Project Management National Conference 2011                                  PMI India




  Exploring Critical Risks for Green
  Construction in India



      S.Lakshmi Narayanan
      Department of Civil Engineering National
      Institute of Technology (NIT)




2|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                                       PMI India




                                                                                                         Contents


  1   ABSTRACT.......................................................................................................................4
  2   INTRODUCTION..............................................................................................................4
  3   PROBLEM STATEMENT................................................................................................5
  4   RISK IDENTIFICATION .................................................................................................6
  5   COST OVERRUN FACTOR ANALYSIS........................................................................6
  6   SIMULATION FOR RISK PREDICTION.......................................................................8
  7   CONCLUSIONS..............................................................................................................11
  8   REFERENCES.................................................................................................................11
  9   AUTHOR’S PROFILE:...................................................................................................13




3|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India




                 1     ABSTRACT

                 Green construction projects are initiated in complex and dynamic environments
                 resulting in circumstances of high uncertainty and risk, which are compounded
                 by demanding cost & time constraints. This paper describes a systematic way to
                 consider and quantify uncertainty in green construction process based on LEED
                 rating system adopted by Indian Green Building Council (IGBC). The system
                 incorporates knowledge and experience acquired from many experts, project-
                 specific information, decision analysis techniques, and a simulation model to
                 predict risks for different green ratings in the construction schedule at the
                 initiation of a project. The model provides sensitivity analyses for different
                 outcomes wherein the effect of critical and significant risk factors can be
                 evaluated. The study focuses on lessons learned from past projects and
                 describes a risk assessment process involving typical inputs and expected
                 outputs. The paper also investigates practical applications of risk management in
                 green construction industry.


                 Keywords: Project Management, Risk management, Risk Assessment, Green
                 Buildings, Construction projects


                 2     INTRODUCTION

                 A 1992 worldwide survey reported that the majority of construction projects fail to
                 achieve the objectives of the schedule (Cooper 1994). For many projects
                 schedule overrun analysis was not seem adequate at the beginning of the
                 project. However schedule targets are vanished because of unforeseen events
                 that even experienced construction managers could not anticipate. However,
                 schedule target dates are more often missed because of events, such as design
                 problems and industrial disputes, that were predictable but their likelihood and
                 effects are difficult to predict with any precision because no two construction
                 projects are the same (Thompson and Perry 1992)


                 A survey by Laufer and Stukhart (1992) of forty U.S. construction managers and
                 owners indicated that for scope and design objectives only 35% of the projects
                 considered had low uncertainty and the remaining 65% had medium to very high
                 uncertainty at the beginning of construction. The costs of the projects averaged
                 $5,000,000 which confirmed another report by Laufer and Howell (1993). It also
                 concluded that approximately 80% of projects at beginning of construction
                 possessed a high level of uncertainty.


                 The aim of green construction is primarily to minimize demand on non-renewable
                 resources and maximize utilization efficiency of resources when in use. Secondly

4|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India



                 it aims at maximizing reuse and recycling of available resources, and improving
                 indoor environment quality thereby aiming to lower the operational and
                 maintenance cost. The challenge of a green building is to achieve all its benefits
                 at an affordable cost.


                 The amount of uncertainty in internal and external environments of a green
                 construction project is an important factor in determining the likelihood of
                 schedule overrun. However, attempting to consider realistically the uncertainty in
                 construction schedules poses three challenges. The first challenge is that
                 systems are not endorsed professionally or available commercially such that it
                 can be used to structure project uncertainty and measure the effects on the
                 project schedule. The second challenge is lack of easily accessible information
                 and documentation of experience of construction industry or the knowledge
                 scattered within a corporation. The third challenge is difficult motivating
                 involvement of senior project management team to address adequately schedule
                 risks. Project teams generally are too preoccupied with solving current problems
                 involved with getting work done and therefore have insufficient time to think
                 about, much less time to carry out, a formal risk assessment program (Oglesby
                 et al. 1989).


                 This paper explores all the important risk factors contributing to cost & time
                 overrun and identifying the critical elements in green construction sector so that
                 appropriate mitigation measures can be devised.


                 The study envisages analysis at three levels primarily the planning, execution,
                 and the closing down phases in green construction process with respect to the
                 primary data obtained from professionals through questionnaires and personal
                 interviews. The indicators obtained from the above analysis are further
                 scrutinized and analyzed with the aid of secondary data and by which general
                 solutions and observations are formulated. This study will pave way for further
                 research in risk assessment, cost & time overruns in green construction industry.


                 3     PROBLEM STATEMENT

                 Various attempts have been made to understand the present status of the green
                 construction industry. This has thrown light on lack of exploration of various cost
                 management strategies, tools and techniques adopted in green construction
                 process, apart from certain case studies highlighting various problems
                 associated with the lack of efficient risk management leading to time and cost
                 overruns


                 During the study, 34 factors were identified and analyzed for assessment of
                 potential overruns associated with duration and cost in the green construction
                 industry. The status of cost & time overruns in green construction industry is
5|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                            PMI India



                 untouched, and this study offers an insight into identification of risk for project
                 time & cost overruns in green construction sector.


                 4     RISK IDENTIFICATION

                 A perusal of the guidelines on green rating systems included Leadership in
                 Energy and Environmental Design (LEED) India –CS & Green Rating for
                 Integrated Habitat Assessment. Expert opinions from LEED professionals and
                 other green experts utilized to identify a number of time & cost overrun causes in
                 the green construction industry scenario. In India 80 green projects are
                 registered under LEED of which only 28 have been completed. In total thirty four
                 (34) factors were finalized to be made part of the survey questionnaire.


                 Three types of questionnaires were prepared based on the guidelines prescribed
                 by LEED INDIA-CS & GRIHA. In this study the three main aspects taken into
                 account are: (i) Planning Stage, (ii) Construction Stage, and (iii) Closing down
                 Stage.


                 A survey was conducted through internet, postal mail and personal interviews in
                 which respondents were asked to rank and score these factors according to their
                 experience along with the cost overruns during the projects they had undertaken.
                 Twenty five (25) construction firms were approached for these surveys out of
                 which seventeen (17) responses were received with the response rate of 68%.


                 5     COST OVERRUN FACTOR ANALYSIS

                 In totality 34 factors were identified and the respondents ranked them for
                 duration & cost overruns. The risks are qualitatively those that have both the
                 highest impact on the project and are most likely to occur. Here the impact,
                 probability, and severity (criticality) of each risk factors were quantified into zones
                 in the probability-impact matrix (Graves et al 2000).


                 The risks associated with the construction industry were extensively analyzed
                 using factor analysis with multiple regression models, ANOVA and T-tests
                 (Sundarajulu et al 2007). The values used for probability and impact are indices
                 that represent combined effect of the risks. The quantitative assessment is based
                 on the mean values which was proposed by Sundarajulu et al 2007 This study
                 incorporates nonnumeric probability scale (a three-level scale), where 1=Low
                 Probability, 2=Intermediate Probability, 3=High Probability, and impact is
                 measured as deviation in project schedule which is also represented on a
                 nonnumeric scale of 1-3 where 1=Low Impact, 2=Intermediate Impact, 3=High
                 Impact which is presented in Table 1. The impact on the project schedule was
                 measured for the schedule project delay on a scale of 1-3 Graves et al 2000.

6|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                  PMI India



                             Table 1 Rating Risk Impact on a Three-Level Scale


                  Scale                        1                         2                    3

               Risk Impact                Less Delay                 Some Delay             Delay

            Risk on schedule of         Overall project         Overall project         Overall project
                  project                delay<5%               delay<5-25%              delay>25%



                     In conjunction with this, a list of 34 factors was provided to the respondents to
                     rank and score them according to the severity on the scale of 1 to 10 and they
                     were instructed to rate score 1 to the factors which they find least contributing
                     towards the time & cost overrun and a score of 10 to those factors they regard as
                     most significant towards generating project time & cost overruns, and rating of in
                     between to mark the severity of factor ranging from low to high.


                     Impact of each factor is calculated by



                                            impact =
                                                        ∑   fi × i
                                                                     ……. Equation (1)
                                                            n

                     Where:


                                i –the severity score from 1 to 10


                                fi -the frequency of factor getting score i


                                n –number of responses


                     Figure 1 indicates the resultant impact ranking of the time & cost overrun factors
                     as depicted by the survey analysis, impact ranges were divided into three
                     regions, range of 0 to 2.5 (on severity impact axis) is neglected from the analysis
                     due its insignificance and ranges are developed for severity impact as low,
                     medium and high.


                     Low severity range (with impact score of 2.5 to 5), medium severity range
                     (impact score of 5 to 7.5) and high severity range (ranges from 7.5 to 10).Results
                     represents that very few (3) factors were rated as low severe, majority of the
                     scores lies in the high medium severity




7|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India




                                            Figure 1 Severity Analysis


                 6     SIMULATION FOR RISK PREDICTION

                 In this study, range for random variable for each of the factors was identified
                 based on the probability distribution curves developed from the primary survey.
                 Cumulative probability of occurrence of each risk is calculated based on the
                 response received in the survey. A random number generated is linked to a risk
                 based on the class intervals decided by the cumulative probability obtained from
                 survey.


                 Monte Carlo Simulation was used as an effective tool for risk prediction.
                 Simulation runs of 1000, 10000, 50000 and 100000 were tabulated to predict the
                 risks identified using survey response. All the inputs were taken from green
                 experts to take the process more close to the real world.. Simulation was carried
                 out varying the number of runs to determine any converging trend in the overruns
                 associated with cost and duration for various types of rating according to LEED
                 INDIA CS. The results based on this simulation analysis are presented in table 2.
                 The result based on the simulation model indicates that minimum credits that are
                 required for each type of rating with most likely overrun with respect to cost and
                 duration. It is evident from the study that the duration overrun associated with the
                 project targeting Platinum rating is comparatively lesser than the Silver rating
                 while the cost overrun associated with a Platinum rated green building is more in
                 comparison with silver rated building. This is due to the fact that the execution of
                 various activities associated with the Platinum rated building is carried out with
                 an efficient technology and advanced materials. However there is only a
                 marginal variation when Platinum rated building is compared with the Gold rated
                 construction. This is due to the fact that the variation in credit requirement is
8|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                 minimal in between the two certifications. However a large overrun is observed in
                 the case of Green Certified building compared to the higher rating even though
                 the credit requirement according to LEED NC is lowest for this group. This is due
                 to higher degree of randomness associated with this type of construction. It was
                 observed during the simulation study that as the higher rating system is target for
                 a building, the randomness associated with various parameters is reduced.


                                    TABLE 2 Simulation results


  Type of
                                            100 runs       1000runs      10,000runs     50,000runs
Certification
  Platinum          Total Credits              59              59            59             60
Rated Green     Duration Overrun (%)          13.42           7.84          12.04          11.43
  Building       Cost Overrun (%)             23.96          13.99          21.49          20.40
 Gold Rated         Total Credits              44              48            46             48
   Green        Duration Overrun (%)          11.53          18.19          16.19          67.09
  Building       Cost Overrun (%)             10.65           4.78          12.06          23.34
Silver Rated        Total Credits              38              33            34             33
   Green        Duration Overrun (%)          1.75           27.94          39.60          89.02
  Building       Cost Overrun (%)             2.45           10.96          13.23          12.43
  Certified         Total Credits              32              31            30             31
   Green        Duration Overrun (%)          10.45          98.56          93.95          15.99
  Building       Cost Overrun (%)             17.89          17.57          16.76          89.76


                 Based on the analysis the risks identified are ranked according to the likelihood
                 of occurrence and impact on the project which is targeting various rating. The
                 various intends required for the green rating is rated based on the cost impact
                 and duration impact from lower value to higher value on the project based on the
                 simulation study. The results obtained in this study presented in Table 3
                 indicates for obtaining any rating, the reduction in site disturbance has the lowest
                 impact on the project with respect to cost and duration while the next higher
                 impact is for the factor site selection amongst various factors that need to be
                 considered in Sustainable sites.




9|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                                                                                                       PMI India



                                                                                                                    TABLE 3 Risk ranking for different green ratings of the building


                                                                                                                                            Credits   Certified    Silver   Gold       Platinum
                                                                                                          Reduced Site Disturbance             1           1          1       1             1
  Sustainable Sites




                                                                                                          Site Selection                       1           2          2       2             2
                                                                                                          Alternative Transportation          1-3          3          4       3             3
                                                                                                          Storm water Design, Quantity
                                                                                                                                               1           4          3        4           4
                                                                                                          Control
                                                                                                          Development Density &
                                                                                                                                               1           5          5        5           5
                                                                                                          Community Connectivity
                                                                                                          Brownfield Redevelopment             1           6          6        6           6
                                                                                                          Heat Island Effect, Roof             1           8          8        8           8
  Innovation in Indoor Environmental Quality Materials & Resources Energy & Atmosphere Water Efficiency




                                                                                                          Water Efficiency                    1-2          2          2        2           2
                                                                                                          Water Efficiency in Air-
                                                                                                                                               1           4          4        3           3
                                                                                                          conditioning System
                                                                                                          Innovative Waste Water
                                                                                                                                               1           1          1        1           1
                                                                                                          Technologies
                                                                                                          Water Use Reduction                 1-2          3          3        4           4
                                                                                                          Optimize Energy Performance         1-10         5          5        1           5
                                                                                                          Renewable Energy                     1-3         1          1        2           1
                                                                                                          Additional Commissioning              1          2          2        3           2
                                                                                                          Ozone Depletion                       1          3          3        4           3


                                                                                                          Measurement & Verification           1           4          4        5           4


                                                                                                          Building Reuse                      1-3          4          4        6           4
                                                                                                          Construction Waste Management       1-2          1          1        4           1
                                                                                                          Resource Reuse                      1-2          2          2        1           2
                                                                                                          Recycled Content                    1-2          6          6        2           6
                                                                                                          Local / Regional Materials          1-2          3          3        3           3
                                                                                                          Rapidly Renewable Materials          1           5          5        5           5

                                                                                                          Certified Wood                       1           7          7        7           7

                                                                                                          Outdoor Air Delivery Monitoring      1           3          3        3           3
                                                                                                          Increased Ventilation                1           4          4        4           4
                                                                                                          Construction IAQ Management
                                                                                                                                              1-2          5          5        5           5
                                                                                                          Plan
                                                                                                          Low-Emitting Materials              1-4          6          6        6           6
                                                                                                          Indoor Chemical & Pollutant
                                                                                                                                               1           1          1        1           1
                                                                                                          Source Control
                                                                                                          Controllability of Systems          1-2          7          7        7           7
                                                                                                          Thermal Comfort, Design              1           8          8        8           8
                                                                                                          Thermal Comfort, Verification        1           9          9        9           9
                                                                                                          Daylight & Views                    1-2          2          2        2           2

                                                                                                          Innovation in Design                1-4          2          2        2           2

                                                                                                          LEEDTM Accredited Professional       1           1          1        1           1



10|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India

  Design




                 7     CONCLUSIONS

                 The study was carried out based on various green building construction projects
                 in India and abroad. However emphasis was given in developing a risk modeling
                 tool that can predict the overrun associated with duration and cost of Green
                 Building. The survey results indicated that the majority of cost overrun factors
                 (89%) lie in medium severity impact range. However these factors need to be
                 attended as they tend to increase in the cost of the project compared to the initial
                 estimation. Even though the likelihood of cost overrun for construction projects
                 targeting green rating is high, minimum range of cost overrun in percentage of
                 the estimated cost is found to be 8%. The highest risks were associated with
                 Reduced Site Disturbance, Innovative Waste Water Technologies, Renewable
                 Energy, Construction Waste Management, Indoor Chemical & Pollutant Source
                 Control, and LEED Accredited Professional. Care and proper mitigation
                 measures should therefore be taken while including the factors with lower rank in
                 risk factors.


                 8     REFERENCES

                       [1]. A Guide to the Project Management Body of Knowledge, Project
                       Management Institute, 1996.


                       [2]. Akintola S Akintoye and Malcolm J MacLeod(1997). “Risk analysis
                       and management in construction” International Journal of Project
                       Management Vol. 15, No. 1: 31-38, 1997.


                       [3]. Alfredo del Can,and M. Pilar de la Cruz(December      2002).
                       “Integrated   Methodology for Project Risk Management” Journal of
                       Construction Engineering and Management, ASCE: 473-485 .


                       [4]. Artem Aleshin.(2001) “Risk management of international projects in
                       Russia.” International Journal of Project Management Vol. 19: 207-222.


                       [5]. Bing, L., Tiong, R. L. K., Wong, W. F., and Chow, D.(1999) “Risk
                       management of international construction joint ventures.” Journal of
                       Construction Engineering and Management, ASCE, 125(4): 277–284.




11|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                        PMI India



                       [6]. Darrin and Mervyn K Lewis.(2002) “Evaluating the risks of public
                       private partnerships for infrastructure projects.” International Journal of
                       Project Management: 107-118.


                       [7]. Daud Nasir, Brenda McCabe and Loesie Hartono(October, 2003)
                       “Evaluating Risk in Construction–Schedule Model (ERIC–S) Construction
                       Schedule Risk Model.” Journal of Construction Engineering and
                       Management, ASCE, Vol. 129, No. 5: 518-527.


                       [8]. El-Diraby.T. A and Gill S. M. (March 2006) “A Taxonomy For
                       Construction Terms In Privatized Infrastructure Finance, Supporting
                       Semantic Exchange Of Project Risk Information.” Construction
                       Management and Economics: 271–285.


                       [9]. Eric Verzuh.(2005) “The Fast Forward MBA in Project Management”
                       Wiley – 2nd Edn:105-109.


                       [10]. Garg.A.K.(February 2005) “Risk Management In Construction
                       Contacts” Construction Materials Purchase: 14-16.


                       [11]. Gregory H. Kats. “Green Building Costs and Financial Benefits.”


                       [12]. Narendra D. Patel and Nikesh P. Shah.(September 2007) “Green
                       housing – Review, Rating Systems And Implementation.” The Indian
                       Concrete Journal.


                       [13]. B. Mulholland and J. Christian(January/February 1999) “Risk
                       Assessment In Construction Schedules.”    Journal Of Construction
                       Engineering And Management


                       [14]. Archibald, R. D, and Lichtenberg(1994) “Uncertainty And Change
                       Require A New Management Model.” Pm Network, VIII(5): 6–10.


                       [15]. Birrell, G. S.(1983) “Construction Planning—Beyond The Critical
                       Path.” J. Constr. Div., ASCE, 106: 389–407.


                       [16]. Cooper, K. G.(1994) “The $2,000 hour: How Managers Influence
                       Project Performance Through The Rework Cycle.’’ PM J., XXV(1): 11–24.


                       [17]. Cowie, G. F., and Carr, J. P. (1984) “Discussion Of Integrated Project
                       And Process Management”, Constr. Engrg. And Mgmt, ASCE, 110: 121–
                       122.

12|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                        PMI India



                       [18]. “LEED reference guide, Version 1.0.” Indian Green Building
                       Council(2001).


                       [19]. “International Initiative for Sustainable Built Environment.” Advanced
                       Building News. ABN2(2004).


                       [20]. “White Paper On Sustainability: A Report On The Green Building
                       Movement.” Supplement To The Building Design & Construction,
                       (November 2003).


                       [21]. Cole, R.(2001). “A building environmental assessment method for
                       British Columbia.” Final report to BC Green Buildings Ad-Hoc Committee.
                       (www.buildsmart.ca/pdfs/ASSESSMENT%20REPORT.PDF).


                       [22]. “Building momentum: National Trends And Prospects For High
                       Performance Green Buildings” U.S. Green Building Council, Baltimore
                       (2002).




                 9     AUTHOR’S PROFILE:




                 S.Lakshmi Narayanan, is working in the Strategy & Business
                 Development department of Shapoorji Pallonji & Co. Ltd in New Delhi.
                 His areas of interests include International project management, Green
                 Construction & Green Supply Chain Optimization. He is also an author of
                 2 International journal papers specifically relating to overruns. He also
                 reviews for reputed international journals like journal of supercomputing,
                 Inderscience etc.


                 lniyer88@gmail.com



13|P a g e
 Application of Select Tools of Psychology for Effective Project Management

More Related Content

What's hot

30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)IAESIJEECS
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
Smarter Oil and Gas - IBM Rational Point of View
Smarter Oil and Gas - IBM Rational Point of ViewSmarter Oil and Gas - IBM Rational Point of View
Smarter Oil and Gas - IBM Rational Point of ViewDerek Newton
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Project risk management
Project risk managementProject risk management
Project risk managementHaseeb Khan
 
IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...IRJET Journal
 
Optimizing Building Plan for a (9m X 12m) House Using Learning Systems
Optimizing Building Plan for a (9m X 12m) House Using Learning SystemsOptimizing Building Plan for a (9m X 12m) House Using Learning Systems
Optimizing Building Plan for a (9m X 12m) House Using Learning SystemsIJCSIS Research Publications
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.kiebut
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksIRJET Journal
 
059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS
059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS
059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPSDr Fereidoun Dejahang
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
ResearchTopicDevelopment_21Aug2014
ResearchTopicDevelopment_21Aug2014ResearchTopicDevelopment_21Aug2014
ResearchTopicDevelopment_21Aug2014Enyo Agbodo
 

What's hot (20)

30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
 
Smarter Oil and Gas - IBM Rational Point of View
Smarter Oil and Gas - IBM Rational Point of ViewSmarter Oil and Gas - IBM Rational Point of View
Smarter Oil and Gas - IBM Rational Point of View
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...
 
Optimizing Building Plan for a (9m X 12m) House Using Learning Systems
Optimizing Building Plan for a (9m X 12m) House Using Learning SystemsOptimizing Building Plan for a (9m X 12m) House Using Learning Systems
Optimizing Building Plan for a (9m X 12m) House Using Learning Systems
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS
059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS
059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
ResearchTopicDevelopment_21Aug2014
ResearchTopicDevelopment_21Aug2014ResearchTopicDevelopment_21Aug2014
ResearchTopicDevelopment_21Aug2014
 

Viewers also liked

Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sanePMI2011
 
Bhavesh pmi final
Bhavesh  pmi finalBhavesh  pmi final
Bhavesh pmi finalPMI2011
 

Viewers also liked (9)

PMC7
PMC7PMC7
PMC7
 
DPPM2
DPPM2DPPM2
DPPM2
 
DPPM6
DPPM6DPPM6
DPPM6
 
ETPM5
ETPM5ETPM5
ETPM5
 
PMC6
PMC6PMC6
PMC6
 
MCP4
MCP4MCP4
MCP4
 
DPPM5
DPPM5DPPM5
DPPM5
 
Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sane
 
Bhavesh pmi final
Bhavesh  pmi finalBhavesh  pmi final
Bhavesh pmi final
 

Similar to MCP2

USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...IRJET Journal
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewIRJET Journal
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementJoe Osborn
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
IRJET- A Review Paper on Lean Management in Construction Sites
IRJET-  	  A Review Paper on Lean Management in Construction SitesIRJET-  	  A Review Paper on Lean Management in Construction Sites
IRJET- A Review Paper on Lean Management in Construction SitesIRJET Journal
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...Harish Rajmane
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportMuhammad Daniyal
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsIRJET Journal
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSIAEME Publication
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 

Similar to MCP2 (20)

USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project Management
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
IRJET- A Review Paper on Lean Management in Construction Sites
IRJET-  	  A Review Paper on Lean Management in Construction SitesIRJET-  	  A Review Paper on Lean Management in Construction Sites
IRJET- A Review Paper on Lean Management in Construction Sites
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business Decisions
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
PMC2
PMC2PMC2
PMC2
 

More from PMI2011

Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyyaPMI2011
 
Final chakradhar purohith proposal milieu analysis (without account data un...
Final chakradhar purohith proposal milieu analysis (without account data   un...Final chakradhar purohith proposal milieu analysis (without account data   un...
Final chakradhar purohith proposal milieu analysis (without account data un...PMI2011
 
Wilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyWilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyPMI2011
 
Vs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiVs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiPMI2011
 
Vineet jain
Vineet jainVineet jain
Vineet jainPMI2011
 
Yamuna padmanaban
Yamuna padmanabanYamuna padmanaban
Yamuna padmanabanPMI2011
 
Vimal kumarkhanna
Vimal kumarkhannaVimal kumarkhanna
Vimal kumarkhannaPMI2011
 
Venkatraman l
Venkatraman lVenkatraman l
Venkatraman lPMI2011
 
Vardarajan sethuraman
Vardarajan sethuramanVardarajan sethuraman
Vardarajan sethuramanPMI2011
 
Soumen de
Soumen deSoumen de
Soumen dePMI2011
 
Sujit sopan barhate
Sujit sopan barhateSujit sopan barhate
Sujit sopan barhatePMI2011
 
Srinivasa desikanraghavan
Srinivasa desikanraghavanSrinivasa desikanraghavan
Srinivasa desikanraghavanPMI2011
 
Sharad pandey abhisek goswami
Sharad pandey abhisek goswamiSharad pandey abhisek goswami
Sharad pandey abhisek goswamiPMI2011
 
Soma roy sarkar
Soma roy sarkarSoma roy sarkar
Soma roy sarkarPMI2011
 
Shallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanShallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanPMI2011
 
Regeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebRegeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebPMI2011
 
Ramesh ganiga
Ramesh ganigaRamesh ganiga
Ramesh ganigaPMI2011
 
Pranabendu
PranabenduPranabendu
PranabenduPMI2011
 
Rt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyRt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyPMI2011
 
Pradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadavPradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadavPMI2011
 

More from PMI2011 (20)

Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
 
Final chakradhar purohith proposal milieu analysis (without account data un...
Final chakradhar purohith proposal milieu analysis (without account data   un...Final chakradhar purohith proposal milieu analysis (without account data   un...
Final chakradhar purohith proposal milieu analysis (without account data un...
 
Wilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyWilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthy
 
Vs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiVs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakraborti
 
Vineet jain
Vineet jainVineet jain
Vineet jain
 
Yamuna padmanaban
Yamuna padmanabanYamuna padmanaban
Yamuna padmanaban
 
Vimal kumarkhanna
Vimal kumarkhannaVimal kumarkhanna
Vimal kumarkhanna
 
Venkatraman l
Venkatraman lVenkatraman l
Venkatraman l
 
Vardarajan sethuraman
Vardarajan sethuramanVardarajan sethuraman
Vardarajan sethuraman
 
Soumen de
Soumen deSoumen de
Soumen de
 
Sujit sopan barhate
Sujit sopan barhateSujit sopan barhate
Sujit sopan barhate
 
Srinivasa desikanraghavan
Srinivasa desikanraghavanSrinivasa desikanraghavan
Srinivasa desikanraghavan
 
Sharad pandey abhisek goswami
Sharad pandey abhisek goswamiSharad pandey abhisek goswami
Sharad pandey abhisek goswami
 
Soma roy sarkar
Soma roy sarkarSoma roy sarkar
Soma roy sarkar
 
Shallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanShallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuraman
 
Regeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebRegeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoyceb
 
Ramesh ganiga
Ramesh ganigaRamesh ganiga
Ramesh ganiga
 
Pranabendu
PranabenduPranabendu
Pranabendu
 
Rt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyRt sundari ashutosh_pandey
Rt sundari ashutosh_pandey
 
Pradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadavPradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadav
 

Recently uploaded

8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 

Recently uploaded (20)

8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 

MCP2

  • 1.
  • 2. Project Management National Conference 2011 PMI India Exploring Critical Risks for Green Construction in India S.Lakshmi Narayanan Department of Civil Engineering National Institute of Technology (NIT) 2|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 3. Project Management National Conference 2011 PMI India Contents 1 ABSTRACT.......................................................................................................................4 2 INTRODUCTION..............................................................................................................4 3 PROBLEM STATEMENT................................................................................................5 4 RISK IDENTIFICATION .................................................................................................6 5 COST OVERRUN FACTOR ANALYSIS........................................................................6 6 SIMULATION FOR RISK PREDICTION.......................................................................8 7 CONCLUSIONS..............................................................................................................11 8 REFERENCES.................................................................................................................11 9 AUTHOR’S PROFILE:...................................................................................................13 3|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 4. Project Management National Conference 2011 PMI India 1 ABSTRACT Green construction projects are initiated in complex and dynamic environments resulting in circumstances of high uncertainty and risk, which are compounded by demanding cost & time constraints. This paper describes a systematic way to consider and quantify uncertainty in green construction process based on LEED rating system adopted by Indian Green Building Council (IGBC). The system incorporates knowledge and experience acquired from many experts, project- specific information, decision analysis techniques, and a simulation model to predict risks for different green ratings in the construction schedule at the initiation of a project. The model provides sensitivity analyses for different outcomes wherein the effect of critical and significant risk factors can be evaluated. The study focuses on lessons learned from past projects and describes a risk assessment process involving typical inputs and expected outputs. The paper also investigates practical applications of risk management in green construction industry. Keywords: Project Management, Risk management, Risk Assessment, Green Buildings, Construction projects 2 INTRODUCTION A 1992 worldwide survey reported that the majority of construction projects fail to achieve the objectives of the schedule (Cooper 1994). For many projects schedule overrun analysis was not seem adequate at the beginning of the project. However schedule targets are vanished because of unforeseen events that even experienced construction managers could not anticipate. However, schedule target dates are more often missed because of events, such as design problems and industrial disputes, that were predictable but their likelihood and effects are difficult to predict with any precision because no two construction projects are the same (Thompson and Perry 1992) A survey by Laufer and Stukhart (1992) of forty U.S. construction managers and owners indicated that for scope and design objectives only 35% of the projects considered had low uncertainty and the remaining 65% had medium to very high uncertainty at the beginning of construction. The costs of the projects averaged $5,000,000 which confirmed another report by Laufer and Howell (1993). It also concluded that approximately 80% of projects at beginning of construction possessed a high level of uncertainty. The aim of green construction is primarily to minimize demand on non-renewable resources and maximize utilization efficiency of resources when in use. Secondly 4|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 5. Project Management National Conference 2011 PMI India it aims at maximizing reuse and recycling of available resources, and improving indoor environment quality thereby aiming to lower the operational and maintenance cost. The challenge of a green building is to achieve all its benefits at an affordable cost. The amount of uncertainty in internal and external environments of a green construction project is an important factor in determining the likelihood of schedule overrun. However, attempting to consider realistically the uncertainty in construction schedules poses three challenges. The first challenge is that systems are not endorsed professionally or available commercially such that it can be used to structure project uncertainty and measure the effects on the project schedule. The second challenge is lack of easily accessible information and documentation of experience of construction industry or the knowledge scattered within a corporation. The third challenge is difficult motivating involvement of senior project management team to address adequately schedule risks. Project teams generally are too preoccupied with solving current problems involved with getting work done and therefore have insufficient time to think about, much less time to carry out, a formal risk assessment program (Oglesby et al. 1989). This paper explores all the important risk factors contributing to cost & time overrun and identifying the critical elements in green construction sector so that appropriate mitigation measures can be devised. The study envisages analysis at three levels primarily the planning, execution, and the closing down phases in green construction process with respect to the primary data obtained from professionals through questionnaires and personal interviews. The indicators obtained from the above analysis are further scrutinized and analyzed with the aid of secondary data and by which general solutions and observations are formulated. This study will pave way for further research in risk assessment, cost & time overruns in green construction industry. 3 PROBLEM STATEMENT Various attempts have been made to understand the present status of the green construction industry. This has thrown light on lack of exploration of various cost management strategies, tools and techniques adopted in green construction process, apart from certain case studies highlighting various problems associated with the lack of efficient risk management leading to time and cost overruns During the study, 34 factors were identified and analyzed for assessment of potential overruns associated with duration and cost in the green construction industry. The status of cost & time overruns in green construction industry is 5|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 6. Project Management National Conference 2011 PMI India untouched, and this study offers an insight into identification of risk for project time & cost overruns in green construction sector. 4 RISK IDENTIFICATION A perusal of the guidelines on green rating systems included Leadership in Energy and Environmental Design (LEED) India –CS & Green Rating for Integrated Habitat Assessment. Expert opinions from LEED professionals and other green experts utilized to identify a number of time & cost overrun causes in the green construction industry scenario. In India 80 green projects are registered under LEED of which only 28 have been completed. In total thirty four (34) factors were finalized to be made part of the survey questionnaire. Three types of questionnaires were prepared based on the guidelines prescribed by LEED INDIA-CS & GRIHA. In this study the three main aspects taken into account are: (i) Planning Stage, (ii) Construction Stage, and (iii) Closing down Stage. A survey was conducted through internet, postal mail and personal interviews in which respondents were asked to rank and score these factors according to their experience along with the cost overruns during the projects they had undertaken. Twenty five (25) construction firms were approached for these surveys out of which seventeen (17) responses were received with the response rate of 68%. 5 COST OVERRUN FACTOR ANALYSIS In totality 34 factors were identified and the respondents ranked them for duration & cost overruns. The risks are qualitatively those that have both the highest impact on the project and are most likely to occur. Here the impact, probability, and severity (criticality) of each risk factors were quantified into zones in the probability-impact matrix (Graves et al 2000). The risks associated with the construction industry were extensively analyzed using factor analysis with multiple regression models, ANOVA and T-tests (Sundarajulu et al 2007). The values used for probability and impact are indices that represent combined effect of the risks. The quantitative assessment is based on the mean values which was proposed by Sundarajulu et al 2007 This study incorporates nonnumeric probability scale (a three-level scale), where 1=Low Probability, 2=Intermediate Probability, 3=High Probability, and impact is measured as deviation in project schedule which is also represented on a nonnumeric scale of 1-3 where 1=Low Impact, 2=Intermediate Impact, 3=High Impact which is presented in Table 1. The impact on the project schedule was measured for the schedule project delay on a scale of 1-3 Graves et al 2000. 6|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 7. Project Management National Conference 2011 PMI India Table 1 Rating Risk Impact on a Three-Level Scale Scale 1 2 3 Risk Impact Less Delay Some Delay Delay Risk on schedule of Overall project Overall project Overall project project delay<5% delay<5-25% delay>25% In conjunction with this, a list of 34 factors was provided to the respondents to rank and score them according to the severity on the scale of 1 to 10 and they were instructed to rate score 1 to the factors which they find least contributing towards the time & cost overrun and a score of 10 to those factors they regard as most significant towards generating project time & cost overruns, and rating of in between to mark the severity of factor ranging from low to high. Impact of each factor is calculated by impact = ∑ fi × i ……. Equation (1) n Where: i –the severity score from 1 to 10 fi -the frequency of factor getting score i n –number of responses Figure 1 indicates the resultant impact ranking of the time & cost overrun factors as depicted by the survey analysis, impact ranges were divided into three regions, range of 0 to 2.5 (on severity impact axis) is neglected from the analysis due its insignificance and ranges are developed for severity impact as low, medium and high. Low severity range (with impact score of 2.5 to 5), medium severity range (impact score of 5 to 7.5) and high severity range (ranges from 7.5 to 10).Results represents that very few (3) factors were rated as low severe, majority of the scores lies in the high medium severity 7|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 8. Project Management National Conference 2011 PMI India Figure 1 Severity Analysis 6 SIMULATION FOR RISK PREDICTION In this study, range for random variable for each of the factors was identified based on the probability distribution curves developed from the primary survey. Cumulative probability of occurrence of each risk is calculated based on the response received in the survey. A random number generated is linked to a risk based on the class intervals decided by the cumulative probability obtained from survey. Monte Carlo Simulation was used as an effective tool for risk prediction. Simulation runs of 1000, 10000, 50000 and 100000 were tabulated to predict the risks identified using survey response. All the inputs were taken from green experts to take the process more close to the real world.. Simulation was carried out varying the number of runs to determine any converging trend in the overruns associated with cost and duration for various types of rating according to LEED INDIA CS. The results based on this simulation analysis are presented in table 2. The result based on the simulation model indicates that minimum credits that are required for each type of rating with most likely overrun with respect to cost and duration. It is evident from the study that the duration overrun associated with the project targeting Platinum rating is comparatively lesser than the Silver rating while the cost overrun associated with a Platinum rated green building is more in comparison with silver rated building. This is due to the fact that the execution of various activities associated with the Platinum rated building is carried out with an efficient technology and advanced materials. However there is only a marginal variation when Platinum rated building is compared with the Gold rated construction. This is due to the fact that the variation in credit requirement is 8|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 9. Project Management National Conference 2011 PMI India minimal in between the two certifications. However a large overrun is observed in the case of Green Certified building compared to the higher rating even though the credit requirement according to LEED NC is lowest for this group. This is due to higher degree of randomness associated with this type of construction. It was observed during the simulation study that as the higher rating system is target for a building, the randomness associated with various parameters is reduced. TABLE 2 Simulation results Type of 100 runs 1000runs 10,000runs 50,000runs Certification Platinum Total Credits 59 59 59 60 Rated Green Duration Overrun (%) 13.42 7.84 12.04 11.43 Building Cost Overrun (%) 23.96 13.99 21.49 20.40 Gold Rated Total Credits 44 48 46 48 Green Duration Overrun (%) 11.53 18.19 16.19 67.09 Building Cost Overrun (%) 10.65 4.78 12.06 23.34 Silver Rated Total Credits 38 33 34 33 Green Duration Overrun (%) 1.75 27.94 39.60 89.02 Building Cost Overrun (%) 2.45 10.96 13.23 12.43 Certified Total Credits 32 31 30 31 Green Duration Overrun (%) 10.45 98.56 93.95 15.99 Building Cost Overrun (%) 17.89 17.57 16.76 89.76 Based on the analysis the risks identified are ranked according to the likelihood of occurrence and impact on the project which is targeting various rating. The various intends required for the green rating is rated based on the cost impact and duration impact from lower value to higher value on the project based on the simulation study. The results obtained in this study presented in Table 3 indicates for obtaining any rating, the reduction in site disturbance has the lowest impact on the project with respect to cost and duration while the next higher impact is for the factor site selection amongst various factors that need to be considered in Sustainable sites. 9|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 10. Project Management National Conference 2011 PMI India TABLE 3 Risk ranking for different green ratings of the building Credits Certified Silver Gold Platinum Reduced Site Disturbance 1 1 1 1 1 Sustainable Sites Site Selection 1 2 2 2 2 Alternative Transportation 1-3 3 4 3 3 Storm water Design, Quantity 1 4 3 4 4 Control Development Density & 1 5 5 5 5 Community Connectivity Brownfield Redevelopment 1 6 6 6 6 Heat Island Effect, Roof 1 8 8 8 8 Innovation in Indoor Environmental Quality Materials & Resources Energy & Atmosphere Water Efficiency Water Efficiency 1-2 2 2 2 2 Water Efficiency in Air- 1 4 4 3 3 conditioning System Innovative Waste Water 1 1 1 1 1 Technologies Water Use Reduction 1-2 3 3 4 4 Optimize Energy Performance 1-10 5 5 1 5 Renewable Energy 1-3 1 1 2 1 Additional Commissioning 1 2 2 3 2 Ozone Depletion 1 3 3 4 3 Measurement & Verification 1 4 4 5 4 Building Reuse 1-3 4 4 6 4 Construction Waste Management 1-2 1 1 4 1 Resource Reuse 1-2 2 2 1 2 Recycled Content 1-2 6 6 2 6 Local / Regional Materials 1-2 3 3 3 3 Rapidly Renewable Materials 1 5 5 5 5 Certified Wood 1 7 7 7 7 Outdoor Air Delivery Monitoring 1 3 3 3 3 Increased Ventilation 1 4 4 4 4 Construction IAQ Management 1-2 5 5 5 5 Plan Low-Emitting Materials 1-4 6 6 6 6 Indoor Chemical & Pollutant 1 1 1 1 1 Source Control Controllability of Systems 1-2 7 7 7 7 Thermal Comfort, Design 1 8 8 8 8 Thermal Comfort, Verification 1 9 9 9 9 Daylight & Views 1-2 2 2 2 2 Innovation in Design 1-4 2 2 2 2 LEEDTM Accredited Professional 1 1 1 1 1 10|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 11. Project Management National Conference 2011 PMI India Design 7 CONCLUSIONS The study was carried out based on various green building construction projects in India and abroad. However emphasis was given in developing a risk modeling tool that can predict the overrun associated with duration and cost of Green Building. The survey results indicated that the majority of cost overrun factors (89%) lie in medium severity impact range. However these factors need to be attended as they tend to increase in the cost of the project compared to the initial estimation. Even though the likelihood of cost overrun for construction projects targeting green rating is high, minimum range of cost overrun in percentage of the estimated cost is found to be 8%. The highest risks were associated with Reduced Site Disturbance, Innovative Waste Water Technologies, Renewable Energy, Construction Waste Management, Indoor Chemical & Pollutant Source Control, and LEED Accredited Professional. Care and proper mitigation measures should therefore be taken while including the factors with lower rank in risk factors. 8 REFERENCES [1]. A Guide to the Project Management Body of Knowledge, Project Management Institute, 1996. [2]. Akintola S Akintoye and Malcolm J MacLeod(1997). “Risk analysis and management in construction” International Journal of Project Management Vol. 15, No. 1: 31-38, 1997. [3]. Alfredo del Can,and M. Pilar de la Cruz(December 2002). “Integrated Methodology for Project Risk Management” Journal of Construction Engineering and Management, ASCE: 473-485 . [4]. Artem Aleshin.(2001) “Risk management of international projects in Russia.” International Journal of Project Management Vol. 19: 207-222. [5]. Bing, L., Tiong, R. L. K., Wong, W. F., and Chow, D.(1999) “Risk management of international construction joint ventures.” Journal of Construction Engineering and Management, ASCE, 125(4): 277–284. 11|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 12. Project Management National Conference 2011 PMI India [6]. Darrin and Mervyn K Lewis.(2002) “Evaluating the risks of public private partnerships for infrastructure projects.” International Journal of Project Management: 107-118. [7]. Daud Nasir, Brenda McCabe and Loesie Hartono(October, 2003) “Evaluating Risk in Construction–Schedule Model (ERIC–S) Construction Schedule Risk Model.” Journal of Construction Engineering and Management, ASCE, Vol. 129, No. 5: 518-527. [8]. El-Diraby.T. A and Gill S. M. (March 2006) “A Taxonomy For Construction Terms In Privatized Infrastructure Finance, Supporting Semantic Exchange Of Project Risk Information.” Construction Management and Economics: 271–285. [9]. Eric Verzuh.(2005) “The Fast Forward MBA in Project Management” Wiley – 2nd Edn:105-109. [10]. Garg.A.K.(February 2005) “Risk Management In Construction Contacts” Construction Materials Purchase: 14-16. [11]. Gregory H. Kats. “Green Building Costs and Financial Benefits.” [12]. Narendra D. Patel and Nikesh P. Shah.(September 2007) “Green housing – Review, Rating Systems And Implementation.” The Indian Concrete Journal. [13]. B. Mulholland and J. Christian(January/February 1999) “Risk Assessment In Construction Schedules.” Journal Of Construction Engineering And Management [14]. Archibald, R. D, and Lichtenberg(1994) “Uncertainty And Change Require A New Management Model.” Pm Network, VIII(5): 6–10. [15]. Birrell, G. S.(1983) “Construction Planning—Beyond The Critical Path.” J. Constr. Div., ASCE, 106: 389–407. [16]. Cooper, K. G.(1994) “The $2,000 hour: How Managers Influence Project Performance Through The Rework Cycle.’’ PM J., XXV(1): 11–24. [17]. Cowie, G. F., and Carr, J. P. (1984) “Discussion Of Integrated Project And Process Management”, Constr. Engrg. And Mgmt, ASCE, 110: 121– 122. 12|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 13. Project Management National Conference 2011 PMI India [18]. “LEED reference guide, Version 1.0.” Indian Green Building Council(2001). [19]. “International Initiative for Sustainable Built Environment.” Advanced Building News. ABN2(2004). [20]. “White Paper On Sustainability: A Report On The Green Building Movement.” Supplement To The Building Design & Construction, (November 2003). [21]. Cole, R.(2001). “A building environmental assessment method for British Columbia.” Final report to BC Green Buildings Ad-Hoc Committee. (www.buildsmart.ca/pdfs/ASSESSMENT%20REPORT.PDF). [22]. “Building momentum: National Trends And Prospects For High Performance Green Buildings” U.S. Green Building Council, Baltimore (2002). 9 AUTHOR’S PROFILE: S.Lakshmi Narayanan, is working in the Strategy & Business Development department of Shapoorji Pallonji & Co. Ltd in New Delhi. His areas of interests include International project management, Green Construction & Green Supply Chain Optimization. He is also an author of 2 International journal papers specifically relating to overruns. He also reviews for reputed international journals like journal of supercomputing, Inderscience etc. lniyer88@gmail.com 13|P a g e Application of Select Tools of Psychology for Effective Project Management