Report for po no 7400005491.docx

Report

EXPEDITING REPORT
STDFORM2
RFE REFERENCE: 2023-JY-TATA-0006
REPORT NO.: 001
SHEET 1 OF
JOB CODE : 0-8936-2 PROJECT NAME : GTPP / Golden Triangle
Polymers Project
TO : Mr. Ronald Ryan PO NO. : 7400005491
ATTN. : Mr. Ronald Ryan PO ISSUE DATE : 24/11/2022
COPY TO
FROM : 7/8/2023 to 22/8/2023 VENDOR : Siemens Energy INC
MANUFACTURER : Sparkle cleantech Pvt Ltd
EXPEDITER : Naganathan Iyer LOCATION : Khopoli Mumbai
CHECKED BY : CONTACT/TITLE : Mr. Rakesh Ranjan
ISSUE DATE : (22/8/2023) PHONE NO. : +91 7304481682
MTRL DESCRIPTION : Process Water Clean-up Unit (10-X-2400) E-MAIL :
rakesh@sparklecleantech.com
STATUS OF THE SUBJECT AS CHECKED ON 22/8/2023 IS AS FOLLOWS:
1. Latest promise related to contractual date □ MAINTAINED □ IMPROVED □ SLIPPED □✔ REVISED
PO Delivery Date & Terms : 25/12/2023
Previous Promise : 25/12/2023
Current Promise : 19/1/2024
Expediter’s Estimate : 25/1/2024 as per schedule
Reason for Delivery SLIPPAGE / REVISION:
There is delay in bought out item delivery and yet the complete engineering not freezed and document approval in
Code A is under process
Earlier Delivery Components Such As Template, Anchor Bolts, etc.: □ YES □✔ NO
If yes, Components Description Flowserve Seal Plan
Delivery Date End of December 2023
2. Action to be taken
ITEM ACTION REQUIRED ACTION BY
1) Document Submission status is attached to report need to expedite the approval
process
JKJV
2) Rhu pumps is not responding by email so need to Visit the facility to understand the
bottleneck
Sparkle
3)
4)
5)
6)
(To obtain Vendor’s required date to close out each item)
3. Highlights :
4. Next Visit Scheduled Date:
5. Expediting Hours This Visit
(If, Applicable)
Expediting: 8/Day Travel: 1/day Reporting: 1hr
Kilometers : Other Cost:
EXPEDITING REPORT
STDFORM2
6. INDIVIDUAL ITEM DELIVERY PROMISED
PO
Item No.
Equipment No.
Tag No.
Vendor
Ref.
No.
PO Delivery
Date
Promised
Del. Date
Expediter’s
Forecast
Remarks
1 10-X-2400 2022-
06-20-
USGCII
Rev L
25/12/2023 19/1/2024
25/1/2024
2 10-V-2400 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
3 10-P-2400A/B 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
4 10-P-2402A/B 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
5 10-P-2403A/B 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
6 10-V-2401A/B/C 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
7 10−P−2401 A/B/C 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
8 10−P−2404A/B 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
9 10−V−2402 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
10 10−V−2403 2022-
06-20-
USGCII
Rev L
25/12/2023
19/1/2024 25/1/2024
ITEM ACTION BY:
7. ATTENDEES:
(JGC) :
(Vendor) : Mr. Rakesh Ranjan
8. VERIFICATION OF PREVIOUS ACTION ITEMS: (IF APPLICABLE)
EXPEDITING REPORT
STDFORM2
ITEM ACTION BY:
(to confirm if each of the previous action items have been closed)
9. JGC’S P.O., REQUISITION, AND SPECIFICATIONS:
Yes
Sparkle & JGC
10. OUTSTANDING CORRESPONDENCES AND ISSUES:
Communication is on going
Sparkle & JGC
11. CRITICAL PATH DOCUMENTS:
Refer the updated sheet for vendor document status
JKJV
JKJV
12. VENDOR DOCUMENT STATUS:
Refer the updated sheet for vendor document status
13. VENDOR MONTHLY REPORT (VMR) STATUS
Last Issue Date: 20/7/2023
Next Issue Date: 20/8/2023
14. MATERIALS/COMPONENTS SUB-ORDERING STATUS:
Refer Enclosed Annexure A
Sparkle
15. FABRICATION STATUS:
Refer Annexure B &C
16. INSPECTION:
NA
NA
17. PACKING AND SHIPPING:
3 months Sparkle
18. WORKLOAD/ ANY OTHER BUSINESS
One More Project of ONGC is running
NA
19. ANY OTHER MATTERS
NA
NA
20. VENDOR ORGANIZATION
Yes
NA
EXPEDITING REPORT
STDFORM2
ITEM ACTION BY:
Project Manager : Rakesh Ranjan
Commercial : Pradip Mankame
Engineering : Nitesh
Procurement : Jyoti
QC : Anil Potdar
Fabrication : Kirti
Shipping : NA
21. CONCLUSION:
Hereby I conclude major items ordered are from Rhu Pumps whose delivery is constraint
as he sub ordering from flow serve so need have intense follow-up’s with the sub vendor
Note: Flash Report to be submitted if there is any critical issues found

Recomendados

Draft document for project no ufc85 por
Draft document for project no ufc85Draft document for project no ufc85
Draft document for project no ufc85Uyen Nguyen
1K vistas38 diapositivas
Mainsolicitation por
MainsolicitationMainsolicitation
MainsolicitationBryan Johnson
619 vistas155 diapositivas
Fabrication Schedule of Main Equipment items - ALASCON.pdf por
Fabrication Schedule of Main Equipment items - ALASCON.pdfFabrication Schedule of Main Equipment items - ALASCON.pdf
Fabrication Schedule of Main Equipment items - ALASCON.pdfFayezAlahmadi1
15 vistas1 diapositiva
ADWEA_APPROVED_VENDORS_LIST.pdf por
ADWEA_APPROVED_VENDORS_LIST.pdfADWEA_APPROVED_VENDORS_LIST.pdf
ADWEA_APPROVED_VENDORS_LIST.pdfMohamed9871
54 vistas311 diapositivas
LANDSIDE.pdf por
LANDSIDE.pdfLANDSIDE.pdf
LANDSIDE.pdfSankaranarayanan196410
1 vista1 diapositiva
total report por
total reporttotal report
total reportyasser abouzeid,MD,CCE
139 vistas45 diapositivas

Más contenido relacionado

Similar a Report for po no 7400005491.docx

( Itp ag pipe) rapid p006 a scs qac itp 3200 0007 por
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007Tonni Bruce
8.1K vistas38 diapositivas
10. Overall Implementation Programme por
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation ProgrammeSam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
420 vistas15 diapositivas
for estimate.pdf por
for estimate.pdffor estimate.pdf
for estimate.pdfIan Abarado
18 vistas14 diapositivas
Nmdc nspb c 2684 qap-approved por
Nmdc nspb c 2684 qap-approvedNmdc nspb c 2684 qap-approved
Nmdc nspb c 2684 qap-approvedPankaj Singh Rana
94 vistas6 diapositivas
check list 1 (Generator Transformer).pdf por
check list 1 (Generator Transformer).pdfcheck list 1 (Generator Transformer).pdf
check list 1 (Generator Transformer).pdfshoaib376207
18 vistas3 diapositivas
PO P15-3-RKC rev. 6 dtd 21.06.2023.pdf por
PO P15-3-RKC rev. 6 dtd 21.06.2023.pdfPO P15-3-RKC rev. 6 dtd 21.06.2023.pdf
PO P15-3-RKC rev. 6 dtd 21.06.2023.pdfssuser3b06c0
2 vistas1 diapositiva

Similar a Report for po no 7400005491.docx(20)

( Itp ag pipe) rapid p006 a scs qac itp 3200 0007 por Tonni Bruce
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
Tonni Bruce8.1K vistas
check list 1 (Generator Transformer).pdf por shoaib376207
check list 1 (Generator Transformer).pdfcheck list 1 (Generator Transformer).pdf
check list 1 (Generator Transformer).pdf
shoaib37620718 vistas
PO P15-3-RKC rev. 6 dtd 21.06.2023.pdf por ssuser3b06c0
PO P15-3-RKC rev. 6 dtd 21.06.2023.pdfPO P15-3-RKC rev. 6 dtd 21.06.2023.pdf
PO P15-3-RKC rev. 6 dtd 21.06.2023.pdf
ssuser3b06c02 vistas
182060001-GA-001 SHT 02 REV_1 por Henjo Capelle
182060001-GA-001 SHT 02 REV_1182060001-GA-001 SHT 02 REV_1
182060001-GA-001 SHT 02 REV_1
Henjo Capelle67 vistas
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI... por Harish Sharma
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
Harish Sharma1.6K vistas
23055 - LAVALIN PROJECT - Shop Drawing.pdf por MODI20077
23055 - LAVALIN PROJECT - Shop Drawing.pdf23055 - LAVALIN PROJECT - Shop Drawing.pdf
23055 - LAVALIN PROJECT - Shop Drawing.pdf
MODI200776 vistas
Antara Dashboard-002.pptx por TalebAlfihan
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
TalebAlfihan18 vistas
altaf resume work preparation por Altaf Tanwar
altaf resume work preparationaltaf resume work preparation
altaf resume work preparation
Altaf Tanwar505 vistas

Último

2023 Photo Contest.pptx por
2023 Photo Contest.pptx2023 Photo Contest.pptx
2023 Photo Contest.pptxculhama
32 vistas185 diapositivas
December 2023 - Meat on the Bones por
December 2023 - Meat on the BonesDecember 2023 - Meat on the Bones
December 2023 - Meat on the BonesNZSG
24 vistas11 diapositivas
Root Cause Analysis (RCA) por
Root Cause Analysis (RCA)Root Cause Analysis (RCA)
Root Cause Analysis (RCA)Operational Excellence Consulting (Singapore)
41 vistas28 diapositivas
Quandoo - Passion - Matthias M.pptx por
Quandoo - Passion - Matthias M.pptxQuandoo - Passion - Matthias M.pptx
Quandoo - Passion - Matthias M.pptxMatthias Maximilian
23 vistas5 diapositivas
v s.pptx por
v s.pptxv s.pptx
v s.pptxravikhadalwal
10 vistas2 diapositivas
Presentation on proposed acquisition of leading European asset manager Aermon... por
Presentation on proposed acquisition of leading European asset manager Aermon...Presentation on proposed acquisition of leading European asset manager Aermon...
Presentation on proposed acquisition of leading European asset manager Aermon...KeppelCorporation
240 vistas11 diapositivas

Último(20)

2023 Photo Contest.pptx por culhama
2023 Photo Contest.pptx2023 Photo Contest.pptx
2023 Photo Contest.pptx
culhama32 vistas
December 2023 - Meat on the Bones por NZSG
December 2023 - Meat on the BonesDecember 2023 - Meat on the Bones
December 2023 - Meat on the Bones
NZSG24 vistas
Presentation on proposed acquisition of leading European asset manager Aermon... por KeppelCorporation
Presentation on proposed acquisition of leading European asset manager Aermon...Presentation on proposed acquisition of leading European asset manager Aermon...
Presentation on proposed acquisition of leading European asset manager Aermon...
KeppelCorporation240 vistas
The Talent Management Navigator Performance Management por Seta Wicaksana
The Talent Management Navigator Performance ManagementThe Talent Management Navigator Performance Management
The Talent Management Navigator Performance Management
Seta Wicaksana29 vistas
How UiPath’s European Founder Kept Control and Built an Expert Board of Direc... por Christian Dahlen
How UiPath’s European Founder Kept Control and Built an Expert Board of Direc...How UiPath’s European Founder Kept Control and Built an Expert Board of Direc...
How UiPath’s European Founder Kept Control and Built an Expert Board of Direc...
Christian Dahlen51 vistas
Assignment 4: Reporting to Management.pptx por BethanyAline
Assignment 4: Reporting to Management.pptxAssignment 4: Reporting to Management.pptx
Assignment 4: Reporting to Management.pptx
BethanyAline20 vistas
Super Solar Mounting Solutions 20230509(1).pdf por carrie55bradshaw
Super Solar Mounting Solutions 20230509(1).pdfSuper Solar Mounting Solutions 20230509(1).pdf
Super Solar Mounting Solutions 20230509(1).pdf
carrie55bradshaw11 vistas
Nevigating Sucess.pdf por TEWMAGAZINE
Nevigating Sucess.pdfNevigating Sucess.pdf
Nevigating Sucess.pdf
TEWMAGAZINE24 vistas
Building Careers at Specialty TRE 2023 por Jennifer Sanborn
Building Careers at Specialty TRE 2023Building Careers at Specialty TRE 2023
Building Careers at Specialty TRE 2023
Jennifer Sanborn50 vistas
Why are KPIs(key performance indicators) important? por Epixel MLM Software
Why are KPIs(key performance indicators) important? Why are KPIs(key performance indicators) important?
Why are KPIs(key performance indicators) important?
See the new MTN tariffs effected November 28, 2023 por Kweku Zurek
See the new MTN tariffs effected November 28, 2023See the new MTN tariffs effected November 28, 2023
See the new MTN tariffs effected November 28, 2023
Kweku Zurek29.5K vistas
Top 10 Web Development Companies in California por TopCSSGallery
Top 10 Web Development Companies in CaliforniaTop 10 Web Development Companies in California
Top 10 Web Development Companies in California
TopCSSGallery74 vistas
The Truth About Customer Journey Mapping por Aggregage
The Truth About Customer Journey MappingThe Truth About Customer Journey Mapping
The Truth About Customer Journey Mapping
Aggregage105 vistas
Engaging Senior Leaders to Accelerate Your Continuous Improvement Program por KaiNexus
Engaging Senior Leaders to Accelerate Your Continuous Improvement ProgramEngaging Senior Leaders to Accelerate Your Continuous Improvement Program
Engaging Senior Leaders to Accelerate Your Continuous Improvement Program
KaiNexus12 vistas

Report for po no 7400005491.docx

  • 1. EXPEDITING REPORT STDFORM2 RFE REFERENCE: 2023-JY-TATA-0006 REPORT NO.: 001 SHEET 1 OF JOB CODE : 0-8936-2 PROJECT NAME : GTPP / Golden Triangle Polymers Project TO : Mr. Ronald Ryan PO NO. : 7400005491 ATTN. : Mr. Ronald Ryan PO ISSUE DATE : 24/11/2022 COPY TO FROM : 7/8/2023 to 22/8/2023 VENDOR : Siemens Energy INC MANUFACTURER : Sparkle cleantech Pvt Ltd EXPEDITER : Naganathan Iyer LOCATION : Khopoli Mumbai CHECKED BY : CONTACT/TITLE : Mr. Rakesh Ranjan ISSUE DATE : (22/8/2023) PHONE NO. : +91 7304481682 MTRL DESCRIPTION : Process Water Clean-up Unit (10-X-2400) E-MAIL : rakesh@sparklecleantech.com STATUS OF THE SUBJECT AS CHECKED ON 22/8/2023 IS AS FOLLOWS: 1. Latest promise related to contractual date □ MAINTAINED □ IMPROVED □ SLIPPED □✔ REVISED PO Delivery Date & Terms : 25/12/2023 Previous Promise : 25/12/2023 Current Promise : 19/1/2024 Expediter’s Estimate : 25/1/2024 as per schedule Reason for Delivery SLIPPAGE / REVISION: There is delay in bought out item delivery and yet the complete engineering not freezed and document approval in Code A is under process Earlier Delivery Components Such As Template, Anchor Bolts, etc.: □ YES □✔ NO If yes, Components Description Flowserve Seal Plan Delivery Date End of December 2023 2. Action to be taken ITEM ACTION REQUIRED ACTION BY 1) Document Submission status is attached to report need to expedite the approval process JKJV 2) Rhu pumps is not responding by email so need to Visit the facility to understand the bottleneck Sparkle 3) 4) 5) 6) (To obtain Vendor’s required date to close out each item) 3. Highlights : 4. Next Visit Scheduled Date: 5. Expediting Hours This Visit (If, Applicable) Expediting: 8/Day Travel: 1/day Reporting: 1hr Kilometers : Other Cost:
  • 2. EXPEDITING REPORT STDFORM2 6. INDIVIDUAL ITEM DELIVERY PROMISED PO Item No. Equipment No. Tag No. Vendor Ref. No. PO Delivery Date Promised Del. Date Expediter’s Forecast Remarks 1 10-X-2400 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 2 10-V-2400 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 3 10-P-2400A/B 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 4 10-P-2402A/B 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 5 10-P-2403A/B 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 6 10-V-2401A/B/C 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 7 10−P−2401 A/B/C 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 8 10−P−2404A/B 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 9 10−V−2402 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 10 10−V−2403 2022- 06-20- USGCII Rev L 25/12/2023 19/1/2024 25/1/2024 ITEM ACTION BY: 7. ATTENDEES: (JGC) : (Vendor) : Mr. Rakesh Ranjan 8. VERIFICATION OF PREVIOUS ACTION ITEMS: (IF APPLICABLE)
  • 3. EXPEDITING REPORT STDFORM2 ITEM ACTION BY: (to confirm if each of the previous action items have been closed) 9. JGC’S P.O., REQUISITION, AND SPECIFICATIONS: Yes Sparkle & JGC 10. OUTSTANDING CORRESPONDENCES AND ISSUES: Communication is on going Sparkle & JGC 11. CRITICAL PATH DOCUMENTS: Refer the updated sheet for vendor document status JKJV JKJV 12. VENDOR DOCUMENT STATUS: Refer the updated sheet for vendor document status 13. VENDOR MONTHLY REPORT (VMR) STATUS Last Issue Date: 20/7/2023 Next Issue Date: 20/8/2023 14. MATERIALS/COMPONENTS SUB-ORDERING STATUS: Refer Enclosed Annexure A Sparkle 15. FABRICATION STATUS: Refer Annexure B &C 16. INSPECTION: NA NA 17. PACKING AND SHIPPING: 3 months Sparkle 18. WORKLOAD/ ANY OTHER BUSINESS One More Project of ONGC is running NA 19. ANY OTHER MATTERS NA NA 20. VENDOR ORGANIZATION Yes NA
  • 4. EXPEDITING REPORT STDFORM2 ITEM ACTION BY: Project Manager : Rakesh Ranjan Commercial : Pradip Mankame Engineering : Nitesh Procurement : Jyoti QC : Anil Potdar Fabrication : Kirti Shipping : NA 21. CONCLUSION: Hereby I conclude major items ordered are from Rhu Pumps whose delivery is constraint as he sub ordering from flow serve so need have intense follow-up’s with the sub vendor Note: Flash Report to be submitted if there is any critical issues found