John F. Kennedy Space Center
                                                      LAUNCH SERVICES PROGRAM




       Over 50 Successful Launches: Priceless

                                   Amanda Mitskevich
                                Launch Services Program
                                  Flight Projects Office




2/21/2007                                                                       1
Launch Services Program
 John F. Kennedy Space Center
                                                                                    LAUNCH SERVICES PROGRAM

                                 NASA Mission Directorates
                                   Exploration Systems
                                         Science
                                     Space Operations
                                   Aeronautics Research         AA for Space
                                                                 Operations
               NASA
             Spacecraft                                                          AAA
             Programs                                                           Launch
                                                                               Services

                           HQ                          KSC                          Flight
                          S&MA                       Center                        Planning
                                                     Director                       Board



                                                                        *
                                           Chief
                      S&MA Office                       Procuremnt          Engineering       Launch Services
                                         Financial                                             Launch Services
                                                           Office           Directorate       Program Manager
                                          Officer                                              Program Manager


                                                      *New Technical Authority Relationship with LSP as of 10-1-06

               Interface with other NASA Centers

                                GSFC/WFF
                                 GSFC/WFF                   MSFC                           SSC
                                Educational                  MSFC                           SSC
                                 Educational             ELV Support                    ELV Support
                                 Payloads                 ELV Support                    ELV Support
                                  Payloads
2/21/2007                                                                                                            2
SC/LSP LSP Mission Spacecraft Project
                      Life Cycle           LSP provides support throughout the SC Life Cycle
                                                        Formulation                                                       Implementation

                                        Pre-
                                        Phase A       Phase A              Phase B            Phase C                                 Phase D                                     Phase E
                                        Concept       Concept              Preliminary           Final                                                                           Operations &
                                        Studies     Development              Design              Design                          Fabrication, Assembly & Test                    Sustainment
         Phases




                                                                                               Baseline
                                                    Pre-                                                             L/V & S/C          Launch
                                                                            Mission            Mission &                                                     Launch                Post
                                                    Mission                                                          Engin’g &          Site Ops &
                                                                            Planning           Procure                                                                             Launch
                                                    Planning                                                         Manfact’g          Launch
                                                                                               Launch
                                                                                                                                        Campaign
                                                                                               Services
                                            Launch (L) - 4-10 yrs    L - 3-4 yrs         L - 2-3 yrs        L - 3 yrs-3 mons     L – 3 mons – 10 dys     L -10 dys - Launch     L + 5 mons
Gates




                                                                                                                                                 Pre
                                                                                                                            SC
                                                               MDR                 PDR/NAR                                                       Mate                                  L+5 Mon
                                         MCR                                                           CDR/SIR            Preship                                     FRR
                                                                                                                                                Review

                                                                                                                 •AIM               •THEMIS
                   •GEC       •Midex                                  •MMS               •GOES P**                                                                               •STEREO
                                                                                                                 •GLAST
                   •JWST** •New Millenium                             •JUNO              •WISE                                                                                   •CALIPSO*
                                                                                                                 •IBEX
                   •GOES R •Geo ITM                                                      •AQUARIUS*                                                                              •CLOUDSAT
                                                                                                                 •SDO
                   •LISA      •Geo RBM                                                   •ST-8
                                                                                                                 •LRO
                   •ConX      •AMS                                                       •MSL
                                                                                                                 •GOES O**
                   •LDCM      •YUMA
                                                                                                                 GLORY
                   •RBSP                                                                                         •NOAA-N’
                   •TDRS                                                                                         •NPP                                                               GSFC
                   •SIM                                                                                          •STSS
                                                                                                                                                                                    JPL
                   •ST-9                                                                                                                                                            DOD
                                                                                                                 •STSSB2010                                                         Other
                   •GPMC**                                                                                       •DAWN                                                              ARC
                   •Discovery                                                                                    •PHOENIX                                                            JSC
                   •LPRP                                                                                         •OCO                                                         *International
                   •Mars Scout                                                                                   •OSTM*
                                                                                                                                                                        **Potential Advisory
                                                                                                                                                                        Underline is Competed
                                                                                                                 •KEPLER                                                Update as of 1-30-07
                                                                                                                 •LCROSS
NASA Launch Services and Spacecraft Life Cycles
Spacecraft Project


                                     Formulation                                                                                    Implementation
   Life Cycle




                     Pre-
                     Phase A       Phase A             Phase B                        Phase C                                                  Phase D                                Phase E
                     Concept       Concept             Preliminary                     Final                                                                                         Operations &
                     Studies     Development             Design                        Design                                             Fabrication, Assembly & Test               Sustainment

                                                                                      Baseline
                                                                                                                                                 Launch
  LSP Mission




                                 Pre-                                                 Mission &                               L/V & S/C
                                                        Mission                                                                                  Site Ops &          Launch            Post
                                 Mission
    Phases




                                                        Planning                      Procure                                 Engin’g &                                                Launch
                                 Planning                                                                                     Manfact’g          Launch
                                                                                      Launch
                                                                                                                                                 Campaign
                                                                                      Services
                         Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch   L + 5 mons




                                                                                                 Payload Fairing
                                                                                                 (PLF)



                                                                                                                   Payload


                                                                                       Centaur




                                                                      Atlas                 RL-10 Engine
                                                                      Common Core
                                                                      Booster




                                                                      RD-180 Engine




                          •    Provide Spacecraft customer with information for Design and Development
  Description




                          •    Early mission studies
  High Level




                          •    Spacecraft Announcement of Opportunities (AO) release & proposal reviews
                          •    Spacecraft Systems Requirements Review (SRR)
                          •    Selection of spacecraft developer (in house or contractor)
                          •    SOMD FPB mission manifesting
                          •    LSP assignment of key support personnel to Mission Teams                                                                                  Major Product:
                          •    Launch Services mission budget established                                                                                            Integrated Mission Plan
Mission: SWIFT
 John F. Kennedy Space Center
                                                                              LAUNCH SERVICES PROGRAM
  Introduction:
  •     2 year mission, first-of-its-kind multi-wavelength observatory dedicated to
        the study of gamma-ray burst (GRB) science

  Timeline:
  •    SWIFT was built in the “Better, Faster, Cheaper” era and had begun
       to build “easy” interface hardware prior to engaging the Launch Services
       Program (during Pre-Mission Planning Phase).

  Problem:
  •    SWIFT built their payload adapter using a Boeing Payload Planner’s Guide
  •    This guide was an old version that had an incorrect drawing in it resulting in the
       spacecraft side of the adapter being too thick.

  Other occurring issues:
  •    The launch vehicle side of the interface was modified to accommodate; however, this was expensive and
       forced the use of the flight adapter for vibe testing.
  •    And now PAF was first flight!

  Immediate/long term Mitigation:
  •   Alerted next mission with the same bus (STSS Block 2010) and informed GSFC/JPL
  •   LSP must actively engage all missions earlier
  •   Identify early and communicate often the discontinuities between contractor payload planners guides and
      the NASA Launch Services (NLS) Contract
  •   Promote synchronization of deliverable schedules, both launch vehicle and spacecraft, and share areas
      of flexibility. Assists in creating better spacecraft subcontract definition…and eliminates some surprises
2/21/2007                                                                                                      5
LSP Mission Spacecraft Project
                                            NASA Launch Services and Spacecraft Life Cycles
                                                 Formulation                                                                                    Implementation
               Life Cycle




                                 Pre-
                                 Phase A       Phase A             Phase B                        Phase C                                                  Phase D                                 Phase E
                                 Concept       Concept             Preliminary                     Final                                                                                          Operations &
                                 Studies     Development             Design                        Design                                             Fabrication, Assembly & Test                Sustainment

                                                                                                  Baseline
                                             Pre-                                                                                         L/V & S/C          Launch
                                                                    Mission                       Mission &                                                                      Launch             Post
                                             Mission                                                                                      Engin’g &          Site Ops &
  Phases




                                                                    Planning                      Procure                                                                                           Launch
                                             Planning                                                                                     Manfact’g          Launch
                                                                                                  Launch
                                                                                                                                                             Campaign
                                                                                                  Services
                                     Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch    L + 5 mons




                                                                                                             Payload Fairing
                                                                                                             (PLF)



                                                                                                                               Payload


                                                                                                   Centaur




                                                                                  Atlas                 RL-10 Engine
                                                                                  Common Core
                                                                                  Booster




                                                                                  RD-180 Engine
Description
High Level




                                     •     Initial vehicle trade studies conducted
                                     •     Spacecraft Preliminary Design Review (PDR), Mission
                                           Confirmation Review (MCR)                                                                                                                    Major Product:
                                     •     Spacecraft Interface Requirements Document (IRD) developed                                                                                  Spacecraft/Vehicle
                                     •     Vehicle acquisition strategy agreed upon                                                                                                  requirements baseline
                                     •     Safety Working Group established
Mission: SPIDR
 John F. Kennedy Space Center
                                                                           LAUNCH SERVICES PROGRAM

     Introduction:
     •    SPIDR’s mission was to answer fundamental questions concerning the formation and evolution of
          galaxies, clusters of galaxies, and other large structures in the universe

     Timeline:
     •  Mission selected from AO 7/02; Mission Planning Phase
     •  Launch Service was ATP’ed on 12/02 (prior to s/c Confirmation Review) with launch date of 6/30/05
          – Early ATP was authorized to take advantage of lower contractual launch service cost (CY02 vs
             CY03).

     Problem:
     •  SPIDR mission did not get confirmed; launch service was on contract

     Other occurring issues:
     •  Shortened mission timeline had Confirmation Review after L-24 months. Initiation of launch service
        after L-24 would have cost significant $.

     Immediate/long term Mitigation:
     •  LSP negotiated an “Advance Agreement on Mission Revisions” into the SPIDR Task Order
          – Allowed reassignment of launch service.
          – Tailored payment schedule to move primary payments after Confirmation Review
     •  AIM mission was replacement for SPIDR. AIM launch date was September 29, 2006
          – No additional cost to AIM and AIM got benefit of L-35 ATP for same price as nominal integration
     •  Heightened awareness of need for significant coordination prior to initiation of launch service
     •  Engage LSP early so that we can work together to maximize flexibility and minimize risk . Early
        involvement improves capability to address challenges faced in launch service acquisition
2/21/2007                                                                                                     7
LSP Mission Spacecraft Project
                                            NASA Launch Services and Spacecraft Life Cycles
                                                 Formulation                                                                                    Implementation
               Life Cycle




                                 Pre-
                                 Phase A       Phase A             Phase B                        Phase C                                                  Phase D                                Phase E
                                 Concept       Concept             Preliminary                     Final                                                                                         Operations &
                                 Studies     Development             Design                        Design                                             Fabrication, Assembly & Test               Sustainment

                                                                                                  Baseline
                                             Pre-                                                                                         L/V & S/C          Launch
                                                                    Mission                       Mission &                                                                      Launch            Post
                                             Mission                                                                                      Engin’g &          Site Ops &
  Phases




                                                                    Planning                      Procure                                                                                          Launch
                                             Planning                                                                                     Manfact’g          Launch
                                                                                                  Launch
                                                                                                                                                             Campaign
                                                                                                  Services
                                     Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch   L + 5 mons




                                                                                                             Payload Fairing
                                                                                                             (PLF)



                                                                                                                               Payload


                                                                                                   Centaur




                                                                                  Atlas                 RL-10 Engine
                                                                                  Common Core
                                                                                  Booster




                                                                                  RD-180 Engine
Description




                                 •    LSP competes launch services (vehicle)
High Level




                                 •    Flight Planning Board reconfirms launch date, provides authority to proceed, concurrence with
                                      recommended vehicle services contractor selection                                                                                                    Major Product:
                                 •    Program Requirements Control Board (PRCB) approves ATP of mission                                                                                    Mission Design
                                 •    Spacecraft Critical Design Review (CDR) is held                                                                                                       and Launch
                                 •    Launch service budget may be revised based on outcome of procurement                                                                                  Service Task
                                 •    Extensive Mission Integration Working Group (MIWG) activity, involving spacecraft and LSP                                                              baselines
                                      personnel
Mission: LRO/LCROSS
 John F. Kennedy Space Center
                                                                          LAUNCH SERVICES PROGRAM

   Introduction:
   •    LRO/LCROSS - Secondary mission was desired by the customer to use excess EELV performance
        capability.

   Timeline:
   •  During launch services competition (~2 1/2 years prior to launch)

   Problem:
   •  LCROSS mission was solicited and selected after the launch service procurement had begun for LRO

   Other occurring issues:
   •  Quick turn around on competitive procurement for complex secondary mission
   •  LRO already fell within shortened integration timeline for large class vehicle

   Immediate/long term Mitigation:
   •  Incorporated late breaking requirements
   •  ESMD customer involved LSP early in the selection process for the secondary to ensure compatibility
      between payloads prior to selection
   •  Preparation and coordination allowed LCROSS to be added without re-bid
   •  Knowledge of contractor capabilities, late breaking mission requirements, experience with dual
      manifest missions allowed smooth incorporation
   •  Encourage participation from SC community in vehicle procurement process to ensure mission
      requirements are understood and met.
2/21/2007                                                                                                   9
NASA Launch Services and Spacecraft Life Cycles
Spacecraft Project


                                       Formulation                                                                                    Implementation
   Life Cycle




                     Pre-
                     Phase A         Phase A             Phase B                        Phase C                                                  Phase D                                Phase E
                     Concept         Concept             Preliminary                     Final                                                                                         Operations &
                     Studies       Development             Design                        Design                                             Fabrication, Assembly & Test               Sustainment

                                                                                        Baseline
                                   Pre-                                                                                                            Launch
 LSP Mission




                                                          Mission                       Mission &                               L/V & S/C                              Launch            Post
                                   Mission                                                                                      Engin’g &          Site Ops &
   Phases




                                                          Planning                      Procure                                                                                          Launch
                                   Planning                                                                                     Manfact’g          Launch
                                                                                        Launch
                                                                                                                                                   Campaign
                                                                                        Services
                           Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch   L + 5 mons




                                                                                                   Payload Fairing
                                                                                                   (PLF)



                                                                                                                     Payload


                                                                                         Centaur




                                                                        Atlas                 RL-10 Engine
                                                                        Common Core
                                                                        Booster




                                                                        RD-180 Engine




                       •     Extensive Working Group activities
 Description




                       •     Updated Interface Control Document (ICD) baseline and baselined Launch Site
 High Level




                             Support Plan (LSSP)                                                                                                                                Major Product:
                       •     Spacecraft and Launch Vehicle hardware in build and testing                                                                                            Spacecraft &
                       •     Vehicle Hardware Acceptance Reviews                                                                                                                vehicle ready to
                       •     LSP ensures launch site facilities/services are ready for spacecraft arrival; Ground                                                               begin launch site
                             Operations Review (GOR) conducted by LSP for customer                                                                                               operations and
                       •     Safety & Mission Assurance review; Pre-launch safety packages approved for                                                                            integration
                             spacecraft arrival
Mission: MESSENGER
 John F. Kennedy Space Center
                                                                             LAUNCH SERVICES PROGRAM
     Introduction:
     •    Mercury Surface, Space, Environment, Geochemistry, and Ranging, is the first scientific investigation
          of the planet Mercury from orbit.

     Timeline:
     •  Less than 6 months from launch

     Problem:
     •  The MESSENGER mission had changed its launch date. This resulted in changing its mass
        properties, desired propellant load and tank fill fraction. The new propellant load was not adequately
        bounded by nutation time constant testing performed years earlier which was used to define
        adequate fuel tank baffle and vortex dampers.

     Other occurring issues:
     •  The spacecraft was at the launch site and scheduled to be fueled within months
     •  Trajectory design was modified to accommodate the different launch period requiring more fuel and
        higher fill fraction
     •  Re-test was recommended to the spacecraft

     Immediate/long term Mitigation:
     •  The spacecraft conducted additional drop test which yielded a modification in the allowable propellant
        load to ensure vehicle controllability and bounded target dispersions.
     •  Actively applied to all spin stabilized missions with high spin rates. LSP has contracted with Hubert
        Astronautics to develop a design guidelines book for spacecraft developers. The original book,
        Behavior of Spinning Space Vehicles with Onboard Liquids, was published in August 2003 by Hubert
        Astronautics

2/21/2007                                                                                                         11
LSP Mission Spacecraft Project
                                              NASA Launch Services and Spacecraft Life Cycles
                                                   Formulation                                                                                    Implementation
               Life Cycle




                                 Pre-
                                 Phase A         Phase A             Phase B                        Phase C                                                  Phase D                                Phase E
                                 Concept         Concept             Preliminary                     Final                                                                                         Operations &
                                 Studies       Development             Design                        Design                                             Fabrication, Assembly & Test               Sustainment

                                                                                                    Baseline
                                               Pre-                                                                                         L/V & S/C          Launch
                                                                      Mission                       Mission &                                                                      Launch            Post
                                               Mission                                                                                      Engin’g &          Site Ops &
  Phases




                                                                      Planning                      Procure                                                                                          Launch
                                               Planning                                                                                     Manfact’g          Launch
                                                                                                    Launch
                                                                                                                                                               Campaign
                                                                                                    Services
                                       Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch   L + 5 mons




                                                                                                               Payload Fairing
                                                                                                               (PLF)



                                                                                                                                 Payload


                                                                                                     Centaur




                                                                                    Atlas                 RL-10 Engine
                                                                                    Common Core
                                                                                    Booster




                                                                                    RD-180 Engine




                                   •      Spacecraft Pre-Ship Review (PSR)
                                   •      Spacecraft and Ground Support Equipment (GSE) arrive at launch site
   Description
   High Level




                                   •      Complete spacecraft pre-mate assembly and testing                                                                                              Major Product:
                                   •      Complete Range Safety (USAF) Review package                                                                                                   Mission Team,
                                   •      Integrate spacecraft to launch vehicle and perform testing                                                                                 including spacecraft
                                   •      Launch Vehicle Readiness Review (LVRR)                                                                                                         and LSP ready to
                                   •      Spacecraft Mission Readiness Review (MRR)                                                                                                proceed to Launch Phase
                                   •      Independent Safety & Mission Assurance Readiness Review (SMSRR)                                                                                 and Launch
                                   •      Spacecraft participates in mission success letter for launch service
Mission: MRO
 John F. Kennedy Space Center
                                                                           LAUNCH SERVICES PROGRAM


     Introduction:
     •    Mars Reconnaissance Orbiter (MRO) was the first NASA mission to launch on Atlas V vehicle

     Timeline:
     •  Spacecraft closeouts the weekend prior to the scheduled launch

     Problem:
     •  Condensation discovered within the fairing and surrounding spacecraft instruments leading to one
        of the primary science instruments, the HIRISE camera, experiencing fogging of its lens.

     Other occurring issues:
     •  Other issues/activities were ongoing and access was required
          – Fire alarms at the Vertical Integration Facility
          – Multiple Flight Termination System battery failures
          – Spacecraft propellant line heating concerns

     Immediate/long term Mitigation:
     •  Developing an integrated door control access plan
        and manage dual/parallel close timelines for both spacecraft and
        launch vehicle.
     •  Actively applied to MSL mission during the procurement phase
        as well as Phoenix, launching this year.



2/21/2007                                                                                                  13
LSP Mission Spacecraft Project
                                             NASA Launch Services and Spacecraft Life Cycles
                                                  Formulation                                                                                    Implementation
               Life Cycle




                                 Pre-
                                 Phase A        Phase A             Phase B                        Phase C                                                  Phase D                                Phase E
                                 Concept        Concept             Preliminary                     Final                                                                                         Operations &
                                 Studies      Development             Design                        Design                                             Fabrication, Assembly & Test               Sustainment

                                                                                                   Baseline
                                              Pre-                                                                                         L/V & S/C          Launch
                                                                     Mission                       Mission &                                                                      Launch            Post
                                              Mission                                                                                      Engin’g &          Site Ops &
  Phases




                                                                     Planning                      Procure                                                                                          Launch
                                              Planning                                                                                     Manfact’g          Launch
                                                                                                   Launch
                                                                                                                                                              Campaign
                                                                                                   Services
                                      Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch   L + 5 mons




                                                                                                              Payload Fairing
                                                                                                              (PLF)



                                                                                                                                Payload


                                                                                                    Centaur




                                                                                   Atlas                 RL-10 Engine
                                                                                   Common Core
                                                                                   Booster




                                                                                   RD-180 Engine




                                  •     Flight Readiness Review
Description
High Level




                                  •     Launch Management Coordination Meeting and dress rehearsal for launch
                                  •     Launch Readiness Review
                                  •     Spacecraft conducts final consumables top-offs, battery charging, and close-out                                                                 Major Product:
                                        activities                                                                                                                                           Launch
                                  •     Final ICD changes and verifications of interface requirements
                                  •     Launch Countdown
Mission: NOAA-L
 John F. Kennedy Space Center
                                                                          LAUNCH SERVICES PROGRAM
     Introduction:
     •    NOAA-L spacecraft launched on a Titan II provided by the USAF

     Timeline:
     •   Day of launch with a 10 minute launch window

     Problem:
     •  Launch was not “typical” for a NASA mission-- vehicle owned by the Air Force.
     •  The countdown was behind the timeline, due to a later than normal mobile service tower roll.
     •  An issue surfaced involving the validity of the inertial navigation units calibration data.
     •  The countdown continued while discussions regarding this anomaly occurred on NASA, AF, and LMA
        channels. After long deliberations, LMA and the AF determined that the navigation unit was flight
        worthy and that launch vehicle was ready.
     •  NASA team was not ready to commit to launch. Additional anomaly net discussions continued but
        it became apparent to LSP that there were too many questions still unresolved coupled with a
        countdown that had been fragmented and appeared to be "rushed".
     •  It was determined by LSP that this was not the day to try to launch the NOAA-L spacecraft and a NO
        GO was called at about T-10 minutes.

     Immediate/long term mitigation:
     •  LSP worked closely with their customer as well as the Air Force and Lockheed Martin during entire
        anomaly discussion, and although the NO GO call was not unanimous, it was well understood by all
        agencies.
     •  This scrub call validated the processes that LSP uses every launch day. Even with the non-standard
        approach of having NASA, the USAF, and a launch service contractor involved, the communications
        flow-down of the entire team worked very well and the process exhibited robustness.
     •  Thorough coordination meetings and dress rehearsals continue to be held for every NASA mission
2/21/2007                                                                                                    15
LSP Mission Spacecraft Project
                                            NASA Launch Services and Spacecraft Life Cycles
                                                 Formulation                                                                                    Implementation
               Life Cycle




                                 Pre-
                                 Phase A       Phase A             Phase B                        Phase C                                                  Phase D                                Phase E
                                 Concept       Concept             Preliminary                     Final                                                                                         Operations &
                                 Studies     Development             Design                        Design                                             Fabrication, Assembly & Test               Sustainment

                                                                                                  Baseline
                                             Pre-                                                                                         L/V & S/C          Launch
                                                                    Mission                       Mission &                                                                      Launch            Post
                                             Mission                                                                                      Engin’g &          Site Ops &
  Phases




                                                                    Planning                      Procure                                                                                          Launch
                                             Planning                                                                                     Manfact’g          Launch
                                                                                                  Launch
                                                                                                                                                             Campaign
                                                                                                  Services
                                     Launch (L) - 4-10 yrs   L - 3-4 yrs         L - 2-3 yrs                                      L - 3 yrs-3 mons    L – 3 mons – 10 dys   L -10 dys - Launch   L + 5 mons




                                                                                                             Payload Fairing
                                                                                                             (PLF)



                                                                                                                               Payload


                                                                                                   Centaur




                                                                                  Atlas                 RL-10 Engine
                                                                                  Common Core
                                                                                  Booster




                                                                                  RD-180 Engine
Description
High Level




                                      •    Launch site close-out activity                                                                                                        Major Product:
                                      •    Spacecraft effort transferred to operations control center                                                                            Mission Success
                                      •    Post-launch flight reports                                                                                                             Determination
Mission: DART
 John F. Kennedy Space Center
                                                                           LAUNCH SERVICES PROGRAM

   Introduction:
   •    Demonstration of Autonomous Rendezvous Technology (DART) was a 24-hour mission to
        demonstrate technologies required to locate and autonomously rendezvous with another craft in
        space using only computers and sensors

   Timeline:
   •  On orbit operations

   Problem:
   •  After a successful rendezvous, acquisition of the target spacecraft, and approach,
      DART placed itself in the retirement phase before completing all planned
      proximity operations, ending the mission prematurely.

   Other occurring issues:
   •  Launch occurred from Vandenberg AFB
        – Most launch team traveled home after successful launch and many could not be contacted
   •  Effectivity of LSP Contingency Plan had expired

   Immediate/long term Mitigation:
   •  The LSP Interim Response Team members contacted and instructed to impound launch vehicle
      data to support investigation
   •  LSP contingency plan was modified and effectivity was extended to 24 hours after successful
      separation of the spacecraft. This allows rapid impoundment of launch vehicle data if required by
      the spacecraft during early on orbit operations
   •  Key personnel are required to remain in contact through this 24 hour period

2/21/2007                                                                                                 17
In Closing….
 John F. Kennedy Space Center
                                                           LAUNCH SERVICES PROGRAM




      •     Launch Services Program (LSP) brings experience from NASA’s
            expendable launch vehicle fleet and launch site processing facilities
            combined with spacecraft interfaces
      •     LSP is implementing a new lessons learned process to capture and
            share the knowledge that will improve service to customers
      •     The goal of the Launch Services Program is to increase mission
            success through strengthened customer relationships from early
            involvement in spacecraft missions through to launch




              Learning from the past, engaging in the future…

2/21/2007                                                                            18
JFK Space Center Launch Services Program: Over 50 Successful Launches

Más contenido relacionado

La actualidad más candente

Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbainNASAPMC
 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycuttNASAPMC
 
Standing cxp.panel
Standing cxp.panelStanding cxp.panel
Standing cxp.panelNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Mary.faller
Mary.fallerMary.faller
Mary.fallerNASAPMC
 
James.lewis
James.lewisJames.lewis
James.lewisNASAPMC
 
Carol.scott
Carol.scottCarol.scott
Carol.scottNASAPMC
 
Garrett.skrobot
Garrett.skrobotGarrett.skrobot
Garrett.skrobotNASAPMC
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robertNASAPMC
 
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionCloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionNewvewm
 
Building A High Performance City
Building A High Performance CityBuilding A High Performance City
Building A High Performance Cityc_gallagher
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastleNASAPMC
 
Gonzalez.matthew
Gonzalez.matthewGonzalez.matthew
Gonzalez.matthewNASAPMC
 
Nick.chrissotimos
Nick.chrissotimosNick.chrissotimos
Nick.chrissotimosNASAPMC
 
Growing Up - strategies for applying agile at scale
Growing Up - strategies for applying agile at scaleGrowing Up - strategies for applying agile at scale
Growing Up - strategies for applying agile at scaleiwmontgomery
 

La actualidad más candente (17)

Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycutt
 
Standing cxp.panel
Standing cxp.panelStanding cxp.panel
Standing cxp.panel
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Mary.faller
Mary.fallerMary.faller
Mary.faller
 
James.lewis
James.lewisJames.lewis
James.lewis
 
Carol.scott
Carol.scottCarol.scott
Carol.scott
 
Garrett.skrobot
Garrett.skrobotGarrett.skrobot
Garrett.skrobot
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robert
 
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionCloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
 
Building A High Performance City
Building A High Performance CityBuilding A High Performance City
Building A High Performance City
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastle
 
Gonzalez.matthew
Gonzalez.matthewGonzalez.matthew
Gonzalez.matthew
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Nick.chrissotimos
Nick.chrissotimosNick.chrissotimos
Nick.chrissotimos
 
Transition GPS MSC CCC crash course
Transition GPS MSC CCC crash courseTransition GPS MSC CCC crash course
Transition GPS MSC CCC crash course
 
Growing Up - strategies for applying agile at scale
Growing Up - strategies for applying agile at scaleGrowing Up - strategies for applying agile at scale
Growing Up - strategies for applying agile at scale
 

Destacado

Hoyt diana
Hoyt dianaHoyt diana
Hoyt dianaNASAPMC
 
Sweeney.dan
Sweeney.danSweeney.dan
Sweeney.danNASAPMC
 
Love.john
Love.johnLove.john
Love.johnNASAPMC
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.samNASAPMC
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegemanNASAPMC
 
King richardson
King richardsonKing richardson
King richardsonNASAPMC
 
Carol.mullenax
Carol.mullenaxCarol.mullenax
Carol.mullenaxNASAPMC
 

Destacado (8)

Hoyt diana
Hoyt dianaHoyt diana
Hoyt diana
 
Sweeney.dan
Sweeney.danSweeney.dan
Sweeney.dan
 
Love.john
Love.johnLove.john
Love.john
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegeman
 
Grieman
GriemanGrieman
Grieman
 
King richardson
King richardsonKing richardson
King richardson
 
Carol.mullenax
Carol.mullenaxCarol.mullenax
Carol.mullenax
 

Similar a JFK Space Center Launch Services Program: Over 50 Successful Launches

Daisy.mueller
Daisy.muellerDaisy.mueller
Daisy.muellerNASAPMC
 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
 
Majerowicz
MajerowiczMajerowicz
MajerowiczNASAPMC
 
Phillip.hall
Phillip.hallPhillip.hall
Phillip.hallNASAPMC
 
Phillip.hall
Phillip.hallPhillip.hall
Phillip.hallNASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vinceNASAPMC
 
Kelly.j.crumbley.t
Kelly.j.crumbley.tKelly.j.crumbley.t
Kelly.j.crumbley.tNASAPMC
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012NASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leisingNASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leisingNASAPMC
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Pianificazione Progetti 4
Pianificazione Progetti 4Pianificazione Progetti 4
Pianificazione Progetti 4Tek Com
 
Measurement effectiveness of offshoring
Measurement effectiveness of offshoringMeasurement effectiveness of offshoring
Measurement effectiveness of offshoringNesma
 
Serena Orchestrated ALM
Serena Orchestrated ALMSerena Orchestrated ALM
Serena Orchestrated ALMmikelohmann
 
Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7Mark Bethel
 
Albert sierra
Albert sierraAlbert sierra
Albert sierraNASAPMC
 
Fayssal.safie
Fayssal.safieFayssal.safie
Fayssal.safieNASAPMC
 

Similar a JFK Space Center Launch Services Program: Over 50 Successful Launches (20)

Daisy.mueller
Daisy.muellerDaisy.mueller
Daisy.mueller
 
Ed.mango
Ed.mangoEd.mango
Ed.mango
 
Majerowicz
MajerowiczMajerowicz
Majerowicz
 
Phillip.hall
Phillip.hallPhillip.hall
Phillip.hall
 
Phillip.hall
Phillip.hallPhillip.hall
Phillip.hall
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
Kelly.j.crumbley.t
Kelly.j.crumbley.tKelly.j.crumbley.t
Kelly.j.crumbley.t
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 
Mukai
MukaiMukai
Mukai
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Pianificazione Progetti 4
Pianificazione Progetti 4Pianificazione Progetti 4
Pianificazione Progetti 4
 
Measurement effectiveness of offshoring
Measurement effectiveness of offshoringMeasurement effectiveness of offshoring
Measurement effectiveness of offshoring
 
Serena Orchestrated ALM
Serena Orchestrated ALMSerena Orchestrated ALM
Serena Orchestrated ALM
 
Distributed Agile Development
Distributed Agile DevelopmentDistributed Agile Development
Distributed Agile Development
 
Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7
 
Albert sierra
Albert sierraAlbert sierra
Albert sierra
 
Mosp spring 2011
Mosp spring 2011Mosp spring 2011
Mosp spring 2011
 
Fayssal.safie
Fayssal.safieFayssal.safie
Fayssal.safie
 

Más de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

Más de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Último

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 

Último (20)

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 

JFK Space Center Launch Services Program: Over 50 Successful Launches

  • 1. John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Over 50 Successful Launches: Priceless Amanda Mitskevich Launch Services Program Flight Projects Office 2/21/2007 1
  • 2. Launch Services Program John F. Kennedy Space Center LAUNCH SERVICES PROGRAM NASA Mission Directorates Exploration Systems Science Space Operations Aeronautics Research AA for Space Operations NASA Spacecraft AAA Programs Launch Services HQ KSC Flight S&MA Center Planning Director Board * Chief S&MA Office Procuremnt Engineering Launch Services Financial Launch Services Office Directorate Program Manager Officer Program Manager *New Technical Authority Relationship with LSP as of 10-1-06 Interface with other NASA Centers GSFC/WFF GSFC/WFF MSFC SSC Educational MSFC SSC Educational ELV Support ELV Support Payloads ELV Support ELV Support Payloads 2/21/2007 2
  • 3. SC/LSP LSP Mission Spacecraft Project Life Cycle LSP provides support throughout the SC Life Cycle Formulation Implementation Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Phases Baseline Pre- L/V & S/C Launch Mission Mission & Launch Post Mission Engin’g & Site Ops & Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Gates Pre SC MDR PDR/NAR Mate L+5 Mon MCR CDR/SIR Preship FRR Review •AIM •THEMIS •GEC •Midex •MMS •GOES P** •STEREO •GLAST •JWST** •New Millenium •JUNO •WISE •CALIPSO* •IBEX •GOES R •Geo ITM •AQUARIUS* •CLOUDSAT •SDO •LISA •Geo RBM •ST-8 •LRO •ConX •AMS •MSL •GOES O** •LDCM •YUMA GLORY •RBSP •NOAA-N’ •TDRS •NPP GSFC •SIM •STSS JPL •ST-9 DOD •STSSB2010 Other •GPMC** •DAWN ARC •Discovery •PHOENIX JSC •LPRP •OCO *International •Mars Scout •OSTM* **Potential Advisory Underline is Competed •KEPLER Update as of 1-30-07 •LCROSS
  • 4. NASA Launch Services and Spacecraft Life Cycles Spacecraft Project Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Launch LSP Mission Pre- Mission & L/V & S/C Mission Site Ops & Launch Post Mission Phases Planning Procure Engin’g & Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine • Provide Spacecraft customer with information for Design and Development Description • Early mission studies High Level • Spacecraft Announcement of Opportunities (AO) release & proposal reviews • Spacecraft Systems Requirements Review (SRR) • Selection of spacecraft developer (in house or contractor) • SOMD FPB mission manifesting • LSP assignment of key support personnel to Mission Teams Major Product: • Launch Services mission budget established Integrated Mission Plan
  • 5. Mission: SWIFT John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • 2 year mission, first-of-its-kind multi-wavelength observatory dedicated to the study of gamma-ray burst (GRB) science Timeline: • SWIFT was built in the “Better, Faster, Cheaper” era and had begun to build “easy” interface hardware prior to engaging the Launch Services Program (during Pre-Mission Planning Phase). Problem: • SWIFT built their payload adapter using a Boeing Payload Planner’s Guide • This guide was an old version that had an incorrect drawing in it resulting in the spacecraft side of the adapter being too thick. Other occurring issues: • The launch vehicle side of the interface was modified to accommodate; however, this was expensive and forced the use of the flight adapter for vibe testing. • And now PAF was first flight! Immediate/long term Mitigation: • Alerted next mission with the same bus (STSS Block 2010) and informed GSFC/JPL • LSP must actively engage all missions earlier • Identify early and communicate often the discontinuities between contractor payload planners guides and the NASA Launch Services (NLS) Contract • Promote synchronization of deliverable schedules, both launch vehicle and spacecraft, and share areas of flexibility. Assists in creating better spacecraft subcontract definition…and eliminates some surprises 2/21/2007 5
  • 6. LSP Mission Spacecraft Project NASA Launch Services and Spacecraft Life Cycles Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Pre- L/V & S/C Launch Mission Mission & Launch Post Mission Engin’g & Site Ops & Phases Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine Description High Level • Initial vehicle trade studies conducted • Spacecraft Preliminary Design Review (PDR), Mission Confirmation Review (MCR) Major Product: • Spacecraft Interface Requirements Document (IRD) developed Spacecraft/Vehicle • Vehicle acquisition strategy agreed upon requirements baseline • Safety Working Group established
  • 7. Mission: SPIDR John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • SPIDR’s mission was to answer fundamental questions concerning the formation and evolution of galaxies, clusters of galaxies, and other large structures in the universe Timeline: • Mission selected from AO 7/02; Mission Planning Phase • Launch Service was ATP’ed on 12/02 (prior to s/c Confirmation Review) with launch date of 6/30/05 – Early ATP was authorized to take advantage of lower contractual launch service cost (CY02 vs CY03). Problem: • SPIDR mission did not get confirmed; launch service was on contract Other occurring issues: • Shortened mission timeline had Confirmation Review after L-24 months. Initiation of launch service after L-24 would have cost significant $. Immediate/long term Mitigation: • LSP negotiated an “Advance Agreement on Mission Revisions” into the SPIDR Task Order – Allowed reassignment of launch service. – Tailored payment schedule to move primary payments after Confirmation Review • AIM mission was replacement for SPIDR. AIM launch date was September 29, 2006 – No additional cost to AIM and AIM got benefit of L-35 ATP for same price as nominal integration • Heightened awareness of need for significant coordination prior to initiation of launch service • Engage LSP early so that we can work together to maximize flexibility and minimize risk . Early involvement improves capability to address challenges faced in launch service acquisition 2/21/2007 7
  • 8. LSP Mission Spacecraft Project NASA Launch Services and Spacecraft Life Cycles Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Pre- L/V & S/C Launch Mission Mission & Launch Post Mission Engin’g & Site Ops & Phases Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine Description • LSP competes launch services (vehicle) High Level • Flight Planning Board reconfirms launch date, provides authority to proceed, concurrence with recommended vehicle services contractor selection Major Product: • Program Requirements Control Board (PRCB) approves ATP of mission Mission Design • Spacecraft Critical Design Review (CDR) is held and Launch • Launch service budget may be revised based on outcome of procurement Service Task • Extensive Mission Integration Working Group (MIWG) activity, involving spacecraft and LSP baselines personnel
  • 9. Mission: LRO/LCROSS John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • LRO/LCROSS - Secondary mission was desired by the customer to use excess EELV performance capability. Timeline: • During launch services competition (~2 1/2 years prior to launch) Problem: • LCROSS mission was solicited and selected after the launch service procurement had begun for LRO Other occurring issues: • Quick turn around on competitive procurement for complex secondary mission • LRO already fell within shortened integration timeline for large class vehicle Immediate/long term Mitigation: • Incorporated late breaking requirements • ESMD customer involved LSP early in the selection process for the secondary to ensure compatibility between payloads prior to selection • Preparation and coordination allowed LCROSS to be added without re-bid • Knowledge of contractor capabilities, late breaking mission requirements, experience with dual manifest missions allowed smooth incorporation • Encourage participation from SC community in vehicle procurement process to ensure mission requirements are understood and met. 2/21/2007 9
  • 10. NASA Launch Services and Spacecraft Life Cycles Spacecraft Project Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Pre- Launch LSP Mission Mission Mission & L/V & S/C Launch Post Mission Engin’g & Site Ops & Phases Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine • Extensive Working Group activities Description • Updated Interface Control Document (ICD) baseline and baselined Launch Site High Level Support Plan (LSSP) Major Product: • Spacecraft and Launch Vehicle hardware in build and testing Spacecraft & • Vehicle Hardware Acceptance Reviews vehicle ready to • LSP ensures launch site facilities/services are ready for spacecraft arrival; Ground begin launch site Operations Review (GOR) conducted by LSP for customer operations and • Safety & Mission Assurance review; Pre-launch safety packages approved for integration spacecraft arrival
  • 11. Mission: MESSENGER John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • Mercury Surface, Space, Environment, Geochemistry, and Ranging, is the first scientific investigation of the planet Mercury from orbit. Timeline: • Less than 6 months from launch Problem: • The MESSENGER mission had changed its launch date. This resulted in changing its mass properties, desired propellant load and tank fill fraction. The new propellant load was not adequately bounded by nutation time constant testing performed years earlier which was used to define adequate fuel tank baffle and vortex dampers. Other occurring issues: • The spacecraft was at the launch site and scheduled to be fueled within months • Trajectory design was modified to accommodate the different launch period requiring more fuel and higher fill fraction • Re-test was recommended to the spacecraft Immediate/long term Mitigation: • The spacecraft conducted additional drop test which yielded a modification in the allowable propellant load to ensure vehicle controllability and bounded target dispersions. • Actively applied to all spin stabilized missions with high spin rates. LSP has contracted with Hubert Astronautics to develop a design guidelines book for spacecraft developers. The original book, Behavior of Spinning Space Vehicles with Onboard Liquids, was published in August 2003 by Hubert Astronautics 2/21/2007 11
  • 12. LSP Mission Spacecraft Project NASA Launch Services and Spacecraft Life Cycles Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Pre- L/V & S/C Launch Mission Mission & Launch Post Mission Engin’g & Site Ops & Phases Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine • Spacecraft Pre-Ship Review (PSR) • Spacecraft and Ground Support Equipment (GSE) arrive at launch site Description High Level • Complete spacecraft pre-mate assembly and testing Major Product: • Complete Range Safety (USAF) Review package Mission Team, • Integrate spacecraft to launch vehicle and perform testing including spacecraft • Launch Vehicle Readiness Review (LVRR) and LSP ready to • Spacecraft Mission Readiness Review (MRR) proceed to Launch Phase • Independent Safety & Mission Assurance Readiness Review (SMSRR) and Launch • Spacecraft participates in mission success letter for launch service
  • 13. Mission: MRO John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • Mars Reconnaissance Orbiter (MRO) was the first NASA mission to launch on Atlas V vehicle Timeline: • Spacecraft closeouts the weekend prior to the scheduled launch Problem: • Condensation discovered within the fairing and surrounding spacecraft instruments leading to one of the primary science instruments, the HIRISE camera, experiencing fogging of its lens. Other occurring issues: • Other issues/activities were ongoing and access was required – Fire alarms at the Vertical Integration Facility – Multiple Flight Termination System battery failures – Spacecraft propellant line heating concerns Immediate/long term Mitigation: • Developing an integrated door control access plan and manage dual/parallel close timelines for both spacecraft and launch vehicle. • Actively applied to MSL mission during the procurement phase as well as Phoenix, launching this year. 2/21/2007 13
  • 14. LSP Mission Spacecraft Project NASA Launch Services and Spacecraft Life Cycles Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Pre- L/V & S/C Launch Mission Mission & Launch Post Mission Engin’g & Site Ops & Phases Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine • Flight Readiness Review Description High Level • Launch Management Coordination Meeting and dress rehearsal for launch • Launch Readiness Review • Spacecraft conducts final consumables top-offs, battery charging, and close-out Major Product: activities Launch • Final ICD changes and verifications of interface requirements • Launch Countdown
  • 15. Mission: NOAA-L John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • NOAA-L spacecraft launched on a Titan II provided by the USAF Timeline: • Day of launch with a 10 minute launch window Problem: • Launch was not “typical” for a NASA mission-- vehicle owned by the Air Force. • The countdown was behind the timeline, due to a later than normal mobile service tower roll. • An issue surfaced involving the validity of the inertial navigation units calibration data. • The countdown continued while discussions regarding this anomaly occurred on NASA, AF, and LMA channels. After long deliberations, LMA and the AF determined that the navigation unit was flight worthy and that launch vehicle was ready. • NASA team was not ready to commit to launch. Additional anomaly net discussions continued but it became apparent to LSP that there were too many questions still unresolved coupled with a countdown that had been fragmented and appeared to be "rushed". • It was determined by LSP that this was not the day to try to launch the NOAA-L spacecraft and a NO GO was called at about T-10 minutes. Immediate/long term mitigation: • LSP worked closely with their customer as well as the Air Force and Lockheed Martin during entire anomaly discussion, and although the NO GO call was not unanimous, it was well understood by all agencies. • This scrub call validated the processes that LSP uses every launch day. Even with the non-standard approach of having NASA, the USAF, and a launch service contractor involved, the communications flow-down of the entire team worked very well and the process exhibited robustness. • Thorough coordination meetings and dress rehearsals continue to be held for every NASA mission 2/21/2007 15
  • 16. LSP Mission Spacecraft Project NASA Launch Services and Spacecraft Life Cycles Formulation Implementation Life Cycle Pre- Phase A Phase A Phase B Phase C Phase D Phase E Concept Concept Preliminary Final Operations & Studies Development Design Design Fabrication, Assembly & Test Sustainment Baseline Pre- L/V & S/C Launch Mission Mission & Launch Post Mission Engin’g & Site Ops & Phases Planning Procure Launch Planning Manfact’g Launch Launch Campaign Services Launch (L) - 4-10 yrs L - 3-4 yrs L - 2-3 yrs L - 3 yrs-3 mons L – 3 mons – 10 dys L -10 dys - Launch L + 5 mons Payload Fairing (PLF) Payload Centaur Atlas RL-10 Engine Common Core Booster RD-180 Engine Description High Level • Launch site close-out activity Major Product: • Spacecraft effort transferred to operations control center Mission Success • Post-launch flight reports Determination
  • 17. Mission: DART John F. Kennedy Space Center LAUNCH SERVICES PROGRAM Introduction: • Demonstration of Autonomous Rendezvous Technology (DART) was a 24-hour mission to demonstrate technologies required to locate and autonomously rendezvous with another craft in space using only computers and sensors Timeline: • On orbit operations Problem: • After a successful rendezvous, acquisition of the target spacecraft, and approach, DART placed itself in the retirement phase before completing all planned proximity operations, ending the mission prematurely. Other occurring issues: • Launch occurred from Vandenberg AFB – Most launch team traveled home after successful launch and many could not be contacted • Effectivity of LSP Contingency Plan had expired Immediate/long term Mitigation: • The LSP Interim Response Team members contacted and instructed to impound launch vehicle data to support investigation • LSP contingency plan was modified and effectivity was extended to 24 hours after successful separation of the spacecraft. This allows rapid impoundment of launch vehicle data if required by the spacecraft during early on orbit operations • Key personnel are required to remain in contact through this 24 hour period 2/21/2007 17
  • 18. In Closing…. John F. Kennedy Space Center LAUNCH SERVICES PROGRAM • Launch Services Program (LSP) brings experience from NASA’s expendable launch vehicle fleet and launch site processing facilities combined with spacecraft interfaces • LSP is implementing a new lessons learned process to capture and share the knowledge that will improve service to customers • The goal of the Launch Services Program is to increase mission success through strengthened customer relationships from early involvement in spacecraft missions through to launch Learning from the past, engaging in the future… 2/21/2007 18