SlideShare a Scribd company logo
1 of 32
2012 NASA PM Challenge:

Low Cost Earned Value Management System (EVMS)
Implementation

Presented by:
Zakir Mahmood CGFM, PMP
Andrew Porter PMP, SSGB

Presented on:
February 22-23, 2012
Agenda

Introduction to Earned Value Management (EVM)
 • Concepts
 • Business case
Case Study: Earned Value Management System (EVMS)
Implementation at a Federal Agency
 • Background
 • Alternative Analysis
 • Requirements
 • Approach
 • Recession Proof EVM Solution
 • Results
EVM with Agile
Conclusion
Questions & Answer
                                                    2
Introduction to EVM
  Concepts

                  How well is this project performing?
        $1,400



        $1,200
                                   Plan $             Actual $
        $1,000
Costs




         $800



         $600



         $400



         $200



           $0
                 Jan-10   Feb-10    Mar-10   Apr-10    May-10   Jun-10   Jul-10   Aug-10   Sep-10   Oct-10   Nov-10   Dec-10

                                                                Time
                                                                                                                               3
Introduction to EVM
Concepts

What is Earned Value Management (EVM)?
EVM is a project management tool, which effectively integrates the scope of
work with the schedule and cost elements for optimum investment planning
and control.


Why is EVM important right now?
       Investment capital is scarce
       Greater emphasis on project success and value
       Increased demand for improved efficiency and ROI
       Increased demand for accountability and transparency



                                                                          4
Introduction to EVM
 Concepts


                                                                              Estimate At Completion
                                     Budget At Completion
                                                                                     Variance at
                        Planned Value (PV)                                           Completion

                                                             Projected
                                                             Schedule Delay     Estimate To
Costs




                                                             at Completion      Complete
        Schedule                                       Projected Costs
        Variance
        (SV)                                 Cost Variance (CV)
               Actual
               Costs
                                         Status Date


                              Earned Value (EV)
                                             Time
                                                                                                       5
Introduction to EVM
Business Case

              Benefits                             Drawbacks
Integrates project’s scope, schedule, Time required for data measurement
& cost                                can be considerable

                                        Schedule variances do not address
Improves organizational effectiveness
                                        the critical path

Allows for performance analysis         Value earned without respect to
                                        quality
Provides early warning signals of
schedule slippages & cost overruns      Root cause of performance issues
                                        are not revealed



                                                                            6
Case Study: EVMS Implementation
Background
Economic Correction of 2008
     Businesses
       •    Slashed budgets & projects
       •    Abandoned or delayed applications
        Fee-Funded Federal Agency
       •    Revenues drop by 50% +
       •    Discretionary budgets cut by similar rate
        Office of Chief Information Officer (OCIO)
       •    Virtually all projects reevaluated or halted
       •    Delivering successful projects became top priority
Our task: Develop a mechanism, process, artifacts to convey state of IT Investments
                                                                                      7
Case Study: EVMS Implementation
Background

 Start of 2008; significant issues within organization

     Culture              Reactive, low morale, high turnover
     Policies             SDLC was not adhered
     Project Scheduling   Approach varied
     Project Budgeting    Processes not standardized
     Integration          Little internal coordination
     Reporting            Ad-hoc
     Analysis             Rarely performed




                                                                8
Case Study: EVMS Implementation
Alternative Analysis

                                 Recession-Proof
            Criteria                                  COTS
                                      EVM
Duration of implementation
                                     < 1 year         > 1 year
process
                                                   2-4% of project
Implementation cost                  1-2 FTE
                                                      portfolio
Change management requirement          Low           Moderate

Personnel training requirement         Low           Moderate

PMO maturity requirement               Low              High

Forecasting accuracy                 Moderate           High

                                                                 9
Case Study: EVMS Implementation
Approach

  Issue
  •   Limited investment capital available
  •   Little leverage from existing systems & artifacts
  Requirements
  •   Develop a project budget process
  •   Improve project schedule process
  •   Link schedule & budget processes
  •   Develop project reporting & analysis processes
  Approach
  •   Recession-Proof EVM
  •   Leverage existing systems and artifacts

                                                          10
Case Study: EVMS Implementation
Recession-Proof EVM Solution

 Analyze existing processes for EVM capabilities
 •   Identify process to improve
 •   Identify opportunities for automation
 Design EVMS solution
 •   Improve existing project scheduling process
 •   Design new project budget process
 •   Identify ways to link schedule & budget: “Four-way Match”
 Implement EVMS
 •   Build EVM tools to standardize and automate processes
 •   Integrate schedule and budget processes
 •   Standardize reporting & analysis procedures

                                                             11
Case Study: EVMS Implementation
Recession-Proof EVM Solution
                        EVMS Elements

 Activity Statusing                     Actual Costs   Activity Costing

                      Actual Schedule




                      Planned Schedule Planned Costs


Activity Sequencing
                                                       Activity Resourcing



                                   “Four-Way Match”                          12
Recession Proof EVM Solution
Planned Schedule

     EVMS Requirement                               Solution

  Standardize project planning         Use SDLC phases to proxy activities


                                       Summarize planned start & end dates
 Estimate duration at activity level
                                             at SDLC phase level




                                                                             13
Recession-Proof EVM Solution
Planned Costs

       EVMS Requirement                              Solution
Develop cost estimates at activity     Require costs to be planned at SDLC
level                                  phase level
Link resource rates to planned hours   Upload blended government and
                                       contractor rates
Assign all procurement costs to an     Require PM to select a SDLC phase
activity                               for all procurements
Provide time phased estimates by       Require PM to select a SDLC phase
activity level                         for all procurements
Map control accounts to activities     Links Budget Organizations with
                                       Project Codes



                                                                             14
Recession-Proof EVM Solution
Planned Costs (cont.)
Project Resource Estimation Worksheet (PREW):
   Excel based model - derives planned costs from planned schedule


        Feature           Previous Tool             Implemented Tool
Costs linked to phase   Labor only            Both labor & material
Time to cost project    Two days              Two hours
Excel lines             1,000                 150
Rate table linkage      Manual                Macro-enabled
Time phased             Yes; generic dates    Yes; precise dates




                                                                       15
Recession-Proof EVM Solution
Actual Schedule


      EVMS Requirement                              Solution
Project activity start & end dates are
                                       PM updates project schedule weekly
routinely updated


All project activity % physical
                                    PM updates physical percent complete
complete amounts are updated




                                                                            16
Recession-Proof EVM Solution
Actual Costs

        EVMS Requirement                              Solution
Enter internal labor time into T&A     Leverage cost accounting system,
system by project activity             provide training to ensure accuracy
                                       Provide PM resource usage data for
Provide PM resource usage reporting
                                       validation

Link internal labor costs to project   Leverage Time & Attendance system,
activity level                         General Ledger

Link actual procurement cost to project
                                        Leverage General Ledger
activity level




                                                                             17
Recession-Proof EVM Solution
Actual Costs (cont.)
General Ledger, Time & Attendance System:
   Queries actual costs by project activity; links to project budget

                                            Previous          Implemented
               Feature
                                             Method               Tool
Leverage of Cost accounting             Weak               Substantial
Reporting level                         Project            Activity
Data source for procurement costs       Cuff records       General ledger
Data source for internal labor          Not used           T&A system

Internal labor reporting                Not Available      Bi-weekly




                                                                            18
Recession-Proof EVM Solution
Integrate Schedule and Cost
EVM Model:
   Leverages “Four-Way Match” to calculate EVM scores; generate reports
                                      Previous          Implemented
             Feature
                                      Method                Tool
Integrity of EVM Calculations     Non-credible       Highly credible
Reporting process                 Ad-hoc             Mostly automated
Cost & Schedule reporting level   Project level      Activity level
Variance reporting                $ variance at      % and $ variance at
                                  project level      activity level
Forecasting level                 Not Available      Activity level
Forecasting accuracy              Not Available      Moderately
                                                     dependable


                                                                          19
Recession-Proof EVM Solution
Integrate Schedule and Cost

Analysis Tool:
  Provides analyst with overview of key metrics

     Evaluates EVMS elements
     •   Planned costs vs. actual costs
     •   Planned schedule vs. actual schedule
     Examines key trends & variances of EVM scores
     Values outside tolerances are flagged
     Large variances are researched for root cause
     •   Programmatic
     •   Accounting
     •   Reporting
                                                     20
Recession-Proof EVM Solution
Process Map
Integrated Process     Project Management Office                            Finance Division

                            Managerial                                           Financial
          Analyze            Analysis                                            Analysis
                              Performance                                       Trend & Variance




                                                       EVM
           Monitor &
                                                     Reporting
            Control                                  Status Reports




            Project                 Actual                             Actual Costs
           Execution               Schedule                                General Ledger,
                                    Status Updates                    Time & Attendance System




             Project                Planned
            Planning                                                  Planned Costs
                                    Schedule                                Budget Tool
                                      Project Plan




                                                                                                   21
Case Study: EVMS Implementation
Results

   EVM reports generated for 30 reports (>$100+M)
    •     Standard reporting performed
    •     Forecast reliability increased
    •     Executive reporting for strategic decision making
   EVM analysis is routinely performed
    •     EVM dashboards to draw focus to key EVM metrics
    •     Client staff trained to analyze metrics
   Accountability & transparency have increased
    •     Project Manager
    •     Project performance
   Project success rate has improved
                                                              22
Conclusion
Implementing Recession-Proof EVM
  Requires:
     • Smaller capital investment (~2 FTE for 1 year)
     • Lower personnel impact
  Succeeds by leveraging existing:
     • Systems - General Ledger & Time and Attendance
     • Tools - Project formulation & execution
     • Policies & procedures – SDLC
  Yields:
     • Majority of EVMS benefits
     • Foundation for transitioning to a COTS EVMS


                                                        23
EVM Schedule Information
for Agile Investments

• Graphical comparison of scheduled Budget vs. Actual
  (using percentages over time)
   – Time phased line graph comparing:
      • Linear burn rate of planned execution for investment
      • Planned Burn rate (if non-linear and known)
          – Requires a tool that captures this data; update
            and refine throughout the project life
      • Actual execution
          – Are we on ahead or behind schedule and why?



                                                               24
EVM Cost Information for Agile Investments


• Compare percentages over time for the following:
  – Total Cost vs. Planned Cost
  – Labor Category Breakout Cost vs. Planned Cost
     • Separate Labor, SW/HW, Indirect Costs,
       project contingency funds, etc.
  – Labor only vs. Planned Labor Cost
     • More predictable than HW/SW purchases
     • Timing and amount of non-labor purchases
       are known and under control

                                                 25
Lessons Learned


• EVM is a management tool
   – Requires leadership sponsorship
       • Update policies and procedures to drive success
   – Metrics should drive decision making
• Budget at Completion (BAC) is critical
   – Tied to every EVM metric except actual cost
   – Evaluate and improve budgeting tools
• EVM is only as good as the data used to report
• Consider Materiality of Investments
   – How significant are non-labor costs?
   – What is the probability that they will be different than the plan?
• Leverage best practices, but allow flexibility to make a tailored solution
  that works for your investment(s)
                                                                               26
Question & Answer




Thank You!


                    27
Appendix

 EVM Formulas
 • Foundation
 • Variance
 • Efficiency
 • Forecasting




                 28
EVM Metrics
Foundation


    Metric               Definition             Analytical question
 Budget At                                     What is the budget for this
           BAC    Total baseline cost
Completion                                     project?

                                               What is the estimated value
 Planned          Estimated cost of all work
             PV                                of the work planned to be
  Value           scheduled to be completed
                                               done?
                                              What is the actual cost
                  Cost incurred to accomplish
Actual Cost AC                                incurred for the work
                  the work
                                              accomplished?

                                               What is the estimated value
 Earned           Budgeted cost of actual
             EV                                of the work actually
  Value           work completed
                                               accomplished?

                                                                             29
EVM Metrics
Variance


    Metric          Formula        Analytical question

 Schedule                     How is the project progressing against
             SV   SV=EV-PV    the planned schedule?
 Variance



   Cost                       How is the project progressing against
             CV   CV=EV-AC    the budget?
 Variance




                                                                   30
EVM Metrics
Efficiency


        Metric             Formula     Analytical question

                                      How are we progressing vs. the
     Schedule                         original plan?
                    SPI   SPI=EV/PV
Performance Index



Cost Performance                      What is the value earned per
                    CPI   CPI=EV/AC   dollar spent ratio?
      Index




                                                                     31
EVM Metrics
Forecasting


    Metric           Formula         Analytical question

Estimate at                          What is the new projected total
            EAC     EAC = BAC/CPI    estimate based on CPI?
Completion


Estimate to
                                     How much more will the
 Complete     ETC   ETC = EAC - AC   project cost?




                                                                  32

More Related Content

What's hot

Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahaniNASAPMC
 
Esker.linda
Esker.lindaEsker.linda
Esker.lindaNASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonceNASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey NASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butlerNASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbierNASAPMC
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 

What's hot (20)

Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 
Esker.linda
Esker.lindaEsker.linda
Esker.linda
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Symons
SymonsSymons
Symons
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butler
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbier
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Price.rick
Price.rickPrice.rick
Price.rick
 

Viewers also liked

Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayneNASAPMC
 
Kelly.elliott
Kelly.elliottKelly.elliott
Kelly.elliottNASAPMC
 
Fuller.david
Fuller.davidFuller.david
Fuller.davidNASAPMC
 
Garg.sanjay
Garg.sanjayGarg.sanjay
Garg.sanjayNASAPMC
 
White.charles
White.charlesWhite.charles
White.charlesNASAPMC
 
Zimmerman
ZimmermanZimmerman
ZimmermanNASAPMC
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jeanNASAPMC
 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycuttNASAPMC
 
Inter mitchell
Inter mitchellInter mitchell
Inter mitchellNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardoNASAPMC
 
Newman.steve
Newman.steveNewman.steve
Newman.steveNASAPMC
 
Miller.charles
Miller.charlesMiller.charles
Miller.charlesNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Black.j.smith.g
Black.j.smith.gBlack.j.smith.g
Black.j.smith.gNASAPMC
 
Dean.david
Dean.davidDean.david
Dean.davidNASAPMC
 
Lovell.randy
Lovell.randyLovell.randy
Lovell.randyNASAPMC
 
Majerowicz
MajerowiczMajerowicz
MajerowiczNASAPMC
 
Nichols.hornback.moses
Nichols.hornback.mosesNichols.hornback.moses
Nichols.hornback.mosesNASAPMC
 

Viewers also liked (20)

Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 
Kelly.elliott
Kelly.elliottKelly.elliott
Kelly.elliott
 
Fuller.david
Fuller.davidFuller.david
Fuller.david
 
Glavich
GlavichGlavich
Glavich
 
Garg.sanjay
Garg.sanjayGarg.sanjay
Garg.sanjay
 
White.charles
White.charlesWhite.charles
White.charles
 
Zimmerman
ZimmermanZimmerman
Zimmerman
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jean
 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycutt
 
Inter mitchell
Inter mitchellInter mitchell
Inter mitchell
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardo
 
Newman.steve
Newman.steveNewman.steve
Newman.steve
 
Miller.charles
Miller.charlesMiller.charles
Miller.charles
 
Paradis william
Paradis williamParadis william
Paradis william
 
Black.j.smith.g
Black.j.smith.gBlack.j.smith.g
Black.j.smith.g
 
Dean.david
Dean.davidDean.david
Dean.david
 
Lovell.randy
Lovell.randyLovell.randy
Lovell.randy
 
Majerowicz
MajerowiczMajerowicz
Majerowicz
 
Nichols.hornback.moses
Nichols.hornback.mosesNichols.hornback.moses
Nichols.hornback.moses
 

Similar to Mahmood porter

Evms Presentation (July2006)Repro
Evms Presentation (July2006)ReproEvms Presentation (July2006)Repro
Evms Presentation (July2006)ReproJim Kendrick
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication GapBrent Barton
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
at ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systemsat ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained SystemsBrent Barton
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost managementNiraj Agarwal
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
Translating Points to Dollars
Translating Points to Dollars Translating Points to Dollars
Translating Points to Dollars Brent Barton
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Glen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project ManagementMartin Mehalchin
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentationGlen Alleman
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 

Similar to Mahmood porter (20)

Evms Presentation (July2006)Repro
Evms Presentation (July2006)ReproEvms Presentation (July2006)Repro
Evms Presentation (July2006)Repro
 
How to setup EVM within a PMO
How to setup EVM within a PMOHow to setup EVM within a PMO
How to setup EVM within a PMO
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
at ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systemsat ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systems
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost management
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Translating Points to Dollars
Translating Points to Dollars Translating Points to Dollars
Translating Points to Dollars
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project Management
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Value chain analysis 4
Value chain analysis 4Value chain analysis 4
Value chain analysis 4
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amandaNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 

Recently uploaded

Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdfChris Skinner
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Associazione Digital Days
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 

Recently uploaded (20)

Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 

Mahmood porter

  • 1. 2012 NASA PM Challenge: Low Cost Earned Value Management System (EVMS) Implementation Presented by: Zakir Mahmood CGFM, PMP Andrew Porter PMP, SSGB Presented on: February 22-23, 2012
  • 2. Agenda Introduction to Earned Value Management (EVM) • Concepts • Business case Case Study: Earned Value Management System (EVMS) Implementation at a Federal Agency • Background • Alternative Analysis • Requirements • Approach • Recession Proof EVM Solution • Results EVM with Agile Conclusion Questions & Answer 2
  • 3. Introduction to EVM Concepts How well is this project performing? $1,400 $1,200 Plan $ Actual $ $1,000 Costs $800 $600 $400 $200 $0 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Time 3
  • 4. Introduction to EVM Concepts What is Earned Value Management (EVM)? EVM is a project management tool, which effectively integrates the scope of work with the schedule and cost elements for optimum investment planning and control. Why is EVM important right now? Investment capital is scarce Greater emphasis on project success and value Increased demand for improved efficiency and ROI Increased demand for accountability and transparency 4
  • 5. Introduction to EVM Concepts Estimate At Completion Budget At Completion Variance at Planned Value (PV) Completion Projected Schedule Delay Estimate To Costs at Completion Complete Schedule Projected Costs Variance (SV) Cost Variance (CV) Actual Costs Status Date Earned Value (EV) Time 5
  • 6. Introduction to EVM Business Case Benefits Drawbacks Integrates project’s scope, schedule, Time required for data measurement & cost can be considerable Schedule variances do not address Improves organizational effectiveness the critical path Allows for performance analysis Value earned without respect to quality Provides early warning signals of schedule slippages & cost overruns Root cause of performance issues are not revealed 6
  • 7. Case Study: EVMS Implementation Background Economic Correction of 2008 Businesses • Slashed budgets & projects • Abandoned or delayed applications Fee-Funded Federal Agency • Revenues drop by 50% + • Discretionary budgets cut by similar rate Office of Chief Information Officer (OCIO) • Virtually all projects reevaluated or halted • Delivering successful projects became top priority Our task: Develop a mechanism, process, artifacts to convey state of IT Investments 7
  • 8. Case Study: EVMS Implementation Background Start of 2008; significant issues within organization Culture Reactive, low morale, high turnover Policies SDLC was not adhered Project Scheduling Approach varied Project Budgeting Processes not standardized Integration Little internal coordination Reporting Ad-hoc Analysis Rarely performed 8
  • 9. Case Study: EVMS Implementation Alternative Analysis Recession-Proof Criteria COTS EVM Duration of implementation < 1 year > 1 year process 2-4% of project Implementation cost 1-2 FTE portfolio Change management requirement Low Moderate Personnel training requirement Low Moderate PMO maturity requirement Low High Forecasting accuracy Moderate High 9
  • 10. Case Study: EVMS Implementation Approach Issue • Limited investment capital available • Little leverage from existing systems & artifacts Requirements • Develop a project budget process • Improve project schedule process • Link schedule & budget processes • Develop project reporting & analysis processes Approach • Recession-Proof EVM • Leverage existing systems and artifacts 10
  • 11. Case Study: EVMS Implementation Recession-Proof EVM Solution Analyze existing processes for EVM capabilities • Identify process to improve • Identify opportunities for automation Design EVMS solution • Improve existing project scheduling process • Design new project budget process • Identify ways to link schedule & budget: “Four-way Match” Implement EVMS • Build EVM tools to standardize and automate processes • Integrate schedule and budget processes • Standardize reporting & analysis procedures 11
  • 12. Case Study: EVMS Implementation Recession-Proof EVM Solution EVMS Elements Activity Statusing Actual Costs Activity Costing Actual Schedule Planned Schedule Planned Costs Activity Sequencing Activity Resourcing “Four-Way Match” 12
  • 13. Recession Proof EVM Solution Planned Schedule EVMS Requirement Solution Standardize project planning Use SDLC phases to proxy activities Summarize planned start & end dates Estimate duration at activity level at SDLC phase level 13
  • 14. Recession-Proof EVM Solution Planned Costs EVMS Requirement Solution Develop cost estimates at activity Require costs to be planned at SDLC level phase level Link resource rates to planned hours Upload blended government and contractor rates Assign all procurement costs to an Require PM to select a SDLC phase activity for all procurements Provide time phased estimates by Require PM to select a SDLC phase activity level for all procurements Map control accounts to activities Links Budget Organizations with Project Codes 14
  • 15. Recession-Proof EVM Solution Planned Costs (cont.) Project Resource Estimation Worksheet (PREW): Excel based model - derives planned costs from planned schedule Feature Previous Tool Implemented Tool Costs linked to phase Labor only Both labor & material Time to cost project Two days Two hours Excel lines 1,000 150 Rate table linkage Manual Macro-enabled Time phased Yes; generic dates Yes; precise dates 15
  • 16. Recession-Proof EVM Solution Actual Schedule EVMS Requirement Solution Project activity start & end dates are PM updates project schedule weekly routinely updated All project activity % physical PM updates physical percent complete complete amounts are updated 16
  • 17. Recession-Proof EVM Solution Actual Costs EVMS Requirement Solution Enter internal labor time into T&A Leverage cost accounting system, system by project activity provide training to ensure accuracy Provide PM resource usage data for Provide PM resource usage reporting validation Link internal labor costs to project Leverage Time & Attendance system, activity level General Ledger Link actual procurement cost to project Leverage General Ledger activity level 17
  • 18. Recession-Proof EVM Solution Actual Costs (cont.) General Ledger, Time & Attendance System: Queries actual costs by project activity; links to project budget Previous Implemented Feature Method Tool Leverage of Cost accounting Weak Substantial Reporting level Project Activity Data source for procurement costs Cuff records General ledger Data source for internal labor Not used T&A system Internal labor reporting Not Available Bi-weekly 18
  • 19. Recession-Proof EVM Solution Integrate Schedule and Cost EVM Model: Leverages “Four-Way Match” to calculate EVM scores; generate reports Previous Implemented Feature Method Tool Integrity of EVM Calculations Non-credible Highly credible Reporting process Ad-hoc Mostly automated Cost & Schedule reporting level Project level Activity level Variance reporting $ variance at % and $ variance at project level activity level Forecasting level Not Available Activity level Forecasting accuracy Not Available Moderately dependable 19
  • 20. Recession-Proof EVM Solution Integrate Schedule and Cost Analysis Tool: Provides analyst with overview of key metrics Evaluates EVMS elements • Planned costs vs. actual costs • Planned schedule vs. actual schedule Examines key trends & variances of EVM scores Values outside tolerances are flagged Large variances are researched for root cause • Programmatic • Accounting • Reporting 20
  • 21. Recession-Proof EVM Solution Process Map Integrated Process Project Management Office Finance Division Managerial Financial Analyze Analysis Analysis Performance Trend & Variance EVM Monitor & Reporting Control Status Reports Project Actual Actual Costs Execution Schedule General Ledger, Status Updates Time & Attendance System Project Planned Planning Planned Costs Schedule Budget Tool Project Plan 21
  • 22. Case Study: EVMS Implementation Results EVM reports generated for 30 reports (>$100+M) • Standard reporting performed • Forecast reliability increased • Executive reporting for strategic decision making EVM analysis is routinely performed • EVM dashboards to draw focus to key EVM metrics • Client staff trained to analyze metrics Accountability & transparency have increased • Project Manager • Project performance Project success rate has improved 22
  • 23. Conclusion Implementing Recession-Proof EVM Requires: • Smaller capital investment (~2 FTE for 1 year) • Lower personnel impact Succeeds by leveraging existing: • Systems - General Ledger & Time and Attendance • Tools - Project formulation & execution • Policies & procedures – SDLC Yields: • Majority of EVMS benefits • Foundation for transitioning to a COTS EVMS 23
  • 24. EVM Schedule Information for Agile Investments • Graphical comparison of scheduled Budget vs. Actual (using percentages over time) – Time phased line graph comparing: • Linear burn rate of planned execution for investment • Planned Burn rate (if non-linear and known) – Requires a tool that captures this data; update and refine throughout the project life • Actual execution – Are we on ahead or behind schedule and why? 24
  • 25. EVM Cost Information for Agile Investments • Compare percentages over time for the following: – Total Cost vs. Planned Cost – Labor Category Breakout Cost vs. Planned Cost • Separate Labor, SW/HW, Indirect Costs, project contingency funds, etc. – Labor only vs. Planned Labor Cost • More predictable than HW/SW purchases • Timing and amount of non-labor purchases are known and under control 25
  • 26. Lessons Learned • EVM is a management tool – Requires leadership sponsorship • Update policies and procedures to drive success – Metrics should drive decision making • Budget at Completion (BAC) is critical – Tied to every EVM metric except actual cost – Evaluate and improve budgeting tools • EVM is only as good as the data used to report • Consider Materiality of Investments – How significant are non-labor costs? – What is the probability that they will be different than the plan? • Leverage best practices, but allow flexibility to make a tailored solution that works for your investment(s) 26
  • 28. Appendix EVM Formulas • Foundation • Variance • Efficiency • Forecasting 28
  • 29. EVM Metrics Foundation Metric Definition Analytical question Budget At What is the budget for this BAC Total baseline cost Completion project? What is the estimated value Planned Estimated cost of all work PV of the work planned to be Value scheduled to be completed done? What is the actual cost Cost incurred to accomplish Actual Cost AC incurred for the work the work accomplished? What is the estimated value Earned Budgeted cost of actual EV of the work actually Value work completed accomplished? 29
  • 30. EVM Metrics Variance Metric Formula Analytical question Schedule How is the project progressing against SV SV=EV-PV the planned schedule? Variance Cost How is the project progressing against CV CV=EV-AC the budget? Variance 30
  • 31. EVM Metrics Efficiency Metric Formula Analytical question How are we progressing vs. the Schedule original plan? SPI SPI=EV/PV Performance Index Cost Performance What is the value earned per CPI CPI=EV/AC dollar spent ratio? Index 31
  • 32. EVM Metrics Forecasting Metric Formula Analytical question Estimate at What is the new projected total EAC EAC = BAC/CPI estimate based on CPI? Completion Estimate to How much more will the Complete ETC ETC = EAC - AC project cost? 32