The document provides a weekly update on activities at the Wizards Stadium Project for the week of May 17, 2010. Mass excavation and grading continued in areas 1 and 3, while storm sewer and electrical ductbank installation were ongoing. Foundations work such as footing installation was in progress. Structural steel erection was nearing completion in area 1 up to column line 23. Planned activities for the next week included continuing excavation, utility installation, foundations work, and beginning structural steel erection in sequence 1-4. Photos documented progress on encasement, reinforcing, decking, and concrete work.
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 5.19.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
5.17.2010
Current Activities this Week:
Mass Excavation:
Grading is ongoing in Area 3. Backfilling of on-grade
is ongoing in Area 1.
Site Utilities:
Installation of the new electrical ductbank is complete.
Field Level Area 1 – Wizards Team Bench
Storm Sewer installation (Line 6000) is ongoing on concrete is placed.
east side of France Family Drive.
Foundations:
Area 3 Field Level – Footing installation is ongoing and is
Complete to Column Line 6.
Area 4 Mezzanine Level – Installation of Drilled Piers
are ongoing.
Structural Steel Erection: Field Level Area 1 – South Field Wall
Area 1 – Steel Erection in sequence 1-2 is nearly installation is ongoing.
complete to Column Line 23
Decking is nearly complete in sequence 1-1 on
Mezzanine and Concourse Levels. Installation of studs
and edge plates have started. Decking on Suite Level
has started.
Area 2 – Electrical Ductbank relocation is
complete.
Building the Future
2. Underground Electrical:
Secondary service ducts is complete from Electrical Room
01.34.04 south past Column Line 25.
Installation of secondary service ducts at Column Line D
Is installed to Column Line 24.
Projected Activities occurring next Week: Concourse Level Area 1 – Decking, studs and
edge plating installed at Main Club.
Mass Excavation:
Grading at Truck Dock Area will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue.
Deep Underground Plumbing:
Sanitary in Area 3 will continue.
Area 1 – Structural Steel Erection at West
Foundations: Building to Suite Level 1 Floor is nearly
Area 2 Field Level – Placement of foundation walls east of complete to 23-Line.
Stage will continue.
Area 3 Field Level – Footing placement will continue and
wall installation will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-4 will begin.
Decking installation on Suite Level of Sequence 1-1 will
continue.
Field Level Area 1 – Shot looking north from
Concourse Level.
Building the Future
3. Additional Photos:
Field Level Area 1 – Concrete encasement of Field Level Area 3 – Wall reinforcing mats
Structural Steel columns. installed at SE vomitory and A-Line wall.
Field Level Area 2 – A-Line reinforcing in Field Level Area 1 – Hydrotherapy pit base
place from Column Lines 14-12. concrete being installed.
Mezzanine Level Area 1 – Decking, studs and
edge plating nearly complete at VIP Field Level Area 1 – Shot looking NW at
Entrance. Wizards Team Bench Area.