 826 special 10 april  2016
New base 826 special 10 april 2016Khaled Al Awadi
 
New base 01 november 2017 energy news issue 1094 by khaled al awadi-compre...
New base 01 november 2017 energy news issue   1094  by khaled al awadi-compre...New base 01 november 2017 energy news issue   1094  by khaled al awadi-compre...
New base 01 november 2017 energy news issue 1094 by khaled al awadi-compre...Khaled Al Awadi
 
The future for renewable energy in the mena region
The future for renewable energy in the mena regionThe future for renewable energy in the mena region
The future for renewable energy in the mena regionRashida Amahtullah
 
New base energy news issue 860 dated 29 may 2016
New base energy news issue  860 dated 29 may 2016New base energy news issue  860 dated 29 may 2016
New base energy news issue 860 dated 29 may 2016Khaled Al Awadi
 
New base energy news 10 october 2020 issue no. 1380 senior editor eng...
New base energy news 10 october 2020   issue no. 1380       senior editor eng...New base energy news 10 october 2020   issue no. 1380       senior editor eng...
New base energy news 10 october 2020 issue no. 1380 senior editor eng...Khaled Al Awadi
 

La actualidad más candente (20)

New base 687 special 15 september 2015
New base 687 special  15 september 2015New base 687 special  15 september 2015
New base 687 special 15 september 2015
 
New base 700 special 05 october 2015
New base 700 special  05 october 2015New base 700 special  05 october 2015
New base 700 special 05 october 2015
 
New base 558 special 11 march 2015
New base 558 special 11 march  2015New base 558 special 11 march  2015
New base 558 special 11 march 2015
 
African Energy Project Development Challenges Power Gen Africa 092012
African Energy Project Development Challenges   Power Gen Africa 092012African Energy Project Development Challenges   Power Gen Africa 092012
African Energy Project Development Challenges Power Gen Africa 092012
 
New base 23 december 2019 energy news issue 1304 by khaled al awadi -compr...
New base 23 december 2019 energy news issue   1304  by khaled al awadi -compr...New base 23 december 2019 energy news issue   1304  by khaled al awadi -compr...
New base 23 december 2019 energy news issue 1304 by khaled al awadi -compr...
 
New base 1033 special 23 may 2017 energy news
New base 1033 special 23 may 2017 energy newsNew base 1033 special 23 may 2017 energy news
New base 1033 special 23 may 2017 energy news
 
Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...
Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...
Missing Strategic Links - Gawadar Port CPEC, Maritime Industry and Offshore E...
 
New base 486 special 25 november 2014
New base 486 special  25 november  2014New base 486 special  25 november  2014
New base 486 special 25 november 2014
 
NewBase April 04-2022 Energy News issue - 1501 by Khaled Al Awadi.pdf
NewBase April 04-2022  Energy News issue - 1501  by Khaled Al Awadi.pdfNewBase April 04-2022  Energy News issue - 1501  by Khaled Al Awadi.pdf
NewBase April 04-2022 Energy News issue - 1501 by Khaled Al Awadi.pdf
 
Microsoft word new base 994 special 02 february 2017 energy news
Microsoft word   new base 994 special 02 february 2017 energy newsMicrosoft word   new base 994 special 02 february 2017 energy news
Microsoft word new base 994 special 02 february 2017 energy news
 
Ne base 07 march 2018 energy news issue 1148 by khaled al awadi
Ne base 07 march 2018 energy news issue   1148  by khaled al awadiNe base 07 march 2018 energy news issue   1148  by khaled al awadi
Ne base 07 march 2018 energy news issue 1148 by khaled al awadi
 
E&P partnership for India’s energy security
E&P partnership for India’s energy securityE&P partnership for India’s energy security
E&P partnership for India’s energy security
 
2019 Election| LNG| Natural Resources| Canada| August 2019
2019 Election| LNG| Natural Resources| Canada| August 20192019 Election| LNG| Natural Resources| Canada| August 2019
2019 Election| LNG| Natural Resources| Canada| August 2019
 
New base 1185 special 09 july 2018 energy news 22
New base 1185 special 09 july  2018 energy news 22New base 1185 special 09 july  2018 energy news 22
New base 1185 special 09 july 2018 energy news 22
 
New base 11 may 2021 energy news issue 1431 by khaled al awadi
New base 11 may 2021 energy news issue   1431  by khaled al awadiNew base 11 may 2021 energy news issue   1431  by khaled al awadi
New base 11 may 2021 energy news issue 1431 by khaled al awadi
 
New base 826 special 10 april 2016
New base 826 special 10 april  2016New base 826 special 10 april  2016
New base 826 special 10 april 2016
 
New base 01 november 2017 energy news issue 1094 by khaled al awadi-compre...
New base 01 november 2017 energy news issue   1094  by khaled al awadi-compre...New base 01 november 2017 energy news issue   1094  by khaled al awadi-compre...
New base 01 november 2017 energy news issue 1094 by khaled al awadi-compre...
 
The future for renewable energy in the mena region
The future for renewable energy in the mena regionThe future for renewable energy in the mena region
The future for renewable energy in the mena region
 
New base energy news issue 860 dated 29 may 2016
New base energy news issue  860 dated 29 may 2016New base energy news issue  860 dated 29 may 2016
New base energy news issue 860 dated 29 may 2016
 
New base energy news 10 october 2020 issue no. 1380 senior editor eng...
New base energy news 10 october 2020   issue no. 1380       senior editor eng...New base energy news 10 october 2020   issue no. 1380       senior editor eng...
New base energy news 10 october 2020 issue no. 1380 senior editor eng...
 

Similar a IBM Oil| Management Solutions for the Liquefied Natural Gas Industry

The Changing Joule Dynamic | Accenture
The Changing Joule Dynamic | AccentureThe Changing Joule Dynamic | Accenture
The Changing Joule Dynamic | Accentureaccenture
 
Renewable Energy: Growing sources of Investment | Aranca Article & Publications
Renewable Energy: Growing sources of Investment | Aranca Article & PublicationsRenewable Energy: Growing sources of Investment | Aranca Article & Publications
Renewable Energy: Growing sources of Investment | Aranca Article & PublicationsAranca
 
Middle East Infrastructure
Middle East InfrastructureMiddle East Infrastructure
Middle East InfrastructureKhaldoon Tabaza
 
IHS Report: Energy and the New Global Industrial Landscape: A Tectonic Shift
IHS Report: Energy and the New Global Industrial Landscape: A Tectonic ShiftIHS Report: Energy and the New Global Industrial Landscape: A Tectonic Shift
IHS Report: Energy and the New Global Industrial Landscape: A Tectonic ShiftMarcellus Drilling News
 
ScottMadden Energy Industry Update February 2011
ScottMadden Energy Industry Update February 2011ScottMadden Energy Industry Update February 2011
ScottMadden Energy Industry Update February 2011kvongunten
 
Power industry blackout risk alert on the rise
Power industry blackout risk alert on the risePower industry blackout risk alert on the rise
Power industry blackout risk alert on the risegaryswandells
 
indian energy sector overview
indian energy sector overviewindian energy sector overview
indian energy sector overviewshivraj negi
 
Energy Trends Technology And Jamaica
Energy Trends Technology And JamaicaEnergy Trends Technology And Jamaica
Energy Trends Technology And Jamaicatomlinson_n
 
Digital Future of Oil & Gas
Digital Future of Oil & GasDigital Future of Oil & Gas
Digital Future of Oil & GasHarjit Birdi
 
Synopsis & toc global renewable energy 2009 - 2018
Synopsis & toc global renewable energy 2009 - 2018Synopsis & toc global renewable energy 2009 - 2018
Synopsis & toc global renewable energy 2009 - 2018Gyan Research And Analytics
 
New base energy news 16 august 2018 no 1195 by khaled al awadi-compressed
New base energy news 16 august 2018 no 1195  by khaled al awadi-compressedNew base energy news 16 august 2018 no 1195  by khaled al awadi-compressed
New base energy news 16 august 2018 no 1195 by khaled al awadi-compressedKhaled Al Awadi
 
New base special 01 october 2014
New base special  01 october  2014New base special  01 october  2014
New base special 01 october 2014Khaled Al Awadi
 
New base 18 january 2018 energy news issue 1129 by khaled al awadi
New base 18 january 2018 energy news issue   1129  by khaled al awadiNew base 18 january 2018 energy news issue   1129  by khaled al awadi
New base 18 january 2018 energy news issue 1129 by khaled al awadiKhaled Al Awadi
 
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 collinsR1
 
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022collinsR1
 

Similar a IBM Oil| Management Solutions for the Liquefied Natural Gas Industry (20)

Ass 1
Ass 1Ass 1
Ass 1
 
Energy india
Energy indiaEnergy india
Energy india
 
The Changing Joule Dynamic | Accenture
The Changing Joule Dynamic | AccentureThe Changing Joule Dynamic | Accenture
The Changing Joule Dynamic | Accenture
 
Ecotech Institute 2010 Clipbook
Ecotech Institute 2010 ClipbookEcotech Institute 2010 Clipbook
Ecotech Institute 2010 Clipbook
 
Renewable Energy: Growing sources of Investment | Aranca Article & Publications
Renewable Energy: Growing sources of Investment | Aranca Article & PublicationsRenewable Energy: Growing sources of Investment | Aranca Article & Publications
Renewable Energy: Growing sources of Investment | Aranca Article & Publications
 
Middle East Infrastructure
Middle East InfrastructureMiddle East Infrastructure
Middle East Infrastructure
 
Risoe Energy Report 7
Risoe Energy Report 7Risoe Energy Report 7
Risoe Energy Report 7
 
IHS Report: Energy and the New Global Industrial Landscape: A Tectonic Shift
IHS Report: Energy and the New Global Industrial Landscape: A Tectonic ShiftIHS Report: Energy and the New Global Industrial Landscape: A Tectonic Shift
IHS Report: Energy and the New Global Industrial Landscape: A Tectonic Shift
 
ScottMadden Energy Industry Update February 2011
ScottMadden Energy Industry Update February 2011ScottMadden Energy Industry Update February 2011
ScottMadden Energy Industry Update February 2011
 
Power industry blackout risk alert on the rise
Power industry blackout risk alert on the risePower industry blackout risk alert on the rise
Power industry blackout risk alert on the rise
 
indian energy sector overview
indian energy sector overviewindian energy sector overview
indian energy sector overview
 
Energy Trends Technology And Jamaica
Energy Trends Technology And JamaicaEnergy Trends Technology And Jamaica
Energy Trends Technology And Jamaica
 
Digital Future of Oil & Gas
Digital Future of Oil & GasDigital Future of Oil & Gas
Digital Future of Oil & Gas
 
Synopsis & toc global renewable energy 2009 - 2018
Synopsis & toc global renewable energy 2009 - 2018Synopsis & toc global renewable energy 2009 - 2018
Synopsis & toc global renewable energy 2009 - 2018
 
New base energy news 16 august 2018 no 1195 by khaled al awadi-compressed
New base energy news 16 august 2018 no 1195  by khaled al awadi-compressedNew base energy news 16 august 2018 no 1195  by khaled al awadi-compressed
New base energy news 16 august 2018 no 1195 by khaled al awadi-compressed
 
New base special 01 october 2014
New base special  01 october  2014New base special  01 october  2014
New base special 01 october 2014
 
New base 18 january 2018 energy news issue 1129 by khaled al awadi
New base 18 january 2018 energy news issue   1129  by khaled al awadiNew base 18 january 2018 energy news issue   1129  by khaled al awadi
New base 18 january 2018 energy news issue 1129 by khaled al awadi
 
Petrolium surviving the post covid
Petrolium surviving the post covidPetrolium surviving the post covid
Petrolium surviving the post covid
 
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
 
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
 

Último

Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 

Último (20)

Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 

IBM Oil| Management Solutions for the Liquefied Natural Gas Industry

  • 1. IBM Global Business Services IBM Institute for Business Value Chemicals and Petroleum A high-stakes race against time Are investors prepared to capture the liquefied natural gas opportunity that emerges from the recession?
  • 2. IBM Institute for Business Value IBM Global Business Services, through the IBM Institute for Business Value, develops fact-based strategic insights for senior business executives around critical industry-specific and cross-industry issues. This executive brief is based on an in-depth study by the Institute’s research team. It is part of an ongoing commitment by IBM Global Business Services to provide analysis and viewpoints that help companies realize business value. You may contact the authors or send an e-mail to iibv@us.ibm.com for more information.
  • 3. A high-stakes race against time Are investors prepared to capture the liquefied natural gas opportunity that emerges from the recession? By Steve Edwards, David Haake and Omar Ishaq Despite the current global financial crisis, which has led to a fall in energy demand and prices, the market for liquefied natural gas is expected to regain its steep growth trajectory in the mid and long terms, spurred by anticipated increases in demand, particularly in emerging markets. In this update to our 2007 study, we find the exact extent of this surge in demand and related investments in infrastructure is difficult to project, however, given complex risk management issues, volatility of natural gas prices and availability of competing fuels. To capitalize on opportunity when it arises, investors must be prepared to mobilize quickly and establish flexible business and operational models for an unpredictable, high-stakes future. The liquefied natural gas (LNG) industry has Indeed, from 2006-2015, the global market for developed slowly over the last half century LNG is expected to increase by 70 percent 2 because, in most heavy-consuming nations, and more than triple by 2030. Not surprisingly, the domestic energy supply has been suffi- investors are anxious to grab their share of this cient to meet demand. However, as energy opportunity. consumption has continued to increase around the world (most dramatically in The rise in energy demand led to a peak in emerging nations), it has become more diffi­ energy prices around mid-2008, followed cult for many nations to satisfy their energy by a recession-generated steep decline. As needs locally. Complicating the situation the short-term impact of the global reces­ further, more than a third of the world’s natural sion subsides, however, natural gas prices gas reserves are located in low-consumption are expected to stabilize again through countries, far from where energy demand is 2011 and then increase for the foreseeable 3 1 highest. Increasingly, nations are turning to the future. These higher gas prices will make mobility and flexibility of LNG to resolve these it economically feasible for businesses and imbalances. 1 A high-stakes race against time
  • 4. nations to again invest in LNG. The cumulative the fact that modern renewable technologies 2007-2030 investment in gas supply infra­ may well overtake gas to become the second- structure is expected to be US$ 5.5 trillion (in largest source of electricity, behind coal, soon 4 6 2007 dollars). Out of this, US$440 billion is after 2010. expected to be made specifically in LNG infra­ structure. 5 The question is: will investors be able to scale their LNG infrastructure quickly enough to However, the same high prices that spur capitalize on this bubble of opportunity? And frenzied investment in LNG could eventu­ equally important, how can they make their ally become detrimental to the industry. The businesses flexible enough to withstand the International Energy Agency forecasts suggest cyclic nature of this industry? that high natural gas prices may prompt consumers to turn to other fuels, reflected in 22 IBM Global Business Services IBM Global Business Services
  • 5. A high-stakes race against time Are investors prepared to capture the liquefied natural gas opportunity that emerges from the recession? Because of its LNG: The opportunity… regional natural gas trade will rise from 52 11 Driven by population and economic growth, percent in 2006 to 69 percent in 2030. “mobility,” LNG will global primary energy demand is expected play a critical role Not surprisingly, investors are anxious to to increase by 45 percent between 2006 and in satisfying rising 2030, with 87 percent of projected growth capture their share of this revenue oppor­ energy demand around 7 tunity. Many were rushing to establish the coming from non-OECD countries. As a infrastructure necessary to capitalize on this the world. But global result, their share of world primary energy upswing in LNG demand before the reces­ economic conditions are demand is expected to rise from 51 percent 8 sion shocked the world energy market, halting to 62 percent. China and India are expected forcing a re-evaluation a great number of these projects (see Figure to account for 51 percent of incremental world of investment priorities. 9 1). The industry was considering proposals to primary energy demand in 2006-2030. Even more than double the world’s 2008 regasifica­ established nations such as the United States tion (regas) capacity by 2013, with more than are likely to see energy use rise by more than 10 100 new plants under planning or construc­ 11 percent between 2007 and 2030. 12 tion globally. On the production side, 30 Most of the world’s known gas reserves are new liquefaction plants were in some stage concentrated in just a few regions – far from of planning or construction to start operation 13 where energy is needed most – and so LNG, by 2013. Investors are no doubt urgently as a means of delivery, has become a more re-evaluating their portfolio of LNG invest­ attractive alternative in recent years. Industry ments, trying to decide which to reactivate, analysts anticipate LNG’s share of inter- which to mothball and which to accelerate going forward. FIGURE 1. An investment of US$440 billion is expected over 2007-2030 in expansion of LNG infrastructure. 30 new liquefaction plants planned or under construction to start by 2013 Pipeline Doubling globally by 2013 Point of Production Processing and export consumption Transport LNG Import and regas Source: “World Energy Outlook 2008,” International Energy Agency; “Natural Gas Market Review 2008,” International Energy Agency. 3 A high-stakes race against time
  • 6. …and the unpredictability Often, governmental control of the supply of Yet, the demand for LNG – perhaps more than natural gas is used as political leverage on the other energy sources – is characterized by world stage. Complicating the situation further, unpredictability. There are inherent uncertain­ many of the particularly gas-rich areas of the ties in any industry based on constrained world are fraught with political instability. The natural resources. New natural gas sources facilities and infrastructure that produce and are increasingly difficult and expensive to find transport LNG are prime targets for terrorism. and develop, more and more remote, and In some cases labor strife, trade embargoes – production volumes are harder to anticipate and even piracy – threaten LNG shipments. and realize. The most volatile factor influencing demand Geopolitical issues also aggravate the for LNG is alternative fuel prices. LNG is inher­ economics of LNG supply and demand. ently caught up in a tug-of-war between the Most nations strive for energy self-sufficiency, price of natural gas and that of oil, with coal but for many, this desire for independence emerging to dominate in the not-too-distant is outpaced by GDP growth and its corre­ future. Lower natural gas prices tend to raise sponding energy demands (see Figure 2). overall demand for gas. The price must also FIGURE 2. Most economies are becoming increasingly energy dependent. 125% 100% Australia 75% Vietnam Total energy independence 50% Venezuela 25% Independence Argentina 0% New Zealand Dependence UK China -25% Brazil Netherlands -50% France U.S. India Czech Republic Germany -75% Finland Italy Japan Israel Turkey 2010 GDP -100% 2005 GDP -125% 0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 2010 GDP growth Notes: The size of the two bubbles for each nation represent the size of the country’s gross domestic product in 2005 as compared to 2010. The position of the bubbles represent their energy independence in those same two years. The energy independence percentage is calculated as the amount of domestic production in excess of consumption divided by overall consumption. A positive value indicates a measure of independence, while a negative value represents the degree of dependence on energy imports. Sources: IBM Corporate Economics analysis; “Annual Energy Outlook 2006,” U.S. Department of Energy, Energy Information Administration. 4 IBM Global Business Services
  • 7. LNG must contend remain high enough to support the higher remained tight overall), LNG shipments to the costs of LNG delivery, but not increase too United States plummeted, as domestic gas with the uncertainty much or consumers will switch to alternative proved a cheaper alternative. of constrained fuels. The threat of substitution is substantial: natural resources, nearly 20 percent of today’s current natural For LNG, this competition among fuels creates geopolitical issues gas usage in the United States can be easily a window of opportunity. But the extent and duration of this opportunity are difficult to and, most of all, fuel switched to other fuels (primarily through dual- fired power plants that can use either coal or project precisely. The International Energy prices, making the Agency predicts that high natural gas prices gas).14 precise window of would ultimately lead to a shift in demand opportunity difficult As the most “mobile” form of natural gas towards coal. The U.S. Department of Energy 15 to predict. supply, LNG imports are particularly vulnerable forecasts that high LNG prices will spur to regional and even local price shifts. When domestic supply, leading to a decline in U.S. higher natural gas prices decrease overall imports over the long run (see Figure 3).16 As a demand, LNG imports tend to be the first cut. result, LNG industry participants face difficult When unexpected spikes in demand occur, choices about how much to invest, where, and buyers often close the gap with LNG. When how fast. Asian demand spiked in 2008 (while supply FIGURE 3. High LNG prices are expected to increase domestic production of natural gas in the United States, leading to a fall in imports over the long run. 4 History Projections Net U.S. natural gas imports by 3 source (trillion cubic feet) 2 Overseas LNG 1 Canada 0 Mexico -1 -2 1990 2000 2010 2020 2030 Source: “Annual Energy Outlook 2009,” U.S. Department of Energy, Energy Information Administration. 5 A high-stakes race against time
  • 8. Complexity and risk As the supply network expands and importers As the LNG supply chain becomes larger and demand more purchasing flexibility, the indus­ more flexible – with more globally distributed try’s historical long-term contracts are steadily liquefaction and regas facilities – the nature of giving way to commodity marketplaces. In the the LNG business is changing, with commen­ 1990s, less than 2 percent of all natural gas surate increases in complexity and risk. transactions were spot trades; by 2007 that , 17 figure had grown to 11 percent. We expect The supply chain – or more precisely, the LNG this trend to accelerate as existing long-term value chain network – has become inordi­ contracts expire. The industry impact could nately more complex to manage. Historical be substantial, given that contracts for a large point-to-point delivery has evolved into an amount of gas sold each year to Asian coun­ intricate network of origination points, trans­ tries will be up for renewal over the coming portation partners and shipping destinations. decade.A commodity-like market structure Each player must manage a complex value is quickly falling into place, with LNG pricing chain of new assets, joint ventures, invest­ mechanisms already established in both the ments, purchase/supply agreements and Atlantic and Pacific Basins. logistics – constantly monitoring both physical and transactional flows in order to react in real­ In addition to the financial complexity intro­ time as situations change (see Figure 4). duced by the expanding commodity market, LNG ventures face another possible side FIGURE 4. This example illustrates the major physical and transactional movements that must be managed as part of an LNG value network. Japan China Physical movements Information and transac­ tional movements Global/regional decision support center Reservoir LNG terminal Malaysia Integrated downstream operations Customers and consumers Australia LNG tanker Source: IBM Institute for Business Value analysis. 6 IBM Global Business Services
  • 9. It’s important for effect. The thinner margins that often accom­ venture its own business practices and tech­ pany commodity trades will likely expose nology standards, making holistic assessment LNG ventues to operational inefficiencies in the supply chain and management of the business extremely focus on actions that previously hidden by higher-margin, long-term challenging. facilitate long-term contracts. flexibility. Early readiness, enduring flexibility As always, production, storage and trans­ So how can industry players and nations port of a fuel such as natural gas requires protect the investments they are making to the utmost attention to safety, reliability and meet global energy demand? How can they regulatory compliance. The general public mitigate risk amid ever-increasing complexity? and the governments that represent them are understandably concerned about protecting It is important for new LNG ventures to focus the environment. Even with superior safety on actions that can accelerate successful records, LNG ventures face a daunting image scale-up, while positioning themselves for challenge, given the magnitude and visibility of long-term flexibility. We believe investment their projects. partners should consider four key actions early in the joint venture process: The scale and complexity of the LNG busi­ • Focus constrained joint venture resources on ness is matched only by the financial stakes differentiated areas of the new business. involved. By almost any measure, LNG ventures are massive, encompassing thou­ • Instill a culture of safety. sands of acres of shoreline, thousands of • Increase visibility for improved decision employees to build and operate, millions of making. design documents and often billions of invest­ • Establish a reusable business model and ment dollars. Constructing a regas terminal, associated infrastructure. for example, typically costs about US$900 million – and the price tag for a gas liquefac­ Focus constrained joint venture resources 18 tion plant begins in the billions. Consider also By nature, most joint ventures operate with that these investments usually have a five-year limited staff. Adding to the challenge, most of lag for engineering and construction before the specialized skills required by new LNG payback begins and are based on a 30-year ventures are in short supply. These ventures business case. are often competing with the petroleum and utilities industries for a shrinking pool of talent Because of the magnitude of the invest­ and expertise. ment (and the risk), most LNG projects are accomplished through joint ventures. These Thus, it is crucial for investors to focus their capital projects involve a complex collabora­ scarce resources on areas of the business tion among engineering firms, equipment that are most strategic, as well as those that suppliers, producers, pipelines, liquefaction carry the highest stakes because of safety plants, shippers, regas facilities, and storage risks or the degree of capital involved. Equally and distribution networks. However, the joint important, investors should consider turning venture structure, in turn, complicates visibility low-risk, low-investment functions over to of investments, assets, inventory and finan­ external specialists that can often perform cials. Each investment partner brings to the those activities more economically and at a higher level of quality. 7 A high-stakes race against time
  • 10. Instill a culture of safety must make a commitment to safety to the In the LNG industry, safety must be a core public, employees and regulators. Early hiring value, designed into the business from the and professional training of operations staff is start. This can be institutionalized through critical to success. the implementation of formal, enterprise-wide safety practices and broadly communicated Increase visibility for improved decision expectations of safety performance. Where making The sponsors and owners of LNG ventures possible, the expected level of performance often lack access to operational, financial, should be explicitly stated and measured logistical and asset management information using standard, industry-accepted metrics. associated with the new business. Conflicting Clear communication channels – up and down business practices, incompatible processes the management chain – must be established and technologies, and different information to surface and correct potential safety issues standards can make it difficult to share infor­ as they arise. Leaders must continuously rein­ mation across corporate boundaries. force an environment where the disclosure of It is critically important to flatten these hurdles problems is encouraged and employees are early in the venture. All investment part­ motivated to do the right thing, even when it ners need a common view of information to might seem difficult. facilitate decision making and more timely Practically every decision a joint venture responses to business changes. As they work makes – from where facilities are located to to improve visibility, investors should implement whom they partner with – should involve a processes and infrastructure that can transi­ safety element. Achieving a positive return on tion smoothly from design and construction investment is inexorably linked to safe and reli­ phases to ongoing operations. able operations. For LNG ventures, safety is not a cost; it’s an investment. Establish a reusable business model and associated infrastructure A key example of instilling safety is through New joint ventures present partners with operator training. Many LNG ventures are a fresh start, an entrepreneurial environ­ essentially start-ups, with no operations history ment where they can adopt industry-leading and few experienced staff. Using design processes, practices and technologies. data from process equipment, automation Partners can bring the best from their respec­ and information technology, sophisticated tive companies, while escaping ineffective operator training simulators can be developed processes and current infrastructure limita­ to support comprehensive training for new tions. hires – long before they must help commission The goal should be to merge diverse partner new LNG facilities. Would an airline allow pilots interests into a flexible business model with to fly a jet on which they had not been simu­ components that can be reused in future lator trained and certified? The LNG industry 8 IBM Global Business Services
  • 11. Standarization early in ventures. Standardization – of processes, operations. These key steps in handover of the business practices, technology platforms facility from the engineering, procurement and a venture helps mitigate and such – lays the groundwork for reuse. construction provider to the owner/operator risk and accelerate Standardization early in the venture is even can be streamlined and enhanced if technolo­ implementation. more beneficial, as it helps mitigate risk and gies are in place early enough to leverage. accelerate implementation timelines. Too often, new ventures postpone process, technology In low-risk, low-investment areas of the busi­ and measurement standardization decisions ness, investors should consider using a until forced by the construction schedule. centralized services approach or possibly Agreeing upfront on key processes, infrastruc­ outsourcing to speed implementation and ture and metrics helps prevent delays that reduce risk (see Figure 5). In strategic areas, might otherwise occur. investors will also want to invest in infrastruc­ ture for standardization and automation. Using today’s digital technologies for example, Financial information sharing, asset manage­ it is possible to electronically exploit facility ment and procurement are some of the key design data within its new operational systems areas to evaluate for standardization opportu­ even before factory acceptance testing, nities. helping smooth site acceptance testing, plant commissioning and both initial and long-term FIGURE 5. Early investment in standardized aspects of the business model reduces variability and focuses efforts on accelerating implementation without compromising safety. Focus investments on strategic and/or high- Consolidate Achieve superiority risk areas • Increase efficiency • Focus the business on High investment and consistency becoming best-in-class • Customization and • Invest to gain unique integration with other competitive advantage business activities may limit outsourcing Manage as utility Leverage specialists • Operate on specific service- • Use best-in-class partners level agreements and usage in areas where internal Low investment capability is not unique • Use partners with low cost of entry and high reliability • Seek tightly integrated, Use standard business exclusive relationships practice templates/ partners to simplify and facilitate Low risk High risk implementation. Source: IBM Institute for Business Value. 9 A high-stakes race against time
  • 12. Ready for the race? • In which areas of our business could stan­ In those very early stages, when a LNG joint dardization and established governance venture is initially forming, investors make processes help reduce costs and risk? critical decisions that impact their long-term Where could we use partners to accelerate odds of success. Delaying those important start-up, improve performance or share decisions simply piles risk onto an already risk? risky endeavor. • How modular and reusable are our processes and business practices? What As a participant in a new LNG venture, here specifically do we plan to redeploy in our are some questions to help you assess your next LNG venture? level of preparedness: • Overall, how confident are we that our • How quickly can we adapt to changing current LNG project will achieve its conditions? Are we locked into an inflex­ expected return on investment? ible business infrastructure that cannot be scaled easily or hard-wired processes that Given the inherent volatility of this business, it constrain innovation? is uncertain how long the present upswing in LNG demand will last. We believe focusing on • What specific steps are we taking to manage the safety risks involved in our the four key action areas we’ve outlined can project? Do our employees understand the help investors move quickly enough to capture safety-related aspects of their roles and the the current LNG opportunity, while remaining decisions they are making? flexible enough to thrive amid a chaotic and cyclic industry. • Do all of our investment partners have access to the information they need? Do we have the necessary information to make fast and accurate decisions as situations change? 10 IBM Global Business Services
  • 13. DPLNG: Preparing for scale-up from start-up In 2006, the Guangdong Dapeng (DPLNG) regas terminal received its inaugural shipment: 66,000 tons of LNG arriving from Australia. The terminal is part of a US$3.6 billion investment that also includes the LNG transpor­ tation infrastructure and pipeline system that connects several fast-growing cities and five new power plants in Southeast China. DPLNG has 11 shareholders, including the China National Offshore Oil Corporation, which owns 33 percent of the venture, and BP, the lone foreign shareholder, which controls a 30-percent stake. DPLNG is China’s first LNG regas terminal. It is a government-endorsed pilot that will serve as a template for other future facilities. Being first has presented the business with some unique challenges: it had no precedents for forming a Chinese LNG joint venture or designing appropriate management practices and business processes. It has been a pioneering effort in almost every way. In addition to facing first-of-its-kind pressures, the venture must also be capable of scaling operations in step with the region’s ever-increasing energy needs. Its strategy for achieving this objective has centered on standardization, optmization and reuse. It selected business processes and technology standards strategi­ cally – not only to support the complexity of its current business, but also to facilitate replication in future regas terminal projects. During construction, business practices were created based on business templates so that when the physical infrastructure was ready, the business infrastructure was available too. This approach allowed the business to move more seamlessly from construction to operations. The choice of standardized business processes and supporting technologies made it easier to integrate and coordinate with the facilities’ myriad upstream and downstream partners. But perhaps more importantly, designing the business with reuse in mind from the start has led to standard, industry-leading practices that can be repeated in subsequent ventures. 11 A high-stakes race against time
  • 14. About the authors Omar Ishaq is the IBM Institute for Business Steve Edwards is the IBM Global Industry Value leader for the Chemicals & Petroleum Leader for the Chemicals and Petroleum Industry. He has extensive experience in industries. He has been consulting for over Strategy & Change consulting from the Nordic, 25 years with his recent focus involving and has worked with a number of large cross-border business transformation and global Chemicals & Petroleum clients. Omar associated technologies for super major has a dual Master of Science in Strategy/ and national oil companies. Recently, he has Organizational Psychology and Business/ devoted significant time in key oil and gas Economics, and he is considered a subject territories including Russia, China and India, matter expert on future energy. He can be as well as in Central and Eastern Europe, Latin contacted at omar.ishaq@no.ibm.com. America, North America, Australia and the Contributor Middle East. Mr. Edwards is a Fellow of the Krishna Kaushik, strategy consultant, IBM Institute of Management Consultants and an Global Business Services affiliated member of the Institute of Chartered Accountants in England and Wales. He is a The right partner for a changing frequent speaker at conferences including the world Oil and Money Conference in London, China At IBM Global Business Services, we Business Forum Beijing, and Oil and Gas collaborate with our clients, bringing together World Economic Forum Moscow. business insight, advanced research and tech­ David Haake is a Chemicals and Petroleum nology to give them a distinct advantage in Industry Solutions Executive in IBM Global today’s rapidly changing environment. Through Business Services focusing on asset our integrated approach to business design management solutions and value network and execution, we help turn strategies into management for the LNG industry. Mr. Haake’s action. And with expertise in 17 industries and career background includes more than a global capabilities that span 170 countries, we decade in process automation with ABB can help clients anticipate change and profit and The Foxboro Company (now Invensys) from new opportunities. focused on capital projects worldwide. He has spent the past ten years working with business transformation and technology projects in the global Oil and Gas Industry. Mr. Haake recently participated in a panel discussion at the LNG San Antonio 2007 conference. 12 IBM Global Business Services
  • 15. References 11 “World Energy Outlook 2008.” International 1 “World Energy Outlook 2008.” International Energy Agency. Energy Agency. 12 “Natural Gas Market Review 2008.” 2 Ibid. International Energy Agency. 13 3 “Annual Energy Outlook 2009.” U.S. Ibid. Department of Energy, Energy Information 14 “World Energy Outlook 2008.” International Administration. Energy Agency. 4 “World Energy Outlook 2008.” International 15 Ibid. Energy Agency. 16 “Annual Energy Outlook 2009.” U.S. 5 Ibid. Department of Energy, Energy Information 6 Ibid. Administration. 17 7 Ibid “Natural Gas Market Review 2008.” 8 International Energy Agency. Ibid. 18 9 Ibid. Ibid. 10 “Annual Energy Outlook 2009.” U.S. Department of Energy, Energy Information Administration. 13 A high-stakes race against time
  • 16. © Copyright IBM Corporation 2009 IBM Global Services Route 100 Somers, NY 10589 U.S.A. Produced in the United States of America July 2009 All Rights Reserved IBM, the IBM logo and ibm.com are trademarks or registered trademarks of International Business Machines Corporation in the United States, other countries, or both. If these and other IBM trademarked terms are marked on their first occurrence in this information with a trademark symbol (® or ™), these symbols indicate U.S. registered or common law trademarks owned by IBM at the time this information was published. Such trademarks may also be registered or common law trademarks in other countries. A current list of IBM trademarks is available on the Web at “Copyright and trademark information” at ibm.com/legal/copytrade.shtml Other company, product and service names may be trademarks or service marks of others. References in this publication to IBM products and services do not imply that IBM intends to make them available in all countries in which IBM operates. GBE03239-USEN-01