SlideShare a Scribd company logo
1 of 137
Download to read offline
R-1E-1 MV-2 V-1 MV-3
SYNTHESIS SECTION
SAIPEM PROCESS
PRESENTED BY
Prem Baboo
National fertilizers Ltd. India.
An Expert for
www.ureaknowhow.com
Fellow of Institution of Engineers
India.
Plant & Equipment's Designer
R-1E-1 MV-2 V-1 MV-3
2
POINTS TO DISCUSS
START UP
SHUT DOWN
TROUBLE SHOOTINGS
R-1E-1 MV-2 V-1 MV-3
3
Initial start up
Cold start up
Hot start up
Start Up
R-1E-1 MV-2 V-1 MV-3
4
Start Up
Initial start up means:
– All the sections are depressurized and /or without process
fluids.
Cold start up means:
– All the sections are pressurized with process fluids but HP
Reactor is empty and HP loop depressurized.
Hot start up means:
– All the sections are pressurized with process fluids and HP
Reactor is full and HP loop pressurized.
R-1E-1 MV-2 V-1 MV-3
5
START UP
CLEARANCE TO BE TAKEN FROM
1. MECHANICAL
2. ELECTRICAL
3. INSTRUMENT
CLEARANCE TO BE TAKEN FROM
1. AMMONIA-II
2. UREA-I
R-1E-1 MV-2 V-1 MV-3
6
Start Up With Empty Reactor
General
During this phase it has been assumed that all pre-
start operations have been completed together with
Mechanical check of the unit.
R-1E-1 MV-2 V-1 MV-3
7
Sealing Tests Of All Sections
Purpose
– To eliminate leaks, if any, before charging process
fluids.
R-1E-1 MV-2 V-1 MV-3
8
Sealing Test
Fluid
– Steam condensate.
Temperature
– Ambient (cold test)
Pressure
– Operating value
R-1E-1 MV-2 V-1 MV-3
9
Sealing Test Conceptual Procedure
Admit the fluid from the lowest points and keep the
vent at highest points opened.
Slowly increase the pressure to the test value.
Check all flanges and connections in order to identify
leaks and eliminate them.
If the pressure does not fall appreciably after 4 hours
the test can be considered satisfactory, otherwise it
will be necessary to look and to eliminate them and
then repeat the test.
R-1E-1 MV-2 V-1 MV-3
10
Very Important
Keep the highest point vents in open position
during section emptying
Reactor draining to be started after completion
of draining of Carbamate condenser. This is to
avoid bulging of reactor lining.
R-1E-1 MV-2 V-1 MV-3
11
Purging By N2 Of M.P. & L.P.Sections
Purpose
This operation must be carried out before
plant start-up in order to remove all the O2
present, avoiding any risk of explosive mixture
formation during ammonia charging.
R-1E-1 MV-2 V-1 MV-3
12
Purging By N2 - Conceptual Procedure
Admit Nitrogen keeping the pressure
controller in automatic mode.
When N2 comes out from drain close block
valves.
Depressurize the system up to positive
pressure of about 0.5 kg/cm2
Analyze the gas outlet. If O2 content is 0.1% by
vol. The purging is performed.
R-1E-1 MV-2 V-1 MV-3
13
Charging of Ammonia in MP Section
Purpose
To have a make-up of NH3 (Raw material)
Pressurize the M.P.section
Test H.P.NH3 pump
Ammoniation
R-1E-1 MV-2 V-1 MV-3
14
Ammonia Solution Preparation in V-3
Purpose
Preparation of L.P.section to receive process
fluid
The concentration of NH3 in V-3 solution is
about 30%
R-1E-1 MV-2 V-1 MV-3
15
Plant Heating Before Start Up
Purpose
Whenever start-up is to be performed with the unit empty
and at ambient temperature the equipment shall be
previously heated in order to bring them to the best
conditions to feed the process fluids to the above
equipment.
This is to avoid:
Thermal stresses on the material
Possibility of crystallization of products in cold piping and walls
R-1E-1 MV-2 V-1 MV-3
16
Plant Heating Before Start Up
The section of High pressure synthesis shall be
heated up to the temperature of 150 ~ 160°C
before introducing the process fluids.
Important
The heating rate shall never exceed the values
recommended by the equipment manufacturers (~
30°C/hr)
R-1E-1 MV-2 V-1 MV-3
17
Conditions Before Ammoniation
CO2 compressor ready to be started with high
pressure line heated up.
Compressor will be put in running before
Ammoniation period.
High pressure pumps ready to be started.
High pressure section heated up and ready for
Ammoniation
R-1E-1 MV-2 V-1 MV-3
18
Conditions Before Ammoniation
M.P. section charged and pressurized by ammonia with NH3
booster pump running in closed recycle to Ammonia
receiver.
L.P. section charged with NH3 solution and M.P. carbonate
solution pump(P-3) running in circulation to Carbonate
receiver(V-3) through M.P. Absorber.
Vacuum section ready to be taken in line.
Prilling system ready to be started
Waste water section in running condition.
R-1E-1 MV-2 V-1 MV-3
19
Ammoniation
Purpose
To reach the best conditions to start the reactions
inside the reactor.
Conceptual procedure
It consists in the pressurization of H.P.loop with
ammonia vapors up to 90 kg/cm2
The “Ammoniation” operation requires about 3 hours
and then the unit can be fed by NH3 and CO2 to Urea
Reactor.
R-1E-1 MV-2 V-1 MV-3
20
Ammoniation
The main steps are:
1. Start the pressurization of the Synthesis
system by sending NH3 via Ammonia booster
(P-5) to Start-up line, leaving opened the
suction and delivery valves of H.P.Ammonia
pump (P-1).the NH3 is vaporized in the jacket
line.
2. Control that the NH3 vapor temp is over
140°C.
R-1E-1 MV-2 V-1 MV-3
21
Ammoniation
3. When the H.P.system reaches the value of
Booster pump delivery pressure, start the
H.P.Ammonia pump(P-1) in recycle to
Ammonia Receiver (By opening the relevant
valves) and adjust the ammonia rate by
feeding a small flow to start-up line, so to
gradually increase the pressure of the system
up to about 90 kg/cm2g.
R-1E-1 MV-2 V-1 MV-3
22
Ammoniation
4. When the set value of pressure is reached (90kg/cm2),stop
NH3 feeding to Start-up line by closing the inlet valves and
simultaneously stop P1pump then proceed to close steam
to jacket of start-up line and wash this line by KW for a few
minutes.
5. The speed of pressure increasing on H.P.section (PIC-7)
has to be maintained at 30 kg/cm2 / hour to arrive at the
set of 90 kg/cm2g.
R-1E-1 MV-2 V-1 MV-3
23
Plant Preparation for Start Up
(section by section)
M.P. & L.P. section preparation
Ammonia has been fed into NH3 receiver and
both sections (M.P. & L.P.section) are
pressurized with ammonia vapors at 15
kg/cm2g and 3 kg/cm2g respectively.
MP carbonate solution pump (P-3) is running
with a weak ammonia solution in recycle to
Carbonate solution accumulator (via MP
condenser & MP absorber).
R-1E-1 MV-2 V-1 MV-3
24
Plant Preparation for Start Up
(section by section)
M.P. & L.P. section preparation
To increase the ammonia content into this
solution, feed a small reflux flow to MP
absorber keeping the MP carbonate solution
pump (P-3) running in recycle.
Stop the ammonia reflux to MP absorber (C-1)
top only when the Carbonate solution
accumulator analysis indicates an ammonia
content of 35% by wt.
R-1E-1 MV-2 V-1 MV-3
25
Plant Preparation for Start Up
(section by section)
M.P. & L.P. section preparation
Feed steam into shell sides of the M.P. and
L.P.decomposers by opening the relevant
control valves of the 10 – 15 % and heat up
these equipment's by sending HW/LW at the
inlet. Keep a level on the M.P. & L.P.
decomposer holders.
Put the steam tracing in service in all the
process lines.
R-1E-1 MV-2 V-1 MV-3
26
Plant Preparation for Start Up
(section by section)
Vacuum evaporation section
The evaporation section is to be put in water
recirculation to the urea solution tank via
vacuum concentrator/separator/urea solution
pump (P-8).
R-1E-1 MV-2 V-1 MV-3
27
Plant Preparation for Start Up
(section by section)
Process water treatment section
The process water treatment section is running
water that from distillation tower (C-2)
R-1E-1 MV-2 V-1 MV-3
28
Plant Preparation for Start Up
(section by section)
CO2 compressor and passivation air system
Start and load the CO2 compressor and stabilize it
venting the CO2 to the atmosphere from final
discharge vent (pressure control valve) in auto.
Open the passivation air flow and put in service
the O2 analyzer.
R-1E-1 MV-2 V-1 MV-3
29
Initial Start Up (Feed in)
Following action to be taken for Feed in
– Send condensate to Reactor for 10 minutes.
– Feed NH3 for about 15 minutes.
– Feed CO2 to Reactor
– Feed Carbamate at Reactor overflow
– Start passivation air injection (K-3)
– Parameter stabilization and production started
R-1E-1 MV-2 V-1 MV-3
30
NH3 and CO2 Feed in
Send condensate to
– Reactor (R-1)
– Carbamate condenser (E-5)
for about 10 minutes by means of H.P. flushing pump (KW
injection points) and after that close the valves and close
HV1(CO2 to R1).
The NH3 present in the Reactor dissolves in the water
releasing heat and causing a temperature increase at the
Reactor bottom.
R-1E-1 MV-2 V-1 MV-3
31
NH3 and CO2 Feed in
When the NH3 & H2O solution reaches the saturation and
this is shown by Reactor bottom temperature that stops to
increase (After about 10 minutes), proceed to open block
valve and motorized valve on NH3 discharge line and close
Carbonate recycle valve from H.P. Separator.
Then start feeding Ammonia to the Reactor. The NH3
feeding flow rate must be about 50 rpm of P-1 ammonia
feed pump.
R-1E-1 MV-2 V-1 MV-3
32
NH3 and CO2 Feed in
After about 10 minutes from introduction of
NH3,proceed to open the valves on CO2 to Reactor,
controlling the reactor bottom temperature.
Before feeding CO2 to Reactor, be sure to inject the
passivation air in CO2 stream
R-1E-1 MV-2 V-1 MV-3
33
NH3 and CO2 Feed in
At the overflow (after about 2 hours since reactor
feed in) of the reactor,
– open Carbamate recycle valve HV-2 from H.P. Separator,
– start sending the H.P.Carbamate solution to the
Carbamate condenser by opening the relevant valves
(HV-6).
– Monitor pump amperage
(pump P-2 already running in circulation to C-1).
R-1E-1 MV-2 V-1 MV-3
34
NH3 and CO2 Feed in
At reactor overflow,
start opening the motorized valve (HV-5) at
Stripper outlet line and regulate the stripper level
controller (LV-2) in Manual mode.
On manual mode adjust the opening of the MS
steam pressure control valve (PV-14) admitting
steam to shell side of Stripper, checking that the
bottom temperature never exceeds 207°C.
R-1E-1 MV-2 V-1 MV-3
35
NH3 and CO2 Feed in
The bottom pressure and temperature of reactor
shall be increased and maintained at about 179°C
and 155~160 kg/cm2. respectively.
As a corrective action the flow rates of NH3 and CO2
can be reduced or increased in order to adjust
temperature and pressure of reactor.
R-1E-1 MV-2 V-1 MV-3
36
NH3 and CO2 Feed in
Temperature increase:
– The NH3/CO2 ratio is decreasing, with consequent
pressure reduction in the system, it is necessary to
increase NH3.
Temperature decrease:
– The NH3/CO2 ratio is increasing, the pressure will
tend to rise, it is necessary to decrease NH3 or
increase CO2.
R-1E-1 MV-2 V-1 MV-3
37
NH3 and CO2 Feed in
As a guide, the weight ratio NH3/CO2 to
reactor should be around 1.15~1.2 during this
phase.
The M.P. section is going to receive urea
solution.
R-1E-1 MV-2 V-1 MV-3
38
M.P./L.P. sections going to receive urea
solution
As soon as urea from R-1 enters the E-1, a decrease
in steam pressure in the shell will be noticed.
Adjust the MS flow to E-1 according to E-1 bottom
temperature.
Feed Carbamate to R-1
Urea solution from E-1 bottom passes to MP
decomposer, then to LP decomposer and initially
to V-5 ( after stabilization, passes to vacuum
section).
R-1E-1 MV-2 V-1 MV-3
39
Slightly open manually FV-102 sending NH3 to the
top of the C-1 and keep recirculation of carbonate
solution from V-3 to C-1 controlling bottom level
and temperature.
Send condensate to top of C-3 so as to absorb NH3
present in the inert gas when level is established
at the E-11 bottom start P-7 and send sol. to C-1
and control the level.
M.P./L.P. sections going to receive urea
solution
R-1E-1 MV-2 V-1 MV-3
40
Maintain MP/ LP urea holder temperature
Maintain MP /LP section pressure By putting PIC-
108 / PIC-133 on auto mode
Pre concentrator level and start the pump
Preconcentrator pump(P-50) and ww water
pump(P-52).Vacuum ejectors also to be taken in
line
M.P./L.P. sections going to receive urea
solution
R-1E-1 MV-2 V-1 MV-3
41
NH3 and CO2 Feed in
H.P. loop heating (including hot
bolting)
5 to 8 hours
Condensate draining before
pressurization
½ hour
Pressurization with NH3 Via start
up line
3½ hours
NH3 and CO2 to reactor until
overflow occurs
2 to 3 hours
Stabilization of running condition 1 hour
UREA REACTOR AND HP SEPERATOR
STRIPPER AND HP CONDENSER
AMMONIA START UP LINE
HIC4
MP DECOMPOSER & AMMONIA ABSORBER
R-1E-1 MV-2 V-1 MV-3
46
R-1E-1 MV-2 V-1 MV-3
R-1E-1 MV-2 V-1 MV-3
48
R-1E-1 MV-2 V-1 MV-3
49
R-1E-1 MV-2 V-1 MV-3
50
AMMONIA RECEIVER
LP SECTION
R-1E-1 MV-2 V-1 MV-3
53
Shut Down
Flushing
Short shut down
Long shut down
Emergency shutdown
R-1E-1 MV-2 V-1 MV-3
54
Flushing system
Urea plant shutdown main hazard is choking
First and foremost priority is proper flushing
of the lines and vessels.
There are three tier flushing system
– High pressure system
– Medium pressure system
– Low pressure system
R-1E-1 MV-2 V-1 MV-3
55
HP Flushing system
Pump is a reciprocating one (P-11). It takes suction
from medium pressure pump discharge and
discharge water to different high pressure loop
washing point.
Before starting KW washing, the pump discharge
pressure has to be set at 30Kg/cm2 more than that
of high pressure loop pressure.
R-1E-1 MV-2 V-1 MV-3
56
HP Flushing system
Before injecting flushing water confirm V-2 temp
>60-70oC and drain the water first to make the
flowing water hot.
Close the drain tightly and inject water.
Check the KW pressure.
Check if pressure has dropped or not. If pressure
has dropped that means line is clear.
R-1E-1 MV-2 V-1 MV-3
57
HP Flushing system
If pressure has not dropped it means flushing has
not taken place.
De-choke the line immediately and then do the
flushing.
During HP loop flushing remember one thing
– Do not open water simultaneously at numerous points.
– Do flushing at one point at a time.
R-1E-1 MV-2 V-1 MV-3
58
MP Flushing system
Pressure 36 kg.cm2 – a centrifugal pump(P-6).
Water goes to :
– MP section,
– PV-07A D/S pipe
– HV-05 D/S pipe
– P-3 discharge
– P-2 suction
– P-8 discharge
R-1E-1 MV-2 V-1 MV-3
59
LP Flushing system
Normally low pressure flushing pump (P-10) is
always in line. it is a centrifugal pump with
discharge pressure 15 kg/cm2.
Water goes to:
– LP section, Vacuum section, C-2 and LTs’ flushing.
Remember P-8 discharge is having MP flushing.
R-1E-1 MV-2 V-1 MV-3
60
Plant shutdown
1. Short shutdown means:
– HP loop hold up.
2. Long shutdown means:
– Necessitating HP loop draining.
3. Emergency shutdown
– Due to power failure.
– Due to cooling water failure.
– Due to instrument air failure.
– Due to steam failure.
R-1E-1 MV-2 V-1 MV-3
61
Short Shutdown Procedure
As soon as CO2 compressor trips HV-1 gets closed.PV-03
gets open. Close HV-08 and its I/V.
If P-1 pump has not tripped, give Ammonia to Reactor for
10 minutes then stop P-1.
Close HV-7 and I/V after P-1 has stopped.
Close 2nd discharge valve of P-1A or B (which ever is in
line).
Close HV-2.
Stop P-2 (Carbamate pump).
Close HV-6 & its I/V. Open FV-34.
R-1E-1 MV-2 V-1 MV-3
62
Short Shutdown Procedure
Close PV-7A (if pressure is not getting hold, close
its I/V ).
Close LV-02 & HV-05 after bringing down stripper
level to minimum.
Increase HV-03 opening.
Check P-10, P-6, P-11 (flushing pumps) are
running.
– P-11 discharge pressure 170Kg/cm2.
R-1E-1 MV-2 V-1 MV-3
63
Short Shutdown Procedure
Divert prilling to V-5 via HV-132.immediately
after feed cut .
Open PIC-140 & 141 first & second vacuum
pressure control valves.
Divert ME-3 to E-14 (HV-140) towards V-5.
Open LP flushing water at E-14 inlet.
Open HW at P-8 discharge to displace the Urea
solution in the vertical line.
R-1E-1 MV-2 V-1 MV-3
64
Short Shutdown Procedure
Run P-8 on water for at least 5min. on load.
Be careful enough so that LV-138 at P-8 discharge
should not get closed fully.
P-8 discharge is not having any NRV so that hold
up solution in the vertical line gets drained to MV-7
easily if LV-138 is open.
R-1E-1 MV-2 V-1 MV-3
65
Short Shutdown Procedure
Close ME-2 level control valve after ME-2 level is minimum.
Check C-1 level. If required drain to V-3 via HV-102. Close
LIC-102.
Reduce pure Ammonia reflux to C-1 according to the temp.
of C-1 top.
Open P-3 recycle valve so that P-3 can have enough recycle
flow as auto recycle valve is not there.
R-1E-1 MV-2 V-1 MV-3
66
Short Shutdown Procedure
Wash CO2 line towards reactor. Check KW pressure has
reduced to confirm flushing.
Check physically that HV-1 has opened in field during
flushing.
Flush ammonia line D/S of HV-7 to reactor.
Flush HV-2 up stream & down stream.
Flush LV-2 towards E-1 through the flushing line between
LV-2 & HV-5. Then flush through HV-5 by closing LV-2.
R-1E-1 MV-2 V-1 MV-3
67
Short Shutdown Procedure
Flush PV-07A open KW between I/V & control valve.
Flush towards MV-1 then flush through PV-7A by closing
isolation valve & opening PV-7A.
After flushing close PV-7A control valve.
Flush HV-6 towards E-5 (Carbamate condenser) by opening
isolation valve of HV06.
Flush P-2 discharge line down stream of NRV with KW.
First flush through FV-34 then close FV-34. Let the line get
pressurized open HV-6 check pressure has come down to
confirm flushing to E-5.
R-1E-1 MV-2 V-1 MV-3
68
Short Shutdown Procedure
Open HW (MP flushing water) to LV-101 up stream & down stream.
Open HW to MV-2 from HV-5 D/S.
Open HW to PV-7A D/S.
Open HW in P-3 discharge & flush through LIC-102 to E-7.
Flush HIC-102 line if C-1 draining is over.
Open LW (LP flushing water) through ME-3 down stream line to V-5.
Open HW in C-1 to P-2 line.
Flush P-2 (Carbamate pump) from suction thoroughly. Check in open
drain that water is clear of Carbamate.
R-1E-1 MV-2 V-1 MV-3
69
Short Shutdown Procedure
Flush and fill MV-8 (CO2 discharge drum) thoroughly after
de-pressurizing vessel.
Reduce the steam to stripper, MP & LP decomposer.
Close PV-14, TIC-102 & its by-pass, TIC-131 & LV-03.
Shut the reflux to C-1.
Stop condensate to C-3 & C-4.
Stop P-7 after E-11 level is minimum.
R-1E-1 MV-2 V-1 MV-3
70
Short Shutdown Procedure
PLEASE REMEMBER :
Open KW only one point at a time.
Confirm KW flushing by checking reduction in KW
pressure.
Close the process isolation valve first & then the
water injection valve.
HW & LW can be opened at various point
simultaneously.
R-1E-1 MV-2 V-1 MV-3
71
Long Shutdown Procedure
(HP loop draining)
IF SHUTDOWN IS PRE-PLANNED
– CHECK R-1 DRAIN LINE PRIOR TO FEED CUT.
Checking of R-1 drain line
Check KW pressure is about 180Kg/cm2.
Inject KW through R-1 drain line injection towards HV-4.
Be careful that R-1 open drain & close drain valves are tightly closed.
Open HV-4 & let KW to flow through HV-4 & HV-5 towards MV-2.
Check KW pressure has dropped to about 50Kg/cm2 to confirm drain
line is clear.
R-1E-1 MV-2 V-1 MV-3
72
Long Shutdown Procedure
(HP loop draining)
If pressure has not dropped, line is in choked condition.
Do external steam heating U/S of HV-4.
Do pressurization & de-pressurization of line up to HV-4
repeatedly by keeping HV-4 close.
Check again if drain line has got cleared in the previous
method.
If drain line is clear, start reactor draining.
R-1E-1 MV-2 V-1 MV-3
73
Long Shutdown Procedure
(HP loop draining)
Keep the following valves conditions as follows;
I/Vs of HV-6,HV-7and HV-8 close
LV-2 close.
HV-2 close
LV-3 ~10% open.
I/V of HV-102 open.
PV-7A I/V close.
HV-140 and its I/V open.
R-1E-1 MV-2 V-1 MV-3
74
Long Shutdown Procedure
(HP loop draining)
Open Reactor drain I/V towards HV-4.
Open HV-4 & HV-5.
Open HV-1 (HV-1 inter lock to be by-passed from I-
1 on ESD)
Feel the sound of flow.
R-1E-1 MV-2 V-1 MV-3
75
Long Shutdown Procedure
(HP loop draining)
Check level has come in ME-2 in Control Room &
physically in side glass.
Control the Reactor draining rate to MP section
using HIC-4 & HIC-1.
R-1E-1 MV-2 V-1 MV-3
76
Long Shutdown Procedure
(HP loop draining)
Maintain Ammonia reflux to C-1 from P-5 to
maintain C-1 temperature.
Maintain E-7 outlet temp. with LIC-102 minimum
30% open & with TIC-101 on auto.
Maintain C-1 level by draining through HIC-102
to V-3.
R-1E-1 MV-2 V-1 MV-3
77
Long Shutdown Procedure
(HP loop draining)
Use greater amount of steam to E-2 without over
loading C-1 so that to recover a greater amount of
Ammonia to V-1.
Check pressure drop is at a rate not more than
30Kg/cm2 per hour.
R-1E-1 MV-2 V-1 MV-3
78
The temperature and pressure decline in the
synthesis system is controlled by adjusting the
reactor drain rate. The adjustment is made with
HIC-4 on manual control.
Long Shutdown Procedure
(HP loop draining)
R-1E-1 MV-2 V-1 MV-3
79
Check the temperature in the low pressure
decomposer in view of getting the maximum
concentration of urea solution and avoiding and
excessive quantity of ammonia being delivered to
the vacuum concentration system.
Long Shutdown Procedure
(HP loop draining)
R-1E-1 MV-2 V-1 MV-3
80
Long Shutdown Procedure
(HP loop draining)
When no solution is coming out from reactor at a pressure
of about ~40Kg/cm2 drain Carbamate condenser to MV-2
through HV-4.
Open HIC-2 and drain MV-1 to MV-2 thru’ HV-4
After feed cut and before depressurization of HP loop close
air to reactor weep holes
Confirm that draining is over, when LV-101 & LV-131 gets
almost closed.
R-1E-1 MV-2 V-1 MV-3
81
Long Shutdown Procedure
(HP Loop Draining)
When the synthesis loop pressure and the pressure of the
medium pressure section are equal:
Cut HP loop from MP by closing HV-1, HV-4, HV-5. and wash
all lines and equipment of the high pressure section
draining to the closed drain.
Start depressurization of HP loop to BD header through PV-
7B.
Shut the steam to the decomposers, open the washing on
the outlet line bottom solution stripper, bottom
decomposer M.P. and L.P. and flush together with 2
decomposers.
R-1E-1 MV-2 V-1 MV-3
82
Long Shutdown Procedure
(HP loop draining)
Close the delivery valve and stop P-3A/B.
Stop NH3 at the top of C-1 by FIC-102 in manual
control.
R-1E-1 MV-2 V-1 MV-3
83
Long Shutdown Procedure
(HP loop draining)
Stop the ammonia booster pump and close the suction and
delivery valves.
Send washing water to the top of C-1 for few minutes.
Drain the liquid of the C-1 to the carbonate tank through
HV-102 when washing is finished. Shut off the water and
drain the column to the closed drain.
Isolate the NH3 tank and absorber from the other medium
pressure equipment, leaving the pressure control in
automatic position.
R-1E-1 MV-2 V-1 MV-3
84
Long Shutdown Procedure
(HP loop draining)
Gradually depressurize the absorption column and the
medium pressure decomposer through LV-101.
Take care not to pressurize the low pressure decomposer.
Shut the steam to the decomposers E-3.
Isolate the carbonate tank V-3 from C-1 leaving pressure
controller PRC-133 on auto.
Dilute MP condenser E-7 and condenser E-11 solutions and
drain them out.
R-1E-1 MV-2 V-1 MV-3
85
Long Shutdown Procedure
(HP loop draining)
Stop the vacuum section circulation after MV-7 level comes
to minimum & after confirming proper flushing and PIC-
140 & 141 open.
Stop flushing water to E-14 & other points.
Cut steams to E-14 & E-15.
Cut the condensate outlet to condensate tank.
Cut steam to ejectors.
Cut cooling water to condensers, if required.
Stop V-9 transfer to V-6 by stopping P-21, if required.
R-1E-1 MV-2 V-1 MV-3
86
Long Shutdown Procedure
(HP loop draining)
After depressurization and close draining of HP loop is over
open LP steam to reactor for 3-4 hrs.
Cut steam to reactor/HP loop.
Open MP washing water to HP loop through 3” quick filling
line at reactor bottom with HV-1 open PV-7B open, HV-3
sample point drain open and HV-2 close.
Filling completion of reactor is indicated by water coming
out from HV-3 sample point, close it.
Filling completion of HP loop total is indicated by rise in
PV-7B pressure.
R-1E-1 MV-2 V-1 MV-3
87
Long Shutdown Procedure
(HP loop draining)
If vessel man entry is to be permitted then overflow HP
loop through PV-7B for 7-8 hrs. Other wise 3-4 hrs
overflow will do.
Stop filling water, start draining HP loop from E-1 drain,
from LV-2 sample point drain, from E-5 sample point drain
& HV-3 sample point drain.
When water stops coming out from HV-3 sample point
drain, open reactor drain through HV-1 I/V gradually to full
open condition.
Total draining normally takes 8-10 hrs.
R-1E-1 MV-2 V-1 MV-3
88
Long Shutdown Procedure
(HP loop draining)
During HP loop draining, PV-7B should be open,
HV-2 should be close.
During filling of HP loop E-5 shell side should be
depressurized & drained to enhance cooling.
Either steam circuit should be depressurized or all
tracing / jacket steam should be closed and
stripper shell side should be depressurized.
R-1E-1 MV-2 V-1 MV-3
89
Long Shutdown Procedure
(HP loop draining)
When water stops coming out from HV-3 sample
point reactor top manhole cover should be opened
to enhance draining & cooling.
When water stops coming out from HV-3 sample
point, HV-3 may be handed over to maintenance, if
required.
R-1E-1 MV-2 V-1 MV-3
90
Long Shutdown Procedure
(HP loop draining)
When water stops coming out from E-5 or
E-1 bottom drains, E-5 or E-1 may be
handed over.
During condensate draining smell the drain
water for ammonia to have an idea of
atmosphere inside HP loop vessels.
R-1E-1 MV-2 V-1 MV-3
91
EMERGENCY SHUT DOWN
The emergency situations which are likely to arise
are several and extremely variable as to duration
and seriousness.
R-1E-1 MV-2 V-1 MV-3
92
EMERGENCY SHUT DOWN
Principal causes:
1. Process reasons:
Considerable pressure and / or temperature increases
Pipe line clogging because of crystallization
2. Sudden failure of services
3. Fires, and / or ruptures with uncontrollable losses of
toxic gasses.
R-1E-1 MV-2 V-1 MV-3
93
EMERGENCY SHUT DOWN
Safety interlocks
Based on the above emergency causes, an interlock
trip system has been provided for the protection of
personal and equipment initiating an automatic
shut down system
R-1E-1 MV-2 V-1 MV-3
94
EMERGENCY SHUT DOWN
Safety interlocks
For point No. 3 (if occur) push buttons are
provided on urea desk to stop the principal
machines. The valves which isolate the synthesis
loop & NH3 to P-1will than be closed.
R-1E-1 MV-2 V-1 MV-3
95
The evaluation of the seriousness of an emergency
situation and there fore the decision of how to shut
the plant down is a matter of the operators’
experience. He should take prompt and corrective
action.
However, the inter lock system is designed to
minimize the number of manual operations.
EMERGENCY SHUT DOWN
R-1E-1 MV-2 V-1 MV-3
96
Should the point no. 1 occur lines and equipment
should be washed, the trip causes eliminated
EMERGENCY SHUT DOWN
R-1E-1 MV-2 V-1 MV-3
97
Electric Failure
Should a total failure of electric power occur,
the CO2 compressor and all the pumps of the
unit will stop.
In this case restart the plant, locally starting
up the machines not re-accelerated.
R-1E-1 MV-2 V-1 MV-3
98
Electric Failure
If on the contrary, the power failure is more
than momentary, only the pumps of
emergency network will restart automatically.
But, in this case, the cooling water will be
missing and, as a consequence a pressure
increase will occur in the medium and low
pressure sections and vacuum will be lost in
the evaporation section.
R-1E-1 MV-2 V-1 MV-3
99
Electric Failure
Then the plant must be stopped following the
instructions shown here under. Introduce
washing water to the following points :
Introduce washing water to the following
points :
1. Inlet to the concentrator E-14.
2. Bottom outlet stripper and outlet of the medium
and low pressure decomposers.
3. P-3A/B delivery line and C-1 trays.
R-1E-1 MV-2 V-1 MV-3
100
4. High pressure Carbamate pump suction and
delivery lines.
5. CO2 and NH3 lines to reactor Carbamate to
ejector HV-2 (up streams and down stream).
Electric Failure
R-1E-1 MV-2 V-1 MV-3
101
Now proceed as described for normal
shutdown.
Electric Failure
R-1E-1 MV-2 V-1 MV-3
102
The plant uses steam at 23 kg/cm2g in
stripper E-1.
Failure of this service also involves the
failure of the condensate from the stripper
which feed the MP decomposer E-2 &
subsequently the Carbamate condensers
E-5.
Steam Failure
R-1E-1 MV-2 V-1 MV-3
103
The main plant and the ammonical water
treatment section should be shutdown since
there will be no steam production at
4.5kg/cm2g.
Steam Failure
R-1E-1 MV-2 V-1 MV-3
104
The main machines must immediately be
tripped :
1. CO2 compressor,
2. P-1A/B NH3pump, and
3. P-2A/B Carbamate pump.
Column C-1 shall be recycled to V-3 and
diluted, sending water to P-3A/B delivery
line. Wash and dilute all lines of the high
pressure section.
Steam Failure
R-1E-1 MV-2 V-1 MV-3
105
Wash the medium and low pressure
decomposers outlet lines to avoid
crystallizations.
Stop and dilute the vacuum evaporation
section following the procedure described
for normal shutdown.
Steam Failure
R-1E-1 MV-2 V-1 MV-3
106
The plant is thus in a safe shutdown
condition and ready to restart following the
usual restarting procedure, in case of steam
failure and/or long plant shutdown, it is
necessary to further dilute the solution
contained in tanks and apparatuses
recovering it as soon as the steam
availability is assured.
Steam Failure
R-1E-1 MV-2 V-1 MV-3
107
Cooling Water Failure
The plant equipment employing cooling
water. Principal users are:
– CO2 compressor (inter-stage cooler)
– Condensers , coolers and the pump coolers.
Lack of this service causes a pressure
increases in the medium and low pressure
system for lack of condensation in the
respective condensers and vacuum loss in
the vacuum evaporation section.
R-1E-1 MV-2 V-1 MV-3
108
Cooling Water Failure
Proceed as follows :
– Open E-41,E-9,E-7 top cooling water vents
– Stop feeding to the reactor. Trip compressor,
P-1,P-2 and all the pumps except for the washing
pumps must be stopped.
– Close LV-2,HV-5 and closing the steam valve
(PV-14) to the stripper
R-1E-1 MV-2 V-1 MV-3
109
Cooling Water Failure
– Close the steam valve to the E-2,E-3,to both
vacuum evaporators and to the column C-2 and
the ejectors.
– Send washing water to the delivery line of P-3A/B
to the trays of column C-1 to the condensers E-11
and E-8 absorb NH3 thus reducing the pressure,
Now, proceed as described for short shutdown.
R-1E-1 MV-2 V-1 MV-3
110
Instrument Air Failure
In case off instrument air failure, the control
valves assume such positions as to ensure
the plant safety without the immediate
intervention of the operators, who however,
must be will aware of the general view of
these positions.
R-1E-1 MV-2 V-1 MV-3
111
Instrument Air Failure
As soon as the instrument air is lacking, the
operator must switch to manual control all
instruments on DCS at zero signal position.
So that, when air gets in again, the valves do
not move.
R-1E-1 MV-2 V-1 MV-3
112
Instrument Air Failure
The synthesis loop gets blocked and
automatically is isolated from the rest of the
plant. Shutdown must be actuated following
the same procedure as That described for
the electric power failure.
R-1E-1 MV-2 V-1 MV-3
113
Important Checks
Communicate to the followings before S/D:
urea-I
Ammonia-II
Bagging
Check reverse rotation if any, for K-1.
Before shut down keep V-1, V-3 level at
minimum.
R-1E-1 MV-2 V-1 MV-3
114
Important Checks
Check both P-11 are available.
Keep P-11 running before feed cut.
Before shutdown R-1 drain line & E-5 drain
lines to be checked for any choking, clear
these lines if found choked.
Before shutdown HIC-102 line to be checked
for any choking, clear these lines if found
choked
R-1E-1 MV-2 V-1 MV-3
115
Important Checks
After shutdown do proper flushing of HP, MP
& LP lines.
After S/D do proper flushing of vacuum
section with LW at E-14, P-8 circulation.
Confirm P-8 is taking load. Double confirm
vacuum section flushing.
R-1E-1 MV-2 V-1 MV-3
116
Important Checks
After feed cut and before depressurization of
HP loop close air to reactor weep holes.
R-1E-1 MV-2 V-1 MV-3
117
Important Checks
Keep close check on P-33 level.
Put a fire hose without coupling in R-1 drain
line. Closely monitor B/L analysis.
Isolate MV-8 and depressurize MV-8 after
compressor tripping. Flush MV-8.
R-1E-1 MV-2 V-1 MV-3
118
Depressurize MP loop
– E-9 should be kept isolated from V-1.
– MV-2, E-7, C-1 & E-9 through 2” BD header on
C-1.
– HP loop should be kept isolated from MP loop.
– Steam / MP steam condensate should be cut to
E-2.
MP Loop Hand Over
R-1E-1 MV-2 V-1 MV-3
119
After depressurization is complete start filling
water from bottom of vessels with C-1 BD
header valve open and also open vent
isolation valve on MV-2 vapor line open.
When water starts coming out from MV-2
vent & C-1 BD header let the overflow
continue till the water gets almost clear of
ammonia or for 1-2 hrs.
MP Loop Hand Over
R-1E-1 MV-2 V-1 MV-3
120
Then stop filling and start draining from all drain
points.
BD vent and open to atmosphere vent should be
open during draining.
After the draining is over the MP loop vessels barring
V-1, E-11 & C-3 can be handed over for opening to
maintenance.
Cooling water to E-7 and E-9 should be cut only
after depressurization is completed.
MP Loop Hand Over
R-1E-1 MV-2 V-1 MV-3
121
V-1 should be tightly isolated from rest MP
loop before MV-2 to E-9 depressurization.
Continue vaporizing ammonia till P-5 is
taking load.
Stop P-5 when V-1 is empty. Close P-5
discharge valve tightly.
V-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
122
E-11 cooling water should be open during
depressurization.
Open close drain of V-1 & C-3/E-11.
Simultaneously depressurize V-1, C-3/E-11
through PV-108 to BD header.
When depressurization is completed, start
filling water to V-1, C-3/E-11.
V-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
123
PV-108 should be open full during filling.
Allow the water to over flow through PV-108
for some time.
Stop filling, start draining through all drains
including P-5 suction strainer flange.
After draining is completed, V-1& C-3/E-11
can be handed over to maintenance for
opening.
V-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
124
Keep V-3 level minimum before feed cut.
After reactor draining through MP & LP is over, flush
the LP section thoroughly.
Isolate V-3 from E-8(liquid & vapor line both) if V-3 is
not to be opened.
Depressurize and drain ME-3-E-3-MV-3 & E-8
completely through the open to atmosphere vent.
Fill flush overflow & drain the system.
During draining vent should be confirmed to be open
to atmosphere.
L P Loop Handing Over
R-1E-1 MV-2 V-1 MV-3
125
E-1 Handing Over
After filling and draining twice check for
ammonia in E-1 drain and skin temperature.
While draining 2nd time give SWP to open
alternate bolts.
If NH3 in the drain sample in too high further
fill E-1 only and drain it.
R-1E-1 MV-2 V-1 MV-3
126
E-1 Handing Over
If NH3 is not there in drain sample give SWP
to open man holes HV-3, LV-2, E-1 LT
tapping /thermocouple are to be removed.
Put DM water hose at the top after E-1 top &
bottom cover is opened.
Put air hose at bottom through LV-2 after it
gets opened.
R-1E-1 MV-2 V-1 MV-3
127
Slip plate E-1 vapor line to E-5 (8” flange).
Check whether MV-4 has been
depressurized and drained.
E-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
128
For E-1 shell side pressure testing give SWP
to blind following points, check steam circuit
to MV-4 has been depressurized and
drained.
MS steam inlet flange -10”.
Condensate outlet flange to MV-4 -6”.
MV-4 balance line- 2”.
PSV-5 flange- 6”.
E-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
129
Check E-5 is isolated depressurized and
drained from shell side.
After filling tube side and draining E-5
second time with water check ammonia in
drain sample.
Check start-up line both E-1 side valves
closed.
E-1 vapor line to E-5 is also blinded.
E-5 Handing Over
R-1E-1 MV-2 V-1 MV-3
130
Confirm first steam system is in
depressurized condition.
Give SWP for blinds in following points.
1. Export condensate flange-4”
2. Import line NRV flange-2”
3. LG tapping – upper one LG auxiliaries should be
removed by instrumentation.
E-5 Handing Over
R-1E-1 MV-2 V-1 MV-3
131
4. Line from
1. MV-4 –6”
2. Steam outlet flange 2 no.-20”
5. PSV flanges
1. 2 no. –6”.
2. E-5 shell side drain one no. 3”
Total 8 blinds. LT tapping 2no.
E-5 Handing Over
R-1E-1 MV-2 V-1 MV-3
132
Lower LG tapping flange should be
connected with a flanged ½” nipple with
isolation valve for air injection.
Simultaneously give SWP to open E-5, ME-1
after confirming no ammonia in drain.
– E-5 manhole is to be opened.
– E-5 bottom and top flanges are to be gapped so
that air circulation can take place in E-5.
E-5 Handing Over
R-1E-1 MV-2 V-1 MV-3
133
As soon as HV-1, HV-2 are opened put air
hose through the gap in the reactor.
While giving SWP to open HV-1, HV-2 &
PRC-12.
R-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
134
Check –
1. R-1 open drains are in open condition.
2. R-1 CD are in closed position HV-4 close.
3. MV-8 is depressurized condition.
4. Confirm all the injections are closed.
5. Confirm P-11 is not running.
6. No water is coming out of HV-2 up stream
drain. Check HV-3 is removed
R-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
135
7. P-1 to HV-7 is in depressurized and flushed
condition.
8. HV-7 isolation valve is in closed condition.
9. P-1 discharge valve is in closed condition.
10. PV-7A isolation valve is in closed condition.
R-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
136
11. Tracing drains are open. Steam of circuit is
in depressurized condition.
12. Arrange to get R-1 top sample analyzed
with a blower and PVC piping arrangement.
R-1 Handing Over
R-1E-1 MV-2 V-1 MV-3
137
For any type of queries
Please contact to
Prem Baboo
Mob-+919425735974
+918718870316
Prem.baboo@nfl.co.in
pbaboo@hotmail.com

More Related Content

What's hot

Ammonia plant fundamentals
Ammonia plant fundamentalsAmmonia plant fundamentals
Ammonia plant fundamentalsPrem Baboo
 
urea processes - Copy.pptx
urea processes - Copy.pptxurea processes - Copy.pptx
urea processes - Copy.pptxArmaanKhan92
 
Ammonia synthesis converter
Ammonia synthesis converterAmmonia synthesis converter
Ammonia synthesis converterPrem Baboo
 
Various ammonia technology
Various ammonia technologyVarious ammonia technology
Various ammonia technologyPrem Baboo
 
4 b = 58 p 45 basic ur plant description 06.09.2021-1
4 b = 58 p  45 basic ur plant description 06.09.2021-14 b = 58 p  45 basic ur plant description 06.09.2021-1
4 b = 58 p 45 basic ur plant description 06.09.2021-1ameermudasar
 
Ammonia plant material balance
Ammonia plant material balanceAmmonia plant material balance
Ammonia plant material balancePrem Baboo
 
Urea production process
Urea production processUrea production process
Urea production processSHIKHA THAPA
 
SULFUR RECOVERY UNIT DESIGN
SULFUR RECOVERY UNIT DESIGNSULFUR RECOVERY UNIT DESIGN
SULFUR RECOVERY UNIT DESIGNTosin Orimoyegun
 
Urea Dust & Ammonia Emission Control Prill Tower Project at Al Bayroni
Urea Dust & Ammonia Emission Control Prill Tower Project at Al BayroniUrea Dust & Ammonia Emission Control Prill Tower Project at Al Bayroni
Urea Dust & Ammonia Emission Control Prill Tower Project at Al BayroniAli Akbar
 
Steam ejector working principle
Steam ejector working principleSteam ejector working principle
Steam ejector working principleKarnav Rana
 
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdfA case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdfPremBaboo4
 
Amm plant description
Amm plant descriptionAmm plant description
Amm plant descriptionameermudasar
 
AMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfAMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfPremBaboo4
 

What's hot (20)

Ammonia plant fundamentals
Ammonia plant fundamentalsAmmonia plant fundamentals
Ammonia plant fundamentals
 
urea processes - Copy.pptx
urea processes - Copy.pptxurea processes - Copy.pptx
urea processes - Copy.pptx
 
Ammonia plant
Ammonia plantAmmonia plant
Ammonia plant
 
Ammonia synthesis converter
Ammonia synthesis converterAmmonia synthesis converter
Ammonia synthesis converter
 
Various ammonia technology
Various ammonia technologyVarious ammonia technology
Various ammonia technology
 
4 b = 58 p 45 basic ur plant description 06.09.2021-1
4 b = 58 p  45 basic ur plant description 06.09.2021-14 b = 58 p  45 basic ur plant description 06.09.2021-1
4 b = 58 p 45 basic ur plant description 06.09.2021-1
 
Ammonia plant flowsheets
Ammonia plant flowsheetsAmmonia plant flowsheets
Ammonia plant flowsheets
 
Ammonia plant material balance
Ammonia plant material balanceAmmonia plant material balance
Ammonia plant material balance
 
Urea plant
Urea plantUrea plant
Urea plant
 
Urea plant NFL Intern report
Urea plant NFL Intern reportUrea plant NFL Intern report
Urea plant NFL Intern report
 
Urea production process
Urea production processUrea production process
Urea production process
 
SULFUR RECOVERY UNIT DESIGN
SULFUR RECOVERY UNIT DESIGNSULFUR RECOVERY UNIT DESIGN
SULFUR RECOVERY UNIT DESIGN
 
Urea Dust & Ammonia Emission Control Prill Tower Project at Al Bayroni
Urea Dust & Ammonia Emission Control Prill Tower Project at Al BayroniUrea Dust & Ammonia Emission Control Prill Tower Project at Al Bayroni
Urea Dust & Ammonia Emission Control Prill Tower Project at Al Bayroni
 
Kbr
KbrKbr
Kbr
 
Steam ejector working principle
Steam ejector working principleSteam ejector working principle
Steam ejector working principle
 
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdfA case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
A case study on Process Condensate Stripper in Ammonia Plant by Prem Baboo.pdf
 
Uhde ammonia
Uhde ammoniaUhde ammonia
Uhde ammonia
 
Amm plant description
Amm plant descriptionAmm plant description
Amm plant description
 
Urea 2000plus
Urea 2000plusUrea 2000plus
Urea 2000plus
 
AMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfAMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdf
 

Similar to Operation of urea fertilizers plant

new prentation.pptx
new prentation.pptxnew prentation.pptx
new prentation.pptxssuser1d6ff4
 
air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump) air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump) Rhitesh Gupta
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Manohar Tatwawadi
 
Presentation-api-521.ppt
Presentation-api-521.pptPresentation-api-521.ppt
Presentation-api-521.pptGowrishankar NS
 
POWER PLANT SIMULATOR 210 MW
POWER PLANT SIMULATOR 210 MW POWER PLANT SIMULATOR 210 MW
POWER PLANT SIMULATOR 210 MW Manohar Tatwawadi
 
Compressor fundamentals
Compressor fundamentalsCompressor fundamentals
Compressor fundamentalsPrem Baboo
 
Se prod thermo_chapter_2_compressor
Se prod thermo_chapter_2_compressorSe prod thermo_chapter_2_compressor
Se prod thermo_chapter_2_compressorVJTI Production
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineRAVI PAL SINGH
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdfyusuf699644
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdfMBouderbala
 

Similar to Operation of urea fertilizers plant (20)

new prentation.pptx
new prentation.pptxnew prentation.pptx
new prentation.pptx
 
air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump) air evacuation system and lrpv (liquid ring vacuum pump)
air evacuation system and lrpv (liquid ring vacuum pump)
 
Plant Air & Inst Air.ppt
Plant Air & Inst Air.pptPlant Air & Inst Air.ppt
Plant Air & Inst Air.ppt
 
Aircompressor unit 5
Aircompressor unit 5Aircompressor unit 5
Aircompressor unit 5
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
NFL Report.pdf
NFL Report.pdfNFL Report.pdf
NFL Report.pdf
 
Presentation-api-521.ppt
Presentation-api-521.pptPresentation-api-521.ppt
Presentation-api-521.ppt
 
steam_blowing.pdf
steam_blowing.pdfsteam_blowing.pdf
steam_blowing.pdf
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
POWER PLANT SIMULATOR 210 MW
POWER PLANT SIMULATOR 210 MW POWER PLANT SIMULATOR 210 MW
POWER PLANT SIMULATOR 210 MW
 
Compressor fundamentals
Compressor fundamentalsCompressor fundamentals
Compressor fundamentals
 
Se prod thermo_chapter_2_compressor
Se prod thermo_chapter_2_compressorSe prod thermo_chapter_2_compressor
Se prod thermo_chapter_2_compressor
 
Compressor
CompressorCompressor
Compressor
 
STEFFO REPORT
STEFFO REPORTSTEFFO REPORT
STEFFO REPORT
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
SPE-169923-MS
SPE-169923-MSSPE-169923-MS
SPE-169923-MS
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 

More from Prem Baboo

The explosion hazard in urea process (1)
The explosion hazard in urea process (1)The explosion hazard in urea process (1)
The explosion hazard in urea process (1)Prem Baboo
 
Urea process flow diagram
Urea process flow diagramUrea process flow diagram
Urea process flow diagramPrem Baboo
 
Materialtechnologyforfertilizersindustries
MaterialtechnologyforfertilizersindustriesMaterialtechnologyforfertilizersindustries
MaterialtechnologyforfertilizersindustriesPrem Baboo
 
Neemcoatedureaaphilosophyforenvironment
NeemcoatedureaaphilosophyforenvironmentNeemcoatedureaaphilosophyforenvironment
NeemcoatedureaaphilosophyforenvironmentPrem Baboo
 
Nano ureathephilosophyoffuture
Nano ureathephilosophyoffutureNano ureathephilosophyoffuture
Nano ureathephilosophyoffuturePrem Baboo
 
Installation of s 50 in ammonia plants
Installation of s 50 in ammonia plantsInstallation of s 50 in ammonia plants
Installation of s 50 in ammonia plantsPrem Baboo
 
Super conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency traysSuper conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency traysPrem Baboo
 
Sswi april may-2021_lowres
Sswi april may-2021_lowresSswi april may-2021_lowres
Sswi april may-2021_lowresPrem Baboo
 
Sweet and sour experience of commissioning 1
Sweet and sour experience of commissioning 1Sweet and sour experience of commissioning 1
Sweet and sour experience of commissioning 1Prem Baboo
 
How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...Prem Baboo
 
Experience of material in fertilizers industries
Experience of material in fertilizers industriesExperience of material in fertilizers industries
Experience of material in fertilizers industriesPrem Baboo
 
Fertilizers technology book
Fertilizers technology bookFertilizers technology book
Fertilizers technology bookPrem Baboo
 
High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)Prem Baboo
 
High pressure vessel leakage in urea plants
High pressure vessel leakage in urea plantsHigh pressure vessel leakage in urea plants
High pressure vessel leakage in urea plantsPrem Baboo
 
P & i diagram and tagging philosphy for
P & i diagram and tagging philosphy forP & i diagram and tagging philosphy for
P & i diagram and tagging philosphy forPrem Baboo
 
Ureaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsUreaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsPrem Baboo
 
5000 tpd urea mega plants design
5000 tpd urea  mega plants design5000 tpd urea  mega plants design
5000 tpd urea mega plants designPrem Baboo
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practicesPrem Baboo
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practicesPrem Baboo
 

More from Prem Baboo (20)

The explosion hazard in urea process (1)
The explosion hazard in urea process (1)The explosion hazard in urea process (1)
The explosion hazard in urea process (1)
 
Urea process flow diagram
Urea process flow diagramUrea process flow diagram
Urea process flow diagram
 
Materialtechnologyforfertilizersindustries
MaterialtechnologyforfertilizersindustriesMaterialtechnologyforfertilizersindustries
Materialtechnologyforfertilizersindustries
 
Neemcoatedureaaphilosophyforenvironment
NeemcoatedureaaphilosophyforenvironmentNeemcoatedureaaphilosophyforenvironment
Neemcoatedureaaphilosophyforenvironment
 
Nano ureathephilosophyoffuture
Nano ureathephilosophyoffutureNano ureathephilosophyoffuture
Nano ureathephilosophyoffuture
 
Installation of s 50 in ammonia plants
Installation of s 50 in ammonia plantsInstallation of s 50 in ammonia plants
Installation of s 50 in ammonia plants
 
Super conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency traysSuper conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency trays
 
Sswi april may-2021_lowres
Sswi april may-2021_lowresSswi april may-2021_lowres
Sswi april may-2021_lowres
 
Sweet and sour experience of commissioning 1
Sweet and sour experience of commissioning 1Sweet and sour experience of commissioning 1
Sweet and sour experience of commissioning 1
 
How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...
 
Experience of material in fertilizers industries
Experience of material in fertilizers industriesExperience of material in fertilizers industries
Experience of material in fertilizers industries
 
Fertilizers technology book
Fertilizers technology bookFertilizers technology book
Fertilizers technology book
 
High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)
 
High pressure vessel leakage in urea plants
High pressure vessel leakage in urea plantsHigh pressure vessel leakage in urea plants
High pressure vessel leakage in urea plants
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
P & i diagram and tagging philosphy for
P & i diagram and tagging philosphy forP & i diagram and tagging philosphy for
P & i diagram and tagging philosphy for
 
Ureaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsUreaplantenergysavingbyselectionoflinermaterialandinernals
Ureaplantenergysavingbyselectionoflinermaterialandinernals
 
5000 tpd urea mega plants design
5000 tpd urea  mega plants design5000 tpd urea  mega plants design
5000 tpd urea mega plants design
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
 

Recently uploaded

"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

Recently uploaded (20)

"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

Operation of urea fertilizers plant

  • 1. R-1E-1 MV-2 V-1 MV-3 SYNTHESIS SECTION SAIPEM PROCESS PRESENTED BY Prem Baboo National fertilizers Ltd. India. An Expert for www.ureaknowhow.com Fellow of Institution of Engineers India. Plant & Equipment's Designer
  • 2. R-1E-1 MV-2 V-1 MV-3 2 POINTS TO DISCUSS START UP SHUT DOWN TROUBLE SHOOTINGS
  • 3. R-1E-1 MV-2 V-1 MV-3 3 Initial start up Cold start up Hot start up Start Up
  • 4. R-1E-1 MV-2 V-1 MV-3 4 Start Up Initial start up means: – All the sections are depressurized and /or without process fluids. Cold start up means: – All the sections are pressurized with process fluids but HP Reactor is empty and HP loop depressurized. Hot start up means: – All the sections are pressurized with process fluids and HP Reactor is full and HP loop pressurized.
  • 5. R-1E-1 MV-2 V-1 MV-3 5 START UP CLEARANCE TO BE TAKEN FROM 1. MECHANICAL 2. ELECTRICAL 3. INSTRUMENT CLEARANCE TO BE TAKEN FROM 1. AMMONIA-II 2. UREA-I
  • 6. R-1E-1 MV-2 V-1 MV-3 6 Start Up With Empty Reactor General During this phase it has been assumed that all pre- start operations have been completed together with Mechanical check of the unit.
  • 7. R-1E-1 MV-2 V-1 MV-3 7 Sealing Tests Of All Sections Purpose – To eliminate leaks, if any, before charging process fluids.
  • 8. R-1E-1 MV-2 V-1 MV-3 8 Sealing Test Fluid – Steam condensate. Temperature – Ambient (cold test) Pressure – Operating value
  • 9. R-1E-1 MV-2 V-1 MV-3 9 Sealing Test Conceptual Procedure Admit the fluid from the lowest points and keep the vent at highest points opened. Slowly increase the pressure to the test value. Check all flanges and connections in order to identify leaks and eliminate them. If the pressure does not fall appreciably after 4 hours the test can be considered satisfactory, otherwise it will be necessary to look and to eliminate them and then repeat the test.
  • 10. R-1E-1 MV-2 V-1 MV-3 10 Very Important Keep the highest point vents in open position during section emptying Reactor draining to be started after completion of draining of Carbamate condenser. This is to avoid bulging of reactor lining.
  • 11. R-1E-1 MV-2 V-1 MV-3 11 Purging By N2 Of M.P. & L.P.Sections Purpose This operation must be carried out before plant start-up in order to remove all the O2 present, avoiding any risk of explosive mixture formation during ammonia charging.
  • 12. R-1E-1 MV-2 V-1 MV-3 12 Purging By N2 - Conceptual Procedure Admit Nitrogen keeping the pressure controller in automatic mode. When N2 comes out from drain close block valves. Depressurize the system up to positive pressure of about 0.5 kg/cm2 Analyze the gas outlet. If O2 content is 0.1% by vol. The purging is performed.
  • 13. R-1E-1 MV-2 V-1 MV-3 13 Charging of Ammonia in MP Section Purpose To have a make-up of NH3 (Raw material) Pressurize the M.P.section Test H.P.NH3 pump Ammoniation
  • 14. R-1E-1 MV-2 V-1 MV-3 14 Ammonia Solution Preparation in V-3 Purpose Preparation of L.P.section to receive process fluid The concentration of NH3 in V-3 solution is about 30%
  • 15. R-1E-1 MV-2 V-1 MV-3 15 Plant Heating Before Start Up Purpose Whenever start-up is to be performed with the unit empty and at ambient temperature the equipment shall be previously heated in order to bring them to the best conditions to feed the process fluids to the above equipment. This is to avoid: Thermal stresses on the material Possibility of crystallization of products in cold piping and walls
  • 16. R-1E-1 MV-2 V-1 MV-3 16 Plant Heating Before Start Up The section of High pressure synthesis shall be heated up to the temperature of 150 ~ 160°C before introducing the process fluids. Important The heating rate shall never exceed the values recommended by the equipment manufacturers (~ 30°C/hr)
  • 17. R-1E-1 MV-2 V-1 MV-3 17 Conditions Before Ammoniation CO2 compressor ready to be started with high pressure line heated up. Compressor will be put in running before Ammoniation period. High pressure pumps ready to be started. High pressure section heated up and ready for Ammoniation
  • 18. R-1E-1 MV-2 V-1 MV-3 18 Conditions Before Ammoniation M.P. section charged and pressurized by ammonia with NH3 booster pump running in closed recycle to Ammonia receiver. L.P. section charged with NH3 solution and M.P. carbonate solution pump(P-3) running in circulation to Carbonate receiver(V-3) through M.P. Absorber. Vacuum section ready to be taken in line. Prilling system ready to be started Waste water section in running condition.
  • 19. R-1E-1 MV-2 V-1 MV-3 19 Ammoniation Purpose To reach the best conditions to start the reactions inside the reactor. Conceptual procedure It consists in the pressurization of H.P.loop with ammonia vapors up to 90 kg/cm2 The “Ammoniation” operation requires about 3 hours and then the unit can be fed by NH3 and CO2 to Urea Reactor.
  • 20. R-1E-1 MV-2 V-1 MV-3 20 Ammoniation The main steps are: 1. Start the pressurization of the Synthesis system by sending NH3 via Ammonia booster (P-5) to Start-up line, leaving opened the suction and delivery valves of H.P.Ammonia pump (P-1).the NH3 is vaporized in the jacket line. 2. Control that the NH3 vapor temp is over 140°C.
  • 21. R-1E-1 MV-2 V-1 MV-3 21 Ammoniation 3. When the H.P.system reaches the value of Booster pump delivery pressure, start the H.P.Ammonia pump(P-1) in recycle to Ammonia Receiver (By opening the relevant valves) and adjust the ammonia rate by feeding a small flow to start-up line, so to gradually increase the pressure of the system up to about 90 kg/cm2g.
  • 22. R-1E-1 MV-2 V-1 MV-3 22 Ammoniation 4. When the set value of pressure is reached (90kg/cm2),stop NH3 feeding to Start-up line by closing the inlet valves and simultaneously stop P1pump then proceed to close steam to jacket of start-up line and wash this line by KW for a few minutes. 5. The speed of pressure increasing on H.P.section (PIC-7) has to be maintained at 30 kg/cm2 / hour to arrive at the set of 90 kg/cm2g.
  • 23. R-1E-1 MV-2 V-1 MV-3 23 Plant Preparation for Start Up (section by section) M.P. & L.P. section preparation Ammonia has been fed into NH3 receiver and both sections (M.P. & L.P.section) are pressurized with ammonia vapors at 15 kg/cm2g and 3 kg/cm2g respectively. MP carbonate solution pump (P-3) is running with a weak ammonia solution in recycle to Carbonate solution accumulator (via MP condenser & MP absorber).
  • 24. R-1E-1 MV-2 V-1 MV-3 24 Plant Preparation for Start Up (section by section) M.P. & L.P. section preparation To increase the ammonia content into this solution, feed a small reflux flow to MP absorber keeping the MP carbonate solution pump (P-3) running in recycle. Stop the ammonia reflux to MP absorber (C-1) top only when the Carbonate solution accumulator analysis indicates an ammonia content of 35% by wt.
  • 25. R-1E-1 MV-2 V-1 MV-3 25 Plant Preparation for Start Up (section by section) M.P. & L.P. section preparation Feed steam into shell sides of the M.P. and L.P.decomposers by opening the relevant control valves of the 10 – 15 % and heat up these equipment's by sending HW/LW at the inlet. Keep a level on the M.P. & L.P. decomposer holders. Put the steam tracing in service in all the process lines.
  • 26. R-1E-1 MV-2 V-1 MV-3 26 Plant Preparation for Start Up (section by section) Vacuum evaporation section The evaporation section is to be put in water recirculation to the urea solution tank via vacuum concentrator/separator/urea solution pump (P-8).
  • 27. R-1E-1 MV-2 V-1 MV-3 27 Plant Preparation for Start Up (section by section) Process water treatment section The process water treatment section is running water that from distillation tower (C-2)
  • 28. R-1E-1 MV-2 V-1 MV-3 28 Plant Preparation for Start Up (section by section) CO2 compressor and passivation air system Start and load the CO2 compressor and stabilize it venting the CO2 to the atmosphere from final discharge vent (pressure control valve) in auto. Open the passivation air flow and put in service the O2 analyzer.
  • 29. R-1E-1 MV-2 V-1 MV-3 29 Initial Start Up (Feed in) Following action to be taken for Feed in – Send condensate to Reactor for 10 minutes. – Feed NH3 for about 15 minutes. – Feed CO2 to Reactor – Feed Carbamate at Reactor overflow – Start passivation air injection (K-3) – Parameter stabilization and production started
  • 30. R-1E-1 MV-2 V-1 MV-3 30 NH3 and CO2 Feed in Send condensate to – Reactor (R-1) – Carbamate condenser (E-5) for about 10 minutes by means of H.P. flushing pump (KW injection points) and after that close the valves and close HV1(CO2 to R1). The NH3 present in the Reactor dissolves in the water releasing heat and causing a temperature increase at the Reactor bottom.
  • 31. R-1E-1 MV-2 V-1 MV-3 31 NH3 and CO2 Feed in When the NH3 & H2O solution reaches the saturation and this is shown by Reactor bottom temperature that stops to increase (After about 10 minutes), proceed to open block valve and motorized valve on NH3 discharge line and close Carbonate recycle valve from H.P. Separator. Then start feeding Ammonia to the Reactor. The NH3 feeding flow rate must be about 50 rpm of P-1 ammonia feed pump.
  • 32. R-1E-1 MV-2 V-1 MV-3 32 NH3 and CO2 Feed in After about 10 minutes from introduction of NH3,proceed to open the valves on CO2 to Reactor, controlling the reactor bottom temperature. Before feeding CO2 to Reactor, be sure to inject the passivation air in CO2 stream
  • 33. R-1E-1 MV-2 V-1 MV-3 33 NH3 and CO2 Feed in At the overflow (after about 2 hours since reactor feed in) of the reactor, – open Carbamate recycle valve HV-2 from H.P. Separator, – start sending the H.P.Carbamate solution to the Carbamate condenser by opening the relevant valves (HV-6). – Monitor pump amperage (pump P-2 already running in circulation to C-1).
  • 34. R-1E-1 MV-2 V-1 MV-3 34 NH3 and CO2 Feed in At reactor overflow, start opening the motorized valve (HV-5) at Stripper outlet line and regulate the stripper level controller (LV-2) in Manual mode. On manual mode adjust the opening of the MS steam pressure control valve (PV-14) admitting steam to shell side of Stripper, checking that the bottom temperature never exceeds 207°C.
  • 35. R-1E-1 MV-2 V-1 MV-3 35 NH3 and CO2 Feed in The bottom pressure and temperature of reactor shall be increased and maintained at about 179°C and 155~160 kg/cm2. respectively. As a corrective action the flow rates of NH3 and CO2 can be reduced or increased in order to adjust temperature and pressure of reactor.
  • 36. R-1E-1 MV-2 V-1 MV-3 36 NH3 and CO2 Feed in Temperature increase: – The NH3/CO2 ratio is decreasing, with consequent pressure reduction in the system, it is necessary to increase NH3. Temperature decrease: – The NH3/CO2 ratio is increasing, the pressure will tend to rise, it is necessary to decrease NH3 or increase CO2.
  • 37. R-1E-1 MV-2 V-1 MV-3 37 NH3 and CO2 Feed in As a guide, the weight ratio NH3/CO2 to reactor should be around 1.15~1.2 during this phase. The M.P. section is going to receive urea solution.
  • 38. R-1E-1 MV-2 V-1 MV-3 38 M.P./L.P. sections going to receive urea solution As soon as urea from R-1 enters the E-1, a decrease in steam pressure in the shell will be noticed. Adjust the MS flow to E-1 according to E-1 bottom temperature. Feed Carbamate to R-1 Urea solution from E-1 bottom passes to MP decomposer, then to LP decomposer and initially to V-5 ( after stabilization, passes to vacuum section).
  • 39. R-1E-1 MV-2 V-1 MV-3 39 Slightly open manually FV-102 sending NH3 to the top of the C-1 and keep recirculation of carbonate solution from V-3 to C-1 controlling bottom level and temperature. Send condensate to top of C-3 so as to absorb NH3 present in the inert gas when level is established at the E-11 bottom start P-7 and send sol. to C-1 and control the level. M.P./L.P. sections going to receive urea solution
  • 40. R-1E-1 MV-2 V-1 MV-3 40 Maintain MP/ LP urea holder temperature Maintain MP /LP section pressure By putting PIC- 108 / PIC-133 on auto mode Pre concentrator level and start the pump Preconcentrator pump(P-50) and ww water pump(P-52).Vacuum ejectors also to be taken in line M.P./L.P. sections going to receive urea solution
  • 41. R-1E-1 MV-2 V-1 MV-3 41 NH3 and CO2 Feed in H.P. loop heating (including hot bolting) 5 to 8 hours Condensate draining before pressurization ½ hour Pressurization with NH3 Via start up line 3½ hours NH3 and CO2 to reactor until overflow occurs 2 to 3 hours Stabilization of running condition 1 hour
  • 42. UREA REACTOR AND HP SEPERATOR
  • 43. STRIPPER AND HP CONDENSER
  • 44. AMMONIA START UP LINE HIC4
  • 45. MP DECOMPOSER & AMMONIA ABSORBER
  • 46. R-1E-1 MV-2 V-1 MV-3 46
  • 48. R-1E-1 MV-2 V-1 MV-3 48
  • 49. R-1E-1 MV-2 V-1 MV-3 49
  • 50. R-1E-1 MV-2 V-1 MV-3 50
  • 53. R-1E-1 MV-2 V-1 MV-3 53 Shut Down Flushing Short shut down Long shut down Emergency shutdown
  • 54. R-1E-1 MV-2 V-1 MV-3 54 Flushing system Urea plant shutdown main hazard is choking First and foremost priority is proper flushing of the lines and vessels. There are three tier flushing system – High pressure system – Medium pressure system – Low pressure system
  • 55. R-1E-1 MV-2 V-1 MV-3 55 HP Flushing system Pump is a reciprocating one (P-11). It takes suction from medium pressure pump discharge and discharge water to different high pressure loop washing point. Before starting KW washing, the pump discharge pressure has to be set at 30Kg/cm2 more than that of high pressure loop pressure.
  • 56. R-1E-1 MV-2 V-1 MV-3 56 HP Flushing system Before injecting flushing water confirm V-2 temp >60-70oC and drain the water first to make the flowing water hot. Close the drain tightly and inject water. Check the KW pressure. Check if pressure has dropped or not. If pressure has dropped that means line is clear.
  • 57. R-1E-1 MV-2 V-1 MV-3 57 HP Flushing system If pressure has not dropped it means flushing has not taken place. De-choke the line immediately and then do the flushing. During HP loop flushing remember one thing – Do not open water simultaneously at numerous points. – Do flushing at one point at a time.
  • 58. R-1E-1 MV-2 V-1 MV-3 58 MP Flushing system Pressure 36 kg.cm2 – a centrifugal pump(P-6). Water goes to : – MP section, – PV-07A D/S pipe – HV-05 D/S pipe – P-3 discharge – P-2 suction – P-8 discharge
  • 59. R-1E-1 MV-2 V-1 MV-3 59 LP Flushing system Normally low pressure flushing pump (P-10) is always in line. it is a centrifugal pump with discharge pressure 15 kg/cm2. Water goes to: – LP section, Vacuum section, C-2 and LTs’ flushing. Remember P-8 discharge is having MP flushing.
  • 60. R-1E-1 MV-2 V-1 MV-3 60 Plant shutdown 1. Short shutdown means: – HP loop hold up. 2. Long shutdown means: – Necessitating HP loop draining. 3. Emergency shutdown – Due to power failure. – Due to cooling water failure. – Due to instrument air failure. – Due to steam failure.
  • 61. R-1E-1 MV-2 V-1 MV-3 61 Short Shutdown Procedure As soon as CO2 compressor trips HV-1 gets closed.PV-03 gets open. Close HV-08 and its I/V. If P-1 pump has not tripped, give Ammonia to Reactor for 10 minutes then stop P-1. Close HV-7 and I/V after P-1 has stopped. Close 2nd discharge valve of P-1A or B (which ever is in line). Close HV-2. Stop P-2 (Carbamate pump). Close HV-6 & its I/V. Open FV-34.
  • 62. R-1E-1 MV-2 V-1 MV-3 62 Short Shutdown Procedure Close PV-7A (if pressure is not getting hold, close its I/V ). Close LV-02 & HV-05 after bringing down stripper level to minimum. Increase HV-03 opening. Check P-10, P-6, P-11 (flushing pumps) are running. – P-11 discharge pressure 170Kg/cm2.
  • 63. R-1E-1 MV-2 V-1 MV-3 63 Short Shutdown Procedure Divert prilling to V-5 via HV-132.immediately after feed cut . Open PIC-140 & 141 first & second vacuum pressure control valves. Divert ME-3 to E-14 (HV-140) towards V-5. Open LP flushing water at E-14 inlet. Open HW at P-8 discharge to displace the Urea solution in the vertical line.
  • 64. R-1E-1 MV-2 V-1 MV-3 64 Short Shutdown Procedure Run P-8 on water for at least 5min. on load. Be careful enough so that LV-138 at P-8 discharge should not get closed fully. P-8 discharge is not having any NRV so that hold up solution in the vertical line gets drained to MV-7 easily if LV-138 is open.
  • 65. R-1E-1 MV-2 V-1 MV-3 65 Short Shutdown Procedure Close ME-2 level control valve after ME-2 level is minimum. Check C-1 level. If required drain to V-3 via HV-102. Close LIC-102. Reduce pure Ammonia reflux to C-1 according to the temp. of C-1 top. Open P-3 recycle valve so that P-3 can have enough recycle flow as auto recycle valve is not there.
  • 66. R-1E-1 MV-2 V-1 MV-3 66 Short Shutdown Procedure Wash CO2 line towards reactor. Check KW pressure has reduced to confirm flushing. Check physically that HV-1 has opened in field during flushing. Flush ammonia line D/S of HV-7 to reactor. Flush HV-2 up stream & down stream. Flush LV-2 towards E-1 through the flushing line between LV-2 & HV-5. Then flush through HV-5 by closing LV-2.
  • 67. R-1E-1 MV-2 V-1 MV-3 67 Short Shutdown Procedure Flush PV-07A open KW between I/V & control valve. Flush towards MV-1 then flush through PV-7A by closing isolation valve & opening PV-7A. After flushing close PV-7A control valve. Flush HV-6 towards E-5 (Carbamate condenser) by opening isolation valve of HV06. Flush P-2 discharge line down stream of NRV with KW. First flush through FV-34 then close FV-34. Let the line get pressurized open HV-6 check pressure has come down to confirm flushing to E-5.
  • 68. R-1E-1 MV-2 V-1 MV-3 68 Short Shutdown Procedure Open HW (MP flushing water) to LV-101 up stream & down stream. Open HW to MV-2 from HV-5 D/S. Open HW to PV-7A D/S. Open HW in P-3 discharge & flush through LIC-102 to E-7. Flush HIC-102 line if C-1 draining is over. Open LW (LP flushing water) through ME-3 down stream line to V-5. Open HW in C-1 to P-2 line. Flush P-2 (Carbamate pump) from suction thoroughly. Check in open drain that water is clear of Carbamate.
  • 69. R-1E-1 MV-2 V-1 MV-3 69 Short Shutdown Procedure Flush and fill MV-8 (CO2 discharge drum) thoroughly after de-pressurizing vessel. Reduce the steam to stripper, MP & LP decomposer. Close PV-14, TIC-102 & its by-pass, TIC-131 & LV-03. Shut the reflux to C-1. Stop condensate to C-3 & C-4. Stop P-7 after E-11 level is minimum.
  • 70. R-1E-1 MV-2 V-1 MV-3 70 Short Shutdown Procedure PLEASE REMEMBER : Open KW only one point at a time. Confirm KW flushing by checking reduction in KW pressure. Close the process isolation valve first & then the water injection valve. HW & LW can be opened at various point simultaneously.
  • 71. R-1E-1 MV-2 V-1 MV-3 71 Long Shutdown Procedure (HP loop draining) IF SHUTDOWN IS PRE-PLANNED – CHECK R-1 DRAIN LINE PRIOR TO FEED CUT. Checking of R-1 drain line Check KW pressure is about 180Kg/cm2. Inject KW through R-1 drain line injection towards HV-4. Be careful that R-1 open drain & close drain valves are tightly closed. Open HV-4 & let KW to flow through HV-4 & HV-5 towards MV-2. Check KW pressure has dropped to about 50Kg/cm2 to confirm drain line is clear.
  • 72. R-1E-1 MV-2 V-1 MV-3 72 Long Shutdown Procedure (HP loop draining) If pressure has not dropped, line is in choked condition. Do external steam heating U/S of HV-4. Do pressurization & de-pressurization of line up to HV-4 repeatedly by keeping HV-4 close. Check again if drain line has got cleared in the previous method. If drain line is clear, start reactor draining.
  • 73. R-1E-1 MV-2 V-1 MV-3 73 Long Shutdown Procedure (HP loop draining) Keep the following valves conditions as follows; I/Vs of HV-6,HV-7and HV-8 close LV-2 close. HV-2 close LV-3 ~10% open. I/V of HV-102 open. PV-7A I/V close. HV-140 and its I/V open.
  • 74. R-1E-1 MV-2 V-1 MV-3 74 Long Shutdown Procedure (HP loop draining) Open Reactor drain I/V towards HV-4. Open HV-4 & HV-5. Open HV-1 (HV-1 inter lock to be by-passed from I- 1 on ESD) Feel the sound of flow.
  • 75. R-1E-1 MV-2 V-1 MV-3 75 Long Shutdown Procedure (HP loop draining) Check level has come in ME-2 in Control Room & physically in side glass. Control the Reactor draining rate to MP section using HIC-4 & HIC-1.
  • 76. R-1E-1 MV-2 V-1 MV-3 76 Long Shutdown Procedure (HP loop draining) Maintain Ammonia reflux to C-1 from P-5 to maintain C-1 temperature. Maintain E-7 outlet temp. with LIC-102 minimum 30% open & with TIC-101 on auto. Maintain C-1 level by draining through HIC-102 to V-3.
  • 77. R-1E-1 MV-2 V-1 MV-3 77 Long Shutdown Procedure (HP loop draining) Use greater amount of steam to E-2 without over loading C-1 so that to recover a greater amount of Ammonia to V-1. Check pressure drop is at a rate not more than 30Kg/cm2 per hour.
  • 78. R-1E-1 MV-2 V-1 MV-3 78 The temperature and pressure decline in the synthesis system is controlled by adjusting the reactor drain rate. The adjustment is made with HIC-4 on manual control. Long Shutdown Procedure (HP loop draining)
  • 79. R-1E-1 MV-2 V-1 MV-3 79 Check the temperature in the low pressure decomposer in view of getting the maximum concentration of urea solution and avoiding and excessive quantity of ammonia being delivered to the vacuum concentration system. Long Shutdown Procedure (HP loop draining)
  • 80. R-1E-1 MV-2 V-1 MV-3 80 Long Shutdown Procedure (HP loop draining) When no solution is coming out from reactor at a pressure of about ~40Kg/cm2 drain Carbamate condenser to MV-2 through HV-4. Open HIC-2 and drain MV-1 to MV-2 thru’ HV-4 After feed cut and before depressurization of HP loop close air to reactor weep holes Confirm that draining is over, when LV-101 & LV-131 gets almost closed.
  • 81. R-1E-1 MV-2 V-1 MV-3 81 Long Shutdown Procedure (HP Loop Draining) When the synthesis loop pressure and the pressure of the medium pressure section are equal: Cut HP loop from MP by closing HV-1, HV-4, HV-5. and wash all lines and equipment of the high pressure section draining to the closed drain. Start depressurization of HP loop to BD header through PV- 7B. Shut the steam to the decomposers, open the washing on the outlet line bottom solution stripper, bottom decomposer M.P. and L.P. and flush together with 2 decomposers.
  • 82. R-1E-1 MV-2 V-1 MV-3 82 Long Shutdown Procedure (HP loop draining) Close the delivery valve and stop P-3A/B. Stop NH3 at the top of C-1 by FIC-102 in manual control.
  • 83. R-1E-1 MV-2 V-1 MV-3 83 Long Shutdown Procedure (HP loop draining) Stop the ammonia booster pump and close the suction and delivery valves. Send washing water to the top of C-1 for few minutes. Drain the liquid of the C-1 to the carbonate tank through HV-102 when washing is finished. Shut off the water and drain the column to the closed drain. Isolate the NH3 tank and absorber from the other medium pressure equipment, leaving the pressure control in automatic position.
  • 84. R-1E-1 MV-2 V-1 MV-3 84 Long Shutdown Procedure (HP loop draining) Gradually depressurize the absorption column and the medium pressure decomposer through LV-101. Take care not to pressurize the low pressure decomposer. Shut the steam to the decomposers E-3. Isolate the carbonate tank V-3 from C-1 leaving pressure controller PRC-133 on auto. Dilute MP condenser E-7 and condenser E-11 solutions and drain them out.
  • 85. R-1E-1 MV-2 V-1 MV-3 85 Long Shutdown Procedure (HP loop draining) Stop the vacuum section circulation after MV-7 level comes to minimum & after confirming proper flushing and PIC- 140 & 141 open. Stop flushing water to E-14 & other points. Cut steams to E-14 & E-15. Cut the condensate outlet to condensate tank. Cut steam to ejectors. Cut cooling water to condensers, if required. Stop V-9 transfer to V-6 by stopping P-21, if required.
  • 86. R-1E-1 MV-2 V-1 MV-3 86 Long Shutdown Procedure (HP loop draining) After depressurization and close draining of HP loop is over open LP steam to reactor for 3-4 hrs. Cut steam to reactor/HP loop. Open MP washing water to HP loop through 3” quick filling line at reactor bottom with HV-1 open PV-7B open, HV-3 sample point drain open and HV-2 close. Filling completion of reactor is indicated by water coming out from HV-3 sample point, close it. Filling completion of HP loop total is indicated by rise in PV-7B pressure.
  • 87. R-1E-1 MV-2 V-1 MV-3 87 Long Shutdown Procedure (HP loop draining) If vessel man entry is to be permitted then overflow HP loop through PV-7B for 7-8 hrs. Other wise 3-4 hrs overflow will do. Stop filling water, start draining HP loop from E-1 drain, from LV-2 sample point drain, from E-5 sample point drain & HV-3 sample point drain. When water stops coming out from HV-3 sample point drain, open reactor drain through HV-1 I/V gradually to full open condition. Total draining normally takes 8-10 hrs.
  • 88. R-1E-1 MV-2 V-1 MV-3 88 Long Shutdown Procedure (HP loop draining) During HP loop draining, PV-7B should be open, HV-2 should be close. During filling of HP loop E-5 shell side should be depressurized & drained to enhance cooling. Either steam circuit should be depressurized or all tracing / jacket steam should be closed and stripper shell side should be depressurized.
  • 89. R-1E-1 MV-2 V-1 MV-3 89 Long Shutdown Procedure (HP loop draining) When water stops coming out from HV-3 sample point reactor top manhole cover should be opened to enhance draining & cooling. When water stops coming out from HV-3 sample point, HV-3 may be handed over to maintenance, if required.
  • 90. R-1E-1 MV-2 V-1 MV-3 90 Long Shutdown Procedure (HP loop draining) When water stops coming out from E-5 or E-1 bottom drains, E-5 or E-1 may be handed over. During condensate draining smell the drain water for ammonia to have an idea of atmosphere inside HP loop vessels.
  • 91. R-1E-1 MV-2 V-1 MV-3 91 EMERGENCY SHUT DOWN The emergency situations which are likely to arise are several and extremely variable as to duration and seriousness.
  • 92. R-1E-1 MV-2 V-1 MV-3 92 EMERGENCY SHUT DOWN Principal causes: 1. Process reasons: Considerable pressure and / or temperature increases Pipe line clogging because of crystallization 2. Sudden failure of services 3. Fires, and / or ruptures with uncontrollable losses of toxic gasses.
  • 93. R-1E-1 MV-2 V-1 MV-3 93 EMERGENCY SHUT DOWN Safety interlocks Based on the above emergency causes, an interlock trip system has been provided for the protection of personal and equipment initiating an automatic shut down system
  • 94. R-1E-1 MV-2 V-1 MV-3 94 EMERGENCY SHUT DOWN Safety interlocks For point No. 3 (if occur) push buttons are provided on urea desk to stop the principal machines. The valves which isolate the synthesis loop & NH3 to P-1will than be closed.
  • 95. R-1E-1 MV-2 V-1 MV-3 95 The evaluation of the seriousness of an emergency situation and there fore the decision of how to shut the plant down is a matter of the operators’ experience. He should take prompt and corrective action. However, the inter lock system is designed to minimize the number of manual operations. EMERGENCY SHUT DOWN
  • 96. R-1E-1 MV-2 V-1 MV-3 96 Should the point no. 1 occur lines and equipment should be washed, the trip causes eliminated EMERGENCY SHUT DOWN
  • 97. R-1E-1 MV-2 V-1 MV-3 97 Electric Failure Should a total failure of electric power occur, the CO2 compressor and all the pumps of the unit will stop. In this case restart the plant, locally starting up the machines not re-accelerated.
  • 98. R-1E-1 MV-2 V-1 MV-3 98 Electric Failure If on the contrary, the power failure is more than momentary, only the pumps of emergency network will restart automatically. But, in this case, the cooling water will be missing and, as a consequence a pressure increase will occur in the medium and low pressure sections and vacuum will be lost in the evaporation section.
  • 99. R-1E-1 MV-2 V-1 MV-3 99 Electric Failure Then the plant must be stopped following the instructions shown here under. Introduce washing water to the following points : Introduce washing water to the following points : 1. Inlet to the concentrator E-14. 2. Bottom outlet stripper and outlet of the medium and low pressure decomposers. 3. P-3A/B delivery line and C-1 trays.
  • 100. R-1E-1 MV-2 V-1 MV-3 100 4. High pressure Carbamate pump suction and delivery lines. 5. CO2 and NH3 lines to reactor Carbamate to ejector HV-2 (up streams and down stream). Electric Failure
  • 101. R-1E-1 MV-2 V-1 MV-3 101 Now proceed as described for normal shutdown. Electric Failure
  • 102. R-1E-1 MV-2 V-1 MV-3 102 The plant uses steam at 23 kg/cm2g in stripper E-1. Failure of this service also involves the failure of the condensate from the stripper which feed the MP decomposer E-2 & subsequently the Carbamate condensers E-5. Steam Failure
  • 103. R-1E-1 MV-2 V-1 MV-3 103 The main plant and the ammonical water treatment section should be shutdown since there will be no steam production at 4.5kg/cm2g. Steam Failure
  • 104. R-1E-1 MV-2 V-1 MV-3 104 The main machines must immediately be tripped : 1. CO2 compressor, 2. P-1A/B NH3pump, and 3. P-2A/B Carbamate pump. Column C-1 shall be recycled to V-3 and diluted, sending water to P-3A/B delivery line. Wash and dilute all lines of the high pressure section. Steam Failure
  • 105. R-1E-1 MV-2 V-1 MV-3 105 Wash the medium and low pressure decomposers outlet lines to avoid crystallizations. Stop and dilute the vacuum evaporation section following the procedure described for normal shutdown. Steam Failure
  • 106. R-1E-1 MV-2 V-1 MV-3 106 The plant is thus in a safe shutdown condition and ready to restart following the usual restarting procedure, in case of steam failure and/or long plant shutdown, it is necessary to further dilute the solution contained in tanks and apparatuses recovering it as soon as the steam availability is assured. Steam Failure
  • 107. R-1E-1 MV-2 V-1 MV-3 107 Cooling Water Failure The plant equipment employing cooling water. Principal users are: – CO2 compressor (inter-stage cooler) – Condensers , coolers and the pump coolers. Lack of this service causes a pressure increases in the medium and low pressure system for lack of condensation in the respective condensers and vacuum loss in the vacuum evaporation section.
  • 108. R-1E-1 MV-2 V-1 MV-3 108 Cooling Water Failure Proceed as follows : – Open E-41,E-9,E-7 top cooling water vents – Stop feeding to the reactor. Trip compressor, P-1,P-2 and all the pumps except for the washing pumps must be stopped. – Close LV-2,HV-5 and closing the steam valve (PV-14) to the stripper
  • 109. R-1E-1 MV-2 V-1 MV-3 109 Cooling Water Failure – Close the steam valve to the E-2,E-3,to both vacuum evaporators and to the column C-2 and the ejectors. – Send washing water to the delivery line of P-3A/B to the trays of column C-1 to the condensers E-11 and E-8 absorb NH3 thus reducing the pressure, Now, proceed as described for short shutdown.
  • 110. R-1E-1 MV-2 V-1 MV-3 110 Instrument Air Failure In case off instrument air failure, the control valves assume such positions as to ensure the plant safety without the immediate intervention of the operators, who however, must be will aware of the general view of these positions.
  • 111. R-1E-1 MV-2 V-1 MV-3 111 Instrument Air Failure As soon as the instrument air is lacking, the operator must switch to manual control all instruments on DCS at zero signal position. So that, when air gets in again, the valves do not move.
  • 112. R-1E-1 MV-2 V-1 MV-3 112 Instrument Air Failure The synthesis loop gets blocked and automatically is isolated from the rest of the plant. Shutdown must be actuated following the same procedure as That described for the electric power failure.
  • 113. R-1E-1 MV-2 V-1 MV-3 113 Important Checks Communicate to the followings before S/D: urea-I Ammonia-II Bagging Check reverse rotation if any, for K-1. Before shut down keep V-1, V-3 level at minimum.
  • 114. R-1E-1 MV-2 V-1 MV-3 114 Important Checks Check both P-11 are available. Keep P-11 running before feed cut. Before shutdown R-1 drain line & E-5 drain lines to be checked for any choking, clear these lines if found choked. Before shutdown HIC-102 line to be checked for any choking, clear these lines if found choked
  • 115. R-1E-1 MV-2 V-1 MV-3 115 Important Checks After shutdown do proper flushing of HP, MP & LP lines. After S/D do proper flushing of vacuum section with LW at E-14, P-8 circulation. Confirm P-8 is taking load. Double confirm vacuum section flushing.
  • 116. R-1E-1 MV-2 V-1 MV-3 116 Important Checks After feed cut and before depressurization of HP loop close air to reactor weep holes.
  • 117. R-1E-1 MV-2 V-1 MV-3 117 Important Checks Keep close check on P-33 level. Put a fire hose without coupling in R-1 drain line. Closely monitor B/L analysis. Isolate MV-8 and depressurize MV-8 after compressor tripping. Flush MV-8.
  • 118. R-1E-1 MV-2 V-1 MV-3 118 Depressurize MP loop – E-9 should be kept isolated from V-1. – MV-2, E-7, C-1 & E-9 through 2” BD header on C-1. – HP loop should be kept isolated from MP loop. – Steam / MP steam condensate should be cut to E-2. MP Loop Hand Over
  • 119. R-1E-1 MV-2 V-1 MV-3 119 After depressurization is complete start filling water from bottom of vessels with C-1 BD header valve open and also open vent isolation valve on MV-2 vapor line open. When water starts coming out from MV-2 vent & C-1 BD header let the overflow continue till the water gets almost clear of ammonia or for 1-2 hrs. MP Loop Hand Over
  • 120. R-1E-1 MV-2 V-1 MV-3 120 Then stop filling and start draining from all drain points. BD vent and open to atmosphere vent should be open during draining. After the draining is over the MP loop vessels barring V-1, E-11 & C-3 can be handed over for opening to maintenance. Cooling water to E-7 and E-9 should be cut only after depressurization is completed. MP Loop Hand Over
  • 121. R-1E-1 MV-2 V-1 MV-3 121 V-1 should be tightly isolated from rest MP loop before MV-2 to E-9 depressurization. Continue vaporizing ammonia till P-5 is taking load. Stop P-5 when V-1 is empty. Close P-5 discharge valve tightly. V-1 Handing Over
  • 122. R-1E-1 MV-2 V-1 MV-3 122 E-11 cooling water should be open during depressurization. Open close drain of V-1 & C-3/E-11. Simultaneously depressurize V-1, C-3/E-11 through PV-108 to BD header. When depressurization is completed, start filling water to V-1, C-3/E-11. V-1 Handing Over
  • 123. R-1E-1 MV-2 V-1 MV-3 123 PV-108 should be open full during filling. Allow the water to over flow through PV-108 for some time. Stop filling, start draining through all drains including P-5 suction strainer flange. After draining is completed, V-1& C-3/E-11 can be handed over to maintenance for opening. V-1 Handing Over
  • 124. R-1E-1 MV-2 V-1 MV-3 124 Keep V-3 level minimum before feed cut. After reactor draining through MP & LP is over, flush the LP section thoroughly. Isolate V-3 from E-8(liquid & vapor line both) if V-3 is not to be opened. Depressurize and drain ME-3-E-3-MV-3 & E-8 completely through the open to atmosphere vent. Fill flush overflow & drain the system. During draining vent should be confirmed to be open to atmosphere. L P Loop Handing Over
  • 125. R-1E-1 MV-2 V-1 MV-3 125 E-1 Handing Over After filling and draining twice check for ammonia in E-1 drain and skin temperature. While draining 2nd time give SWP to open alternate bolts. If NH3 in the drain sample in too high further fill E-1 only and drain it.
  • 126. R-1E-1 MV-2 V-1 MV-3 126 E-1 Handing Over If NH3 is not there in drain sample give SWP to open man holes HV-3, LV-2, E-1 LT tapping /thermocouple are to be removed. Put DM water hose at the top after E-1 top & bottom cover is opened. Put air hose at bottom through LV-2 after it gets opened.
  • 127. R-1E-1 MV-2 V-1 MV-3 127 Slip plate E-1 vapor line to E-5 (8” flange). Check whether MV-4 has been depressurized and drained. E-1 Handing Over
  • 128. R-1E-1 MV-2 V-1 MV-3 128 For E-1 shell side pressure testing give SWP to blind following points, check steam circuit to MV-4 has been depressurized and drained. MS steam inlet flange -10”. Condensate outlet flange to MV-4 -6”. MV-4 balance line- 2”. PSV-5 flange- 6”. E-1 Handing Over
  • 129. R-1E-1 MV-2 V-1 MV-3 129 Check E-5 is isolated depressurized and drained from shell side. After filling tube side and draining E-5 second time with water check ammonia in drain sample. Check start-up line both E-1 side valves closed. E-1 vapor line to E-5 is also blinded. E-5 Handing Over
  • 130. R-1E-1 MV-2 V-1 MV-3 130 Confirm first steam system is in depressurized condition. Give SWP for blinds in following points. 1. Export condensate flange-4” 2. Import line NRV flange-2” 3. LG tapping – upper one LG auxiliaries should be removed by instrumentation. E-5 Handing Over
  • 131. R-1E-1 MV-2 V-1 MV-3 131 4. Line from 1. MV-4 –6” 2. Steam outlet flange 2 no.-20” 5. PSV flanges 1. 2 no. –6”. 2. E-5 shell side drain one no. 3” Total 8 blinds. LT tapping 2no. E-5 Handing Over
  • 132. R-1E-1 MV-2 V-1 MV-3 132 Lower LG tapping flange should be connected with a flanged ½” nipple with isolation valve for air injection. Simultaneously give SWP to open E-5, ME-1 after confirming no ammonia in drain. – E-5 manhole is to be opened. – E-5 bottom and top flanges are to be gapped so that air circulation can take place in E-5. E-5 Handing Over
  • 133. R-1E-1 MV-2 V-1 MV-3 133 As soon as HV-1, HV-2 are opened put air hose through the gap in the reactor. While giving SWP to open HV-1, HV-2 & PRC-12. R-1 Handing Over
  • 134. R-1E-1 MV-2 V-1 MV-3 134 Check – 1. R-1 open drains are in open condition. 2. R-1 CD are in closed position HV-4 close. 3. MV-8 is depressurized condition. 4. Confirm all the injections are closed. 5. Confirm P-11 is not running. 6. No water is coming out of HV-2 up stream drain. Check HV-3 is removed R-1 Handing Over
  • 135. R-1E-1 MV-2 V-1 MV-3 135 7. P-1 to HV-7 is in depressurized and flushed condition. 8. HV-7 isolation valve is in closed condition. 9. P-1 discharge valve is in closed condition. 10. PV-7A isolation valve is in closed condition. R-1 Handing Over
  • 136. R-1E-1 MV-2 V-1 MV-3 136 11. Tracing drains are open. Steam of circuit is in depressurized condition. 12. Arrange to get R-1 top sample analyzed with a blower and PVC piping arrangement. R-1 Handing Over
  • 137. R-1E-1 MV-2 V-1 MV-3 137 For any type of queries Please contact to Prem Baboo Mob-+919425735974 +918718870316 Prem.baboo@nfl.co.in pbaboo@hotmail.com