SlideShare una empresa de Scribd logo
1 de 13
Critical Path Method
Project Management
Critical Path Method
• Scheduling and Project Management tool developed in the 1950’s
• Allow us to plan all tasks which must be completed in a project
• Aids time scheduling and resource planning
• They allow progress towards project goals to be tracked
Using the Critical Path Method
• Some activities cannot be started until previous activities have been
completed
• Activities in a critical path method therefore need to be completed in
sequence
• These activities are known as sequential activities
• In addition to these activities there are tasks which can be completed
at any time
• These activities are known as non-dependent or parallel tasks
Drawing a Critical Path Method Chart
Step 1:
• List all the tasks needed for the project in the plan
• This can be done using a Work Breakdown Structure
For each task state:
• The earliest start date
• The estimated time it will take
Drawing a Critical Path Method Chart
Step 2:
• Establish whether the activity is sequential or parallel
• For sequential tasks dependant tasks should be highlighted
Establish sequence by looking at:
• Which tasks should take place before this task happens.
• Which tasks should be completed at the same time as this task.
• Which tasks should happen immediately after this task.
Drawing a Critical Path Method Chart
Step 3:
• Draw each task as part of a circle and arrow diagram
• Each circle or node should show a task within the project and give start and finish
times
• The circles are numbered to allow them to be easily identifiable
• The arrows or arcs which run from circle to circle show the activities needed to
complete the tasks
• A description of the task should be written under the arrow, with the duration of
the task written above it.
• Arrows always run left to right
Examples of Critical Path Method
Drawing a Critical Method Chart
Step 4:
• Identify the critical path
• This is done by determining the four parameters of each task in the network
• Earliest start time (ES) - The earliest time an activity can start once the previous dependent
activities are over.
• Earliest finish time (EF) - ES + activity duration.
• Latest finish time (LF) - The latest time an activity can finish without delaying the project.
• Latest start time (LS) - LF - activity duration.
• The float time for an activity is the time between the earliest (ES) and the latest (LS) start time or
between the earliest (EF) and latest (LF) finish times.
• During the float time, an activity can be delayed without delaying the project finish date.
• The activities in the critical path have an effect on the deadline of the project.
• If an activity of this path is delayed, the project will be delayed.
Benefits of the Critical Path Method
The benefits of CPM are:

• Visual representation
• The project plan can be tested to ensure it is well thought out
• It identifies key tasks which could cause delays to the project if not completed on
time
• It identifies tasks which could be delayed in order to complete other tasks which
are more time crucial
• It identifies the minimum amount of time a project will take to complete
• It identifies any project steps which can be completed faster in order to complete
the project on time
Disadvantages of Critical Path Method
The disadvantages of CPM are:

• Can be more difficult to understand than Gantt Charts
• The time needed for tasks is not as clear as with Gantt Charts
More Information on Critical Path Method
• This is a useful video which sums the information given in the slides
and will aid understanding of the critical path method
http://www.youtube.com/watch?v=SF53ZZsP4ik
Further Reading
• Kelley, J. E. (1963). The critical-path method: Resources planning and
scheduling. Industrial scheduling, 347-365.
• Leach, L. P. (1999). Critical chain project management improves
project performance. Project Management Journal, 30, 39-51.
• Maylor, Project Management. Chapter 7
References
• Maylor, H., 2010. Project Management. 4th Ed. Chester: Pearson.
• MindTools, 2013. Critical Path Analysis and PERT Charts. [Online] Available at:
http://www.mindtools.com/critpath.html [Accessed on 07/11/13]
• Margaret Rouse, 2011. Critical Path Method (CPM). [Online] Available at:
http://whatis.techtarget.com/definition/critical-path-method-CPM [Accessed on
07/11/13]
• Tutorialspoint, 2013. Critical Path Method. [Online] Available at:
http://www.tutorialspoint.com/management_concepts/critical_path_method.ht
m [Accessed on 07/11/13]

Más contenido relacionado

La actualidad más candente

Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt chartsVARSHA RUSTAGI
 
Unit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and schedulingUnit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and schedulingRAMCHANDRA KODAM
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Chapter 6 energy and momentum principles
Chapter 6 energy and momentum principlesChapter 6 energy and momentum principles
Chapter 6 energy and momentum principlesBinu Karki
 
Critical path method
Critical path methodCritical path method
Critical path methodShubhi Verma
 
Float in Projects
Float in ProjectsFloat in Projects
Float in ProjectsRd Pokhrel
 
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsHow To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsPraveen Malik, PMP
 

La actualidad más candente (20)

crashing of project
crashing of project crashing of project
crashing of project
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Arrow
ArrowArrow
Arrow
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Unit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and schedulingUnit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and scheduling
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Chapter 6 energy and momentum principles
Chapter 6 energy and momentum principlesChapter 6 energy and momentum principles
Chapter 6 energy and momentum principles
 
Critical path method
Critical path methodCritical path method
Critical path method
 
PERT
PERTPERT
PERT
 
Float in Projects
Float in ProjectsFloat in Projects
Float in Projects
 
Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsHow To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
 

Destacado (6)

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Process
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 

Similar a The Critical Path Method

Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)anjalatchi
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a projectSailish Cephas
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfssuser8babb7
 

Similar a The Critical Path Method (20)

Critical path method
Critical path methodCritical path method
Critical path method
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Project Management
Project ManagementProject Management
Project Management
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Introduction to Software Engineering
Introduction to Software EngineeringIntroduction to Software Engineering
Introduction to Software Engineering
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Pmp study: time
Pmp study: timePmp study: time
Pmp study: time
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 

Más de Nicola2903

Network diagrams
Network diagramsNetwork diagrams
Network diagramsNicola2903
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown StructureNicola2903
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureNicola2903
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project SchedulingNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt ChartNicola2903
 

Más de Nicola2903 (11)

Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Estimating
EstimatingEstimating
Estimating
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Estimating
EstimatingEstimating
Estimating
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project Scheduling
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 

Último

Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...AliaaTarek5
 
Visualising and forecasting stocks using Dash
Visualising and forecasting stocks using DashVisualising and forecasting stocks using Dash
Visualising and forecasting stocks using Dashnarutouzumaki53779
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 

Último (20)

Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
 
Visualising and forecasting stocks using Dash
Visualising and forecasting stocks using DashVisualising and forecasting stocks using Dash
Visualising and forecasting stocks using Dash
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 

The Critical Path Method

  • 2. Critical Path Method • Scheduling and Project Management tool developed in the 1950’s • Allow us to plan all tasks which must be completed in a project • Aids time scheduling and resource planning • They allow progress towards project goals to be tracked
  • 3. Using the Critical Path Method • Some activities cannot be started until previous activities have been completed • Activities in a critical path method therefore need to be completed in sequence • These activities are known as sequential activities • In addition to these activities there are tasks which can be completed at any time • These activities are known as non-dependent or parallel tasks
  • 4. Drawing a Critical Path Method Chart Step 1: • List all the tasks needed for the project in the plan • This can be done using a Work Breakdown Structure For each task state: • The earliest start date • The estimated time it will take
  • 5. Drawing a Critical Path Method Chart Step 2: • Establish whether the activity is sequential or parallel • For sequential tasks dependant tasks should be highlighted Establish sequence by looking at: • Which tasks should take place before this task happens. • Which tasks should be completed at the same time as this task. • Which tasks should happen immediately after this task.
  • 6. Drawing a Critical Path Method Chart Step 3: • Draw each task as part of a circle and arrow diagram • Each circle or node should show a task within the project and give start and finish times • The circles are numbered to allow them to be easily identifiable • The arrows or arcs which run from circle to circle show the activities needed to complete the tasks • A description of the task should be written under the arrow, with the duration of the task written above it. • Arrows always run left to right
  • 7. Examples of Critical Path Method
  • 8. Drawing a Critical Method Chart Step 4: • Identify the critical path • This is done by determining the four parameters of each task in the network • Earliest start time (ES) - The earliest time an activity can start once the previous dependent activities are over. • Earliest finish time (EF) - ES + activity duration. • Latest finish time (LF) - The latest time an activity can finish without delaying the project. • Latest start time (LS) - LF - activity duration. • The float time for an activity is the time between the earliest (ES) and the latest (LS) start time or between the earliest (EF) and latest (LF) finish times. • During the float time, an activity can be delayed without delaying the project finish date. • The activities in the critical path have an effect on the deadline of the project. • If an activity of this path is delayed, the project will be delayed.
  • 9. Benefits of the Critical Path Method The benefits of CPM are: • Visual representation • The project plan can be tested to ensure it is well thought out • It identifies key tasks which could cause delays to the project if not completed on time • It identifies tasks which could be delayed in order to complete other tasks which are more time crucial • It identifies the minimum amount of time a project will take to complete • It identifies any project steps which can be completed faster in order to complete the project on time
  • 10. Disadvantages of Critical Path Method The disadvantages of CPM are: • Can be more difficult to understand than Gantt Charts • The time needed for tasks is not as clear as with Gantt Charts
  • 11. More Information on Critical Path Method • This is a useful video which sums the information given in the slides and will aid understanding of the critical path method http://www.youtube.com/watch?v=SF53ZZsP4ik
  • 12. Further Reading • Kelley, J. E. (1963). The critical-path method: Resources planning and scheduling. Industrial scheduling, 347-365. • Leach, L. P. (1999). Critical chain project management improves project performance. Project Management Journal, 30, 39-51. • Maylor, Project Management. Chapter 7
  • 13. References • Maylor, H., 2010. Project Management. 4th Ed. Chester: Pearson. • MindTools, 2013. Critical Path Analysis and PERT Charts. [Online] Available at: http://www.mindtools.com/critpath.html [Accessed on 07/11/13] • Margaret Rouse, 2011. Critical Path Method (CPM). [Online] Available at: http://whatis.techtarget.com/definition/critical-path-method-CPM [Accessed on 07/11/13] • Tutorialspoint, 2013. Critical Path Method. [Online] Available at: http://www.tutorialspoint.com/management_concepts/critical_path_method.ht m [Accessed on 07/11/13]