LAPORAN EVALUASI AKHIR PROGRESS PISEW 2019 KAPONTORI - Copy.pptx

  1. INDIKATOR EVALUASI PELAKSANAAN : • PELAKSANAAN KEGIATAN SESUAI DENGAN PETUNJUK TEKNIS PELAKSANAAN KEGIATAN PISEW 2019 • PELAKSANAAN KEGIATAN FISIK • LAPORAN PERTANGGUNGJAWABAN KEUANGAN (LPJ ) • PENGINPUTAN DATA KEGIATAN KE APLIKASI SILKA • SERAH TERIMA PEKERJAAN
  2. ACUAN PELAKSANAAN : • PETUNJUK TEKNIS PELAKSANAAN KEGIATAN PISEW 2019 • KONTRAK PKS ANTARA PPK DAN BKAD • LAPORAN RENCANA PENGGUNAAN DANA • PENCAIRAN DANA TAHAP I ( 70 % ) DAN TAHAP II (30%) OLEH B K AD
  3. OUT-PUT PELAKSANAAN : • PELAKSANAAN KEGIATAN SESUAI DENGAN PETUNJUK TEKNIS ( JUKNIS PISEW 2019 ) • TERCAPAINYA PEMBANGUNAN INFRASTRUKTUR • ADANYA LAPORAN PERTANGGUNGJAWABAN KEGIATAN FISIK • ADANYA LAPORAN PERTANGGUNGJAWABAN KEUANGAN • PENGINPUTAN DATA KE APLIKASI SILKA
  4. JENIS KEGIATAN BERDASARKAN PKS : • PEMBUATAN TAMBATAN TEPI LAUT ( VOLUME = 1 UNIT ) • PENINGKATAN JALAN RUAS JALAN I ( VOLUME = 3.200 M ) • PENINGKATAN JALAN RUAS JALAN II ( VOLUME = 1.100 M ) • PENUNJANG JALAN ( DEUKER PLAT ) 2 UNIT
  5. JENIS KEGIATAN FISIK YANG TELAH DILAKSANAKAN : • PEMBUATAN TAMBATAN TEPI LAUT ( VOLUME = 1 UNIT ) • PENINGKATAN JALAN RUAS JALAN I ( VOLUME = 3.200 M ) • PENINGKATAN JALAN RUAS JALAN II ( VOLUME = 1.100 M )
  6. JENIS KEGIATAN FISIK YANG BELUM DILAKSANAKAN : • PEKERJAAN PENUNJANG JALAN DUEKER PLAT = 2 UNIT
  7. ITEM PEKERJAAN YANG TELAH DILAKSANAKAN : • PEMBUATAN TAMBATAN TEPI LAUT : - PEKERJAAN GALIAN TANAH - PASANGAN BATU KOSONG - PASANGAN BATU 1 PC : 4 PSR - URUGAN TANAH PILIHAN - PEK. RABAT BETON LANTAI - PEKERJAAN BETON • PENINGKATAN JALAN PERKERASAN SIRTU : - MOBILISASI / DEMOBILISASI - PENYIAPAN BADAN JALAN - TIMBUNAN URUGAN PILIHAN - PENGHAMPARANN JALAN ( MEKANIS ) - PEMADATAN JALAN
  8. TARGET PEKERJAAN KE DEPAN : • PEMBANGUNAN PEKERJAAN PENUNJANG JALAN DEKER PLAT ( ADDENDUM ) • PENINGKATAN JALAN PERKERASAN SIRTU : - PEMBENAHAN JALAN ( HASIL MONITORING TENAGA AHLI PROVINSI ) • PEMBUATAN DERMAGA TEPI LAUT : PEMBENAHAN PEKERJAAN ( HASIL MONITORING TA PROVINSI )
  9. PROGRESS TIAP – TIAP PEKERJAAN S/D BULAN INI ( DESEMBER 2019 ) : • PEMBUATAN TAMBATAN TEPI LAUT : 90,65 % • PENINGKATAN JALAN PERKERASAN SIRTU - I : 100 % • PENINGKATAN JALAN PERKERASAN SIRTU - II : 100 % • PEKERJAAN PENUNJANG JALAN ( DEUKER PLAT ) : 0,00 %
  10. PROGRESS PEKERJAAN S/D BULAN INI ( DESEMBER 2019 ) : • REKAPITULASI KEGIATAN SECARA KESELURUHAN : 91,56 %
  11. LAPORAN KEUANGAN BKAD KEC. KAPONTORI : • PENCAIRAN TAHAP I : RP. 420.000.000,. ( EMPAT RATUS DUA PULUH JUTA RUPIAH ) • OPERSIONAL BKAD : RP. 4.950.000,. • BELANJA BAHAN & HOK : RP. 414.355.000,. • SISA SALDO BKAD : RP. 695.000,. ( ENAM RATUS SEMBILAN PULUH LIMA RIBU RUPIAH ) • TOTAL BELANJA : RP. 419.305.000,.
  12. LAPORAN KEUANGAN YANG BELUM DIPERTANGGUNGJAWABKAN OLEH BKAD KEC. KAPONTORI : • PENCAIRAN TAHAP II : RP. 180.000.000,. ( SERATUS DELAPANPULUH JUTA RUPIAH )
  13. KENDALA DAN HAMBATAN DALAM PROGRESS PEKERJAAN : •PEMBUATAN TAMBATAN TEPI LAUT : FAKTOR ALAM ( PASANG-SURUT ) HARI PASAR ( RABU DAN MINGGU ) TENAGA KERJA LOKAL PEMBUATAN LPJ • PENINGKATAN JALAN PERKERASAN SIRTU : KETERSEDIAAN ALAT BERAT INTIMIDASI DARI PEMILIK LAHAN INTERVENSI DARI APARAT DESA BERSAMAAN DENGAN KEGIATAN APBD DAN DANA DESA PEMBUATAN LPJ
  14. KENDALA DAN HAMBATAN DALAM PROGRESS PEKERJAAN : •PEKERJAAN DEUKER PLAT : TITIK LOKASI PEKERJAAN YANG BERUBAH MENUNGGU PENCAIRAN DANA TAHAP II
  15. EVALUASI AKHIR PELAKSANAAN : I N D I K A T O R K I N E R J A H A S I L E V A L U A S I T A R G E T P E N Y E L E S A I A N PELAKSANAAN KEGIATAN SESUAI DENGAN JUKNIS PISEW 2019 • KETERWAKILAN PEREMPUAN BELUM SESUAI DENGAN PETUNJUK TEKNIS • DOKUMEN ADMINISTRASI BKAD BELUM MENGIKUTI BUKU JUKNIS PISEW 2019 • BKAD BERSAMA FM MELAKUKAN KOREKSI DAN VERIFIKASI ULANG TERHADAP DOKUMEN-DOKUMEN BKAD • PERTEMUAN KECAMATAN II AGAR BKAD BERUPAYA MENCAPAI TARGET KETERWAKILAN PEREMPUAN 30% • PENYELESAIAN HASIL EVALUASI SEBELUM TANGGAL 30 DESEMBER 2019
  16. EVALUASI AKHIR PELAKSANAAN : I N D I K A T O R K I N E R J A H A S I L E V A L U A S I T A R G E T P E N Y E L E S A I A N PELAKSANAAN KEGIATAN FISIK ( KONSTRUKSI ) • BACK UP DATA DIPERBAIKI • PEMBENAHAN PEKERJAAN YANG TELAH DILAKSANAKAN • KONTRAK AMANDEMEN BERAKHIR DITANGGAL 14/12/2019 TAPI FISIK BELUM 100% • TERDAPAT CCO ITEM PEKERJAAN • BKAD BERSAMA FM KEMBALI MELAKUKAN BACK UP ATAS HASIL PEKERJAAN TERBARU • BKAD SEGERA MENGUSULKAN ADENDUM/CCO KEPADA PPK ATAS ITEM PEKERJAAN DEUKER PLAT DAN TAMBATAN TEPI LAUT DENGAN BERPEDOMAN PADA HASIL BACK UP DATA OLEH FM • PENYELESAIAN SELURUH KEGIATAN FISIK SEBELUM TANGGAL 28 DESEMBER 2019
  17. EVALUASI AKHIR PELAKSANAAN : I N D I K A T O R K I N E R J A H A S I L E V A L U A S I T A R G E T P E N Y E L E S A I A N LAPORAN KEUANGAN • LPJ 100 % • INPUT DATA SILKA • LPJ 70% SUDAH TUNTAS • PENCAIRAN TAHAP II BELUM DIBUATKAN PERTANGGUNGJAWABAN KEUANGANNYA ( LPJ 100% ) • SERAPANN ANGGARAN DALAM DATA DI APLIKASI SILKA MASIH DIBAWAH 25% SEMENTARA KEUANGAN SUDAH 100% • BKAD DIDAMPINGI OLEH FM SEGERA MEBUAT LPJ 100% • BKAD DIDAMPINGI OLEH FM MELAKUKAN PERCEPATAN PENGINPUTAN DATA KEUANGAN DI APLIKASI SILKA • PENYELESAIAN UNTUK LPJ 100% SEBELUM TANGGAL 28 DESEMBER 2019 • PENGINPUTAN SILKA UNTUK LPJ 70% SEBELUM TANGGAL 28 DESEMBER 2019 DAN UNTUK LPJ 100% SEBELUM TANGGAL 15 JANUARI 2020
  18. EVALUASI AKHIR PELAKSANAAN : I N D I K A T O R K I N E R J A H A S I L E V A L U A S I T A R G E T P E N Y E L E S A I A N S E R A H T E R I M A P E K ER J A A N • BELUM DILAKSANAKAN KEGIATAN PERTEMUAN KECAMATAN II ( PK-2 ) KARENA PEKERJAAN FISIK BELUM TUNTAS 100% • SERAH TERIMA PEKERJAAN BELUM BISA TERLAKSANA • BKAD MELAKUKAN PERCEPATAN PENYELESAIANKEGIATAN FISIK PEKERJAAN AGAR BISA MELAKUKAN PERTEMUANKECAMATAN II DENGAN MENGACU PADA PETUNJUK TEKNIS KEGIATAN PISEW 2019 • BKAD AKTIF MELAKUKAN KOORDINASI DENGAN PEMERINTAH KECAMATAN DAN PEMERINTAH DESA • PERTEMUAN KECAMATAN II PALING LAMBAT DILAKSANAKAN DITANGGAL 29 DESEMBER 2019 • SERAH TERIMA PEKERJAAN DI MINGGU PERTAMA BULAN JANUARI 2020
  19. DOKUMENTASI KEGIATAN PEKERJAAN PEMBUATAN TAMBATAN TEPI LAUT
  20. PEMASANGAN BOUPLANK :
  21. GALIAN TANAH :
  22. PASANGAN BATU :
  23. PASANGAN BATU :
  24. DOKUMENTASI KEGIATAN PEKERJAAN PENINGKATAN JALAN PERKERSAN SIRTU ( V = 4.300 M)
  25. PENYIAPAN BADAN JALAN RUAS II :
  26. PENYIAPAN BADAN JALAN RUAS I :
  27. PENYIAPAN BADAN JALAN :
  28. PENYIAPAN BADAN JALAN :
  29. PENIMBUNAN JALAN :
  30. TIMBUNAN JALAN :
  31. PENGHAMPARAN TIMBUNAN JALAN ( MEKANIS ) :
  32. PEMADATAN TIMBUNAN JALAN ( MEKANIS ) :
  33. PEMADATAN TIMBUNAN JALAN ( MEKANIS ) :
  34. PEMADATAN TIMBUNAN JALAN ( MEKANIS ) :
  35. REKAPITULASI PROGRESS KEGIATAN FISIK PISEW 2019 KEC. KAPONTORI :