Objectives of the Meeting:
1-2
To review factory last month performance
To understand our present position against
management expectation
To know about the scope of improvement
To set next month performance target
Key Discussion points:
1-3
1. Planning, Production & IE KPI:
Monthly Target Vs. achievement status
Monthly Efficiency %
Monthly PCD Hit rate status
Monthly NPT Analysis
Monthly Revenue status
Monthly Profit/Loss status
Monthly Machine utilization %
Operators Skill Matrix Analysis
Monthly Short/excess shipment status
3. Quality Assurance Department KPI:
 Monthly Final inspection pass status
 Monthly OQL% status
Monthly DHU% status
Monthly Top 5 Defects analysis
Fail report analysis against Top 5 Defect
2. Human Resource Department KPI:
 Monthly worker absenteeism status
4. Set next month performance target
1. Planning, Production & IE KPI:
1-4
Overview of Performance:
1-5
Month wise Plan & Floor Target Vs. Achievement status:
1-6
Month wise Machine utilization % :
1-7
Month wise efficiency %:
1-8
Month wise profit/Loss status (Excluding Abnormal Loss) :
1-9
Root Causes Analysis:
1-10
Month wise per Machine Plan Vs. Achieve Revenue status:
1-11
Month wise Plan Vs. Actual Style Analysis (May-22):
1-12
SMV Type Style Type Style Qty
Produced
Minute
Produced Qty
Avg qty % out
of total
Produce Qty
<4.5 Very Basic 1 19737 4386 0.7%
4.51-7.5 Basic 18 2946501 547901 85.8%
7.51-10.5 Semi Critical 4 597419 63195 9.9%
10.51-15 Heavy Semi Critical 1 64134 4420 0.7%
15.1-20 Critical 3 325182 19035 3.0%
20.1- >=28 Heavy Critical 0 0 0 0.0%
6.19 Basic 27 3952974 638937 100.0%
ACTUAL RUNNING STYLE ANALYSIS
SMV Type Style Type Style Qty
Produced
Minute
Plan Qty
Avg qty % out
of total
Produce Qty
<4.5 Very Basic 0 0 0 0.0%
4.51-7.5 Basic 25 3401376 628332 86.2%
7.51-10.5 Semi Critical 3 813660 87000 11.9%
10.51-15 Heavy Semi Critical 1 48289 3328 0.5%
15.1-20 Critical 1 173884 10344 1.4%
20.1- >=28 Heavy Critical 0 0 0 0.0%
6.09 Basic 30 4437209 729004 100.0%
ALLOCATION PLAN STYLE ANALYSIS
Month wise Plan Vs. Actual Style Analysis (June-22):
1-13
SMV Type Style Type Style Qty
Produced
Minute
Plan Qty
Avg qty % out
of total
Produce Qty
<4.5 Very Basic 3 309995 69500 6.7%
4.51-7.5 Basic 18 4763956 889469 85.6%
7.51-10.5 Semi Critical 1 355779 45730 4.4%
10.51-15 Heavy Semi Critical 1 505287 34500 3.3%
15.1-20 Critical 0 0 0 0.0%
20.1- >=28 Heavy Critical 0 0 0 0.0%
5.71 Basic 23 5935017 1039199 100.0%
ALLOCATION PLAN STYLE ANALYSIS
SMV Type Style Type Style Qty
Produced
Minute
Produced Qty
Avg qty % out
of total
Produce Qty
<4.5 Very Basic 4 332628 74549 7.6%
4.51-7.5 Basic 19 4490990 835091 85.1%
7.51-10.5 Semi Critical 2 258906 32089 3.3%
10.51-15 Heavy Semi Critical 1 523155 35720 3.6%
15.1-20 Critical 2 73223 3840 0.4%
20.1- >=28 Heavy Critical 0 0 0 0.0%
5.79 Basic 28 5678902 981289 100.0%
ALLOCATION PLAN STYLE ANALYSIS
Month wise Plan Vs. Actual Style Analysis (July-2022):
1-14
SMV Type Style Type Style Qty
Produced
Minute
Plan Qty
Avg qty % out
of total
Produce Qty
<4.5 Very Basic 3 148586 33740 5.5%
4.51-7.5 Basic 12 2244295 421120 68.1%
7.51-10.5 Semi Critical 4 671156 86250 14.0%
10.51-15 Heavy Semi Critical 4 996253 77000 12.5%
15.1-20 Critical 0 0 0 0.0%
20.1- >=28 Heavy Critical 0 0 0 0.0%
6.57 Basic 23 4060289 618110 100.0%
SMV Type Style Type Style Qty
Produced
Minute
Produced Qty
Avg qty % out
of total
Produce Qty
<4.5 Very Basic 4 128869 29746 6.2%
4.51-7.5 Basic 18 1691691 319402 66.1%
7.51-10.5 Semi Critical 4 558925 71768 14.8%
10.51-15 Heavy Semi Critical 4 810235 62479 12.9%
15.1-20 Critical 0 0 0 0.0%
20.1- >=28 Heavy Critical 0 0 0 0.0%
6.60 Basic 30 3189719 483395 100.0%
Month wise facts analysis :
1-15
SMV 1st
day 2nd
day 3rd
day 4th
day 5th
day 6th
day 7th
day 8th
day 9th
day 10th
day
<4.5 45% 60% 70% 75% 85% 85% 85% 85% 85% 85%
4.51-7.5 40% 55% 65% 70% 75% 75% 75% 75% 75% 80%
7.51-10.5 35% 45% 55% 60% 65% 65% 65% 70% 70% 70%
10.51-15 35% 45% 50% 55% 60% 60% 60% 65% 65% 65%
15.1-20 25% 35% 45% 50% 55% 55% 55% 55% 55% 60%
20.1-28 25% 35% 40% 45% 50% 50% 50% 55% 55% 55%
>=28.1 10% 20% 30% 35% 40% 45% 45% 45% 45% 50%
Efficiency Requirement
Month Factory
No.Style
Running
No.
Styling
No.of
Avg.Line
Run
days/Stylin
g/Line
Expected
Efficiency
Achieved
Efficiency%
May-22 KRC(U-3&4) 22 8 16 42days 75.0% 60.5%
June-22 KRC(U-3&4) 27 7 16 59days 75.0% 67.8%
July-22 KRC(U-3&4) 21 9 16 37days 75.0% 54.8%
70 24 48 45days 75.0% 61.0%
Total
PLAN STYLE RUNNING HEAT MAP,KRC,U-3 Unit 3
Line 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul
No of
Style
A LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 1
B LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 2
C LEGGING LEGGING LEGGING LEGGING T-shirt T-shirt T-shirt 2
D T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2
E HOODY HOODY HOODY HOODY HOODY HOODY HOODY HOODY LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 2
F TANK TOPTANK TOP T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2
G JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET 2
H TANK TOPTANK TOPTANK TOPTANK TOP 1
Style Running Heat Map- KRC U-3 Unit- 3
Line 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul
Number of
styling
Runned
No. of
style
Runned
A
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET 2 3
B T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT
LADIES
DRESS
TANK TOP TANK TOP TANK TOP 3 5
C LEGGING LEGGING LEGGING T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 2 3
C2 LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING - - - - - - - - - - - - - - 1 1
D LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 2 3
E T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT - LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING JACKET JACKET JACKET - - - - 3 3
E+F - - - - - - - - - - - - - - - - - JACKET JACKET JACKET JACKET 1 1
F TANK TOP TANK TOP LEGGING LEGGING TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP - - - - - - - - 2 4
G HOODY
WITH ZIP
HOODY
WITH ZIP
HOODY
WITH ZIP
JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET 2 3
H LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 1 2
STYLE-WISE LINE PLAN VS.EXECUTION COMPARISON OF KRC-U-3
PLAN STYLE RUNNING HEAT MAP,KRC,U-4 Unit 4
Line 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul
No of
Style
A T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2
B T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2
C T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2
D T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 3
E
LADIES
DRESS
LADIES
DRESS
LADIES
DRESS T-shirt T-shirt T-shirt T-shirt TANK TOPTANK TOPTANK TOPTANK TOPTANK TOPTANK TOP 2
F T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 1
G T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER 2
STYLE-WISE LINE PLAN VS.EXECUTION COMPARISON OF KRC-U-4
Style Running Heat Map- KRC U-4 Unit- 4
Line 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul
Number of
styling
Runned
No. of
style
Runned
A T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 4
B T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 3
C T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT - - - - - - - - - - 1 2
C2 - - - - - - - - - - - - - - - - - - - - - 0 0
D T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 4
E JOGGER JOGGER JOGGER JOGGER JOGGER T-SHIRT T-SHIRT - - JOGGER JOGGER T-SHIRT LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 3 4
E+F - - - - - - - - - - - - - - - - - - - - - 0 0
F T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 1
G LADIES
DRESS
LADIES
DRESS
LADIES
DRESS
SHORT
PANT
T-SHIRT
SHORT
PANT
T-SHIRT T-SHIRT
LADIES
DRESS
JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER T-SHIRT T-SHIRT T-SHIRT 4 6
H - - - - - - - - - - - - - - - - - - - - - 0 0
PCD Hit & Fail Status (May-22):
1-18
PCD Hit & Fail Status (June-22):
1-19
PCD Hit & Fail Status (July-22):
1-20
Month wise NPT status :
1-21
Non
Productive
Minute
NPT Value
NPT Value in
Tk.
NPT% NPT (Pcs)
NPT (Man-
Hour)
NPT MC/Day
Total Earning
(Including NPT
Value)
Revenue/MC
(Without NPT)
63205 Min. 4,424.35
$ 367,221৳ 0.97% 10216 Pcs 1053 5.2 MC 343,893.84
$ BDT 86562
136475 Min. 9,553.25
$ 792,920৳ 1.63% 23582 Pcs 2275 9.1 MC 473,161.80
$ BDT 92624
62182 Min. 4,352.74
$ 361,277৳ 1.07% 9424 Pcs 1036 5.6 MC 271,491.04
$ BDT 69293
261862 Min. 18,330.34
$ 1,521,418৳ 1.26% 43222 Pcs 4364 6.6 MC 1,088,546.67
$ BDT 83739
NPT status (MAY-2022):
1-22
NPT status (JUNE-2022):
1-23
NPT status (JULY-2022):
1-24
Operators Skill Matrix Analysis :
1-25
GRADE
NO OF
OPERATOR
PERCENTAGE
(%)
GRADING
PERCENTAGE
(%)
A+ 0 0%
A 21 5%
A- 46 10%
B+ 110 24%
B 138 30%
B- 90 19%
C+ 30 6%
C 24 5%
C- 3 1%
D 0 0% D 0%
462 100% 100%
KRC (U-3&4) Operator Skill Matrix
A
B
C
15%
73%
12%
Month wise On Time Delivery status:
1-26
Month wise short/excess shipment status :
1-27
2. Human Resource Department KPI:
1-28
Month wise worker absenteeism status :
1-29
Factors influencing on efficiency %:
1-30
1. Style Analysis : Allocating the styles in such a way that
maximum line days can be achieved.
2. PCD hit Rate : Ensure PCD to ensure right style line feeding at
right time.
3. Set a standard Target : Target has to be as per feasibility
learning curve to get expected efficiency.
4. Production Monitoring : Ensure process wise production which
leads to target achievement of full line.
5. Line Balancing : Set right person at right place to get maximum
utilization of manpower and get output.
6. Operators Skill Matrix : Identify the right person as per process
& requirement.
7. Operators Availability : Reduction of absenteeism to ensure
operators availability as per requirement.
SUMMARY OF TODAY DISCUSSION :
1-31
OrderConfirmation
Sample Approval Planning Fabric& Accessoriesplanning
File Handover
CuttingPlan
Print/Emb.Plan
SewingStartPlan
SewingProduction
FRIPlan
Order Execution Flow Chart
Style Analysisduringsize set& PPMeeting
Fabric Delay
PCD delay
Productivity Loss
Thank You

Más contenido relacionado

Similar a Factory Monthly KSM- New.ppt

Tablero Gerencial de Mando - Business Intelligence
Tablero Gerencial de Mando - Business IntelligenceTablero Gerencial de Mando - Business Intelligence
Tablero Gerencial de Mando - Business IntelligenceLuis Damian
 
Integrating New Products and the Sales Funnel in Demand Planning
Integrating New Products and the Sales Funnel in Demand PlanningIntegrating New Products and the Sales Funnel in Demand Planning
Integrating New Products and the Sales Funnel in Demand Planningfreighthunter
 
Factory yearly improvement presention
Factory yearly improvement presentionFactory yearly improvement presention
Factory yearly improvement presentionsafiqulislam728
 
SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2
SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2
SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2Reinaldo Leopoldo
 
wealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docx
wealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docxwealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docx
wealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docxmelbruce90096
 
Factory Monthly KPI of Lizfashion.ppt
Factory Monthly KPI of Lizfashion.pptFactory Monthly KPI of Lizfashion.ppt
Factory Monthly KPI of Lizfashion.pptNittamallik216
 
Jj srb7100 c_val
Jj srb7100 c_valJj srb7100 c_val
Jj srb7100 c_valRachel Byrd
 
Factory Monthly Marina.ppt
Factory Monthly Marina.pptFactory Monthly Marina.ppt
Factory Monthly Marina.pptNittamallik216
 
1000 strategic business diagrams for powerful presentations
1000 strategic business diagrams for powerful presentations1000 strategic business diagrams for powerful presentations
1000 strategic business diagrams for powerful presentationshttp://www.drawpack.com
 
Training for Production Management regarding the basic line management procedure
Training for Production Management regarding the basic line management procedureTraining for Production Management regarding the basic line management procedure
Training for Production Management regarding the basic line management procedureRadwan Ahmed Rahat
 
Hyundai 15P-7 Forklift Truck Service Repair Manual.pdf
Hyundai 15P-7 Forklift Truck Service Repair Manual.pdfHyundai 15P-7 Forklift Truck Service Repair Manual.pdf
Hyundai 15P-7 Forklift Truck Service Repair Manual.pdflanji4905796341
 

Similar a Factory Monthly KSM- New.ppt (20)

Tablero Gerencial de Mando - Business Intelligence
Tablero Gerencial de Mando - Business IntelligenceTablero Gerencial de Mando - Business Intelligence
Tablero Gerencial de Mando - Business Intelligence
 
Integrating New Products and the Sales Funnel in Demand Planning
Integrating New Products and the Sales Funnel in Demand PlanningIntegrating New Products and the Sales Funnel in Demand Planning
Integrating New Products and the Sales Funnel in Demand Planning
 
SAT Practice Tests
SAT Practice TestsSAT Practice Tests
SAT Practice Tests
 
Factory yearly improvement presention
Factory yearly improvement presentionFactory yearly improvement presention
Factory yearly improvement presention
 
SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2
SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2
SUPPLY CHAIN AND SOURCING_PROCUREMENT RAISING rev 2
 
STEEL DECK (2).pdf
STEEL DECK (2).pdfSTEEL DECK (2).pdf
STEEL DECK (2).pdf
 
wealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docx
wealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docxwealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docx
wealth age region37 50 M24 88 U14 64 A13 63 U13 66 .docx
 
Dyeing
DyeingDyeing
Dyeing
 
Dyeing
DyeingDyeing
Dyeing
 
Factory Monthly KPI of Lizfashion.ppt
Factory Monthly KPI of Lizfashion.pptFactory Monthly KPI of Lizfashion.ppt
Factory Monthly KPI of Lizfashion.ppt
 
Calculo de esal
Calculo de esalCalculo de esal
Calculo de esal
 
Jj srb7100 c_val
Jj srb7100 c_valJj srb7100 c_val
Jj srb7100 c_val
 
Capex
CapexCapex
Capex
 
Factory Monthly Marina.ppt
Factory Monthly Marina.pptFactory Monthly Marina.ppt
Factory Monthly Marina.ppt
 
1000 strategic business diagrams for powerful presentations
1000 strategic business diagrams for powerful presentations1000 strategic business diagrams for powerful presentations
1000 strategic business diagrams for powerful presentations
 
Training for Production Management regarding the basic line management procedure
Training for Production Management regarding the basic line management procedureTraining for Production Management regarding the basic line management procedure
Training for Production Management regarding the basic line management procedure
 
Report Sample-OPR23.pptx
Report Sample-OPR23.pptxReport Sample-OPR23.pptx
Report Sample-OPR23.pptx
 
Dr. azad hama sharif
Dr. azad hama sharifDr. azad hama sharif
Dr. azad hama sharif
 
WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01
 
Hyundai 15P-7 Forklift Truck Service Repair Manual.pdf
Hyundai 15P-7 Forklift Truck Service Repair Manual.pdfHyundai 15P-7 Forklift Truck Service Repair Manual.pdf
Hyundai 15P-7 Forklift Truck Service Repair Manual.pdf
 

Más de Nittamallik216

Factory Monthly KSM- New.ppt
Factory Monthly KSM- New.pptFactory Monthly KSM- New.ppt
Factory Monthly KSM- New.pptNittamallik216
 
Production_Planning_and_Control_1.ppt
Production_Planning_and_Control_1.pptProduction_Planning_and_Control_1.ppt
Production_Planning_and_Control_1.pptNittamallik216
 
160_16SCCFT4_2020051906270858.pptx
160_16SCCFT4_2020051906270858.pptx160_16SCCFT4_2020051906270858.pptx
160_16SCCFT4_2020051906270858.pptxNittamallik216
 
Factory Monthly KPI OF LDC.ppt
Factory Monthly KPI OF LDC.pptFactory Monthly KPI OF LDC.ppt
Factory Monthly KPI OF LDC.pptNittamallik216
 
Weekly KPI meeting of FHRO.ppt
Weekly KPI meeting of FHRO.pptWeekly KPI meeting of FHRO.ppt
Weekly KPI meeting of FHRO.pptNittamallik216
 
Weekly KPI meeting of IE.ppt
Weekly KPI meeting of IE.pptWeekly KPI meeting of IE.ppt
Weekly KPI meeting of IE.pptNittamallik216
 
Weekly KPI meeting of PPC team.ppt
Weekly KPI meeting of PPC team.pptWeekly KPI meeting of PPC team.ppt
Weekly KPI meeting of PPC team.pptNittamallik216
 
Weekly KPI meeting of Production team .ppt
Weekly KPI meeting of Production team .pptWeekly KPI meeting of Production team .ppt
Weekly KPI meeting of Production team .pptNittamallik216
 
Factory Monthly KPI.ppt
Factory Monthly KPI.pptFactory Monthly KPI.ppt
Factory Monthly KPI.pptNittamallik216
 
Factory Monthly Silvar.ppt
Factory Monthly Silvar.pptFactory Monthly Silvar.ppt
Factory Monthly Silvar.pptNittamallik216
 
Factory Monthly Babylon.ppt
Factory Monthly Babylon.pptFactory Monthly Babylon.ppt
Factory Monthly Babylon.pptNittamallik216
 
Factory Monthly KPI of Lida.ppt
Factory Monthly KPI of Lida.pptFactory Monthly KPI of Lida.ppt
Factory Monthly KPI of Lida.pptNittamallik216
 
Factory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .pptFactory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .pptNittamallik216
 
Factory Monthly ALP.ppt
Factory Monthly ALP.pptFactory Monthly ALP.ppt
Factory Monthly ALP.pptNittamallik216
 
Factory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.pptFactory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.pptNittamallik216
 
Factory Monthly HAMZA.ppt
Factory Monthly HAMZA.pptFactory Monthly HAMZA.ppt
Factory Monthly HAMZA.pptNittamallik216
 
Factory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.pptFactory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.pptNittamallik216
 
Factory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptFactory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptNittamallik216
 
TP MAX SWEATPANT SB.pdf
TP MAX SWEATPANT SB.pdfTP MAX SWEATPANT SB.pdf
TP MAX SWEATPANT SB.pdfNittamallik216
 

Más de Nittamallik216 (20)

Factory Monthly KSM- New.ppt
Factory Monthly KSM- New.pptFactory Monthly KSM- New.ppt
Factory Monthly KSM- New.ppt
 
Production_Planning_and_Control_1.ppt
Production_Planning_and_Control_1.pptProduction_Planning_and_Control_1.ppt
Production_Planning_and_Control_1.ppt
 
160_16SCCFT4_2020051906270858.pptx
160_16SCCFT4_2020051906270858.pptx160_16SCCFT4_2020051906270858.pptx
160_16SCCFT4_2020051906270858.pptx
 
Factory Monthly KPI OF LDC.ppt
Factory Monthly KPI OF LDC.pptFactory Monthly KPI OF LDC.ppt
Factory Monthly KPI OF LDC.ppt
 
Weekly KPI meeting of FHRO.ppt
Weekly KPI meeting of FHRO.pptWeekly KPI meeting of FHRO.ppt
Weekly KPI meeting of FHRO.ppt
 
Weekly KPI meeting of IE.ppt
Weekly KPI meeting of IE.pptWeekly KPI meeting of IE.ppt
Weekly KPI meeting of IE.ppt
 
Weekly KPI meeting of PPC team.ppt
Weekly KPI meeting of PPC team.pptWeekly KPI meeting of PPC team.ppt
Weekly KPI meeting of PPC team.ppt
 
Weekly KPI meeting of Production team .ppt
Weekly KPI meeting of Production team .pptWeekly KPI meeting of Production team .ppt
Weekly KPI meeting of Production team .ppt
 
Factory Monthly KPI.ppt
Factory Monthly KPI.pptFactory Monthly KPI.ppt
Factory Monthly KPI.ppt
 
Factory Monthly Silvar.ppt
Factory Monthly Silvar.pptFactory Monthly Silvar.ppt
Factory Monthly Silvar.ppt
 
Factory Monthly Babylon.ppt
Factory Monthly Babylon.pptFactory Monthly Babylon.ppt
Factory Monthly Babylon.ppt
 
Factory Monthly KPI of Lida.ppt
Factory Monthly KPI of Lida.pptFactory Monthly KPI of Lida.ppt
Factory Monthly KPI of Lida.ppt
 
Factory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .pptFactory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .ppt
 
Factory Monthly ALP.ppt
Factory Monthly ALP.pptFactory Monthly ALP.ppt
Factory Monthly ALP.ppt
 
Factory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.pptFactory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.ppt
 
Factory Monthly HAMZA.ppt
Factory Monthly HAMZA.pptFactory Monthly HAMZA.ppt
Factory Monthly HAMZA.ppt
 
Factory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.pptFactory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.ppt
 
Factory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptFactory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).ppt
 
TP MAX SWEATPANT SB.pdf
TP MAX SWEATPANT SB.pdfTP MAX SWEATPANT SB.pdf
TP MAX SWEATPANT SB.pdf
 
SILAS PJ SET .pdf
SILAS PJ SET .pdfSILAS PJ SET .pdf
SILAS PJ SET .pdf
 

Último

Cash Is Still King: ATM market research '2023
Cash Is Still King: ATM market research '2023Cash Is Still King: ATM market research '2023
Cash Is Still King: ATM market research '2023Vladislav Solodkiy
 
Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024
Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024
Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024Guido X Jansen
 
Strategic CX: A Deep Dive into Voice of the Customer Insights for Clarity
Strategic CX: A Deep Dive into Voice of the Customer Insights for ClarityStrategic CX: A Deep Dive into Voice of the Customer Insights for Clarity
Strategic CX: A Deep Dive into Voice of the Customer Insights for ClarityAggregage
 
MEASURES OF DISPERSION I BSc Botany .ppt
MEASURES OF DISPERSION I BSc Botany .pptMEASURES OF DISPERSION I BSc Botany .ppt
MEASURES OF DISPERSION I BSc Botany .pptaigil2
 
CI, CD -Tools to integrate without manual intervention
CI, CD -Tools to integrate without manual interventionCI, CD -Tools to integrate without manual intervention
CI, CD -Tools to integrate without manual interventionajayrajaganeshkayala
 
AI for Sustainable Development Goals (SDGs)
AI for Sustainable Development Goals (SDGs)AI for Sustainable Development Goals (SDGs)
AI for Sustainable Development Goals (SDGs)Data & Analytics Magazin
 
SFBA Splunk Usergroup meeting March 13, 2024
SFBA Splunk Usergroup meeting March 13, 2024SFBA Splunk Usergroup meeting March 13, 2024
SFBA Splunk Usergroup meeting March 13, 2024Becky Burwell
 
Virtuosoft SmartSync Product Introduction
Virtuosoft SmartSync Product IntroductionVirtuosoft SmartSync Product Introduction
Virtuosoft SmartSync Product Introductionsanjaymuralee1
 
How is Real-Time Analytics Different from Traditional OLAP?
How is Real-Time Analytics Different from Traditional OLAP?How is Real-Time Analytics Different from Traditional OLAP?
How is Real-Time Analytics Different from Traditional OLAP?sonikadigital1
 
The Universal GTM - how we design GTM and dataLayer
The Universal GTM - how we design GTM and dataLayerThe Universal GTM - how we design GTM and dataLayer
The Universal GTM - how we design GTM and dataLayerPavel Šabatka
 
YourView Panel Book.pptx YourView Panel Book.
YourView Panel Book.pptx YourView Panel Book.YourView Panel Book.pptx YourView Panel Book.
YourView Panel Book.pptx YourView Panel Book.JasonViviers2
 
ChistaDATA Real-Time DATA Analytics Infrastructure
ChistaDATA Real-Time DATA Analytics InfrastructureChistaDATA Real-Time DATA Analytics Infrastructure
ChistaDATA Real-Time DATA Analytics Infrastructuresonikadigital1
 
Mapping the pubmed data under different suptopics using NLP.pptx
Mapping the pubmed data under different suptopics using NLP.pptxMapping the pubmed data under different suptopics using NLP.pptx
Mapping the pubmed data under different suptopics using NLP.pptxVenkatasubramani13
 
TINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptx
TINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptxTINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptx
TINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptxDwiAyuSitiHartinah
 
5 Ds to Define Data Archiving Best Practices
5 Ds to Define Data Archiving Best Practices5 Ds to Define Data Archiving Best Practices
5 Ds to Define Data Archiving Best PracticesDataArchiva
 
Elements of language learning - an analysis of how different elements of lang...
Elements of language learning - an analysis of how different elements of lang...Elements of language learning - an analysis of how different elements of lang...
Elements of language learning - an analysis of how different elements of lang...PrithaVashisht1
 
Master's Thesis - Data Science - Presentation
Master's Thesis - Data Science - PresentationMaster's Thesis - Data Science - Presentation
Master's Thesis - Data Science - PresentationGiorgio Carbone
 

Último (17)

Cash Is Still King: ATM market research '2023
Cash Is Still King: ATM market research '2023Cash Is Still King: ATM market research '2023
Cash Is Still King: ATM market research '2023
 
Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024
Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024
Persuasive E-commerce, Our Biased Brain @ Bikkeldag 2024
 
Strategic CX: A Deep Dive into Voice of the Customer Insights for Clarity
Strategic CX: A Deep Dive into Voice of the Customer Insights for ClarityStrategic CX: A Deep Dive into Voice of the Customer Insights for Clarity
Strategic CX: A Deep Dive into Voice of the Customer Insights for Clarity
 
MEASURES OF DISPERSION I BSc Botany .ppt
MEASURES OF DISPERSION I BSc Botany .pptMEASURES OF DISPERSION I BSc Botany .ppt
MEASURES OF DISPERSION I BSc Botany .ppt
 
CI, CD -Tools to integrate without manual intervention
CI, CD -Tools to integrate without manual interventionCI, CD -Tools to integrate without manual intervention
CI, CD -Tools to integrate without manual intervention
 
AI for Sustainable Development Goals (SDGs)
AI for Sustainable Development Goals (SDGs)AI for Sustainable Development Goals (SDGs)
AI for Sustainable Development Goals (SDGs)
 
SFBA Splunk Usergroup meeting March 13, 2024
SFBA Splunk Usergroup meeting March 13, 2024SFBA Splunk Usergroup meeting March 13, 2024
SFBA Splunk Usergroup meeting March 13, 2024
 
Virtuosoft SmartSync Product Introduction
Virtuosoft SmartSync Product IntroductionVirtuosoft SmartSync Product Introduction
Virtuosoft SmartSync Product Introduction
 
How is Real-Time Analytics Different from Traditional OLAP?
How is Real-Time Analytics Different from Traditional OLAP?How is Real-Time Analytics Different from Traditional OLAP?
How is Real-Time Analytics Different from Traditional OLAP?
 
The Universal GTM - how we design GTM and dataLayer
The Universal GTM - how we design GTM and dataLayerThe Universal GTM - how we design GTM and dataLayer
The Universal GTM - how we design GTM and dataLayer
 
YourView Panel Book.pptx YourView Panel Book.
YourView Panel Book.pptx YourView Panel Book.YourView Panel Book.pptx YourView Panel Book.
YourView Panel Book.pptx YourView Panel Book.
 
ChistaDATA Real-Time DATA Analytics Infrastructure
ChistaDATA Real-Time DATA Analytics InfrastructureChistaDATA Real-Time DATA Analytics Infrastructure
ChistaDATA Real-Time DATA Analytics Infrastructure
 
Mapping the pubmed data under different suptopics using NLP.pptx
Mapping the pubmed data under different suptopics using NLP.pptxMapping the pubmed data under different suptopics using NLP.pptx
Mapping the pubmed data under different suptopics using NLP.pptx
 
TINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptx
TINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptxTINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptx
TINJUAN PEMROSESAN TRANSAKSI DAN ERP.pptx
 
5 Ds to Define Data Archiving Best Practices
5 Ds to Define Data Archiving Best Practices5 Ds to Define Data Archiving Best Practices
5 Ds to Define Data Archiving Best Practices
 
Elements of language learning - an analysis of how different elements of lang...
Elements of language learning - an analysis of how different elements of lang...Elements of language learning - an analysis of how different elements of lang...
Elements of language learning - an analysis of how different elements of lang...
 
Master's Thesis - Data Science - Presentation
Master's Thesis - Data Science - PresentationMaster's Thesis - Data Science - Presentation
Master's Thesis - Data Science - Presentation
 

Factory Monthly KSM- New.ppt

  • 1. 1-0
  • 2. Palmal Group of Industries KRC(U-3&4) Monthly Knowledge Sharing Meeting-KSM (May-22 To July-22) Organized by: Central-IE Manufacturing Audit & Central Costing 1-1
  • 3. Objectives of the Meeting: 1-2 To review factory last month performance To understand our present position against management expectation To know about the scope of improvement To set next month performance target
  • 4. Key Discussion points: 1-3 1. Planning, Production & IE KPI: Monthly Target Vs. achievement status Monthly Efficiency % Monthly PCD Hit rate status Monthly NPT Analysis Monthly Revenue status Monthly Profit/Loss status Monthly Machine utilization % Operators Skill Matrix Analysis Monthly Short/excess shipment status 3. Quality Assurance Department KPI:  Monthly Final inspection pass status  Monthly OQL% status Monthly DHU% status Monthly Top 5 Defects analysis Fail report analysis against Top 5 Defect 2. Human Resource Department KPI:  Monthly worker absenteeism status 4. Set next month performance target
  • 5. 1. Planning, Production & IE KPI: 1-4
  • 7. Month wise Plan & Floor Target Vs. Achievement status: 1-6
  • 8. Month wise Machine utilization % : 1-7
  • 10. Month wise profit/Loss status (Excluding Abnormal Loss) : 1-9
  • 12. Month wise per Machine Plan Vs. Achieve Revenue status: 1-11
  • 13. Month wise Plan Vs. Actual Style Analysis (May-22): 1-12 SMV Type Style Type Style Qty Produced Minute Produced Qty Avg qty % out of total Produce Qty <4.5 Very Basic 1 19737 4386 0.7% 4.51-7.5 Basic 18 2946501 547901 85.8% 7.51-10.5 Semi Critical 4 597419 63195 9.9% 10.51-15 Heavy Semi Critical 1 64134 4420 0.7% 15.1-20 Critical 3 325182 19035 3.0% 20.1- >=28 Heavy Critical 0 0 0 0.0% 6.19 Basic 27 3952974 638937 100.0% ACTUAL RUNNING STYLE ANALYSIS SMV Type Style Type Style Qty Produced Minute Plan Qty Avg qty % out of total Produce Qty <4.5 Very Basic 0 0 0 0.0% 4.51-7.5 Basic 25 3401376 628332 86.2% 7.51-10.5 Semi Critical 3 813660 87000 11.9% 10.51-15 Heavy Semi Critical 1 48289 3328 0.5% 15.1-20 Critical 1 173884 10344 1.4% 20.1- >=28 Heavy Critical 0 0 0 0.0% 6.09 Basic 30 4437209 729004 100.0% ALLOCATION PLAN STYLE ANALYSIS
  • 14. Month wise Plan Vs. Actual Style Analysis (June-22): 1-13 SMV Type Style Type Style Qty Produced Minute Plan Qty Avg qty % out of total Produce Qty <4.5 Very Basic 3 309995 69500 6.7% 4.51-7.5 Basic 18 4763956 889469 85.6% 7.51-10.5 Semi Critical 1 355779 45730 4.4% 10.51-15 Heavy Semi Critical 1 505287 34500 3.3% 15.1-20 Critical 0 0 0 0.0% 20.1- >=28 Heavy Critical 0 0 0 0.0% 5.71 Basic 23 5935017 1039199 100.0% ALLOCATION PLAN STYLE ANALYSIS SMV Type Style Type Style Qty Produced Minute Produced Qty Avg qty % out of total Produce Qty <4.5 Very Basic 4 332628 74549 7.6% 4.51-7.5 Basic 19 4490990 835091 85.1% 7.51-10.5 Semi Critical 2 258906 32089 3.3% 10.51-15 Heavy Semi Critical 1 523155 35720 3.6% 15.1-20 Critical 2 73223 3840 0.4% 20.1- >=28 Heavy Critical 0 0 0 0.0% 5.79 Basic 28 5678902 981289 100.0% ALLOCATION PLAN STYLE ANALYSIS
  • 15. Month wise Plan Vs. Actual Style Analysis (July-2022): 1-14 SMV Type Style Type Style Qty Produced Minute Plan Qty Avg qty % out of total Produce Qty <4.5 Very Basic 3 148586 33740 5.5% 4.51-7.5 Basic 12 2244295 421120 68.1% 7.51-10.5 Semi Critical 4 671156 86250 14.0% 10.51-15 Heavy Semi Critical 4 996253 77000 12.5% 15.1-20 Critical 0 0 0 0.0% 20.1- >=28 Heavy Critical 0 0 0 0.0% 6.57 Basic 23 4060289 618110 100.0% SMV Type Style Type Style Qty Produced Minute Produced Qty Avg qty % out of total Produce Qty <4.5 Very Basic 4 128869 29746 6.2% 4.51-7.5 Basic 18 1691691 319402 66.1% 7.51-10.5 Semi Critical 4 558925 71768 14.8% 10.51-15 Heavy Semi Critical 4 810235 62479 12.9% 15.1-20 Critical 0 0 0 0.0% 20.1- >=28 Heavy Critical 0 0 0 0.0% 6.60 Basic 30 3189719 483395 100.0%
  • 16. Month wise facts analysis : 1-15 SMV 1st day 2nd day 3rd day 4th day 5th day 6th day 7th day 8th day 9th day 10th day <4.5 45% 60% 70% 75% 85% 85% 85% 85% 85% 85% 4.51-7.5 40% 55% 65% 70% 75% 75% 75% 75% 75% 80% 7.51-10.5 35% 45% 55% 60% 65% 65% 65% 70% 70% 70% 10.51-15 35% 45% 50% 55% 60% 60% 60% 65% 65% 65% 15.1-20 25% 35% 45% 50% 55% 55% 55% 55% 55% 60% 20.1-28 25% 35% 40% 45% 50% 50% 50% 55% 55% 55% >=28.1 10% 20% 30% 35% 40% 45% 45% 45% 45% 50% Efficiency Requirement Month Factory No.Style Running No. Styling No.of Avg.Line Run days/Stylin g/Line Expected Efficiency Achieved Efficiency% May-22 KRC(U-3&4) 22 8 16 42days 75.0% 60.5% June-22 KRC(U-3&4) 27 7 16 59days 75.0% 67.8% July-22 KRC(U-3&4) 21 9 16 37days 75.0% 54.8% 70 24 48 45days 75.0% 61.0% Total
  • 17. PLAN STYLE RUNNING HEAT MAP,KRC,U-3 Unit 3 Line 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul No of Style A LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 1 B LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 2 C LEGGING LEGGING LEGGING LEGGING T-shirt T-shirt T-shirt 2 D T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2 E HOODY HOODY HOODY HOODY HOODY HOODY HOODY HOODY LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 2 F TANK TOPTANK TOP T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2 G JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET 2 H TANK TOPTANK TOPTANK TOPTANK TOP 1 Style Running Heat Map- KRC U-3 Unit- 3 Line 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul Number of styling Runned No. of style Runned A HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET 2 3 B T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT LADIES DRESS TANK TOP TANK TOP TANK TOP 3 5 C LEGGING LEGGING LEGGING T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 2 3 C2 LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING - - - - - - - - - - - - - - 1 1 D LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 2 3 E T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT - LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING JACKET JACKET JACKET - - - - 3 3 E+F - - - - - - - - - - - - - - - - - JACKET JACKET JACKET JACKET 1 1 F TANK TOP TANK TOP LEGGING LEGGING TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP TANK TOP - - - - - - - - 2 4 G HOODY WITH ZIP HOODY WITH ZIP HOODY WITH ZIP JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET JACKET 2 3 H LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 1 2 STYLE-WISE LINE PLAN VS.EXECUTION COMPARISON OF KRC-U-3
  • 18. PLAN STYLE RUNNING HEAT MAP,KRC,U-4 Unit 4 Line 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul No of Style A T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2 B T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2 C T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 2 D T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 3 E LADIES DRESS LADIES DRESS LADIES DRESS T-shirt T-shirt T-shirt T-shirt TANK TOPTANK TOPTANK TOPTANK TOPTANK TOPTANK TOP 2 F T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt 1 G T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt T-shirt JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER 2 STYLE-WISE LINE PLAN VS.EXECUTION COMPARISON OF KRC-U-4 Style Running Heat Map- KRC U-4 Unit- 4 Line 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 30-Jul 31-Jul Number of styling Runned No. of style Runned A T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 4 B T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 3 C T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT - - - - - - - - - - 1 2 C2 - - - - - - - - - - - - - - - - - - - - - 0 0 D T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 4 E JOGGER JOGGER JOGGER JOGGER JOGGER T-SHIRT T-SHIRT - - JOGGER JOGGER T-SHIRT LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING LEGGING 3 4 E+F - - - - - - - - - - - - - - - - - - - - - 0 0 F T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT T-SHIRT 1 1 G LADIES DRESS LADIES DRESS LADIES DRESS SHORT PANT T-SHIRT SHORT PANT T-SHIRT T-SHIRT LADIES DRESS JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER JOGGER T-SHIRT T-SHIRT T-SHIRT 4 6 H - - - - - - - - - - - - - - - - - - - - - 0 0
  • 19. PCD Hit & Fail Status (May-22): 1-18
  • 20. PCD Hit & Fail Status (June-22): 1-19
  • 21. PCD Hit & Fail Status (July-22): 1-20
  • 22. Month wise NPT status : 1-21 Non Productive Minute NPT Value NPT Value in Tk. NPT% NPT (Pcs) NPT (Man- Hour) NPT MC/Day Total Earning (Including NPT Value) Revenue/MC (Without NPT) 63205 Min. 4,424.35 $ 367,221৳ 0.97% 10216 Pcs 1053 5.2 MC 343,893.84 $ BDT 86562 136475 Min. 9,553.25 $ 792,920৳ 1.63% 23582 Pcs 2275 9.1 MC 473,161.80 $ BDT 92624 62182 Min. 4,352.74 $ 361,277৳ 1.07% 9424 Pcs 1036 5.6 MC 271,491.04 $ BDT 69293 261862 Min. 18,330.34 $ 1,521,418৳ 1.26% 43222 Pcs 4364 6.6 MC 1,088,546.67 $ BDT 83739
  • 26. Operators Skill Matrix Analysis : 1-25 GRADE NO OF OPERATOR PERCENTAGE (%) GRADING PERCENTAGE (%) A+ 0 0% A 21 5% A- 46 10% B+ 110 24% B 138 30% B- 90 19% C+ 30 6% C 24 5% C- 3 1% D 0 0% D 0% 462 100% 100% KRC (U-3&4) Operator Skill Matrix A B C 15% 73% 12%
  • 27. Month wise On Time Delivery status: 1-26
  • 28. Month wise short/excess shipment status : 1-27
  • 29. 2. Human Resource Department KPI: 1-28
  • 30. Month wise worker absenteeism status : 1-29
  • 31. Factors influencing on efficiency %: 1-30 1. Style Analysis : Allocating the styles in such a way that maximum line days can be achieved. 2. PCD hit Rate : Ensure PCD to ensure right style line feeding at right time. 3. Set a standard Target : Target has to be as per feasibility learning curve to get expected efficiency. 4. Production Monitoring : Ensure process wise production which leads to target achievement of full line. 5. Line Balancing : Set right person at right place to get maximum utilization of manpower and get output. 6. Operators Skill Matrix : Identify the right person as per process & requirement. 7. Operators Availability : Reduction of absenteeism to ensure operators availability as per requirement.
  • 32. SUMMARY OF TODAY DISCUSSION : 1-31 OrderConfirmation Sample Approval Planning Fabric& Accessoriesplanning File Handover CuttingPlan Print/Emb.Plan SewingStartPlan SewingProduction FRIPlan Order Execution Flow Chart Style Analysisduringsize set& PPMeeting Fabric Delay PCD delay Productivity Loss