This is a brief slide show that covers my current and recent projects. I have also included CPM reports created in Primavera P6 some of the following subjects; covering critical path, schedule variance, earned value and cash flow as well as predecessor and successor reports. Beyond that I have included examples of 2D and 3D logistics and site plans that I have created in the past.
3. PHILADELPHIA FAMILY COURT
• CURRENT PROJECT.
• A 14 STORY COURTHOUSE
LOCATED IN CENTER CITY
PHILADELPHIA.
• A MULTI-PRIME PROJECT.
• TISHMAN IS SERVING AS
OWNERS
REPRESENTATIVE.
• KEATING BUILDING CORP
IS THE GENERAL
CONTRACTOR.
4. PHILADELPHIA CONVENTION
CENTER
• MY MOST RECENT PROJECT.
• A $786 MILLION EXPANSION
TO THE EXISTING
CONVENTION CENTER.
• NEARLY DOUBLED THE SIZE
OF THE EXISTING CENTER
TO A TOTAL OF 2.3 MILLION
SQUARE FEET.
6. COMCAST CENTER
• AT 975 FEET TALL, THE
COMCAST CENTER IS THE
TALLEST BUILDING IN
PHILADELPHIA AND THE
CENTER IS ALSO THE
TALLEST “GREEN” BUILDING
IN THE COUNTRY.
• HILL INTL. SERVED AS
OWNERS REP FOR THIS $300
MILLION
• LF DRISCOLL WAS THE
GENERAL CONTRACTOR.
8. PHILADELPHIA SCHOOL DISTRICT
RECONSTRUCTION PROGRAM
• A $1.3 BILLION PROGRAM TO
RENOVATE AND REBUILD THE
LEARNING FACILITIES WITH IN
THE PHILADELPHIA SCHOOL
DISTRICT.
• A JOINT VENTURE OF URS/JJS
WITH MCKISSACK &
ASSOCIATES.
• THE JV TEAM OVERSAW
NUMEROUS CM FIRMS &
GENERAL CONTRACTORS ON
PROJECTS DISTRICT WIDE.
17. SAMPLE VARIANCE SCHEDULE
Activity ID Activity Name OD Activity %
Complete
Start Finish Total Float
TotalTotal 88 22-Nov-10 A 04-Apr-11 0
Data Center ExpanData Center Expansion - (Recovery) 88 22-Nov-10 A 04-Apr-11 0
Pre-ConstructionPre-Construction 27 22-Nov-10 A 21-Jan-11 61
PermitingPermiting 0 22-Nov-10 A 21-Jan-11 A
0110 File Permit Drawings 0 100% 22-Nov-10 A
0120 Permit Issuance 0 100% 21-Jan-11 A
BiddingBidding 0 10-Jan-11 10-Jan-11 -19
0160 Award 0 0% 10-Jan-11* -19
MobilizationMobilization 1 10-Jan-11 10-Jan-11 -19
A1000 Mobilization 1 0% 10-Jan-11* 10-Jan-11 -19
Site WorkSite Work 3 10-Jan-11 12-Jan-11 -4
A1010 Temporary Protection 3 0% 10-Jan-11 12-Jan-11 -4
DemoDemo 7 12-Jan-11 20-Jan-11 -4
0230 Partial Demo - Raised Floor @ New Wall Construction Locations 1 0% 12-Jan-11 12-Jan-11 -4
0240 Ceiling 3 0% 13-Jan-11 17-Jan-11 -4
0250 Piping 5 0% 14-Jan-11 20-Jan-11 -4
0350 Ductwork 5 0% 14-Jan-11 20-Jan-11 -4
0360 Lighting 5 0% 14-Jan-11 20-Jan-11 -4
0370 Fire Suppression 5 0% 14-Jan-11 20-Jan-11 -4
0380 Power 5 0% 14-Jan-11 20-Jan-11 -4
0390 Remove & Safe Fire Alarm Detectors 5 0% 14-Jan-11 20-Jan-11 -4
ConstructionConstruction 52 21-Jan-11 04-Apr-11 0
0170 Frame Walls 3 0% 21-Jan-11 25-Jan-11 -4
0470 Rough Fire Supression Piping (Above Ceiling) 5 0% 21-Jan-11 27-Jan-11 17
0480 Rough Electrical Wiring (Above Ceiling) 5 0% 21-Jan-11 27-Jan-11 17
0580 Install Electrical Distribution Panels 5 0% 21-Jan-11 27-Jan-11 47
0600 Install Raceways & Back Boxes For Security System 2 0% 25-Jan-11 26-Jan-11 -4
0180 Rock Walls 5 0% 27-Jan-11 02-Feb-11 -4
0400 Spackle 3 0% 02-Feb-11 04-Feb-11 -4
0520 Install Doors/Frames/Hardware 1 0% 02-Feb-11 02-Feb-11 -2
0190 Paint 3 0% 07-Feb-11 09-Feb-11 -4
0410 Install CRAH Unit Stands 1 0% 09-Feb-11 09-Feb-11 -4
0510 Install PDU Stands 1 0% 09-Feb-11 09-Feb-11 31
0210 Install Ceiling Grid 5 0% 10-Feb-11 16-Feb-11 8
0420 Install Stands - UPS Stands 1 0% 10-Feb-11 10-Feb-11 -4
0500 Install Square D Switch Boards 5 0% 10-Feb-11 16-Feb-11 33
0610 Install Blocking as Required 5 0% 10-Feb-11 16-Feb-11 33
0640 Install CRAH's 7 0% 10-Feb-11 18-Feb-11 31
0690 Install PDU's 7 0% 10-Feb-11 18-Feb-11 31
0490 Install UPS 7 0% 11-Feb-11 21-Feb-11 -4
0200 Install Lighting 4 0% 16-Feb-11 21-Feb-11 8
Jan Feb Mar Apr May
2 2011
Permit Issuance
Award
Mobilization
Temporary Protection
Partial Demo - Raised Floor @ New Wall Construction Locations
Ceiling
Piping
Ductwork
Lighting
Fire Suppression
Power
Remove & Safe Fire Alarm Detectors
Frame Walls
Rough Fire Supression Piping (Above Ceiling)
Rough Electrical Wiring (Above Ceiling)
Install Electrical Distribution Panels
Install Raceways & Back Boxes For Security System
Rock Walls
Spackle
Install Doors/Frames/Hardware
Paint
Install CRAH Unit Stands
Install PDU Stands
Install Ceiling Grid
Install Stands - UPS Stands
Install Square D Switch Boards
Install Blocking as Required
Install CRAH's
Install PDU's
Install UPS
Install Lighting
Full Schedule - Recovery
18. SAMPLE CASH FLOW REPORT
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr ay
2008 2009 2010 2011
$6,000,000
$12,000,000
$18,000,000
$24,000,000
$30,000,000
$60,000,000
$120,000,000
$180,000,000
$240,000,000
$300,000,000
Page 1 of 2 TASK filter: All Activities