SlideShare a Scribd company logo
1 of 5
Download to read offline
International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018
www.ijecs.net
15
A Case Study on Productivity Improvement of
Wearing Insert and Cutting Ring
Dr. C. M. sedani1
, Nikhil Dhumal2
, Pramod Dhanave3
, Hardik Lawande4
, Aniruddha Mule5
1
Professor ,2,3,4,5
UG Students
Department of Mechanical Engineering, PVPIT, Pune, India, 411021
Abstract –The objective of this paper is to present case study on a wearing insert and cutting ring for the efficient
improvements in productivity with the help of various work Study Methods. In this study productivity is improved through
identifying the process that involves the time required for the process as the main reason to achieve the objectives of
increasing the productivity. Time and motion study is one of the necessary factors to set a standard target. The study is
aimed at identifying the unwanted work processes which in turn increases the time required, efforts as well as the cost of
the product. Thus the changes were made in the areas which require improving using work study methods.
Keywords-Work Study, Productivity, Standard Target, Motion and time study.
I- INTRODUCTION
The objective of this case study is to put the topic of
productivity in perspective and productivity
improvement of ''Wearing Insert and Cutting Ring''.
Accordingly, the different definitions and the
measurement problems at different levels are presented
in the next section and the benefits of higher productivity
are discussed in final section. Productivity improvement
is to do the right things better and make it a part of
continuous process. Therefore it is important to adopt
efficient productivity improvement technique so as to
ensure individuals and organization’s growth in
productivity. The aim of this chapter is to introduce and
understand productivity improvement, various
techniques of productivity improvement, work study and
its relation with productivity improvement. In a
production department of an industry there is unwanted
processes are conducted often the same work can be
done using less time by reducing unwanted time and
adapting to less time consuming methods. Time required
for overall production of product can also be reduced by
making small but effective changes in the layout of the
process flow of a product.
Work study is an important management tool to achieve
higher productivity. It is related to human work, method
of doing work and standard of performance. The survival
of any organization is dependent on use of latest
technology and efficient methods of production. To
improve efficiency of production it needs effective
utilization of plant, equipment and labour. This can be
achieved by using work study which studies method and
evaluate the performance. It divides work into smaller
elements, studies it, and rearranges it to get same or
greater efficiency at reduced cost.
Time study is defined as a work measurement technique
for recording the times and rates of working for the
elements of specified job carried out under specified
conditions, and for analyzing the data so as to obtain the
time necessary for carrying out the job at a defined level
of performance. Time and motion study was carried out
for the wearing insert and cutting ring.
International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018
www.ijecs.net
16
Fig1- Cutting Ring
Fig. 2- Cutting Ring (Section View)
Problem Identification: In manufacturing the material
handling equipment involves few parts which undergoes
failure and need to be tested under quality assurance
with maximum non-productive time. Therefore, the
objective is to minimize risk factors with improved
productivity in manufacturing.
Allowances are generally applied to total cycle time as
some percentage of it, but sometimes these are given
separately for machine time as some % and for manual
effort time some other %. However, no allowances are
given for interruptions which may be due to factors
which are within the operator's control or which are
avoidable.
FORMULAE:
1. Basic time= Observed time * rating/ standard rating.
2. Standard time= Work content + contingency delay
allowance.
II-METHOLOGY
1. Study of Problem identification and literature
review.
2. Conduction of method study and time study as
per industry standard.
3. Preparation of flow process chart and finding
basic time and normal time by using time study
for specific operations.
4. Analyze the prepared process flow chart and
Calculate standard time.
5. Calculate normal time with addition of
allowances.
6. 6.Compare existing time and calculated time
required with standard time of process.
7. Finding the Productivity improvement solutions
to obtain results.
III- DATA COLLECTION
Wearing Insert:
Raw material comes in the shop which is a casting
product. This is stored in storage area to be used.
Spectro-test is done on the product to check if material
content in the product as per specification.After Spectro
test that product is sent to the Grinding station where
required surface finish is obtained. Then it is sent to the
VMC-1 station where inner diameter is done. Then it is
unloaded and sent to the VMC-2 station where the outer
diameter is done. After that chamfering and surface
finish is done on the VMC-3 setup. Hardening is done
after finishing of that product is done. Then it is sent to
the quality department where inspection of that product
takes place, and inspection report is written. If the
product passes the inspection. Then it is sent to the
deburring where burrs are removed from the material
using various deburring tools and machines which are
operated manually. Then it is properly washed, dried and
coated with a coat of oil which protects it from various
corrosions. Then it is properly packed and then it is
either shipped to customer or stored in the storage area.
Cutting Ring:
Raw material comes in the shop as bar. Then its
dimensions are measured to see if it is as per
specifications. Then ultra-test is performed manually
followed by spectro test in which percentage of carbon
International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018
www.ijecs.net
17
content in material is identified. If material passes all the
tests then it is transferred to storage area. After spectro-
test that product is sent to the band saw floor where bar
is cut as per specified dimensions. Then the cut portion
is treated as raw for cutting ring. It is sent to CNC-1
setup where its internal diameter is machined as per
dimensions. After ID it is sent to CNC-2 setup for outer
diameter of cutting ring as per dimensions. The
chamfering and finishing operation is done on CNC-3
setup. Hardening is done after finishing of that product is
done. Then it is sent to the quality department where
inspection of that product takes place, and inspection
report is written. If the product passes the inspection.
Then it is sent to the deburring where burrs are removed
from the material using various deburring tools and
machines which are operated manually. Then it is
properly washed, dried and coated with a coat of oil
which protects it from various corrosions. Then it is
properly packed and then it is either shipped to customer
or stored in the storage.
IV- CONDUCTION OF METHOD STUDY AND
TIME STUDY
After conducting time study and method study following
data was gathered about present process and time
required for it and shown in figure below.
Fig. 3: Process Flow For Wearing Insert
Table 1: Wearing Insert Time Chart
Process Basic Time
(Min)
Allowance Std. Time
(Min)
5 85 5 90
10 40 5 45
15 50 5 55
20 22 3 25
25 10 5 15
30 6 4 10
35 15 1 16
40 2 - 2
45 5 0 5
Total Time 263
Fig. 4: Process Flow For Cutting Insert
Table 2: Cutting Ring Time Chart
Process Basic Time
(Min)
Allowance Std. Time
(Min)
5 42 3 45
10 16 4 20
15 14 2 16
20 10 5 15
25 10 5 15
30 5 5 10
35 5 5 10
40 2 - 2
45 5 - 5
Total Time 138
V-ANALYSIS
This section contains the process flows and time chart
after applying proposed methods.
International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018
www.ijecs.net
18
Fig 5: Proposed flow Wearing Insert
Fig 6: Proposed Flow Cutting Ring
Table 4:Propoed Time Chart Wearing Insert
Process Basic Time(Min) Allowance Std.
Time(Min)
5 85 5 90
10 40 5 45
15 50 5 55
20 10 5 15
25 6 4 10
30 15 1 16
35 2 - 2
40 5 0 5
Total Time 238
Table 5: Proposed time chart cutting ring
Process Basic Time(Min) Allowance Std. Time(Min)
5 42 3 45
10 16 4 20
15 14 2 16
20 10 5 15
25 10 5 15
30 5 5 10
35 2 - 2
40 5 - 5
Total Time 128
CONCLUSION
By making simple changes to the process, it can reduce
the time taken for each component to improve the flow
and speed up the process. From the above discussion it
can be concluded that the process can be improved based
on method study, work procedure and proper utilization
of machine. It will improve the current process by
reducing the process, time and the worker’s fatigue.
Table 6: Result Wearing Insert
Particulates
(Wearing
Insert)
Production %
Increase
Per
shift
Per
Day
Per
Week
Regular 6 18 108 7.69
Proposed 6.5 19.5 117
Table 7: Result Cutting Ring
Particulates(Cutting
Ring)
Production %
Increase
Per
shift
Per
Day
Per
week
Regular 7 21 126 12.5
Proposed 8 24 144
ACKNOWLEDGMENT
We thank to the company for giving us this opportunity
to complete our B.E. project titled “A Case Study on
Productivity Improvement of Wearing Insert and Cutting
Ring”.We express our gratitude to Dr. C M Sedani
(Principal, PVPIT) for his guidance and valuable support
towards this project.
REFERENCES
[1] MayankDev Singh “To improve productivity by using work study
& design a fixture in small scale industry”. Research gate
December 2012.
[2] Dr. C. M. Sedani ''A model for adopting good quality practices in
industries and assessing its impact on manufacturing practices
and performance''
[3] Khalid S. Al-Saleh “Productivity improvement of a motor vehicle
inspection station using motion and time study technique”.
Journal of King Saud University 23(1):33–41 · January 2011.
[4] Michal OMÁMIK, Ivan BARÁNEK they work on „Metrological
Control of Selected Surface Types of a Mechanical Part by Using
On-Machine Measurement System‟ Faculty of Material Science
International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018
www.ijecs.net
19
And Technology in Trnava Slovak University of Technology in
Bratislava.
[5] Rishabh Mishra “Productivity improvement in Automobile
industry by using method study” International journal of
scientific Engineering And Applied Science (IJSEAS) – Volume-1,
Issue-4, July 2015.
[6] Prathamesh P. Kulkarni, Sagar S. Kshire, Kailas V. Chandratre,
“Productivity Improvement Through Lean Deployment & Work
Study Methods” International Journal of Research in
Engineering and Technology.
[7] Mr.Dhruv H. Patel, Prof. V. N. Patni, “An Investigation Effect of
Machining Parameters on CNC ROUTER” 2014 IJEDR |
Volume 2, Issue 2 | ISSN: 2321-9939.
[8] Mst. MurshidaKhatun, “Effect of time and motion study on
productivity in garment sector” International Journal of
Scientific & Engineering Research, Volume 5, Issue 5, May-2014
ISSN 2229-5518.
[9] Er.Manpreet Singh, Er. SanjeevVerma, Dr.Sanjiv Kumar Jain, “A
literature review on machining of different materials with CNC”
International Journal of Emerging Research in Techniology,
August-2014.
Details of All Authors (Optional)
Sr.No Photo Details
1 Dr. C. M. Sedani
Email: cmsedani@gmail.com
2 Nikhil Dhumal
Email:
nikhildhumal143@gmail.com
3 Pramod Dhanave
Email:
pdhanave27@gmail.com
4 Hardik Lawande
Email:
lawandehardik@gmail.com
5 Aniruddha Mule
Email: asmule61@gmail.com

More Related Content

What's hot

Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Vishal Shinde
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and qualityMd. Mazadul Hasan Shishir
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET Journal
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurementEr. Vaibhav Agarwal
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET Journal
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET Journal
 
Process flow and process chart
Process flow and process chartProcess flow and process chart
Process flow and process chartParvesh Mittal
 
Industrial engineering for apparel production
Industrial engineering for apparel productionIndustrial engineering for apparel production
Industrial engineering for apparel productionNiloy Rahman
 
Operations Management Introduction
Operations Management IntroductionOperations Management Introduction
Operations Management IntroductionEr. Vaibhav Agarwal
 
Lecture 1 work study according to amravati university syllabus
Lecture 1 work study according to amravati university syllabus Lecture 1 work study according to amravati university syllabus
Lecture 1 work study according to amravati university syllabus rahulmeshram14
 
Quality Control
Quality ControlQuality Control
Quality Controlvishakeb
 
Process Design and Development of Engine Block
Process Design and Development of Engine BlockProcess Design and Development of Engine Block
Process Design and Development of Engine Blockpaperpublications3
 

What's hot (20)

Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)
 
Improving the productivity_and_introducing_the_work_study
Improving the productivity_and_introducing_the_work_studyImproving the productivity_and_introducing_the_work_study
Improving the productivity_and_introducing_the_work_study
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and quality
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurement
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
Work study
Work studyWork study
Work study
 
WORK study& LINE BALANCING
WORK study& LINE BALANCING WORK study& LINE BALANCING
WORK study& LINE BALANCING
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 Housing
 
Management tools
Management toolsManagement tools
Management tools
 
Process flow and process chart
Process flow and process chartProcess flow and process chart
Process flow and process chart
 
Industrial engineering for apparel production
Industrial engineering for apparel productionIndustrial engineering for apparel production
Industrial engineering for apparel production
 
Operations Management Introduction
Operations Management IntroductionOperations Management Introduction
Operations Management Introduction
 
Method study
Method studyMethod study
Method study
 
Lecture 1 work study according to amravati university syllabus
Lecture 1 work study according to amravati university syllabus Lecture 1 work study according to amravati university syllabus
Lecture 1 work study according to amravati university syllabus
 
Work Study Part- I
Work Study Part- IWork Study Part- I
Work Study Part- I
 
Quality Control
Quality ControlQuality Control
Quality Control
 
Process Design and Development of Engine Block
Process Design and Development of Engine BlockProcess Design and Development of Engine Block
Process Design and Development of Engine Block
 

Similar to A case study on productivity improvement of wearing insert and cutting ring

Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringAmanuzzaman Aman
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET Journal
 
Presentation1 work study.pptx
Presentation1 work study.pptxPresentation1 work study.pptx
Presentation1 work study.pptxmesfin88
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction ProjectIRJET Journal
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...IRJET Journal
 
Guidelines industrial engineering
Guidelines industrial engineeringGuidelines industrial engineering
Guidelines industrial engineeringSyed Jafri
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET Journal
 
Productivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodsProductivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodseSAT Journals
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) ConceptIRJET Journal
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET Journal
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...ijtsrd
 
Production management
Production managementProduction management
Production managementVivan Kumar
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingeSAT Publishing House
 
5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workloadeSAT Publishing House
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolIRJET Journal
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...PERUMALSAMY M
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryIRJET Journal
 

Similar to A case study on productivity improvement of wearing insert and cutting ring (20)

Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial Engineering
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
 
Presentation1 work study.pptx
Presentation1 work study.pptxPresentation1 work study.pptx
Presentation1 work study.pptx
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction Project
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...
 
Guidelines industrial engineering
Guidelines industrial engineeringGuidelines industrial engineering
Guidelines industrial engineering
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
Productivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodsProductivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methods
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
 
Work study manual
Work study manualWork study manual
Work study manual
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...
 
Production management
Production managementProduction management
Production management
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

A case study on productivity improvement of wearing insert and cutting ring

  • 1. International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018 www.ijecs.net 15 A Case Study on Productivity Improvement of Wearing Insert and Cutting Ring Dr. C. M. sedani1 , Nikhil Dhumal2 , Pramod Dhanave3 , Hardik Lawande4 , Aniruddha Mule5 1 Professor ,2,3,4,5 UG Students Department of Mechanical Engineering, PVPIT, Pune, India, 411021 Abstract –The objective of this paper is to present case study on a wearing insert and cutting ring for the efficient improvements in productivity with the help of various work Study Methods. In this study productivity is improved through identifying the process that involves the time required for the process as the main reason to achieve the objectives of increasing the productivity. Time and motion study is one of the necessary factors to set a standard target. The study is aimed at identifying the unwanted work processes which in turn increases the time required, efforts as well as the cost of the product. Thus the changes were made in the areas which require improving using work study methods. Keywords-Work Study, Productivity, Standard Target, Motion and time study. I- INTRODUCTION The objective of this case study is to put the topic of productivity in perspective and productivity improvement of ''Wearing Insert and Cutting Ring''. Accordingly, the different definitions and the measurement problems at different levels are presented in the next section and the benefits of higher productivity are discussed in final section. Productivity improvement is to do the right things better and make it a part of continuous process. Therefore it is important to adopt efficient productivity improvement technique so as to ensure individuals and organization’s growth in productivity. The aim of this chapter is to introduce and understand productivity improvement, various techniques of productivity improvement, work study and its relation with productivity improvement. In a production department of an industry there is unwanted processes are conducted often the same work can be done using less time by reducing unwanted time and adapting to less time consuming methods. Time required for overall production of product can also be reduced by making small but effective changes in the layout of the process flow of a product. Work study is an important management tool to achieve higher productivity. It is related to human work, method of doing work and standard of performance. The survival of any organization is dependent on use of latest technology and efficient methods of production. To improve efficiency of production it needs effective utilization of plant, equipment and labour. This can be achieved by using work study which studies method and evaluate the performance. It divides work into smaller elements, studies it, and rearranges it to get same or greater efficiency at reduced cost. Time study is defined as a work measurement technique for recording the times and rates of working for the elements of specified job carried out under specified conditions, and for analyzing the data so as to obtain the time necessary for carrying out the job at a defined level of performance. Time and motion study was carried out for the wearing insert and cutting ring.
  • 2. International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018 www.ijecs.net 16 Fig1- Cutting Ring Fig. 2- Cutting Ring (Section View) Problem Identification: In manufacturing the material handling equipment involves few parts which undergoes failure and need to be tested under quality assurance with maximum non-productive time. Therefore, the objective is to minimize risk factors with improved productivity in manufacturing. Allowances are generally applied to total cycle time as some percentage of it, but sometimes these are given separately for machine time as some % and for manual effort time some other %. However, no allowances are given for interruptions which may be due to factors which are within the operator's control or which are avoidable. FORMULAE: 1. Basic time= Observed time * rating/ standard rating. 2. Standard time= Work content + contingency delay allowance. II-METHOLOGY 1. Study of Problem identification and literature review. 2. Conduction of method study and time study as per industry standard. 3. Preparation of flow process chart and finding basic time and normal time by using time study for specific operations. 4. Analyze the prepared process flow chart and Calculate standard time. 5. Calculate normal time with addition of allowances. 6. 6.Compare existing time and calculated time required with standard time of process. 7. Finding the Productivity improvement solutions to obtain results. III- DATA COLLECTION Wearing Insert: Raw material comes in the shop which is a casting product. This is stored in storage area to be used. Spectro-test is done on the product to check if material content in the product as per specification.After Spectro test that product is sent to the Grinding station where required surface finish is obtained. Then it is sent to the VMC-1 station where inner diameter is done. Then it is unloaded and sent to the VMC-2 station where the outer diameter is done. After that chamfering and surface finish is done on the VMC-3 setup. Hardening is done after finishing of that product is done. Then it is sent to the quality department where inspection of that product takes place, and inspection report is written. If the product passes the inspection. Then it is sent to the deburring where burrs are removed from the material using various deburring tools and machines which are operated manually. Then it is properly washed, dried and coated with a coat of oil which protects it from various corrosions. Then it is properly packed and then it is either shipped to customer or stored in the storage area. Cutting Ring: Raw material comes in the shop as bar. Then its dimensions are measured to see if it is as per specifications. Then ultra-test is performed manually followed by spectro test in which percentage of carbon
  • 3. International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018 www.ijecs.net 17 content in material is identified. If material passes all the tests then it is transferred to storage area. After spectro- test that product is sent to the band saw floor where bar is cut as per specified dimensions. Then the cut portion is treated as raw for cutting ring. It is sent to CNC-1 setup where its internal diameter is machined as per dimensions. After ID it is sent to CNC-2 setup for outer diameter of cutting ring as per dimensions. The chamfering and finishing operation is done on CNC-3 setup. Hardening is done after finishing of that product is done. Then it is sent to the quality department where inspection of that product takes place, and inspection report is written. If the product passes the inspection. Then it is sent to the deburring where burrs are removed from the material using various deburring tools and machines which are operated manually. Then it is properly washed, dried and coated with a coat of oil which protects it from various corrosions. Then it is properly packed and then it is either shipped to customer or stored in the storage. IV- CONDUCTION OF METHOD STUDY AND TIME STUDY After conducting time study and method study following data was gathered about present process and time required for it and shown in figure below. Fig. 3: Process Flow For Wearing Insert Table 1: Wearing Insert Time Chart Process Basic Time (Min) Allowance Std. Time (Min) 5 85 5 90 10 40 5 45 15 50 5 55 20 22 3 25 25 10 5 15 30 6 4 10 35 15 1 16 40 2 - 2 45 5 0 5 Total Time 263 Fig. 4: Process Flow For Cutting Insert Table 2: Cutting Ring Time Chart Process Basic Time (Min) Allowance Std. Time (Min) 5 42 3 45 10 16 4 20 15 14 2 16 20 10 5 15 25 10 5 15 30 5 5 10 35 5 5 10 40 2 - 2 45 5 - 5 Total Time 138 V-ANALYSIS This section contains the process flows and time chart after applying proposed methods.
  • 4. International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018 www.ijecs.net 18 Fig 5: Proposed flow Wearing Insert Fig 6: Proposed Flow Cutting Ring Table 4:Propoed Time Chart Wearing Insert Process Basic Time(Min) Allowance Std. Time(Min) 5 85 5 90 10 40 5 45 15 50 5 55 20 10 5 15 25 6 4 10 30 15 1 16 35 2 - 2 40 5 0 5 Total Time 238 Table 5: Proposed time chart cutting ring Process Basic Time(Min) Allowance Std. Time(Min) 5 42 3 45 10 16 4 20 15 14 2 16 20 10 5 15 25 10 5 15 30 5 5 10 35 2 - 2 40 5 - 5 Total Time 128 CONCLUSION By making simple changes to the process, it can reduce the time taken for each component to improve the flow and speed up the process. From the above discussion it can be concluded that the process can be improved based on method study, work procedure and proper utilization of machine. It will improve the current process by reducing the process, time and the worker’s fatigue. Table 6: Result Wearing Insert Particulates (Wearing Insert) Production % Increase Per shift Per Day Per Week Regular 6 18 108 7.69 Proposed 6.5 19.5 117 Table 7: Result Cutting Ring Particulates(Cutting Ring) Production % Increase Per shift Per Day Per week Regular 7 21 126 12.5 Proposed 8 24 144 ACKNOWLEDGMENT We thank to the company for giving us this opportunity to complete our B.E. project titled “A Case Study on Productivity Improvement of Wearing Insert and Cutting Ring”.We express our gratitude to Dr. C M Sedani (Principal, PVPIT) for his guidance and valuable support towards this project. REFERENCES [1] MayankDev Singh “To improve productivity by using work study & design a fixture in small scale industry”. Research gate December 2012. [2] Dr. C. M. Sedani ''A model for adopting good quality practices in industries and assessing its impact on manufacturing practices and performance'' [3] Khalid S. Al-Saleh “Productivity improvement of a motor vehicle inspection station using motion and time study technique”. Journal of King Saud University 23(1):33–41 · January 2011. [4] Michal OMÁMIK, Ivan BARÁNEK they work on „Metrological Control of Selected Surface Types of a Mechanical Part by Using On-Machine Measurement System‟ Faculty of Material Science
  • 5. International Journal of Engineering and Creative Science, Vol. 1, No. 1, 2018 www.ijecs.net 19 And Technology in Trnava Slovak University of Technology in Bratislava. [5] Rishabh Mishra “Productivity improvement in Automobile industry by using method study” International journal of scientific Engineering And Applied Science (IJSEAS) – Volume-1, Issue-4, July 2015. [6] Prathamesh P. Kulkarni, Sagar S. Kshire, Kailas V. Chandratre, “Productivity Improvement Through Lean Deployment & Work Study Methods” International Journal of Research in Engineering and Technology. [7] Mr.Dhruv H. Patel, Prof. V. N. Patni, “An Investigation Effect of Machining Parameters on CNC ROUTER” 2014 IJEDR | Volume 2, Issue 2 | ISSN: 2321-9939. [8] Mst. MurshidaKhatun, “Effect of time and motion study on productivity in garment sector” International Journal of Scientific & Engineering Research, Volume 5, Issue 5, May-2014 ISSN 2229-5518. [9] Er.Manpreet Singh, Er. SanjeevVerma, Dr.Sanjiv Kumar Jain, “A literature review on machining of different materials with CNC” International Journal of Emerging Research in Techniology, August-2014. Details of All Authors (Optional) Sr.No Photo Details 1 Dr. C. M. Sedani Email: cmsedani@gmail.com 2 Nikhil Dhumal Email: nikhildhumal143@gmail.com 3 Pramod Dhanave Email: pdhanave27@gmail.com 4 Hardik Lawande Email: lawandehardik@gmail.com 5 Aniruddha Mule Email: asmule61@gmail.com