SlideShare una empresa de Scribd logo
1 de 26
Descargar para leer sin conexión
CAD Funded
           Cost Research



Estimating Facilities is Easy....
           Isn't It?
            Glenn Butts
             Office of the CFO
                KSC/GG-G
             February 2012
Houston - We Have a Problem!
 A-3 Test Stand SSC - Ares 1
    $157 M initial estimate
    $320 M latest available project estimate
         2 times original estimate
     Latest available duration 7 years
                                                                                  Some of the
         1.75 times longer than original estimate                            CxP Program Facility
 SET GRC - Orion                                                       Cost and Schedule Growth Issues
    $ 63 M original estimate
    $152 M latest available estimate
         2.4 times original estimate
     Latest available duration 7 years
         1.75 times longer than original estimate
 O&C IOZ KSC - Orion
    $18 M original estimate
    $55.2 M latest available estimate
       Construction Duration 18 months original - actual 27.3 months
 LaRC – Hydro Impact Basin - Orion
     Bid Busted
        Conceptual design construction cost estimate: $1.89M
        Final design construction cost estimate:        $2.60M
     Construction duration - 90 days estimate, 210 days reality
 White Sands – LAS Orion
     Initial estimate: $2M
     Final cost:       $5.7M

    2           Some program requirements did change from initial requests
    However, program requirements can often be interpolated – but no one likes that answer
We build satellites, we don’t need facilities!
  JWST had to spend ~$100 million on JSC Chamber A
      Additional funds spent on GSE/STE




Hubble spent 28.6%
of development cost
    on facilities

   Every NASA project is built and tested in one or more facilities
     3
       Most facilities require repairs, modifications or upgrades
Background
Myth – estimating facilities is easy
Reality – estimating facility costs is difficult
  Early estimates developed with nebulous requirements
       But costs are expected to be accurate
  Facilities have unique set of rules
       Funding
           Approval Requires – Center, HQ & Congressional line item approval
           Phasing – Cost vs. Obligations
               Generally all funding must be available before project can be awarded
           Different colors of money FP&D, CoF, & non CoF
       Schedule - long timelines – Typically 5-7 year process


   4
CoF Typical Timeline
                                            5-7 Years


                          BY-4      BY-3       BY-2            BY-1   BY00       BY+1        BY+2

Project Proposed
Requirement Statement
Requirements
Document
Study(s)
PER (Prelim.Eng.Rep.)
Design
Advertise & Award
Construction/Outfitting
Turnover to O&M
Activation
Operationally Ready

Non-CoF Funded – Blue      Planning Phase             Design           Construction / Outfitting /
CoF Funded – Red                                      Phase                Activation Phase
                                                                                                     5
Assumptions




    Shuttle Operations Concept 1974   Shuttle Operations Reality Today
           What was estimated                  What was built




6
Historical Data
• Single most useful way to quickly estimate new projects
• Must be used with caution to ensure entire scope is represented
   – NASA method of funding projects makes it very difficult to ascertain total
     project costs.
       • Result of different funding streams
           – CoF, R&D, FP&D, GSE, Support Contractors, Etc
• New requirements are excluded from historical data
   – Code changes
   – Human rated systems, taller rockets, larger cryogenic systems
• Project final costs should be
   – Adjusted for scope
   – Escalated to midpoint of construction




   7
Real Life Example
 KSC hired engineering firm to design 4,200 sf facility
    Engineering firms initial estimate for this project was $2.4M
    PM concerned facility had to be downsized or additional funding found
    Instead an independent assessment of the project was done, estimate was $1.3M
        Assessment performed using available historical data
 Awarded value $1.2M (within 3% of independent assessment)
    ½ of initial engineering firms estimate

        This is how it
     How it “should work”

One of the best ways to define early
estimates is to compare to historical
               projects
  However, limited data available
    for these type of assessments                 Replacement Operations Building,
                                                                     8
                                                       Fuel Storage Area No. 1
Real Life Example #2
                          LC39B Lightning Protection Towers Estimate History
Millions ($)




                          Four Towers                                      Three Towers ~600' Tall
               38                                                               (Ares V Capable)
                           ~500' Tall                      A&E ECCP
                            (Ares I Only)                  Gov ECCP
                                                           Award
                                                                                              90%
               33                                          DD250




               28
                                                                                                    95%      100%
                                                                                 30%
                                                                   Study


               23
                                                                                  60%
                                                                                               Award % from estimate
                                                                                               0.4% Original
                                                   Error Bars   10%                            1.4% 100% Design
               18
                        10-05 10-05 11-05   4-06    5-06        6-06   9-06   12-06    1-07    2-07       3-07   6-07   7-07   10-10

                    9
               Had quote for $8M, but historical data suggested this was low
Subset of NASA Current KSC Data



                                   Over 3 Gigabytes
                                  NASA Specific Data
                                  Must be behind NDC
                                   Firewall to access




10
Facility Database Project Vision

 Phase 1 Gather & Validate Historical Data
                 In Work

          Phase 2 Data Analysis
   Analyze & Understand Compiled Data




                                             Maintain
           Phase 3 Create Model
  Normalize Data, Develop CER’s & Model

          Community Education
       If you build it they will come
                                                        11
A3 Initial Estimate Sanity Check
                 AEDC J6 Analogy
                  Altitude (SRB)

                  Plumbrook B2 
                  Adjusted Scope

                  SSC A2 Analogy
                  Adjusted Scope

                  SSC A1 Analogy
                  Adjusted Scope

                      SSC B2
                  Adjusted Scope

                      SSC B1
                  Adjusted Scope


                Average Historical


Includes $24M        A3 Estimate
 Contingency        Initial 2‐16‐07
    (20%)
                                   100    200    300         400 
                                                                    Millions

      13
             Compared projects are not for the same scope
        But give an indication that initial estimate was optimistic
A3 Cost History
             450                         Independent
                                        Cost Estimates
             400

             350

                   Includes $24M
$ Millions




             300
                    Contingency
             250

             200

             150

             100

             50

              0


              14
A3 Schedule
                                    Year 1       Year 2   Year 3   Year 4   Year 5     Year 6   Year 7   Year 8    Year 9
                                     FY07         FY08     FY09     FY10     FY11       FY12     FY13     FY14      FY15

              AEDC J6


              PBS B‐2


              NASA 2X Historic

              Cost Team ‐ Opt. 
Independent
              1A
Assessment
              (65% CI)


              Current Schedule



              Revised & 
              Approved 1509


              Original 1509 
              Prior to PDR

                                                             Assessment Date     Heavy Lift Team First Test Need Date*
                                  Construction                                         J2X First Test Need Date
        15
                                   Activation                                    Remember
                                  Contingency
                                                                       Typical Project Takes 5-7 Years
Facilities Database
                              Phase 1 Status
• Integrating available Facility and GSE databases
   – Data for 1,345 projects has been entered in database
  • Some data is conflicting, validation is slow process
• Actively seeking cost and schedule data from other centers
• Looking for facility GSE, & STE data
   – Data = estimates, summary schedules, bid abstracts, DD250’s, activation
     costs, design costs, pictures


   – Can you help?



                                                                               16
Additional Help
• The new NASA Cost Estimating Handbook
  – Located here
    http://www.nasa.gov/offices/pae/organization/cost_ana
    lysis_division.html
  – Has an Appendix that provides overview of CoF
    Process, and a discussion on how to adjust historical
    facility data
  – Appendix P - Construction of Facilities and Ground
    Support Equipment Cost Assessment



                                                        17
BACKUP

         18
NASA New Start Escalation Index
                     Should NOT be Used For Facilities
  NASA New Start Composition
  Total Weighted Index (weighting values)                          100%
  Labor total without total weighting applied                       81%
  Wages and Salary, Private, Professional, Scientific, Technical          50%
  AHE Aerospace Product and Parts Manufacturing                           10%
  Avg. Hourly Earnings, Computer System Design & Related Svc              10%
  Employment Cost Index, Benefits, Private, All Workers                   30%
  Material total without weighting applied                          12%
  Nonferrous Metals                                                       3%
  Semiconductor & Other Electronic Components                             4%
  Search, Detection, Navigation & Guidance Systems                        5%
  General total without weighting applied                           7%
  CPI (all items less food & energy)                                      5%
  CPI Fuels & Utilities                                                   2%

   19
Index designed for spacecraft, the only thing it should be used on!
Phase 1 Status
•   Data for 1,345 projects has been
    entered in database
     – Some data is conflicting,
       validation is slow process
•   Project is integrating available
    KSC Facility and GSE databases




                                             20
Project Summary
• Project:
   – Facility and Ground Support Equipment (GSE) Project Cost & Schedule
     Database

• Description:
   – KSC has completed 1,500+ facility and GSE projects which are scattered
     across multiple databases. This project requests funding to integrate the
     multiple databases into one database, validate the data and provide a
     search engine so that parametric and detailed project estimates can be
     prepared from actual historical data.
   – Integrate database into the Marshall Space Flight Center Engineering
     Cost Office Resource Data Storage and Retrieval (REDSTAR) system,
     or a REDSTAR type system

• Beneficiaries:
   – Agency wide Facility and GSE Offices.

                                                                                 21
National Aeronautics & Space Administration
NASA’s Constellation program – based largely on
existing technologies – was based on a vision of returning
astronauts back to the Moon by 2020.
However, the program was over budget, behind
schedule, & lacking in innovation due to a failure to
invest in critical new technologies.
The President’s Budget cancels Constellation &
replaces it with a bold new approach that invests in the
building blocks of a more capable approach to space.
 In the last 20 years NASA has spent at least $21B on canceled
                 Space Transportation Programs
                       ~7% of its Budget
  22
              Overruns can have real consequences
Database Screen Shots




         Adobe Acrobat
           Document




                         23
CoF Definition
♦   CoF: Facilities, Facility Systems and Collateral Equipment
        Site work, buildings and building systems normally acquired
         and installed as a part of a facility project
        Collateral Equipment
           General building systems and subsystems such as electrical, plumbing, pneumatic, fire
            protection, and control and monitoring systems.
           Building-type equipment normally required to make a facility useful and operable. Built-in
            or affixed to the facility in such a manner that removal would impair the usefulness, safety,
            or environment of the facility. Includes such items as elevators; heating, ventilating, and
            air-conditioning systems; transformers; and compressors and other like items generally
            accepted as being an inherent part of a building or structure and essential to its utility.
           Built-in or large substantially affixed equipment/property of any type other than building
            type equipment which is built in, affixed to, or installed in real property in such a manner
            that the installation cost including special foundations or unique utility services, or facility
            restoration work required after its removal, exceeds $100,000.




     April 21, 2011
Non-CoF (R&D) Definition
♦   Non-CoF: Outfitting, Activation and Non-Collateral Equipment
        Non-collateral Equipment
           Equipment other than collateral equipment which, when acquired and used in a facility or a
            test apparatus, can be severed and removed after erection or installation without substantial
            loss of value or damage to the premises where installed.
           A unit of equipment may be considered non-collateral if it has such a close relationship to a
            Program project hardware item (i.e., prototype or test article, launch vehicle, spacecraft)
            that it is essentially an extension of the Program hardware item in that its configuration
            and/or operating characteristics must constantly reflect unpredictable changes in the
            Program item.
           The relationship between the equipment item under consideration and the Program item
            must be clear and significant; and, it must be evident that sufficiently frequent changes in
            the equipment item are definitely to be expected due to the nature or complexity of the
            Program item although it may not be possible to predict the extent or actual frequency of
            such changes.




     April 21, 2011
CoF vs. Non-CoF Examples
             Examples of CoF Items                            Example of Non-CoF Items
  Building Structure (foundation, walls, windows,   Furniture and window treatment
  doors, roof, access floor/platforms etc.)         Electronic equipment racks
  Site work, parking, roads, landscaping            Removable raised flooring
  HVAC systems                                      Under floor HVAC for raised flooring systems
  AC Power                                          (cooling for equipment racks, computers, data
  Electrical conduit                                equipment)
  Potable water                                     Fire detection system software
  Fire suppression system                           Communication cables (including data circuits) and
  Fire detection system hardware                    "end item" equipment
  Wastewater system                                 Telephones
  Facility grounding & lightning protection         Computers
  Cranes (including control systems and software    Application software
  programs)                                         Laboratory equipment and systems including work
  Elevators (including control systems and          benches, sinks, cabinets, exhaust hoods
  software programs)                                Uninterruptible Power System (UPS)
  Exhaust systems                                   DC Power
  Cabling duct banks (power & communications)       Paging & Area Warning System (PAWS)
  Emergency power generation                        Fluids/Gases (regulator panels & controls)
  Original finished flooring and ceiling            Operational Intercom systems (OIS-D)
  Facility Propellants Drain Systems                Cafeteria and kitchen equipment/furniture
  Fluids/Gases (Piping, pedestals)                  Activation, relocation/move-in expense
                                                    Calibration & operator certification/training
  Current Non-CoF items to become CoF items in      Groundbreaking & dedication
  FY13:                                             Kennedy Space Center Complex Control System
  Premise wiring                                    (KCCS)
April 21, 2011

Más contenido relacionado

Similar a Estimating Facility Costs is Difficult

IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...
IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...
IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...pramodkrishnani
 
[Qraft] asset allocation with deep learning hyojunmoon
[Qraft] asset allocation with deep learning hyojunmoon[Qraft] asset allocation with deep learning hyojunmoon
[Qraft] asset allocation with deep learning hyojunmoon형식 김
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmermanNASAPMC
 
January.2012.CorporatePresentation
January.2012.CorporatePresentationJanuary.2012.CorporatePresentation
January.2012.CorporatePresentationWestern Potash Corp.
 
How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...
How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...
How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...Sayonsom Chanda
 
Report to the NAC
Report to the NACReport to the NAC
Report to the NACLarry Smarr
 
Benchmark 4 Linkedin
Benchmark 4 LinkedinBenchmark 4 Linkedin
Benchmark 4 Linkedinbenchmarklag
 
Retro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for GoldRetro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for GoldMurray Guy
 
20151009 Amplify PVInsider
20151009 Amplify PVInsider20151009 Amplify PVInsider
20151009 Amplify PVInsiderBrian Grenko
 
최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용
최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용
최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용Tae wook kang
 
Rajasthan Solar Policy PV Services
Rajasthan Solar Policy PV ServicesRajasthan Solar Policy PV Services
Rajasthan Solar Policy PV ServicesExergy
 
Loan Level Analysis Of Cmbs Linkedin
Loan Level Analysis Of Cmbs LinkedinLoan Level Analysis Of Cmbs Linkedin
Loan Level Analysis Of Cmbs Linkedintheanshul
 
Weyburn-Midale and Aquistore, Canada
Weyburn-Midale and Aquistore, CanadaWeyburn-Midale and Aquistore, Canada
Weyburn-Midale and Aquistore, CanadaGlobal CCS Institute
 
ON TIME | ON TARGET: Leasing for Army Transportation Battalion
ON TIME | ON TARGET: Leasing for Army Transportation BattalionON TIME | ON TARGET: Leasing for Army Transportation Battalion
ON TIME | ON TARGET: Leasing for Army Transportation BattalionCurt Cooper
 
Svarcas.rita
Svarcas.ritaSvarcas.rita
Svarcas.ritaNASAPMC
 

Similar a Estimating Facility Costs is Difficult (20)

IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...
IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...
IEEE Power Energy Society 2012 Presentation - Validation of Forecasting techn...
 
[Qraft] asset allocation with deep learning hyojunmoon
[Qraft] asset allocation with deep learning hyojunmoon[Qraft] asset allocation with deep learning hyojunmoon
[Qraft] asset allocation with deep learning hyojunmoon
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmerman
 
January.2012.CorporatePresentation
January.2012.CorporatePresentationJanuary.2012.CorporatePresentation
January.2012.CorporatePresentation
 
How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...
How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...
How to leverage Quantum Computing and Generative AI for Clean Energy Transiti...
 
Cstp project
Cstp projectCstp project
Cstp project
 
How to avoid pit falls in design basis rev 3
How to avoid pit falls in design basis rev 3How to avoid pit falls in design basis rev 3
How to avoid pit falls in design basis rev 3
 
Report to the NAC
Report to the NACReport to the NAC
Report to the NAC
 
Benchmark 4 Linkedin
Benchmark 4 LinkedinBenchmark 4 Linkedin
Benchmark 4 Linkedin
 
Retro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for GoldRetro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for Gold
 
20151009 Amplify PVInsider
20151009 Amplify PVInsider20151009 Amplify PVInsider
20151009 Amplify PVInsider
 
A RESTful WfXML
A RESTful WfXMLA RESTful WfXML
A RESTful WfXML
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용
최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용
최신 3차원 이미지 스캔 역설계 기술 전망 및 건설 활용
 
Rajasthan Solar Policy PV Services
Rajasthan Solar Policy PV ServicesRajasthan Solar Policy PV Services
Rajasthan Solar Policy PV Services
 
Loan Level Analysis Of Cmbs Linkedin
Loan Level Analysis Of Cmbs LinkedinLoan Level Analysis Of Cmbs Linkedin
Loan Level Analysis Of Cmbs Linkedin
 
Weyburn-Midale and Aquistore, Canada
Weyburn-Midale and Aquistore, CanadaWeyburn-Midale and Aquistore, Canada
Weyburn-Midale and Aquistore, Canada
 
Mexcur paul[2]
Mexcur paul[2]Mexcur paul[2]
Mexcur paul[2]
 
ON TIME | ON TARGET: Leasing for Army Transportation Battalion
ON TIME | ON TARGET: Leasing for Army Transportation BattalionON TIME | ON TARGET: Leasing for Army Transportation Battalion
ON TIME | ON TARGET: Leasing for Army Transportation Battalion
 
Svarcas.rita
Svarcas.ritaSvarcas.rita
Svarcas.rita
 

Más de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Más de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Último

How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesManik S Magar
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkPixlogix Infotech
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructureitnewsafrica
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024TopCSSGallery
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesBernd Ruecker
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Hiroshi SHIBATA
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 

Último (20)

How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App Framework
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architectures
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 

Estimating Facility Costs is Difficult

  • 1. CAD Funded Cost Research Estimating Facilities is Easy.... Isn't It? Glenn Butts Office of the CFO KSC/GG-G February 2012
  • 2. Houston - We Have a Problem!  A-3 Test Stand SSC - Ares 1  $157 M initial estimate  $320 M latest available project estimate  2 times original estimate  Latest available duration 7 years Some of the  1.75 times longer than original estimate CxP Program Facility  SET GRC - Orion Cost and Schedule Growth Issues  $ 63 M original estimate  $152 M latest available estimate  2.4 times original estimate  Latest available duration 7 years  1.75 times longer than original estimate  O&C IOZ KSC - Orion  $18 M original estimate  $55.2 M latest available estimate  Construction Duration 18 months original - actual 27.3 months  LaRC – Hydro Impact Basin - Orion  Bid Busted  Conceptual design construction cost estimate: $1.89M  Final design construction cost estimate: $2.60M  Construction duration - 90 days estimate, 210 days reality  White Sands – LAS Orion  Initial estimate: $2M  Final cost: $5.7M 2 Some program requirements did change from initial requests However, program requirements can often be interpolated – but no one likes that answer
  • 3. We build satellites, we don’t need facilities!  JWST had to spend ~$100 million on JSC Chamber A  Additional funds spent on GSE/STE Hubble spent 28.6% of development cost on facilities Every NASA project is built and tested in one or more facilities 3 Most facilities require repairs, modifications or upgrades
  • 4. Background Myth – estimating facilities is easy Reality – estimating facility costs is difficult Early estimates developed with nebulous requirements But costs are expected to be accurate Facilities have unique set of rules Funding  Approval Requires – Center, HQ & Congressional line item approval  Phasing – Cost vs. Obligations  Generally all funding must be available before project can be awarded  Different colors of money FP&D, CoF, & non CoF Schedule - long timelines – Typically 5-7 year process 4
  • 5. CoF Typical Timeline 5-7 Years BY-4 BY-3 BY-2 BY-1 BY00 BY+1 BY+2 Project Proposed Requirement Statement Requirements Document Study(s) PER (Prelim.Eng.Rep.) Design Advertise & Award Construction/Outfitting Turnover to O&M Activation Operationally Ready Non-CoF Funded – Blue Planning Phase Design Construction / Outfitting / CoF Funded – Red Phase Activation Phase 5
  • 6. Assumptions Shuttle Operations Concept 1974 Shuttle Operations Reality Today What was estimated What was built 6
  • 7. Historical Data • Single most useful way to quickly estimate new projects • Must be used with caution to ensure entire scope is represented – NASA method of funding projects makes it very difficult to ascertain total project costs. • Result of different funding streams – CoF, R&D, FP&D, GSE, Support Contractors, Etc • New requirements are excluded from historical data – Code changes – Human rated systems, taller rockets, larger cryogenic systems • Project final costs should be – Adjusted for scope – Escalated to midpoint of construction 7
  • 8. Real Life Example  KSC hired engineering firm to design 4,200 sf facility  Engineering firms initial estimate for this project was $2.4M  PM concerned facility had to be downsized or additional funding found  Instead an independent assessment of the project was done, estimate was $1.3M  Assessment performed using available historical data  Awarded value $1.2M (within 3% of independent assessment)  ½ of initial engineering firms estimate This is how it How it “should work” One of the best ways to define early estimates is to compare to historical projects However, limited data available for these type of assessments Replacement Operations Building, 8 Fuel Storage Area No. 1
  • 9. Real Life Example #2 LC39B Lightning Protection Towers Estimate History Millions ($) Four Towers Three Towers ~600' Tall 38 (Ares V Capable) ~500' Tall A&E ECCP (Ares I Only) Gov ECCP Award 90% 33 DD250 28 95% 100% 30% Study 23 60% Award % from estimate 0.4% Original Error Bars 10% 1.4% 100% Design 18 10-05 10-05 11-05 4-06 5-06 6-06 9-06 12-06 1-07 2-07 3-07 6-07 7-07 10-10 9 Had quote for $8M, but historical data suggested this was low
  • 10. Subset of NASA Current KSC Data Over 3 Gigabytes NASA Specific Data Must be behind NDC Firewall to access 10
  • 11. Facility Database Project Vision Phase 1 Gather & Validate Historical Data In Work Phase 2 Data Analysis Analyze & Understand Compiled Data Maintain Phase 3 Create Model Normalize Data, Develop CER’s & Model Community Education If you build it they will come 11
  • 12.
  • 13. A3 Initial Estimate Sanity Check AEDC J6 Analogy Altitude (SRB) Plumbrook B2  Adjusted Scope SSC A2 Analogy Adjusted Scope SSC A1 Analogy Adjusted Scope SSC B2 Adjusted Scope SSC B1 Adjusted Scope Average Historical Includes $24M A3 Estimate Contingency Initial 2‐16‐07 (20%) 100  200  300  400  Millions 13 Compared projects are not for the same scope But give an indication that initial estimate was optimistic
  • 14. A3 Cost History 450 Independent Cost Estimates 400 350 Includes $24M $ Millions 300 Contingency 250 200 150 100 50 0 14
  • 15. A3 Schedule Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 AEDC J6 PBS B‐2 NASA 2X Historic Cost Team ‐ Opt.  Independent 1A Assessment (65% CI) Current Schedule Revised &  Approved 1509 Original 1509  Prior to PDR Assessment Date Heavy Lift Team First Test Need Date* Construction J2X First Test Need Date 15 Activation Remember Contingency Typical Project Takes 5-7 Years
  • 16. Facilities Database Phase 1 Status • Integrating available Facility and GSE databases – Data for 1,345 projects has been entered in database • Some data is conflicting, validation is slow process • Actively seeking cost and schedule data from other centers • Looking for facility GSE, & STE data – Data = estimates, summary schedules, bid abstracts, DD250’s, activation costs, design costs, pictures – Can you help? 16
  • 17. Additional Help • The new NASA Cost Estimating Handbook – Located here http://www.nasa.gov/offices/pae/organization/cost_ana lysis_division.html – Has an Appendix that provides overview of CoF Process, and a discussion on how to adjust historical facility data – Appendix P - Construction of Facilities and Ground Support Equipment Cost Assessment 17
  • 18. BACKUP 18
  • 19. NASA New Start Escalation Index Should NOT be Used For Facilities NASA New Start Composition Total Weighted Index (weighting values) 100% Labor total without total weighting applied 81% Wages and Salary, Private, Professional, Scientific, Technical 50% AHE Aerospace Product and Parts Manufacturing 10% Avg. Hourly Earnings, Computer System Design & Related Svc 10% Employment Cost Index, Benefits, Private, All Workers 30% Material total without weighting applied 12% Nonferrous Metals 3% Semiconductor & Other Electronic Components 4% Search, Detection, Navigation & Guidance Systems 5% General total without weighting applied 7% CPI (all items less food & energy) 5% CPI Fuels & Utilities 2% 19 Index designed for spacecraft, the only thing it should be used on!
  • 20. Phase 1 Status • Data for 1,345 projects has been entered in database – Some data is conflicting, validation is slow process • Project is integrating available KSC Facility and GSE databases 20
  • 21. Project Summary • Project: – Facility and Ground Support Equipment (GSE) Project Cost & Schedule Database • Description: – KSC has completed 1,500+ facility and GSE projects which are scattered across multiple databases. This project requests funding to integrate the multiple databases into one database, validate the data and provide a search engine so that parametric and detailed project estimates can be prepared from actual historical data. – Integrate database into the Marshall Space Flight Center Engineering Cost Office Resource Data Storage and Retrieval (REDSTAR) system, or a REDSTAR type system • Beneficiaries: – Agency wide Facility and GSE Offices. 21
  • 22. National Aeronautics & Space Administration NASA’s Constellation program – based largely on existing technologies – was based on a vision of returning astronauts back to the Moon by 2020. However, the program was over budget, behind schedule, & lacking in innovation due to a failure to invest in critical new technologies. The President’s Budget cancels Constellation & replaces it with a bold new approach that invests in the building blocks of a more capable approach to space. In the last 20 years NASA has spent at least $21B on canceled Space Transportation Programs ~7% of its Budget 22 Overruns can have real consequences
  • 23. Database Screen Shots Adobe Acrobat Document 23
  • 24. CoF Definition ♦ CoF: Facilities, Facility Systems and Collateral Equipment  Site work, buildings and building systems normally acquired and installed as a part of a facility project  Collateral Equipment  General building systems and subsystems such as electrical, plumbing, pneumatic, fire protection, and control and monitoring systems.  Building-type equipment normally required to make a facility useful and operable. Built-in or affixed to the facility in such a manner that removal would impair the usefulness, safety, or environment of the facility. Includes such items as elevators; heating, ventilating, and air-conditioning systems; transformers; and compressors and other like items generally accepted as being an inherent part of a building or structure and essential to its utility.  Built-in or large substantially affixed equipment/property of any type other than building type equipment which is built in, affixed to, or installed in real property in such a manner that the installation cost including special foundations or unique utility services, or facility restoration work required after its removal, exceeds $100,000. April 21, 2011
  • 25. Non-CoF (R&D) Definition ♦ Non-CoF: Outfitting, Activation and Non-Collateral Equipment  Non-collateral Equipment  Equipment other than collateral equipment which, when acquired and used in a facility or a test apparatus, can be severed and removed after erection or installation without substantial loss of value or damage to the premises where installed.  A unit of equipment may be considered non-collateral if it has such a close relationship to a Program project hardware item (i.e., prototype or test article, launch vehicle, spacecraft) that it is essentially an extension of the Program hardware item in that its configuration and/or operating characteristics must constantly reflect unpredictable changes in the Program item.  The relationship between the equipment item under consideration and the Program item must be clear and significant; and, it must be evident that sufficiently frequent changes in the equipment item are definitely to be expected due to the nature or complexity of the Program item although it may not be possible to predict the extent or actual frequency of such changes. April 21, 2011
  • 26. CoF vs. Non-CoF Examples Examples of CoF Items Example of Non-CoF Items Building Structure (foundation, walls, windows, Furniture and window treatment doors, roof, access floor/platforms etc.) Electronic equipment racks Site work, parking, roads, landscaping Removable raised flooring HVAC systems Under floor HVAC for raised flooring systems AC Power (cooling for equipment racks, computers, data Electrical conduit equipment) Potable water Fire detection system software Fire suppression system Communication cables (including data circuits) and Fire detection system hardware "end item" equipment Wastewater system Telephones Facility grounding & lightning protection Computers Cranes (including control systems and software Application software programs) Laboratory equipment and systems including work Elevators (including control systems and benches, sinks, cabinets, exhaust hoods software programs) Uninterruptible Power System (UPS) Exhaust systems DC Power Cabling duct banks (power & communications) Paging & Area Warning System (PAWS) Emergency power generation Fluids/Gases (regulator panels & controls) Original finished flooring and ceiling Operational Intercom systems (OIS-D) Facility Propellants Drain Systems Cafeteria and kitchen equipment/furniture Fluids/Gases (Piping, pedestals) Activation, relocation/move-in expense Calibration & operator certification/training Current Non-CoF items to become CoF items in Groundbreaking & dedication FY13: Kennedy Space Center Complex Control System Premise wiring (KCCS) April 21, 2011