SlideShare a Scribd company logo
1 of 63
1
NRAP/MoPWNRAP/MoPW
TECHNICAL SECTIONTECHNICAL SECTION
KABUL -AFGHANISTANKABUL -AFGHANISTAN
PART: 02PART: 02
BY: MALYAR TALASHBY: MALYAR TALASH
ROAD DESIGN ENGINEERROAD DESIGN ENGINEER
tmalyar@yahoo.comtmalyar@yahoo.com
malyar@nrap.gov.afmalyar@nrap.gov.af
Superelevation and SpiralSuperelevation and Spiral
CurvesCurves
2
3
4
Objectives
1. Define superelevation runoff length and
methods of attainment (for simple and
spiral curves)
2. Calculate spiral curve length
5
Issues Relating to
Horizontal Curves
1. Need to coordinate with
vertical and topography
2. Not always needed
MAXIMUM CENTERLINE DEFLECTION
NOT REQUIRING HORIZONTAL CURVE
Design Speed, mph Maximum Deflection
25 5°30'
30 3°45'
35 2°45'
40 2°15'
45 1°15'
50 1°15'
55 1°00'
60 1°00'
65 0°45'
70 0°45'
Source: Ohio DOT Design Manual, Figure 202-1E
6
WHAT IS SUPERELEVATION(e) ?
1. The purpose of superelevation or banking of
curves is to counteract the centripetal
acceleration produced as a vehicle rounds a
curve.
2. Consider the force diagram in Figure 4.17. If the vehicle
is traveling around a curve with a radius R at a constant
speed v, there will be a radial acceleration toward the
center of the curv.
7
WHAT IS SUPERELEVATION(e) ?
1. There are practical upper limits to the rate of
superelevation on a horizontal curve. These
limits relate to considerations of climate,
constructability, adjacent land use, and the
frequency of slow-moving vehicles.
2. Where snow and ice are a factor, the rate of
superelevation should not exceed the rate on
which vehicles standing or traveling slowly would
slide toward the center of the curve when the
pavement is icy.
8
WHAT IS SUPERELEVATION(e) ?
1. AASHTO recommends that maximum
superelevation rates be limited to 12 percent for
rural roadways; 8 percent for rural roadways for
which snow or ice are likely to be present; and 6
percent or 4 percent for urban streets.
9
SIDE FRICTION
1. With the wide variation in vehicle speeds on
curves, there usually is an unbalanced force
whether the curve is superelevated or not. This
force results in tire side thrust, which is
counterbalanced by friction between the tires
and the pavement surface. This frictional
counterforce is developed by distortion of the
contact area of the tire
10
WHAT IS SUPERELEVATION(e) ?
11
12
13
14
Attainment of Superelevation -
General
1. Tangent to superelevation
2. Must be done gradually over a distance without
appreciable reduction in speed or safety and
with comfort
3. Change in pavement slope should be consistent
over a distance
4. Methods (Exhibit 3-40 pgs. 194 & 195)
a. Rotate pavement about centerline
b. Rotate about inner edge of pavement
c. Rotate about outside edge of pavement
15
Superelevation
Transition Section
• Tangent Runout Section +
Superelevation Runoff Section
16
17
Tangent Runout Section
• Length of roadway needed to
accomplish a change in outside-lane
cross slope from normal cross
slope rate to zero
For rotation about
centerline
18
Superelevation Runoff
Section
• Length of roadway needed to
accomplish a change in outside-lane
cross slope from 0 to full
superelevation or vice versa
• For undivided highways with cross-
section rotated about centerline
19
Source: A Policy
on Geometric
Design of
Highways and
Streets (The
Green Book).
Washington, DC.
American
Association of
State Highway
and
Transportation
Officials, 2004
5th
Ed.
20
Source: A Policy
on Geometric
Design of
Highways and
Streets (The
Green Book).
Washington, DC.
American
Association of
State Highway
and
Transportation
Officials, 2004
5th
Ed.
21
22
Source: CalTrans Design Manual online,
http://www.dot.ca.gov/hq/oppd/hdm/pdf/chp0200.pdf
23
Source: CalTrans Design Manual online,
http://www.dot.ca.gov/hq/oppd/hdm/pdf/chp0200.pdf
24
Source: Iowa DOT Standard Road
Plans
Same as point E of GB
25
Attainment Location -
WHERE
1. Superelevation must be attained over a
length that includes the tangent and the
curve
2. Typical: 66% on tangent and 33% on
curve of length of runoff if no spiral
3. Iowa uses 70% and 30% if no spiral
4. Super runoff is all attained in spiral if
used
26
Minimum Length of Runoff
for curve
• Lr based on drainage and
aesthetics
• rate of transition of edge line
from NC to full superelevation
traditionally taken at 0.5% ( 1
foot rise per 200 feet along the
road)
• current recommendation varies
from 0.35% at 80 mph to 0.80%
for 15mph (with further
adjustments for number of lanes)
27
Minimum Length of Tangent Runout
Lt = eNC x Lr
ed
where
• eNC = normal cross slope rate (%)
• ed = design superelevation rate
• Lr = minimum length of superelevation
runoff (ft)
28
Length of Superelevation
Runoff
α = multilane adjustment factor
Adjusts for total width
Also note that e and G can be decimals
or percents, as long as consistent
r
29
Relative Gradient (G)
• Maximum longitudinal slope
• Depends on design speed, higher
speed = gentler slope. For example:
• For 15 mph, G = 0.78%
• For 80 mph, G = 0.35%
• See table, next page
30
Maximum Relative
Gradient (G)
Source: A Policy on Geometric Design of
Highways and Streets (The Green Book).
Washington, DC. American Association of
State Highway and Transportation Officials,
2001 4th
Ed.
31
Multilane Adjustment
• Runout and runoff must be adjusted for
multilane rotation.
32
Length of Superelevation
Runoff Example
For a 4-lane divided highway with cross-
section rotated about centerline, design
superelevation rate = 4%. Design speed
is 50 mph. What is the minimum length
of superelevation runoff (ft)
Lr = 12eα
G
•
33
Lr = 12eα = (12) (0.04) (1.5)
G 0.005
Lr = 144 feet
34
Tangent runout length
Example continued
• LT = (eNC / ed ) x Lr
as defined previously, if NC = 2%
Tangent runout for the example is:
LT = 2% / 4% * 144’ = 72 feet
35
From previous example, speed = 50 mph, e = 4%
From chart runoff = 144 feet, same as from calculation
Source: A Policy on Geometric
Design of Highways and
Streets (The Green Book).
Washington, DC. American
Association of State Highway
and Transportation Officials,
2001 4th
Ed.
36
Spiral CurveSpiral Curve
TransitionsTransitions
37
Spiral Curve Transitions
• Vehicles follow a transition path as
they enter or leave a horizontal
curve
• Combination of high speed and sharp
curvature can result in lateral shifts
in position and encroachment on
adjoining lanes
38
Spirals
1. Advantages
a. Provides natural, easy-to-follow path
for drivers (less encroachment,
promotes more uniform speeds), lateral
force increases and decreases
gradually
b. Provides location for superelevation
runoff (not part on tangent/curve)
c. Provides transition in width when
horizontal curve is widened
d. Aesthetic
39
Minimum Length of Spiral
Possible Equations:
Larger of (1) L = 3.15 V3
RC
Where:
L = minimum length of spiral (ft)
V = speed (mph)
R = curve radius (ft)
C = rate of increase in centripetal acceleration
(ft/s3
) use 1-3 ft/s3
for highway)
40
Minimum Length of Spiral
Or (2) L = (24pminR)1/2
Where:
L = minimum length of spiral (ft)
R = curve radius (ft)
pmin = minimum lateral offset between the
tangent and circular curve (0.66 feet)
41
Maximum Length of Spiral
• Safety problems may occur when
spiral curves are too long – drivers
underestimate sharpness of
approaching curve (driver
expectancy)
42
Maximum Length of Spiral
L = (24pmaxR)1/2
Where:
L = maximum length of spiral (ft)
R = curve radius (ft)
pmax = maximum lateral offset between the
tangent and circular curve (3.3 feet)
43
Length of Spiral
o AASHTO also provides desirable spiral
lengths based on driver behavior rather
than a specific equation
o Superelevation runoff length is set equal
to the spiral curve length when spirals are
used.
o Design Note: For construction purposes,
round your designs to a reasonable values;
e.g.
Ls = 147 feet, round it to
Ls = 150 feet.
44Source: Iowa DOT
Design Manual
45Source: Iowa DOT
Design Manual
46Source: Iowa
DOT Design
Manual
47
Source: Iowa DOT Design Manual
SPIRAL TERMINOLOGY
48
Attainment of superelevation
on spiral curves
See sketches that follow:
Normal Crown (DOT – pt A)
1. Tangent Runout (sometimes known as crown
runoff): removal of adverse crown (DOT – A to B)
B = TS
2. Point of reversal of crown (DOT – C) note A to B =
B to C
3. Length of Runoff: length from adverse crown
removed to full superelevated (DOT – B to D), D =
SC
4. Fully superelevate remainder of curve and then
reverse the process at the CS.
49
Image
http://techalive.mtu.edu/modules/module0003/Superelevation.h
50
Source: Iowa DOT Standard Road Plans RP-2
With Spirals
Same as point E of GB
51
With Spirals
Tangent runout (A to B)
52
With Spirals
Removal of crown
53
With Spirals
Transition of
superelevation
Full superelevation
54
Transition Example
Given:
• PI @ station 245+74.24
• D = 4º (R = 1,432.4 ft)
∀∆ = 55.417º
• L = 1385.42 ft
55
With no spiral …
• T = 752.30 ft
• PC = PI – T = 238 +21.94
56
For:
• Design Speed = 50 mph
• superelevation = 0.04
• normal crown = 0.02
Runoff length was found to be 144’
Tangent runout length =
0.02/ 0.04 * 144 = 72 ft.
57
Where to start transition for superelevation?
Using 2/3 of Lr on tangent, 1/3 on curve for
superelevation runoff:
Distance before PC = Lt + 2/3 Lr
=72 +2/3 (144) = 168
Start removing crown at:
PC station – 168’ = 238+21.94 - 168.00
Station = 236+ 53.94
58
Location Example – with spiral
• Speed, e and NC as before and
∀∆ = 55.417º
• PI @ Station 245+74.24
• R = 1,432.4’
• Lr was 144’, so set Ls = 150’
59
Location Example – with spiral
See Iowa DOT design manual for more
equations:
http://www.iowadot.gov/design/dmanual/02c-01.pd
Spiral angle Θs = Ls * D /200 = 3 degrees
• P = 0.65 (calculated)
• Ts = (R + p ) tan (Δ /2) + k = 827.63 ft
60
• TS station = PI – Ts
= 245+74.24 – 827.63
= 237+46.61
Runoff length = length of spiral
Tangent runout length = Lt = (eNC / ed ) x Lr
= 2% / 4% * 150’ = 75’
Therefore: Transition from normal crown begins
at (237+46.61) – (75.00) = 236+71.61
Location Example – with spiral
61
With spirals, the central angle for the
circular curve is reduced by 2 * Θs
Lc = ((Δ – 2 * Θs) / D) * 100
Lc = (55.417-2*3)/4)*100 = 1235.42 ft
Total length of curves = Lc +2 * Ls = 1535.42
Verify that this is exactly 1 spiral length
longer than when spirals are not used
(extra credit for anyone who shows me
why; provide a one-page memo by Monday)
Location Example – with spiral
62
Also note that the tangent length with
a spiral should be longer than the
non-spiraled curve by approximately ½
of the spiral length used. (good check
– but why???)
Location Example – with spiral
63
Notes – Iowa DOT
Source: Iowa DOT Standard Road Plans
Note: Draw a sketch and think about what the last para is saying

More Related Content

What's hot

Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
HARITSEHRAWAT
 

What's hot (20)

INTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERINGINTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERING
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
 
Horizontal alignment of Roads
Horizontal alignment of RoadsHorizontal alignment of Roads
Horizontal alignment of Roads
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignment
 
Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
 
Sight distance
Sight distanceSight distance
Sight distance
 
Vertical Alignment in road design
Vertical Alignment in road designVertical Alignment in road design
Vertical Alignment in road design
 
Superelevation
SuperelevationSuperelevation
Superelevation
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Unit 2
Unit 2Unit 2
Unit 2
 
Horizontal curves PRESENTATION
Horizontal curves PRESENTATIONHorizontal curves PRESENTATION
Horizontal curves PRESENTATION
 
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
 
Horizontal curve- IRC 38
Horizontal curve- IRC 38Horizontal curve- IRC 38
Horizontal curve- IRC 38
 
Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)
 
Interchange design
Interchange designInterchange design
Interchange design
 
Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)
 
Curve setting ppt
Curve setting pptCurve setting ppt
Curve setting ppt
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curves
 

Similar to 2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/Engineer)

18 Superelevation and Spiral Curves.ppt
18 Superelevation and Spiral Curves.ppt18 Superelevation and Spiral Curves.ppt
18 Superelevation and Spiral Curves.ppt
KKKL5
 

Similar to 2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/Engineer) (20)

18 Superelevation and Spiral Curves.ppt
18 Superelevation and Spiral Curves.ppt18 Superelevation and Spiral Curves.ppt
18 Superelevation and Spiral Curves.ppt
 
Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution .
 
hz alignment lec4.pdf
hz alignment lec4.pdfhz alignment lec4.pdf
hz alignment lec4.pdf
 
Horizontal Alignment TOP TOP.pptx
Horizontal Alignment TOP TOP.pptxHorizontal Alignment TOP TOP.pptx
Horizontal Alignment TOP TOP.pptx
 
Sight distance and road allignment
Sight distance and road allignmentSight distance and road allignment
Sight distance and road allignment
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
 
Vertical Curves_Presentation_NR.pptx
Vertical Curves_Presentation_NR.pptxVertical Curves_Presentation_NR.pptx
Vertical Curves_Presentation_NR.pptx
 
Transportation engineering highway part
Transportation engineering highway partTransportation engineering highway part
Transportation engineering highway part
 
IRJET- Traffic Congestion Overcome by Rotary Design
IRJET- Traffic Congestion Overcome by Rotary DesignIRJET- Traffic Congestion Overcome by Rotary Design
IRJET- Traffic Congestion Overcome by Rotary Design
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
 
Highway Project
Highway ProjectHighway Project
Highway Project
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptx
 
Lect 29- traffic rotaries
Lect 29- traffic rotariesLect 29- traffic rotaries
Lect 29- traffic rotaries
 
HIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).docHIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).doc
 
transitioncurve-210816162648.pdf
transitioncurve-210816162648.pdftransitioncurve-210816162648.pdf
transitioncurve-210816162648.pdf
 
L11 Signal Timing Design
L11 Signal Timing Design L11 Signal Timing Design
L11 Signal Timing Design
 
Balancing Diagram ppt
Balancing Diagram pptBalancing Diagram ppt
Balancing Diagram ppt
 
webinar on speed raising to 130or 160 kmph.pptx
webinar on speed raising to 130or 160 kmph.pptxwebinar on speed raising to 130or 160 kmph.pptx
webinar on speed raising to 130or 160 kmph.pptx
 
Capacity at intersection
Capacity at intersectionCapacity at intersection
Capacity at intersection
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
 

More from Malyar Talash (7)

Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
 
1 geometric design elements of road by malyar talash
1 geometric design elements of road by malyar talash1 geometric design elements of road by malyar talash
1 geometric design elements of road by malyar talash
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar Talash
 
Intersection in roads by malyar talash
Intersection in roads by malyar talashIntersection in roads by malyar talash
Intersection in roads by malyar talash
 
Key factors related to traffic crashes by Malyar Talash
Key factors related to traffic crashes by Malyar TalashKey factors related to traffic crashes by Malyar Talash
Key factors related to traffic crashes by Malyar Talash
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 

2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/Engineer)

  • 1. 1 NRAP/MoPWNRAP/MoPW TECHNICAL SECTIONTECHNICAL SECTION KABUL -AFGHANISTANKABUL -AFGHANISTAN PART: 02PART: 02 BY: MALYAR TALASHBY: MALYAR TALASH ROAD DESIGN ENGINEERROAD DESIGN ENGINEER tmalyar@yahoo.comtmalyar@yahoo.com malyar@nrap.gov.afmalyar@nrap.gov.af Superelevation and SpiralSuperelevation and Spiral CurvesCurves
  • 2. 2
  • 3. 3
  • 4. 4 Objectives 1. Define superelevation runoff length and methods of attainment (for simple and spiral curves) 2. Calculate spiral curve length
  • 5. 5 Issues Relating to Horizontal Curves 1. Need to coordinate with vertical and topography 2. Not always needed MAXIMUM CENTERLINE DEFLECTION NOT REQUIRING HORIZONTAL CURVE Design Speed, mph Maximum Deflection 25 5°30' 30 3°45' 35 2°45' 40 2°15' 45 1°15' 50 1°15' 55 1°00' 60 1°00' 65 0°45' 70 0°45' Source: Ohio DOT Design Manual, Figure 202-1E
  • 6. 6 WHAT IS SUPERELEVATION(e) ? 1. The purpose of superelevation or banking of curves is to counteract the centripetal acceleration produced as a vehicle rounds a curve. 2. Consider the force diagram in Figure 4.17. If the vehicle is traveling around a curve with a radius R at a constant speed v, there will be a radial acceleration toward the center of the curv.
  • 7. 7 WHAT IS SUPERELEVATION(e) ? 1. There are practical upper limits to the rate of superelevation on a horizontal curve. These limits relate to considerations of climate, constructability, adjacent land use, and the frequency of slow-moving vehicles. 2. Where snow and ice are a factor, the rate of superelevation should not exceed the rate on which vehicles standing or traveling slowly would slide toward the center of the curve when the pavement is icy.
  • 8. 8 WHAT IS SUPERELEVATION(e) ? 1. AASHTO recommends that maximum superelevation rates be limited to 12 percent for rural roadways; 8 percent for rural roadways for which snow or ice are likely to be present; and 6 percent or 4 percent for urban streets.
  • 9. 9 SIDE FRICTION 1. With the wide variation in vehicle speeds on curves, there usually is an unbalanced force whether the curve is superelevated or not. This force results in tire side thrust, which is counterbalanced by friction between the tires and the pavement surface. This frictional counterforce is developed by distortion of the contact area of the tire
  • 11. 11
  • 12. 12
  • 13. 13
  • 14. 14 Attainment of Superelevation - General 1. Tangent to superelevation 2. Must be done gradually over a distance without appreciable reduction in speed or safety and with comfort 3. Change in pavement slope should be consistent over a distance 4. Methods (Exhibit 3-40 pgs. 194 & 195) a. Rotate pavement about centerline b. Rotate about inner edge of pavement c. Rotate about outside edge of pavement
  • 15. 15 Superelevation Transition Section • Tangent Runout Section + Superelevation Runoff Section
  • 16. 16
  • 17. 17 Tangent Runout Section • Length of roadway needed to accomplish a change in outside-lane cross slope from normal cross slope rate to zero For rotation about centerline
  • 18. 18 Superelevation Runoff Section • Length of roadway needed to accomplish a change in outside-lane cross slope from 0 to full superelevation or vice versa • For undivided highways with cross- section rotated about centerline
  • 19. 19 Source: A Policy on Geometric Design of Highways and Streets (The Green Book). Washington, DC. American Association of State Highway and Transportation Officials, 2004 5th Ed.
  • 20. 20 Source: A Policy on Geometric Design of Highways and Streets (The Green Book). Washington, DC. American Association of State Highway and Transportation Officials, 2004 5th Ed.
  • 21. 21
  • 22. 22 Source: CalTrans Design Manual online, http://www.dot.ca.gov/hq/oppd/hdm/pdf/chp0200.pdf
  • 23. 23 Source: CalTrans Design Manual online, http://www.dot.ca.gov/hq/oppd/hdm/pdf/chp0200.pdf
  • 24. 24 Source: Iowa DOT Standard Road Plans Same as point E of GB
  • 25. 25 Attainment Location - WHERE 1. Superelevation must be attained over a length that includes the tangent and the curve 2. Typical: 66% on tangent and 33% on curve of length of runoff if no spiral 3. Iowa uses 70% and 30% if no spiral 4. Super runoff is all attained in spiral if used
  • 26. 26 Minimum Length of Runoff for curve • Lr based on drainage and aesthetics • rate of transition of edge line from NC to full superelevation traditionally taken at 0.5% ( 1 foot rise per 200 feet along the road) • current recommendation varies from 0.35% at 80 mph to 0.80% for 15mph (with further adjustments for number of lanes)
  • 27. 27 Minimum Length of Tangent Runout Lt = eNC x Lr ed where • eNC = normal cross slope rate (%) • ed = design superelevation rate • Lr = minimum length of superelevation runoff (ft)
  • 28. 28 Length of Superelevation Runoff α = multilane adjustment factor Adjusts for total width Also note that e and G can be decimals or percents, as long as consistent r
  • 29. 29 Relative Gradient (G) • Maximum longitudinal slope • Depends on design speed, higher speed = gentler slope. For example: • For 15 mph, G = 0.78% • For 80 mph, G = 0.35% • See table, next page
  • 30. 30 Maximum Relative Gradient (G) Source: A Policy on Geometric Design of Highways and Streets (The Green Book). Washington, DC. American Association of State Highway and Transportation Officials, 2001 4th Ed.
  • 31. 31 Multilane Adjustment • Runout and runoff must be adjusted for multilane rotation.
  • 32. 32 Length of Superelevation Runoff Example For a 4-lane divided highway with cross- section rotated about centerline, design superelevation rate = 4%. Design speed is 50 mph. What is the minimum length of superelevation runoff (ft) Lr = 12eα G •
  • 33. 33 Lr = 12eα = (12) (0.04) (1.5) G 0.005 Lr = 144 feet
  • 34. 34 Tangent runout length Example continued • LT = (eNC / ed ) x Lr as defined previously, if NC = 2% Tangent runout for the example is: LT = 2% / 4% * 144’ = 72 feet
  • 35. 35 From previous example, speed = 50 mph, e = 4% From chart runoff = 144 feet, same as from calculation Source: A Policy on Geometric Design of Highways and Streets (The Green Book). Washington, DC. American Association of State Highway and Transportation Officials, 2001 4th Ed.
  • 37. 37 Spiral Curve Transitions • Vehicles follow a transition path as they enter or leave a horizontal curve • Combination of high speed and sharp curvature can result in lateral shifts in position and encroachment on adjoining lanes
  • 38. 38 Spirals 1. Advantages a. Provides natural, easy-to-follow path for drivers (less encroachment, promotes more uniform speeds), lateral force increases and decreases gradually b. Provides location for superelevation runoff (not part on tangent/curve) c. Provides transition in width when horizontal curve is widened d. Aesthetic
  • 39. 39 Minimum Length of Spiral Possible Equations: Larger of (1) L = 3.15 V3 RC Where: L = minimum length of spiral (ft) V = speed (mph) R = curve radius (ft) C = rate of increase in centripetal acceleration (ft/s3 ) use 1-3 ft/s3 for highway)
  • 40. 40 Minimum Length of Spiral Or (2) L = (24pminR)1/2 Where: L = minimum length of spiral (ft) R = curve radius (ft) pmin = minimum lateral offset between the tangent and circular curve (0.66 feet)
  • 41. 41 Maximum Length of Spiral • Safety problems may occur when spiral curves are too long – drivers underestimate sharpness of approaching curve (driver expectancy)
  • 42. 42 Maximum Length of Spiral L = (24pmaxR)1/2 Where: L = maximum length of spiral (ft) R = curve radius (ft) pmax = maximum lateral offset between the tangent and circular curve (3.3 feet)
  • 43. 43 Length of Spiral o AASHTO also provides desirable spiral lengths based on driver behavior rather than a specific equation o Superelevation runoff length is set equal to the spiral curve length when spirals are used. o Design Note: For construction purposes, round your designs to a reasonable values; e.g. Ls = 147 feet, round it to Ls = 150 feet.
  • 47. 47 Source: Iowa DOT Design Manual SPIRAL TERMINOLOGY
  • 48. 48 Attainment of superelevation on spiral curves See sketches that follow: Normal Crown (DOT – pt A) 1. Tangent Runout (sometimes known as crown runoff): removal of adverse crown (DOT – A to B) B = TS 2. Point of reversal of crown (DOT – C) note A to B = B to C 3. Length of Runoff: length from adverse crown removed to full superelevated (DOT – B to D), D = SC 4. Fully superelevate remainder of curve and then reverse the process at the CS.
  • 50. 50 Source: Iowa DOT Standard Road Plans RP-2 With Spirals Same as point E of GB
  • 54. 54 Transition Example Given: • PI @ station 245+74.24 • D = 4º (R = 1,432.4 ft) ∀∆ = 55.417º • L = 1385.42 ft
  • 55. 55 With no spiral … • T = 752.30 ft • PC = PI – T = 238 +21.94
  • 56. 56 For: • Design Speed = 50 mph • superelevation = 0.04 • normal crown = 0.02 Runoff length was found to be 144’ Tangent runout length = 0.02/ 0.04 * 144 = 72 ft.
  • 57. 57 Where to start transition for superelevation? Using 2/3 of Lr on tangent, 1/3 on curve for superelevation runoff: Distance before PC = Lt + 2/3 Lr =72 +2/3 (144) = 168 Start removing crown at: PC station – 168’ = 238+21.94 - 168.00 Station = 236+ 53.94
  • 58. 58 Location Example – with spiral • Speed, e and NC as before and ∀∆ = 55.417º • PI @ Station 245+74.24 • R = 1,432.4’ • Lr was 144’, so set Ls = 150’
  • 59. 59 Location Example – with spiral See Iowa DOT design manual for more equations: http://www.iowadot.gov/design/dmanual/02c-01.pd Spiral angle Θs = Ls * D /200 = 3 degrees • P = 0.65 (calculated) • Ts = (R + p ) tan (Δ /2) + k = 827.63 ft
  • 60. 60 • TS station = PI – Ts = 245+74.24 – 827.63 = 237+46.61 Runoff length = length of spiral Tangent runout length = Lt = (eNC / ed ) x Lr = 2% / 4% * 150’ = 75’ Therefore: Transition from normal crown begins at (237+46.61) – (75.00) = 236+71.61 Location Example – with spiral
  • 61. 61 With spirals, the central angle for the circular curve is reduced by 2 * Θs Lc = ((Δ – 2 * Θs) / D) * 100 Lc = (55.417-2*3)/4)*100 = 1235.42 ft Total length of curves = Lc +2 * Ls = 1535.42 Verify that this is exactly 1 spiral length longer than when spirals are not used (extra credit for anyone who shows me why; provide a one-page memo by Monday) Location Example – with spiral
  • 62. 62 Also note that the tangent length with a spiral should be longer than the non-spiraled curve by approximately ½ of the spiral length used. (good check – but why???) Location Example – with spiral
  • 63. 63 Notes – Iowa DOT Source: Iowa DOT Standard Road Plans Note: Draw a sketch and think about what the last para is saying