Se ha denunciado esta presentación.
Se está descargando tu SlideShare. ×

Earned value analysis

Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Próximo SlideShare
Earned Value Analysis
Earned Value Analysis
Cargando en…3
×

Eche un vistazo a continuación

1 de 12 Anuncio

Earned value analysis

Descargar para leer sin conexión

Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
It is a commonly used method of performance measurement for projects.
It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress
By Er.Nikhil Raj, Senior Planning Enginner, Navig Solution Pvt Ltd

Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
It is a commonly used method of performance measurement for projects.
It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress
By Er.Nikhil Raj, Senior Planning Enginner, Navig Solution Pvt Ltd

Anuncio
Anuncio

Más Contenido Relacionado

Presentaciones para usted (20)

A los espectadores también les gustó (20)

Anuncio

Similares a Earned value analysis (20)

Más reciente (20)

Anuncio

Earned value analysis

  1. 1. Earned Value Analysis By Er. NikhilRaj BAC BUDGETED AT COMPLETION PV PLANNED VALUE EV EARNED VALUE SV SCHEDULE VARIANCE CV COST VARIANCE SPI SCHEDULE PERFORMANCE INDEX CPI COST PERFORMANCE INDEX EAC ESTIMATE AT COMPLETION ETC ESTIMATE TO COMPLETION VAC VARIANCE AT COMPLETION 1/21/2016 1all rights reserved to www.tutomaash.com | any queries can be mailed to tutomaash@gmail.com Performance measuring system | Forecasting system
  2. 2. Contents • What is earned value? • Why earned value? • EVM practiced industries • Application example • Application of same example in primavera p6 • Generation of financial s-curve 1/21/2016 2
  3. 3. Definition Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress - PMBOK 5th Edition Pg.217 1/21/2016 3
  4. 4. Why EVM? Quantify and measure program/contract performance, Provide an early warning system for deviation from a baseline, Mitigate risks associated with cost and schedule overruns, Provide a means to forecast final cost and schedule outcomes 1/21/2016 4
  5. 5. EVM practiced industries Department of Defense (DoD) The Federal government Construction IT sector Commercial sector R&D Aerospace 1/21/2016 5
  6. 6. Example 2 weeks into the project Ms Ann completed 35MILES Also spent $15500 “Calculate the Performance” Imagine Ms Ann is the project manager of 100 miles road work She must finish the project in 5 weeks She can spent $10000/week PLANNED ACTUAL 2W 4W 3W 2W 1W 5W 1/21/2016 6
  7. 7. PLANNED VS ACTUAL TOTAL PROJECT BUDGET=$50000 PLAN (TIME) W1 W2 W3 W4 W5 PLAN (COST) $10000 $20000 PV $30000 $40000 $50000 BAC PLAN (%COMPLETE) 20% 20MILES 40% 40 MILES 60% 60 MILES 80% 80 MILES 100% 100 MILES ACTUAL (TIME) W1 W2 W3 W4 W5 ACTUAL (COST) $15500 AC ACTUAL (%COMPLETE) 35% 35 MILES 1/21/2016 7
  8. 8. NAME DEFINITION EQUATION VALUE 2nd week INTERPRETATION BAC | BUDGETED AT COMPLETION The value of total planned work, the project cost baseline $50000 PV | PLANNED VALUE COST The value of the work planned to be completed to a point in time, usually the data date, or project completion $20000 EV | EARNED VALUE COST The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs $17500 AC | ACTUAL COST The actual cost of all the work completed to a point in time, usually the data date $15500 CV | COST VARIANCE The difference between the value of work completed to a point in time, usually the data date, and the actual costs to the same point in time CV = EV – AC $2000 Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost SV | SCHEDULE VARIANCE The difference between the work completed to a point in time, and the work planned to be completed to the same point in time. SV = EV – PV -$2500 Positive = Ahead of Schedule Neutral = On schedule Negative = Behind Schedule CPI | COST PERFORMANCE INDEX A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. CPI = EV/AC 1.129 >1.0 = Under planned cost Exactly 1.0 = On planned cost <1.0 = Over planned cost SPI | SCHEDULE PERFORMANCE INDEX A measure of schedule efficiency expressed as the ratio of earned value to planned value SPI = EV/PV 0.875 >1.0 = Ahead of schedule Exactly 1.0 = On schedule <1.0 = Behind schedule VALUESCALCULATED USINGEQUATION VALUES FROM ACTUAL VALUES FROM PLAN 1/21/2016 8
  9. 9. Project forecast 2WBAC= $50000 (Planned budget) EAC= $44287 (Forecasted Budget calculated Based On 2nd week actual values) ETC= EAC-AC =$28786 (money to finish project)AC= $15500 1/21/2016 9
  10. 10. NAME DEFINITION EQUATION VALUE 2nd week EAC | ESTIMATE AT COMPLETION If the CPI is expected to be the same for the remainder of the project, EAC can be calculated using EAC = BAC/CPI $44286.979 If future work will be accomplished at the planned rate, use: EAC = AC + BAC – EV $48000 If the initial plan is no longer valid, use: EAC = AC + Bottom-up ETC If both the CPI and SPI influence the remaining work, use EAC = AC + [(BAC – EV)/(CPI x SPI)] $48398.899 ETC | ESTIMATE TO COMPLETION Assuming work is proceeding on plan, the cost of completing the remaining authorized work can be calculated using: ETC = EAC – AC $28786 Reestimate the remaining work from the bottom up ETC = Reestimate VAC | VARIANCE AT COMPLETION The estimated difference in cost at the completion of the project. Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost VAC = BAC – EAC $5713.021 1/21/2016 10 FORECASTEDVALUES
  11. 11. See Mix in Action! https://mix.office.com/watch/1otxpj7hz6kbx (Copy the link and paste into your browser. Or, when in a slide show, click the photo.) 1/21/2016 11
  12. 12. Get the add-in Office Mix Learn more at http://aka.ms/officemix 1/21/2016

×