About Production Planning Process of a RMG !!!

Mahibur Rahman
Mahibur RahmanProduction Planner en Mahmud Group

Mahibur Rahman Asst. Manager | Production Planning | Mahmud Jeans Ltd. | Mahmud Group Factory: Hartokitola, Chandra, Kaliakoir, Gazipur Corporate Office: House-25, Road-10, Sector-06, Uttara Model Town, Dhaka-1230, Bangladesh

Training Syllabus
Topic: How we do Plan???
Content ………………………….
1. Key Information
2. Product Range
3. Technical Details
4. Planning & Control
* Planning Strategy
* Consideration
* Priority
* Capacity Allocation as per Buyer Volume
* Buyer Allocation
* Learning Curve / ladder of Productivity
* Execution at a Glance
* Conclusion
1. Key information
Mahmud Jeans Limited (MJL) is one of the leading Garments manufacturer
and exporters of readymade Garments and a sister concern of Mahmud Group.
It’s designed and installed with state of the art equipment, 100% compliant
well equipped Garments manufacturer among the Garments Industries in
Bangladesh.
3200
Employees
22
No. Of Line
Fully Vertical Setup - spinning, waving, stitching, washing and finishing
Year of Establishment: 2009
Production Capacity
Spinning: 30 tons per day
Weaving (Denim): 100,000 yds per day
Sewing & finishing: 40,000 pcs per day
Washing: 45,000 pcs per day
Factory Space: 2, 26000 sft
Group Turnover: USD 102.00 million per year.
Mahmud Jean’s t/o: USD 50.00 million per year.
Total Manpower: 3,200
Management Personnel: 175
Our Motto
Growing business together with our valuable customer by providing
 Best product
 Best quality
 Best service & above all
 On-time delivery
Mahmud Group: Difference is our people…………..
Our renowned customers are.
 Sweden, USA, Europe, Canada, Netherland.
H&M, K.Mart, C&A, Hema, G3, Asmara, Tally Weijl, Mango, OVS, Best Seller
Kauf land, Jordache, Carre Four, Lager
2. Production range (styling)
Basically we are woven garment manufacturer. We produce Trousers, Skirt,
Unlined Jacket, Overall, Short all, Shorts, School Dress, Shirt.
3. Technical detail
 Cutting Section:
Equipped with computer aided designing, marker making, manual
spreading & cutting.
 Computer Aided Designing (CAD):
Computer aided designing equipped with TUKA and Leuctra systems
with digitizing board and full width pattern plotter.
 Sewing Section:
This section is comprised of Latest generation JUKI, FDM, Brothers,
Kansai, Vibe Mac sewing machines with automatic thread trimming and
sucking device also ETON line.
 Finishing Section:
This section is equipped with skilled manpower, metal detector, vacuum
table, steam iron, thread sucker and other modern facilities.
4. Production planning and control
What is planning?
Planning is a detailed proposal of doing or achieving something.
Especially it consists of the planning of routing, scheduling, dispatching
inspection, and coordination.
Production planning without production control is like a bank without a bank
manager, planning initiates action while control is an adjusting process,
providing corrective measures for planned development. Production control
regulates and stimulates the orderly how of materials in the manufacturing
process from the beginning to the end.
Production Planning and Control (PPC) is a process that comprises the
Performance of some critical; functions on either side, viz., planning as well as
Control.
Production Planning and control
Production Planning Production Control
Planning Dispatching
Routing Following up
Scheduling Inspection
Loading Corrective
Production planning:
Production planning may be defined as the technique of foreseeing every step
in a long series of separate operations, each step to be taken at the right time
and in the right place and each operation to be performed in maximum
efficiency. It helps entrepreneur to work out the quantity of material
manpower, machine and money requires for producing predetermined level of
output in given period of time.
Routing: Under this, the operations, their path and sequence are
established. To perform these operations the proper class of machines
and personnel required are also worked out. The main aim of routing is
to determine the best and cheapest sequence of operations and to ensure
this sequence is strictly followed
Scheduling: It means working out of time that should be required to
perform each operation and also the time necessary to perform the entire
series as routed, making allowances for all factors concerned. It mainly
concerns with time element and priorities of a job.
Loading: The next step is the execution of the schedule plan as per the
route chalked out it includes the assignment of the work to the operators
at their machines or places.
So loading determines who will do the work as routing determines where and
scheduling determines when it shall be done.
Dispatching: Dispatching involves issue of production orders for starting
the operations. Necessary authority and conformation is given
Dispatching is an important step as it translates production plans into
production.
Follow up: Every production programmed involves determination of the
progress of work, removing bottlenecks in the flow of work and ensuring
that the productive operations are taking place in accordance with the
plans. It spots delays or deviations from the production plans. It helps to
reveal detects in routing and scheduling, misunderstanding of orders
and instruction, under loading or overloading of work etc. All problems
or deviations are investigated and remedial measures are undertaken to
ensure the completion of work by the planned date.
Inspection: This is mainly to ensure the quality of goods. It can be
required as effective agency of production control.
Corrective measures: Corrective action may involve any of those
activities of adjusting the route, rescheduling of work changing the
workloads, repairs and maintenance of machinery or equipment, control
over inventories of the cause of deviation is the poor performance of the
employees. Certain personnel decisions like training, transfer, demotion
etc. may have to be taken. Alternate methods may be suggested to
handle peak loads.
Capacity Allocation
We have capacity to produce (projected)
Quantity 750000pcs
Minutes 12750000minutes
Production planning Strategy.
1. Opportunity invention
2. Sustains
3. Overcome the weakness
4. Prefer the priority
5. Implement the rules & regulation
6. Evaluate the rules & regulation
7. Projection for next 1 year
8. Mission & Visions
Consideration of planning
 Order quantity
 Pcd, tod and lead time
 Styling (Basic, semi critical, critical)
 Line capability and capacity
 SMV, manpower and working hours
 Learning curve considering previous record
 Machinery and technical attachment
 Wash and finishing
Learning curve and ladder of productivity.
During the style selection we have to follow the ladder diagram and learning
curve like as mentioned below.
Learning Curve 2
Item Basic Pant
SMV 16
M/P 70
W/H 10
Height Efficiency = (70 %) Denim
Height Efficiency = (60 %) Denim
spandex
Required
Pic Day
1st 2nd 3rd 4th 5th
Required % 20% 30% 50% 60% 60%
Actual tgt 447 655 1091 1309 1527
Plan tgt 400 600 1100 1300 1600
Planning (Execution at a glance)
Suppose we are doing H&M buyers order as per our previous history then we
follow the order chart for month also Pcd, X-Factory and X-Country after that
look for line and space which are not loaded /which are near about input
date.
Than talk to merchant about fabric, accessories, PP comments to make sure
size sets before Pcd and make a chart for production schedule as below.
0%
50000%
100000%
150000%
200000%
1st 2nd 3rd 4th 5th
Required %
Actual tgt
Plan tgt
H&M Sunday Tagging / 85983pcs / 1000pcs per day
Date 5 13 16 Total/Day G.ttl
Req Ship Qty
till
15-Jun 0 0
16-Jun 0 0
17-Jun 0 0
18-Jun 0 0
19-Jun 0 0
20-Jun 100 100 100
21-Jun 200 200 300
22-Jun 400 400 700
23-Jun 600 100 700 1400
24-Jun 800 200 1000 2400
25-Jun 900 400 1300 3700
26-Jun 0 3700
27-Jun 1000 600 1600 5300
28-Jun 1000 800 1800 7100
29-Jun 1000 900 1900 9000
30-Jun 1000 1000 2000 11000
1-Jul 1000 1000 2000 13000
2-Jul 1000 1000 2000 15000
3-Jul 0 15000
4-Jul 1000 1000 2000 17000
5-Jul 1000 1000 2000 19000
6-Jul 1000 1000 100 2100 21100
7-Jul 1000 1000 200 2200 23300
8-Jul 1000 1000 400 2400 25700
9-Jul 1000 1000 600 2600 28300
10-Jul 0 28300
11-Jul 1200 1000 800 3000 31300
12-Jul 1200 1000 900 3100 34400 8656
13-Jul 1200 1000 1000 3200 37600 9002
14-Jul 1000 1000 2000 39600
15-Jul 1000 1000 2000 41600
16-Jul 800 800 1600 43200
17-Jul 0 43200
18-Jul 0 43200
19-Jul 0 43200 19508
20-Jul 0 43200 29290
21-Jul 0 43200
22-Jul 0 43200
23-Jul 0 43200
Need SMV from costing department
Make a calculation
Like that…………………………..
Style SMV 16
M/P 70
W/H 10
Wanted efficiency = 70 %
NB. Need to maintain this
Allowance range
4 % PLUS FOR SPANDEX+ DENIM
3% OR 2.50% PLUS FOR NON WASH
here we have to Add 4 % allowance of required qty
of required date
If the line doesn’t meet the qty of require the find
out another suitable line or share the plan
production on another line
Then go to the plan layout
put the day with color of ending day
& give a arrow sign
For an Example……………
Suppose there are every line are blank to get style before the input date.
Then what should we do?
Then talk to merchant. I2f he able to pick the date forward by change the
loading will be loaded as per this condition
Buyer GAP
Style 547882
Smv 24.5
Qty 5086
Input Date 18-Sep
delivery date 30-Sep
Otherwise that early days will be remaining blank & style date will be the
same. Blank 3 0r 4 days may occupied by another qty of another style
After doing this things merchant confirm us about PP & OTHERS APPROVAL
Then we send the mail about fabric transfer regarding on that style to store.
After getting bulk permission we go for bulk production. In the that time we
have to keep our close eyes for current production & productivity .wash
follow up &cutoff schedule also maintain by us by conducting with
production responsible .we take a review meeting every week with all
concern factory for developing, review & problem analysis .
Conclusion: according to this system we are the MJL Planning Team are
trying to meet our Mission & Vision. Though have some discrimination but
trying to overcome it. We are implementing the ERP software planning in the
group. As a result it will be customized & helpful to all team

Recomendados

Capacity Planning In Garments Industry por
Capacity Planning In Garments IndustryCapacity Planning In Garments Industry
Capacity Planning In Garments IndustryShohag Ahammed
892 vistas17 diapositivas
Industrial engineering for apparel production por
Industrial engineering for apparel productionIndustrial engineering for apparel production
Industrial engineering for apparel productionNiloy Rahman
9.2K vistas19 diapositivas
QCO presentation por
QCO presentationQCO presentation
QCO presentationDababrata Mondal
1.1K vistas8 diapositivas
Analysis of sewing section efficiency by time study technique in apparel indu... por
Analysis of sewing section efficiency by time study technique in apparel indu...Analysis of sewing section efficiency by time study technique in apparel indu...
Analysis of sewing section efficiency by time study technique in apparel indu...Khairul Bashar
4.8K vistas31 diapositivas
Capacity planning in garment industry22 (3 files merged) por
Capacity planning in garment industry22 (3 files merged)Capacity planning in garment industry22 (3 files merged)
Capacity planning in garment industry22 (3 files merged)Ankur Shukla
9.9K vistas9 diapositivas
How to Improve Productivity por
How to Improve ProductivityHow to Improve Productivity
How to Improve ProductivitySunjib Anwar; MBA,SCSS
2.7K vistas23 diapositivas

Más contenido relacionado

La actualidad más candente

Application of industrial engineering techniques in garments production por
Application of industrial engineering techniques      in garments productionApplication of industrial engineering techniques      in garments production
Application of industrial engineering techniques in garments productionMd.Abdur Rahim Al Bahar
12.2K vistas88 diapositivas
21548667 t-shirt-operation-breakdown por
21548667 t-shirt-operation-breakdown21548667 t-shirt-operation-breakdown
21548667 t-shirt-operation-breakdownvikram kumar
16K vistas9 diapositivas
Advance manufacturing system in sewing floor por
Advance manufacturing system in sewing floorAdvance manufacturing system in sewing floor
Advance manufacturing system in sewing floorBangladesh University of Textiles
1.9K vistas28 diapositivas
Work study por
Work studyWork study
Work studySaifur Rahman
3.1K vistas81 diapositivas
IE working procedure por
IE working procedureIE working procedure
IE working procedureSafayet Dishan
8.2K vistas13 diapositivas
Line balancing por
Line balancing Line balancing
Line balancing Md. Mazadul Hasan Shishir
1.7K vistas17 diapositivas

La actualidad más candente(20)

Application of industrial engineering techniques in garments production por Md.Abdur Rahim Al Bahar
Application of industrial engineering techniques      in garments productionApplication of industrial engineering techniques      in garments production
Application of industrial engineering techniques in garments production
21548667 t-shirt-operation-breakdown por vikram kumar
21548667 t-shirt-operation-breakdown21548667 t-shirt-operation-breakdown
21548667 t-shirt-operation-breakdown
vikram kumar16K vistas
Analysis of sewing section efficiency by using time study technique in Appare... por Khairul Bashar
Analysis of sewing section efficiency by using time study technique in Appare...Analysis of sewing section efficiency by using time study technique in Appare...
Analysis of sewing section efficiency by using time study technique in Appare...
Khairul Bashar2.7K vistas
Standardization & digitalization of sewing operations por Arpan Mahato
Standardization & digitalization of sewing operationsStandardization & digitalization of sewing operations
Standardization & digitalization of sewing operations
Arpan Mahato3K vistas
Value stream mapping in ethiopian garemnt industry por kibrom G
Value stream mapping in ethiopian garemnt industryValue stream mapping in ethiopian garemnt industry
Value stream mapping in ethiopian garemnt industry
kibrom G1.9K vistas
Lean manufacturing tools for garment industry por Azmir Latif Beg
Lean manufacturing tools for garment industryLean manufacturing tools for garment industry
Lean manufacturing tools for garment industry
Azmir Latif Beg10.7K vistas
Application of industrial engineering in garments sewing floor por Rakibul Hasan
Application of industrial engineering in garments sewing floorApplication of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floor
Rakibul Hasan21.2K vistas
SOP of Seven Zero System or Traffic Light System । TLS por Rabiul Hasan
SOP of Seven Zero System or Traffic Light System । TLSSOP of Seven Zero System or Traffic Light System । TLS
SOP of Seven Zero System or Traffic Light System । TLS
Rabiul Hasan3.7K vistas
Fabric wastage and sewing fault analysis por Rumman Samrat
Fabric wastage and sewing fault analysisFabric wastage and sewing fault analysis
Fabric wastage and sewing fault analysis
Rumman Samrat4.7K vistas
Fabric relaxation procedure por Mazharul Islam
Fabric relaxation procedureFabric relaxation procedure
Fabric relaxation procedure
Mazharul Islam3.7K vistas
Industrial Engineering Tools & Activities of a RMG !!! por Mahibur Rahman
Industrial Engineering Tools & Activities of a RMG !!!Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!
Mahibur Rahman4.6K vistas
Thesis Presentation | Minimization of Sewing Defects through Implementation o... por Md Rakibul Hassan
Thesis Presentation | Minimization of Sewing Defects through Implementation o...Thesis Presentation | Minimization of Sewing Defects through Implementation o...
Thesis Presentation | Minimization of Sewing Defects through Implementation o...
Md Rakibul Hassan313 vistas
PRODUCTION PLANNING AND CONTROL por Disha Pawar
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
Disha Pawar1.1K vistas

Similar a About Production Planning Process of a RMG !!!

IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN... por
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
1K vistas64 diapositivas
sudath por
sudath sudath
sudath Sudath Geegana
604 vistas10 diapositivas
Apparel Merchandising por
Apparel MerchandisingApparel Merchandising
Apparel MerchandisingMd. Mazadul Hasan Shishir
4.2K vistas54 diapositivas
Production Planning & Merchandising por
Production Planning & MerchandisingProduction Planning & Merchandising
Production Planning & MerchandisingMoiz Khan
1K vistas30 diapositivas
Guidelines industrial engineering por
Guidelines industrial engineeringGuidelines industrial engineering
Guidelines industrial engineeringSyed Jafri
5.5K vistas55 diapositivas
Operations Research & Methodology project report por
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project reportPankaj Kumar Dwivedi
1.3K vistas43 diapositivas

Similar a About Production Planning Process of a RMG !!!(20)

IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN... por Karina Islam
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam1K vistas
Production Planning & Merchandising por Moiz Khan
Production Planning & MerchandisingProduction Planning & Merchandising
Production Planning & Merchandising
Moiz Khan1K vistas
Guidelines industrial engineering por Syed Jafri
Guidelines industrial engineeringGuidelines industrial engineering
Guidelines industrial engineering
Syed Jafri5.5K vistas
Operations Research & Methodology project report por Pankaj Kumar Dwivedi
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project report
Pankaj Kumar Dwivedi1.3K vistas
New text document por salunkhev15
New text documentNew text document
New text document
salunkhev15769 vistas
Time and Action planning (TNA) por Muzammel Ananda
Time and Action planning (TNA)Time and Action planning (TNA)
Time and Action planning (TNA)
Muzammel Ananda4.8K vistas
Training & Development of Supervisors por Shubham Singh
Training & Development of SupervisorsTraining & Development of Supervisors
Training & Development of Supervisors
Shubham Singh433 vistas
Customizing job shop scheduling using microsoft dynamics ax part2 3 por Julien Lecadou,MSc.
Customizing job shop scheduling using microsoft dynamics ax part2 3Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3
Julien Lecadou,MSc.3.1K vistas
apparel internship por Anurag Singh
apparel internshipapparel internship
apparel internship
Anurag Singh1.5K vistas

Último

Thanksgiving!.pdf por
Thanksgiving!.pdfThanksgiving!.pdf
Thanksgiving!.pdfEnglishCEIPdeSigeiro
500 vistas17 diapositivas
INT-244 Topic 6b Confucianism por
INT-244 Topic 6b ConfucianismINT-244 Topic 6b Confucianism
INT-244 Topic 6b ConfucianismS Meyer
45 vistas77 diapositivas
PRELIMS ANSWER.pptx por
PRELIMS ANSWER.pptxPRELIMS ANSWER.pptx
PRELIMS ANSWER.pptxsouravkrpodder
50 vistas60 diapositivas
Parts of Speech (1).pptx por
Parts of Speech (1).pptxParts of Speech (1).pptx
Parts of Speech (1).pptxmhkpreet001
46 vistas20 diapositivas
Mineral nutrition and Fertilizer use of Cashew por
 Mineral nutrition and Fertilizer use of Cashew Mineral nutrition and Fertilizer use of Cashew
Mineral nutrition and Fertilizer use of CashewAruna Srikantha Jayawardana
56 vistas107 diapositivas
Class 9 lesson plans por
Class 9 lesson plansClass 9 lesson plans
Class 9 lesson plansTARIQ KHAN
82 vistas34 diapositivas

Último(20)

INT-244 Topic 6b Confucianism por S Meyer
INT-244 Topic 6b ConfucianismINT-244 Topic 6b Confucianism
INT-244 Topic 6b Confucianism
S Meyer45 vistas
Parts of Speech (1).pptx por mhkpreet001
Parts of Speech (1).pptxParts of Speech (1).pptx
Parts of Speech (1).pptx
mhkpreet00146 vistas
Class 9 lesson plans por TARIQ KHAN
Class 9 lesson plansClass 9 lesson plans
Class 9 lesson plans
TARIQ KHAN82 vistas
Creative Restart 2023: Atila Martins - Craft: A Necessity, Not a Choice por Taste
Creative Restart 2023: Atila Martins - Craft: A Necessity, Not a ChoiceCreative Restart 2023: Atila Martins - Craft: A Necessity, Not a Choice
Creative Restart 2023: Atila Martins - Craft: A Necessity, Not a Choice
Taste45 vistas
Career Building in AI - Technologies, Trends and Opportunities por WebStackAcademy
Career Building in AI - Technologies, Trends and OpportunitiesCareer Building in AI - Technologies, Trends and Opportunities
Career Building in AI - Technologies, Trends and Opportunities
WebStackAcademy45 vistas
JQUERY.pdf por ArthyR3
JQUERY.pdfJQUERY.pdf
JQUERY.pdf
ArthyR3105 vistas
EILO EXCURSION PROGRAMME 2023 por info33492
EILO EXCURSION PROGRAMME 2023EILO EXCURSION PROGRAMME 2023
EILO EXCURSION PROGRAMME 2023
info33492202 vistas
Monthly Information Session for MV Asterix (November) por Esquimalt MFRC
Monthly Information Session for MV Asterix (November)Monthly Information Session for MV Asterix (November)
Monthly Information Session for MV Asterix (November)
Esquimalt MFRC107 vistas

About Production Planning Process of a RMG !!!

  • 2. Content …………………………. 1. Key Information 2. Product Range 3. Technical Details 4. Planning & Control * Planning Strategy * Consideration * Priority * Capacity Allocation as per Buyer Volume * Buyer Allocation * Learning Curve / ladder of Productivity * Execution at a Glance * Conclusion 1. Key information Mahmud Jeans Limited (MJL) is one of the leading Garments manufacturer and exporters of readymade Garments and a sister concern of Mahmud Group. It’s designed and installed with state of the art equipment, 100% compliant well equipped Garments manufacturer among the Garments Industries in Bangladesh. 3200 Employees 22 No. Of Line Fully Vertical Setup - spinning, waving, stitching, washing and finishing Year of Establishment: 2009 Production Capacity Spinning: 30 tons per day Weaving (Denim): 100,000 yds per day Sewing & finishing: 40,000 pcs per day Washing: 45,000 pcs per day Factory Space: 2, 26000 sft Group Turnover: USD 102.00 million per year.
  • 3. Mahmud Jean’s t/o: USD 50.00 million per year. Total Manpower: 3,200 Management Personnel: 175 Our Motto Growing business together with our valuable customer by providing  Best product  Best quality  Best service & above all  On-time delivery Mahmud Group: Difference is our people………….. Our renowned customers are.  Sweden, USA, Europe, Canada, Netherland. H&M, K.Mart, C&A, Hema, G3, Asmara, Tally Weijl, Mango, OVS, Best Seller Kauf land, Jordache, Carre Four, Lager 2. Production range (styling) Basically we are woven garment manufacturer. We produce Trousers, Skirt, Unlined Jacket, Overall, Short all, Shorts, School Dress, Shirt. 3. Technical detail  Cutting Section: Equipped with computer aided designing, marker making, manual spreading & cutting.  Computer Aided Designing (CAD): Computer aided designing equipped with TUKA and Leuctra systems with digitizing board and full width pattern plotter.  Sewing Section:
  • 4. This section is comprised of Latest generation JUKI, FDM, Brothers, Kansai, Vibe Mac sewing machines with automatic thread trimming and sucking device also ETON line.  Finishing Section: This section is equipped with skilled manpower, metal detector, vacuum table, steam iron, thread sucker and other modern facilities. 4. Production planning and control What is planning? Planning is a detailed proposal of doing or achieving something. Especially it consists of the planning of routing, scheduling, dispatching inspection, and coordination. Production planning without production control is like a bank without a bank manager, planning initiates action while control is an adjusting process, providing corrective measures for planned development. Production control regulates and stimulates the orderly how of materials in the manufacturing process from the beginning to the end. Production Planning and Control (PPC) is a process that comprises the Performance of some critical; functions on either side, viz., planning as well as Control. Production Planning and control Production Planning Production Control Planning Dispatching Routing Following up Scheduling Inspection Loading Corrective
  • 5. Production planning: Production planning may be defined as the technique of foreseeing every step in a long series of separate operations, each step to be taken at the right time and in the right place and each operation to be performed in maximum efficiency. It helps entrepreneur to work out the quantity of material manpower, machine and money requires for producing predetermined level of output in given period of time. Routing: Under this, the operations, their path and sequence are established. To perform these operations the proper class of machines and personnel required are also worked out. The main aim of routing is to determine the best and cheapest sequence of operations and to ensure this sequence is strictly followed Scheduling: It means working out of time that should be required to perform each operation and also the time necessary to perform the entire series as routed, making allowances for all factors concerned. It mainly concerns with time element and priorities of a job. Loading: The next step is the execution of the schedule plan as per the route chalked out it includes the assignment of the work to the operators at their machines or places. So loading determines who will do the work as routing determines where and scheduling determines when it shall be done. Dispatching: Dispatching involves issue of production orders for starting the operations. Necessary authority and conformation is given Dispatching is an important step as it translates production plans into production. Follow up: Every production programmed involves determination of the progress of work, removing bottlenecks in the flow of work and ensuring that the productive operations are taking place in accordance with the plans. It spots delays or deviations from the production plans. It helps to reveal detects in routing and scheduling, misunderstanding of orders and instruction, under loading or overloading of work etc. All problems or deviations are investigated and remedial measures are undertaken to ensure the completion of work by the planned date. Inspection: This is mainly to ensure the quality of goods. It can be required as effective agency of production control.
  • 6. Corrective measures: Corrective action may involve any of those activities of adjusting the route, rescheduling of work changing the workloads, repairs and maintenance of machinery or equipment, control over inventories of the cause of deviation is the poor performance of the employees. Certain personnel decisions like training, transfer, demotion etc. may have to be taken. Alternate methods may be suggested to handle peak loads. Capacity Allocation We have capacity to produce (projected) Quantity 750000pcs Minutes 12750000minutes Production planning Strategy. 1. Opportunity invention 2. Sustains 3. Overcome the weakness 4. Prefer the priority 5. Implement the rules & regulation 6. Evaluate the rules & regulation 7. Projection for next 1 year 8. Mission & Visions Consideration of planning  Order quantity  Pcd, tod and lead time  Styling (Basic, semi critical, critical)  Line capability and capacity  SMV, manpower and working hours  Learning curve considering previous record  Machinery and technical attachment  Wash and finishing
  • 7. Learning curve and ladder of productivity. During the style selection we have to follow the ladder diagram and learning curve like as mentioned below. Learning Curve 2 Item Basic Pant SMV 16 M/P 70 W/H 10 Height Efficiency = (70 %) Denim Height Efficiency = (60 %) Denim spandex Required Pic Day 1st 2nd 3rd 4th 5th Required % 20% 30% 50% 60% 60% Actual tgt 447 655 1091 1309 1527 Plan tgt 400 600 1100 1300 1600 Planning (Execution at a glance) Suppose we are doing H&M buyers order as per our previous history then we follow the order chart for month also Pcd, X-Factory and X-Country after that look for line and space which are not loaded /which are near about input date. Than talk to merchant about fabric, accessories, PP comments to make sure size sets before Pcd and make a chart for production schedule as below. 0% 50000% 100000% 150000% 200000% 1st 2nd 3rd 4th 5th Required % Actual tgt Plan tgt
  • 8. H&M Sunday Tagging / 85983pcs / 1000pcs per day Date 5 13 16 Total/Day G.ttl Req Ship Qty till 15-Jun 0 0 16-Jun 0 0 17-Jun 0 0 18-Jun 0 0 19-Jun 0 0 20-Jun 100 100 100 21-Jun 200 200 300 22-Jun 400 400 700 23-Jun 600 100 700 1400 24-Jun 800 200 1000 2400 25-Jun 900 400 1300 3700 26-Jun 0 3700 27-Jun 1000 600 1600 5300 28-Jun 1000 800 1800 7100 29-Jun 1000 900 1900 9000 30-Jun 1000 1000 2000 11000 1-Jul 1000 1000 2000 13000 2-Jul 1000 1000 2000 15000 3-Jul 0 15000 4-Jul 1000 1000 2000 17000 5-Jul 1000 1000 2000 19000 6-Jul 1000 1000 100 2100 21100 7-Jul 1000 1000 200 2200 23300 8-Jul 1000 1000 400 2400 25700 9-Jul 1000 1000 600 2600 28300 10-Jul 0 28300 11-Jul 1200 1000 800 3000 31300 12-Jul 1200 1000 900 3100 34400 8656 13-Jul 1200 1000 1000 3200 37600 9002 14-Jul 1000 1000 2000 39600 15-Jul 1000 1000 2000 41600 16-Jul 800 800 1600 43200 17-Jul 0 43200 18-Jul 0 43200 19-Jul 0 43200 19508 20-Jul 0 43200 29290 21-Jul 0 43200 22-Jul 0 43200 23-Jul 0 43200
  • 9. Need SMV from costing department Make a calculation Like that………………………….. Style SMV 16 M/P 70 W/H 10 Wanted efficiency = 70 % NB. Need to maintain this Allowance range 4 % PLUS FOR SPANDEX+ DENIM 3% OR 2.50% PLUS FOR NON WASH here we have to Add 4 % allowance of required qty of required date If the line doesn’t meet the qty of require the find out another suitable line or share the plan production on another line Then go to the plan layout put the day with color of ending day & give a arrow sign For an Example…………… Suppose there are every line are blank to get style before the input date. Then what should we do? Then talk to merchant. I2f he able to pick the date forward by change the loading will be loaded as per this condition Buyer GAP Style 547882 Smv 24.5 Qty 5086 Input Date 18-Sep delivery date 30-Sep
  • 10. Otherwise that early days will be remaining blank & style date will be the same. Blank 3 0r 4 days may occupied by another qty of another style After doing this things merchant confirm us about PP & OTHERS APPROVAL Then we send the mail about fabric transfer regarding on that style to store. After getting bulk permission we go for bulk production. In the that time we have to keep our close eyes for current production & productivity .wash follow up &cutoff schedule also maintain by us by conducting with production responsible .we take a review meeting every week with all concern factory for developing, review & problem analysis . Conclusion: according to this system we are the MJL Planning Team are trying to meet our Mission & Vision. Though have some discrimination but trying to overcome it. We are implementing the ERP software planning in the group. As a result it will be customized & helpful to all team