SlideShare una empresa de Scribd logo
1 de 38
Certified Associate Project Management
CAPM® Exam Prep – Week 2
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Project Managers
 use Process Groups to coordinate the effective flow of a project
from its start to its close using ITTOs & Knowledge Areas.
 in collaboration with the project team are ALWAYS responsible for
planning & developing a successful Project Management Process
 actively manages each of these interactions to meet the Sponsor,
Customer & Stakeholder requirements
Project Management Processes
Chapter 3
PROCESS
 “is a set of interrelated actions & activities performed to create a specific product, service or
result.”
 Project Management has 49 processes
PROCESS GROUPS
 organize the process functions by their Actions
 are the project activities broken down into 5 steps
KNOWLEDGE AREAS
 organizes the process functions by their Subject Matter
 are the process elements broken down into 10 areas
 ARE NOT LINEAR !!!
ITTOs
 “each process is linked & characterized by its INPUTS, TOOLS, TECHNIQUES & OUTPUTS.”
 Inputs – information used in the project ex. EEF, OPAs, Charter, etc
 Outputs – documents, deliverables, decisions
 Tools &Techniques – used to do the work ex. Meetings, Expert, Audits
Project Management Processes
Chapter 3
PHASES
 “a set of processes that are ITERATED several times to achieve the required
outcome.”
 each Phase of the project goes thru all of the 5 Process Groups
Sequential Relationship
 Phases of the project that happen one after another
 Teams work together on each phase
Overlapping Relationship
 Phases of the project deliver results independently
 Teams work on different parts of the project
 Complicated to manage due to increased risk & rework
Project Management Processes
Chapter 3
Project Management Process Groups
 Initiating
 Planning
 Executing
 Monitoring & Controlling
 Closing
Project Management Processes
Chapter 3
Project Management Processes
Chapter 3
Project Management Process Groups
INITIATING Process Group
 Develop the Project Charter
 Project Manager is Authorized
 Business Case
 High level planning – Rough Order of Magnitude estimating
 Initial financial resources are committed
 Scope is conceptualize – Progressive Elaboration
 Identify Stakeholders
 Stakeholder Register - List of Internal & External influences
 Identify their expectations
Project Management Processes
Chapter 3
PLANNING Process Group
“… 24 processes used in the strategy to develop a course of action or path to
successfully complete the project or phase. A well managed plan saves
resources, time & money and gets the Stakeholder’s buy-in & engagement.”
Iterative – each planning process may use the results of the previous process that
may affect or change the plan
 Project Management Plan
 Is an Output that guides the Execution & Control of the project
 Project Documents
 Are Outputs detailing each of the Knowledge Areas
Project Management Processes
Chapter 3
EXECUTING Process Group
“… 10 processes performed to complete the project work defined
in the Project Management Plan to meet the project objectives.”
 PM coordinates People & Resources to Do the work
 Communicates with Stakeholders to manage their expectations
 Proactive analysis of baselines, changes in resource availability,
productivity, expected durations, budgets, etc
 Change requests approvals resulting in Project Doc updates
 Deliverables
 Changes Requests
Project Management Processes
Chapter 3
MONITORING & CONTROLLING Process Group
“… 12 processes required to track & review the progress & performance
of the project. ”
 Key benefit is that project performance is measured & analyzed at
regular intervals to identify variances from the project management plan
 Identifies any areas in which changes to the plan are required
 Recommending corrective or preventive action in anticipating problems
 Approved Change Requests
Project Management Processes
Chapter 3
CLOSING Process Group
“… 1 process performed to formally complete the project or contract
obligations.”
 Obtain acceptance by the Customer or Sponsor to formally Close
 Conduct post-project review
 Document Lessons Learned & update OPAs
 Archive project docs as historical data
 Close out procurement activities to terminate agreements
 Perform team members’ assessments & release project resources
 Close Project
 Celebrate Your Success!!!
Project Management Processes
Chapter 3
Process Groups
organizes functions by Action
 Initiating (2) - Start
 Planning (24) - Plan
 Executing (10) - Do
 Monitoring & Controlling (12) – Check & Act
 Closing (1) - End
Project Management Processes
Chapter 3
KNOWLEDGE AREAS
 Organizes functions by Subject Matter
 “…a complete set of activities that make up a
project area of specialization”
 “…provide a detailed description of the ITTOs”
 10 areas further decomposed into 49 processes
 Integrated among the 5 Process Groups
 Is NOT Linear
Project Management Processes
Chapter 3
49
Integration Management
Chapter 4
“Is the Project Manager’s core responsibilities”
“…. is a group of processes required to ensure that the
various elements of the project are properly coordinated.”
Process Process Group Key Deliverables
4.1 Develop Project Charter Initiating Project Charter
4.2 Develop Project Management Plan Planning Project Management Plan
4.3 Direct and Manage Executing Project Deliverables
4.4 Manage Project Knowledge Executing Document Lessons Learned
4.5 Monitor and Control Project Work Monitoring & Controlling Change Requests
4.6 Perform Integrated Change Control Monitoring & Controlling Approved Change Requests
4.7 Close Project or Phase Closing Finalize Contracts, Payments, Transition
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Key Points
 A project charter formally authorizes the project
 Gives the objectives and business case
 Identifies & authorizes Project Manager use of organizational resources for project use
 Generic enough not to change often
 Written by a Manager higher in authority than Project Manager
 Includes name, description, deliverables
 A project does not start unless it has a Project charter
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
INPUTS
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
TOOLS
 Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page
when making a project decision
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Project Integration Management
Chapter 4
Develop Project Management Plan (PMP)
Process 2
Key Points
 Key benefit: creates the central document that defines all of the project work
 How the project will be executed, monitored & controlled
 Subsidiary plans are integrated into ONE comprehensive PMP
 The PMP is developed by the Project Manager with inputs from the team, stakeholders & management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Kick-off meeting happens after the planning phase and before the project execution. It is typically used
to communicate responsibilities of key stakeholders.
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Key Points
 Key benefit of this process is to provide overall management of the project work
 To lead & perform work as defined in the PMP
 Create deliverables to meet planned project work
 Manage team members & provide them with training
 Obtain, manage & use resources ex. Materials, Equipment, Facilities
 Establish & manage communications internal & external channels
 Manage Stakeholders, Sellers, Risks, Change Requests
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Project Integration Management
Chapter 4
Manage Project Knowledge
Process 4
Key Points
 Use prior organizational knowledge to produce or improve project outcomes
 Knowledge created by the project used to support operations and future projects
 Use existing knowledge and create new knowledge
 Contribute to organizational lessons learned
Project Integration Management
Chapter 4
Manage Project Work
Process 4
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Key Points
 Key benefit: allows stakeholders to understand current state of the project, any steps taken
and budget, schedule & scope forecasts
 Tracks, reviews & reports actual progress & performance against the PMP objectives
 Is conducted from project inception through completion
 Control includes corrective & preventative actions
 Identify & analyze existing and new risks
 Work Authorization System - PM’s system to ensure work is performed at the right time & in
the right sequence (found in the EEF – PMIS)
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Key Points
 Change Requests
 are submitted when issues are found while project work is being performed
 is a formal (written) proposal to modify any document, baseline, deliverable
 Change Log – all WRITTEN requests approved or not
 PM has authority to make changes IF constraints are not effected
 Types of Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 6
Key Points
 Key benefit: allows documented changes to be considered in an integrated manner to the
overall project while reducing risks to other areas of the project
 Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc
 Is conducted from project inception through completion
 Is the ultimate responsibility of the Project Manager to carefully & continuously manage
changes
 Changes can be requested by any stakeholder involved in the project
 Every “documented” change must be approved or rejected by a “responsible person”
 Or by the CCB – Change Control Board
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 6
Project Integration Management
Chapter 4
Close Project or Phase
Process 7
Key Points
 Provides lessons learned, formal ending of the project work & release of the organization’s
resources to pursue new endeavors
 Finalizes all activities across all PM Process Groups
 PM measures the scope baseline against the PMP
 Complete & close all contracts, procurement agreements, financials,
 Archive OPA historical records, reports, etc
 For projects terminated before completion, PM engages all stakeholders to investigate &
document reasons why
Project Integration Management
Chapter 4
Close Project or Phase
Process 7
Project Integration Management
Chapter 4
Key Points
 A project charter formally authorizes the project
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
 Expert Judgment – gaining advice from experts in other dept, outside consultants, industry
groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the
same page when making a project decision
 Subsidiary plans & Baselines are integrated into ONE comprehensive PMP
Project Integration Management
Chapter 4
Key Points
 The PMP is developed by the Project Manager with inputs from the team, stakeholders &
management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Monitor & Control is conducted from project inception through completion
 Control includes corrective & preventative Actions aka Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
 Changes can be made by Crashing or Fast Tracking
Project Integration Management
Chapter 4 - Summary
Project Management Processes
Chapter 4
Group Exercise – The Shuffle Game

Más contenido relacionado

La actualidad más candente

13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder EngagementDavidMcLachlan1
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify StakeholdersDavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Jeffrey Cheah
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesAndrew Mikityuk
 
Project integration management
Project integration managementProject integration management
Project integration managementEhsan Ullah
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Jeffrey Cheah
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
PMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management FrameworkPMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management FrameworkMohamed Loey
 

La actualidad más candente (19)

13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
 
Project integration management
Project integration managementProject integration management
Project integration management
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
PMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management FrameworkPMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management Framework
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 

Similar a CAPM Exam Prep - Project Management Processes

PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Fida Karim 🇵🇰
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training programParamjit Arora
 
Integration Masterclass
Integration MasterclassIntegration Masterclass
Integration MasterclassJeffrey Cheah
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptxAhmedKayed6
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approachMurali Venkatesh
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOswebuploader
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guiderobsonnasc
 

Similar a CAPM Exam Prep - Project Management Processes (20)

CAPM week 1 chapter 3
CAPM week 1 chapter 3CAPM week 1 chapter 3
CAPM week 1 chapter 3
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 
Integration Masterclass
Integration MasterclassIntegration Masterclass
Integration Masterclass
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptx
 
Day 2 PMP.pptx
Day 2 PMP.pptxDay 2 PMP.pptx
Day 2 PMP.pptx
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approach
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOs
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Pmp
PmpPmp
Pmp
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
PMP Study Guide
PMP Study GuidePMP Study Guide
PMP Study Guide
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guide
 

Más de Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

Más de Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 

Último

Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxMusic 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxleah joy valeriano
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsManeerUddin
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 

Último (20)

Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxMusic 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture hons
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 

CAPM Exam Prep - Project Management Processes

  • 1. Certified Associate Project Management CAPM® Exam Prep – Week 2 Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Project Managers  use Process Groups to coordinate the effective flow of a project from its start to its close using ITTOs & Knowledge Areas.  in collaboration with the project team are ALWAYS responsible for planning & developing a successful Project Management Process  actively manages each of these interactions to meet the Sponsor, Customer & Stakeholder requirements Project Management Processes Chapter 3
  • 3. PROCESS  “is a set of interrelated actions & activities performed to create a specific product, service or result.”  Project Management has 49 processes PROCESS GROUPS  organize the process functions by their Actions  are the project activities broken down into 5 steps KNOWLEDGE AREAS  organizes the process functions by their Subject Matter  are the process elements broken down into 10 areas  ARE NOT LINEAR !!! ITTOs  “each process is linked & characterized by its INPUTS, TOOLS, TECHNIQUES & OUTPUTS.”  Inputs – information used in the project ex. EEF, OPAs, Charter, etc  Outputs – documents, deliverables, decisions  Tools &Techniques – used to do the work ex. Meetings, Expert, Audits Project Management Processes Chapter 3
  • 4. PHASES  “a set of processes that are ITERATED several times to achieve the required outcome.”  each Phase of the project goes thru all of the 5 Process Groups Sequential Relationship  Phases of the project that happen one after another  Teams work together on each phase Overlapping Relationship  Phases of the project deliver results independently  Teams work on different parts of the project  Complicated to manage due to increased risk & rework Project Management Processes Chapter 3
  • 5. Project Management Process Groups  Initiating  Planning  Executing  Monitoring & Controlling  Closing Project Management Processes Chapter 3
  • 6. Project Management Processes Chapter 3 Project Management Process Groups
  • 7. INITIATING Process Group  Develop the Project Charter  Project Manager is Authorized  Business Case  High level planning – Rough Order of Magnitude estimating  Initial financial resources are committed  Scope is conceptualize – Progressive Elaboration  Identify Stakeholders  Stakeholder Register - List of Internal & External influences  Identify their expectations Project Management Processes Chapter 3
  • 8. PLANNING Process Group “… 24 processes used in the strategy to develop a course of action or path to successfully complete the project or phase. A well managed plan saves resources, time & money and gets the Stakeholder’s buy-in & engagement.” Iterative – each planning process may use the results of the previous process that may affect or change the plan  Project Management Plan  Is an Output that guides the Execution & Control of the project  Project Documents  Are Outputs detailing each of the Knowledge Areas Project Management Processes Chapter 3
  • 9. EXECUTING Process Group “… 10 processes performed to complete the project work defined in the Project Management Plan to meet the project objectives.”  PM coordinates People & Resources to Do the work  Communicates with Stakeholders to manage their expectations  Proactive analysis of baselines, changes in resource availability, productivity, expected durations, budgets, etc  Change requests approvals resulting in Project Doc updates  Deliverables  Changes Requests Project Management Processes Chapter 3
  • 10. MONITORING & CONTROLLING Process Group “… 12 processes required to track & review the progress & performance of the project. ”  Key benefit is that project performance is measured & analyzed at regular intervals to identify variances from the project management plan  Identifies any areas in which changes to the plan are required  Recommending corrective or preventive action in anticipating problems  Approved Change Requests Project Management Processes Chapter 3
  • 11. CLOSING Process Group “… 1 process performed to formally complete the project or contract obligations.”  Obtain acceptance by the Customer or Sponsor to formally Close  Conduct post-project review  Document Lessons Learned & update OPAs  Archive project docs as historical data  Close out procurement activities to terminate agreements  Perform team members’ assessments & release project resources  Close Project  Celebrate Your Success!!! Project Management Processes Chapter 3
  • 12. Process Groups organizes functions by Action  Initiating (2) - Start  Planning (24) - Plan  Executing (10) - Do  Monitoring & Controlling (12) – Check & Act  Closing (1) - End Project Management Processes Chapter 3
  • 13. KNOWLEDGE AREAS  Organizes functions by Subject Matter  “…a complete set of activities that make up a project area of specialization”  “…provide a detailed description of the ITTOs”  10 areas further decomposed into 49 processes  Integrated among the 5 Process Groups  Is NOT Linear Project Management Processes Chapter 3 49
  • 14.
  • 15. Integration Management Chapter 4 “Is the Project Manager’s core responsibilities” “…. is a group of processes required to ensure that the various elements of the project are properly coordinated.” Process Process Group Key Deliverables 4.1 Develop Project Charter Initiating Project Charter 4.2 Develop Project Management Plan Planning Project Management Plan 4.3 Direct and Manage Executing Project Deliverables 4.4 Manage Project Knowledge Executing Document Lessons Learned 4.5 Monitor and Control Project Work Monitoring & Controlling Change Requests 4.6 Perform Integrated Change Control Monitoring & Controlling Approved Change Requests 4.7 Close Project or Phase Closing Finalize Contracts, Payments, Transition
  • 17. Project Integration Management Chapter 4 Develop Project Charter Process 1 Key Points  A project charter formally authorizes the project  Gives the objectives and business case  Identifies & authorizes Project Manager use of organizational resources for project use  Generic enough not to change often  Written by a Manager higher in authority than Project Manager  Includes name, description, deliverables  A project does not start unless it has a Project charter
  • 18. Project Integration Management Chapter 4 Develop Project Charter Process 1 INPUTS  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense TOOLS  Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision
  • 19. Project Integration Management Chapter 4 Develop Project Charter Process 1
  • 20. Project Integration Management Chapter 4 Develop Project Management Plan (PMP) Process 2 Key Points  Key benefit: creates the central document that defines all of the project work  How the project will be executed, monitored & controlled  Subsidiary plans are integrated into ONE comprehensive PMP  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders.
  • 21. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 22. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 23. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 24. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3 Key Points  Key benefit of this process is to provide overall management of the project work  To lead & perform work as defined in the PMP  Create deliverables to meet planned project work  Manage team members & provide them with training  Obtain, manage & use resources ex. Materials, Equipment, Facilities  Establish & manage communications internal & external channels  Manage Stakeholders, Sellers, Risks, Change Requests
  • 25. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3
  • 26. Project Integration Management Chapter 4 Manage Project Knowledge Process 4 Key Points  Use prior organizational knowledge to produce or improve project outcomes  Knowledge created by the project used to support operations and future projects  Use existing knowledge and create new knowledge  Contribute to organizational lessons learned
  • 27. Project Integration Management Chapter 4 Manage Project Work Process 4
  • 28. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5 Key Points  Key benefit: allows stakeholders to understand current state of the project, any steps taken and budget, schedule & scope forecasts  Tracks, reviews & reports actual progress & performance against the PMP objectives  Is conducted from project inception through completion  Control includes corrective & preventative actions  Identify & analyze existing and new risks  Work Authorization System - PM’s system to ensure work is performed at the right time & in the right sequence (found in the EEF – PMIS)
  • 29. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5 Key Points  Change Requests  are submitted when issues are found while project work is being performed  is a formal (written) proposal to modify any document, baseline, deliverable  Change Log – all WRITTEN requests approved or not  PM has authority to make changes IF constraints are not effected  Types of Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
  • 30. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5
  • 31. Project Integration Management Chapter 4 Perform Integrated Change Control Process 6 Key Points  Key benefit: allows documented changes to be considered in an integrated manner to the overall project while reducing risks to other areas of the project  Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc  Is conducted from project inception through completion  Is the ultimate responsibility of the Project Manager to carefully & continuously manage changes  Changes can be requested by any stakeholder involved in the project  Every “documented” change must be approved or rejected by a “responsible person”  Or by the CCB – Change Control Board
  • 32. Project Integration Management Chapter 4 Perform Integrated Change Control Process 6
  • 33. Project Integration Management Chapter 4 Close Project or Phase Process 7 Key Points  Provides lessons learned, formal ending of the project work & release of the organization’s resources to pursue new endeavors  Finalizes all activities across all PM Process Groups  PM measures the scope baseline against the PMP  Complete & close all contracts, procurement agreements, financials,  Archive OPA historical records, reports, etc  For projects terminated before completion, PM engages all stakeholders to investigate & document reasons why
  • 34. Project Integration Management Chapter 4 Close Project or Phase Process 7
  • 35. Project Integration Management Chapter 4 Key Points  A project charter formally authorizes the project  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense  Expert Judgment – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision  Subsidiary plans & Baselines are integrated into ONE comprehensive PMP
  • 36. Project Integration Management Chapter 4 Key Points  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Monitor & Control is conducted from project inception through completion  Control includes corrective & preventative Actions aka Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong  Changes can be made by Crashing or Fast Tracking
  • 38. Project Management Processes Chapter 4 Group Exercise – The Shuffle Game

Notas del editor

  1. Processes are either: Operational Process & a Project Management Process
  2. Processes are either: Operational Process & a Project Management Process
  3. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?
  4. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?
  5. This is where the PM walks thru the project & gets organized BEFORE actual work begins
  6. Organizes functions by Action
  7. Int: coordinating all of the work so that it happens correctly
  8. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?