LAPORAN PROGRESS PISEW 2019 KAPONTORI - Copy.pptx
1.
2. ACUAN PELAKSANAAN :
• KONTRAK PKS ANTARA PPK DAN BKAD
• LAPORAN RENCANA PENGGUNAAN DANA
• PENCAIRAN DANA TAHAP I ( 70 % ) OLEH B K A D
3. OUT-PUT PELAKSANAAN :
• TERCAPAINYA PEMBANGUNAN INFRASTRUKTUR
• ADANYA LAPORAN PERTANGGUNGJAWABAN KEGIATAN FISIK
• ADANYA LAPORAN PERTANGGUNGJAWABAN KEUANGAN
4. JENIS KEGIATAN BERDASARKAN PKS :
• PEMBUATAN TAMBATAN TEPI LAUT ( VOLUME = 1 UNIT )
• PENINGKATAN JALAN RUAS JALAN I ( VOLUME = 3.200 M )
• PENINGKATAN JALAN RUAS JALAN II ( VOLUME = 1.100 M )
• PENUNJANG JALAN ( DEUKER PLAT ) 2 UNIT
5. JENIS KEGIATAN YANG SEDANG DILAKSANAKAN :
• PEMBUATAN TAMBATAN TEPI LAUT ( VOLUME = 1 UNIT )
• PENINGKATAN JALAN RUAS JALAN I ( VOLUME = 3.200 M )
• PENINGKATAN JALAN RUAS JALAN II ( VOLUME = 1.100 M )
6. ITEM PEKERJAAN YANG TELAH DILAKSANAKAN :
• PEMBUATAN TAMBATAN TEPI LAUT :
- PEKERJAAN GALIAN TANAH
- PASANGAN BATU KOSONG
- PASANGAN BATU 1 PC : 4 PSR
- URUGAN TANAH PILIHAN
- PEK. RABAT BETON LANTAI
- PEKERJAAN BETON
• PENINGKATAN JALAN PERKERASAN SIRTU :
- MOBILISASI / DEMOBILISASI
- PENYIAPAN BADAN JALAN
- TIMBUNAN URUGAN PILIHAN
- PENGHAMPARANN JALAN ( MEKANIS )
- PEMADATAN JALAN
7. TARGET PEKERJAAN KE DEPAN :
• PEMBANGUNAN PEKERJAAN PENUNJANG JALAN
DEKER PLAT ( ADDENDUM )
• PENINGKATAN JALAN PERKERASAN SIRTU :
- PEMBENAHAN JALAN
( HASIL MONITORING TENAGA AHLI
PROVINSI )
• PEMBUATAN DERMAGA TEPI LAUT :
PEMBENAHAN PEKERJAAN
( HASIL MONITORING TA PROVINSI )
8. PROGRESS TIAP – TIAP PEKERJAAN S/D BULAN INI
( OKTOBER 2019 ) :
• PEMBUATAN TAMBATAN TEPI LAUT :
90,65 %
• PENINGKATAN JALAN PERKERASAN SIRTU - I :
90,81 %
• PENINGKATAN JALAN PERKERASAN SIRTU - II :
95,10 %
9. PROGRESS PEKERJAAN S/D BULAN INI ( OKTOBER 2019 ) :
• REKAPITULASI KEGIATAN SECARA KESELURUHAN :
87,31 %
10. LAPORAN KEUANGAN BKAD KEC. KAPONTORI :
• PENCAIRAN TAHAP I : RP. 420.000.000,. ( EMPAT RATUS DUA PULUH JUTA RUPIAH )
• OPERSIONAL BKAD : RP. 4.950.000,.
• BELANJA BAHAN & HOK : RP. 414.355.000,.
• SISA SALDO BKAD : RP. 695.000,. ( ENAM RATUS SEMBILAN PULUH LIMA RIBU RUPIAH )
11. KENDALA DAN HAMBATAN DALAM PROGRESS PEKERJAAN :
•PEMBUATAN TAMBATAN TEPI LAUT :
FAKTOR ALAM ( PASANG-SURUT )
HARI PASAR ( RABU DAN MINGGU )
TENAGA KERJA LOKAL
PEMBUATAN LPJ
• PENINGKATAN JALAN PERKERASAN SIRTU :
KETERSEDIAAN ALAT BERAT
INTIMIDASI DARI PEMILIK LAHAN
INTERVENSI DARI APARAT DESA
BERSAMAAN DENGAN KEGIATAN APBD
DAN DANA DESA
PEMBUATAN LPJ