UNIT-II
PROCESS PLANNING
ACTIVITIES
Introduction:
• Setting process parameters, work holding devices, inspection/quality
assurance methods, economics of process planning.
Process parameters calculation:
• Cutting speed, feed rate, depth of cut.
Cutting speed:
• Surface cutting speed or surface speed, relative speed b/w tool and
w/p.
• Tool or w/p or both may be moving during cutting.(mpm).
Factors affecting the selection of cutting speed:
Process planning activities
Process planning activities
Cutting speeds for different combinations of operation and material
Cutting speed ranges for different combinations of work piece and
tool material
Calculation of cutting speeds
Process planning activities
Process planning activities
Spindle speeds and stroke speeds:
• Turning, boring, milling, drilling-spindle speeds.
• Shaping, planning, slotting-stroke speeds.
Calculation of spindle speeds/no of strokes:
Process planning activities
Feed and feed rate
Feed:
• Distance through which tool advances into w/p during 1 revolution of
the w/p or the cutter.
Feed rate:
• Speed at which the cutting tool penetrates the w/p.
Unit:
• mm/min of spindle revolution.
Factors affecting feed rate:
• W/p material, capacity of m/c tool, cutting tool, cutting fluid
application, surface finish, operation type, nature of cut.
Feed rates for turning and boring in mm/rev for HSS and
carbide tool materials
Feed rates for drilling in mm/rev for HSS and carbide tool drills
Feed rates for milling in mm/tooth for HSS and carbide cutters
Feed rates for shaping and planning:
• 0.05-0.75-shaping.
• 0.5-3.0-planning.
Feed rates for grinding:
• Cross feed surface grinding-1.0-1.5mm/pass.
• Feed rate cylindrical grinding-1.0-1.5mm/pass.
Depth of cut:
• Thickness of the layer of metal removed in one cut or pass, direction
perpendicular to the machined surface(mm).
• Particular operation/c material, surface finish reqd,tool used.
Process planning activities
Machining time calculations:
• Selecting speed, feed rate, depth of cut.
Selection of jigs and fixtures:
• Work holding device as jig or fixture.
• Communicate to tool engg, design and drawings.
Work holding device:
Position and hold workpiece, precise, mfg operations.
Types of work holding devices
General work holding devices:
• Vices, clamps, abutments, chucks, collets, centres, mandrels, face
plates.
Specialist work holding devices:
• Jigs, fixtures.
Jigs: Clamps the m/c table, align the bushes of jig with spindle.
Fixtures:Clamps the m/c table, clamps the w/p during
machining,welding,inspection or assembly.
Process planning activities
Elements of jigs and fixtures
Principles of jigs and fixtures design
factors influencing jigs and fixtures design
Process planning activities
Process planning activities
Process planning activities
Process planning activities
General factors in workholder design and selection
Reasons for using jigs and fixtures
• Reduces marking, measuring and setting of w/p.
• Automatic exact position of workpiece and tool.
• Reduces production cycle time, increases production capacity.
• Interchangeability of production parts.
• Speed, feed, depth of cut.
• Clamp rigidity of w/p.
• Comfort operation.
• Settings eliminated.
• Reduces cost and defects.
Types of jigs-Drill, Boring.
Drill jig:
• Drilling, reaming, tapping, chamfering, spot facing, counter sinking.
Different types of drilling jigs:
• Template, plate, open type, swinging leaf type, box type, solid type,
pot type, index, multistation, universal.
Boring jig:
• Bore holes that is too large to drill or made on odd size.
Types of fixtures:
• Designed specifically operation ,carried out properly for w/p.
Different types of fixtures operation:
• Turning, milling, grinding, broaching, boring/drilling, tapping,
welding,
assembling.
Construction of fixtures:
• Plate, angle plate, vice-jaw, indexing.
Standard parts for jigs and fixtures:
• Mechanical fasteners, locating and supporting devices, indexing pins,
drill bushes, hand knobs, handles.
Selection of quality assurance methods:
• Dimensional and geometric tolerances, surface finish specifications,
inspection criteria, quality engineer, QA tools.
• Balance b/w quality, avoid increase of time & mfg costs.
Tasks:
• Inspection locations, testing methods, evaluation and identification of
corrective action, influences processes, equipment, tools and mfg
parameters.
Quality definition:
• Totality of features and characteristics of a product or service, that
bear on its ability to satisfy stated and implied needs of the customer.
TQM definition:
• Management approach of an organisation, centered on quality,
participation of all its members and aiming longterm success through
Customer satisfaction and benefits to all members of the organisation and
to society.
Principles/concepts of TQM
TQM Framework(Elements of TQM):
Basic quality strategies:
• Detection strategy, prevention strategy.
Detection strategy:
• Non-conformance is detected, various inspection methods, process is
adjusted.
Prevention strategy:
• Non-conformance is minimized/eliminated.
Seven statistical tools of quality:(Q-7)
Statistical quality control:
• Employing inspection methodologies from statistical sampling theory
to conformance requirements.
• Inspected samples of batch in statistical interferences, conclusions for
whole batch.
Two methods of SQC:
• Statistical process control, Acceptance sampling.
Assignable and chance causes of variations:
• Two objects exactly alike, degree of inherent variability.
Four sources of variations:
• Processes, materials, operations, miscellaneous factors.
• Miscellaneous- heat, light, humidity.
Assignable causes of variations:
Larger in magnitude and easily traced and detected.
Reasons
• Differences among machines, materials, processes, overtime,
relationship to one another.
• Analyzing data, identify and eliminate remedial actions.
Chance or random or common causes of variations:
• Inevitable in any process, difficult to trace and control, best conditions
of production, random manner.
• Human variability from one operation cycle to next by raw materials,
fluctuations, lack of skills.
• Process operating under stable system of chance causes said to be
statistical control.
Control charts:
• Graph that displays data taken over time and variations of this data.
Uses
• Process is statistically or not,variability,capability of
production,variation,effect of process change.
Types
• Control charts for variables, attributes.
Process planning activities
Control charts for variables:
• Quality characteristics measured and expressed in specific units of
measurements.
Types:
• Average,range,standard deviation charts.
• Average charts-monitor centering.
• Range charts-dispersion.
• Standard deviation-variation.
Control charts for attributes:
• Attribute refers quality characteristics conform specifications or not
conform specifications.
• Monitors the number of defects or fraction defect rate present in
sample.
Types:
• P-chart: Rejected fraction non-conforming to specifications.
• np chart: Number of non-confirming items.
• C chart:Number of non-conformities.
• U chart:Number of non-conformities per unit.
Process capability:
• Output of an in-control process to specify limits by capability indices.
• Compares customer specification limits or voice of the process.
Definition:
• Minimum spread of specific measurement variation include 99.7% of
measurements from given process.
• 99.7% area (-3σ to 3σ),process capability=6σ(natural tolerance).
Purpose:
• Inherent capable of specified tolerance limits.
• Failing to meet specifications.
Process capability indices(Measures of process capability):
Process capability index Cp
• Process potential performance of natural process to spread specified. Used in
product design phase and pilot production phase.
Cp = Total specification tolerance/process capability
Cp =USL-LSL/6σ
• USL=Upper specification limit, LSL=Lower specification limit,
USL-LSL=Tolerance, σ=population standard
deviation,6σ=Process capability Cp =Capability index.
Interpretation of Cp :
• Cp >1= Process variation meeting the specifications.(better
quality, improves process capability)
• Cp˂1= Process variation not meeting the specifications.
• Cp = 1 process just meeting the specifications.
Process capability index Cpk:
• Location of process.
• Pilot production phase and routine production phase.
• Cpk = min{USL-Mean/3σ,Mean-LSL/3σ}.
• Interpretation of Cpk:
Cpk=or˂ than Cp, Cpk >1-process confirm specifications, Cpk ˂ 1-
process not conform specifications.
• Cpk = 1-process just conform specifications, Cp=Cpk-process
centered.
Inspection and measurement:
• Objective-Product quality is maintained.
• Aims-Conforming and non-conforming product,mfg variations,
discover inefficiency.
Stages(Locations)
Inspection of incoming materials(Preproduction inspection or input
inspection):
• Inspecting and checking the raw materials and parts that supplied
before stock or mfg.
• Inspection at suppliers end.
Inspection of production process(Inspection during production or
process inspection):
• Production process going on, work centres at critical production
points.
• Prevent wastage of time and money, defective units, delays.
Inspection of finished goods(Post-production inspection or output
inspection):
• Finished goods inspected and carried before marketing, poor quality
rejected.
Methods of inspection:
• 100% inspection.
• Sampling inspection.
100% inspection:
• Specifications or standards and acceptance or rejection of parts.
Sampling inspection:
• Avoid more cost, satisfactory random sample, piece by piece
inspection.
• Statistical methods-Quality, reliable.
Types of inspection:
• Inspection of variables, inspection of attributes.
• Qualitative characteristics-attributes.
• Quantified characteristics-variables.
Measurement instruments:
Based on quality of component employed.
Characteristics:
Dimensions, physical properties-quantified.
Functionality, appearance-qualified, counted, checked.
Measurement instruments for variable inspection:
Process planning activities
Measurement instruments used for attributes inspection:
Process planning activities
Selecting measuring instruments(factors considered for selecting
measuring instruments):
Set of documents required for process planning(information
required for process planning):
Process planning activities
Economics of process planning:
• Cost estimating, cost accounting, cost types, cost components,
calculation and manufacturing of product.
• Material type,mfg process, product volume, make or buy, design.
• Classification of costs, elements of costs, total cost of product.
Break even analysis:
• Cost-volume-profit analysis studies the inter-relationship among firm
sales, costs, operating profit, output levels.
• Fixed costs, variable costs, prices, sales mix.
• Effect of changes in volume on profit.
• Cost and revenues are equal-break even point.
Aims of Break even analysis:
• Profit level of o/p, cost and revenues, fixed budgeted sales, make or
buy decision, product mix, promotion mix, plant expansion decisions,
equipment replacement decisions, margin of safety, profit, business
enterprises, facility locations.
Break-even point:
• Sales level at which the total revenues and total costs are equal.
• No profit-No loss point.
• Sells above BEP-profit, Sells below BEP-loss.
• Changes fixed cost, variable cost, selling price.
Determination of break-even point:
Algebraic method, graphical method.
Algebraic method:
Break even point in terms of physical units:
• FC=fixed cost,
• VC=variable cost,
• TVC=total variable cost,
• TC=total costs,
• TR=total revenue
• Q=sales volume
• SP= selling price per unit
• Total costs = fixed cost + variable cost
Total costs=FC+(VC×Q)
• Total revenue=Selling price/unit × quantity sold
TR=SP×Q
BEP,Total costs=Total revenue
TC=TR
FC+(VC×Q)=SP×Q
QBEP=FC/(SP-VC)
Break even quantity= Fixed costs/(Selling price per unit-
Variable cost per unit)
• Break-even point in terms of sales value
Break even sales(BEP in Rs)=Fixed costs/1-(variable cost per
unit/selling price per unit)
BEP in rupees=FC/(1-(VC/SP)
Contribution
• C=SP-VC
• Companion value of revenue product sale covers fixed costs with
remainder takes profit.
• Contribution ratio=contribution/selling price
• Contribution ratio=selling price-variable cost/selling price
P/V ratio(profit-volume ratio)
p/v ratio=contribution/sales
The graphical method(break even chart):
Margin of safety:
• Difference between the existing level of output and the level of output
at BEP.
• Margin of safety(in %)=sales-sales at BEP/sales×100.
• > MOS- > Profit
• <MOS- > incurring losses
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities
Process planning activities

Más contenido relacionado

La actualidad más candente

Group Technology
Group TechnologyGroup Technology
Group Technologysgrsoni45
 
CNC PROGRAMMING FOR BEGAINER Part 1
CNC PROGRAMMING FOR BEGAINER Part 1CNC PROGRAMMING FOR BEGAINER Part 1
CNC PROGRAMMING FOR BEGAINER Part 1Parveen Kumar
 
Computer aided quality control
Computer aided quality controlComputer aided quality control
Computer aided quality controlAhmad Bajwa
 
Unit 1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURINGMohanumar S
 
APT part programming
APT part programmingAPT part programming
APT part programmingnmahi96
 
Computer generated time standards
Computer  generated time standardsComputer  generated time standards
Computer generated time standardsVenu Yadav
 
Uint 1 locating and clamping devices
Uint 1 locating and clamping devicesUint 1 locating and clamping devices
Uint 1 locating and clamping devicesS.DHARANI KUMAR
 
CNC Part programming
CNC Part programmingCNC Part programming
CNC Part programmingjani parth
 
Cncpresentation CNC lathe machine
Cncpresentation CNC lathe machineCncpresentation CNC lathe machine
Cncpresentation CNC lathe machineHaseeb Butt
 
CNC part programming
CNC part programmingCNC part programming
CNC part programmingjntuhcej
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )TAMILMECHKIT
 
Chapter 2 constructional feature of cnc machine
Chapter 2 constructional feature of cnc machineChapter 2 constructional feature of cnc machine
Chapter 2 constructional feature of cnc machineRAHUL THAKER
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGjntuhcej
 
Numerical control machines
Numerical control machines Numerical control machines
Numerical control machines jntuhcej
 
Automation 2018
Automation  2018Automation  2018
Automation 2018vcdas
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMohanKirthik
 

La actualidad más candente (20)

Group Technology
Group TechnologyGroup Technology
Group Technology
 
CNC PROGRAMMING FOR BEGAINER Part 1
CNC PROGRAMMING FOR BEGAINER Part 1CNC PROGRAMMING FOR BEGAINER Part 1
CNC PROGRAMMING FOR BEGAINER Part 1
 
Computer aided quality control
Computer aided quality controlComputer aided quality control
Computer aided quality control
 
Unit 1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
 
APT part programming
APT part programmingAPT part programming
APT part programming
 
part programming (cnc)
part programming (cnc)part programming (cnc)
part programming (cnc)
 
Computer generated time standards
Computer  generated time standardsComputer  generated time standards
Computer generated time standards
 
Cnc machine centre
Cnc machine centreCnc machine centre
Cnc machine centre
 
Uint 1 locating and clamping devices
Uint 1 locating and clamping devicesUint 1 locating and clamping devices
Uint 1 locating and clamping devices
 
CNC Part programming
CNC Part programmingCNC Part programming
CNC Part programming
 
Cncpresentation CNC lathe machine
Cncpresentation CNC lathe machineCncpresentation CNC lathe machine
Cncpresentation CNC lathe machine
 
CNC part programming
CNC part programmingCNC part programming
CNC part programming
 
NC, CNC & DNC Machine
NC, CNC & DNC Machine NC, CNC & DNC Machine
NC, CNC & DNC Machine
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
 
Chapter 2 constructional feature of cnc machine
Chapter 2 constructional feature of cnc machineChapter 2 constructional feature of cnc machine
Chapter 2 constructional feature of cnc machine
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
Numerical control machines
Numerical control machines Numerical control machines
Numerical control machines
 
Automation 2018
Automation  2018Automation  2018
Automation 2018
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATION
 
CNC Machines and its Components
CNC Machines and its ComponentsCNC Machines and its Components
CNC Machines and its Components
 

Similar a Process planning activities

Similar a Process planning activities (20)

Process planning and cost estimation unit ii
Process planning and cost estimation  unit   iiProcess planning and cost estimation  unit   ii
Process planning and cost estimation unit ii
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
SATISTICAL PROCESS CONTROL(SPC)
SATISTICAL PROCESS CONTROL(SPC)SATISTICAL PROCESS CONTROL(SPC)
SATISTICAL PROCESS CONTROL(SPC)
 
statistical process control
 statistical process control statistical process control
statistical process control
 
Spc
Spc  Spc
Spc
 
Statistical process control
Statistical process controlStatistical process control
Statistical process control
 
Rangaraj Resume_SCM
Rangaraj Resume_SCMRangaraj Resume_SCM
Rangaraj Resume_SCM
 
Statistical quality control 1,2
Statistical quality control 1,2Statistical quality control 1,2
Statistical quality control 1,2
 
Quality r (2) (2)
Quality r (2) (2)Quality r (2) (2)
Quality r (2) (2)
 
Quality r (2) (2)
Quality r (2) (2)Quality r (2) (2)
Quality r (2) (2)
 
Prasad Nimbalkar
Prasad NimbalkarPrasad Nimbalkar
Prasad Nimbalkar
 
Introduction to Production Planning and control.
Introduction to Production Planning and control.Introduction to Production Planning and control.
Introduction to Production Planning and control.
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Dipak Prajapati CV_16
Dipak Prajapati CV_16Dipak Prajapati CV_16
Dipak Prajapati CV_16
 
Sqcm
SqcmSqcm
Sqcm
 
Principles of quality management
Principles of quality managementPrinciples of quality management
Principles of quality management
 
Principles of quality management
Principles of quality managementPrinciples of quality management
Principles of quality management
 
new hemant chauhan
new hemant chauhannew hemant chauhan
new hemant chauhan
 

Más de Raja P

UNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptx
UNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptxUNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptx
UNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptxRaja P
 
UNIT-1-Introduction_to_Unconventional_Machining_Processes.pptx
UNIT-1-Introduction_to_Unconventional_Machining_Processes.pptxUNIT-1-Introduction_to_Unconventional_Machining_Processes.pptx
UNIT-1-Introduction_to_Unconventional_Machining_Processes.pptxRaja P
 
UNIT-3 -Chemical and Electro-chemical Based Processes.pptx
UNIT-3 -Chemical and Electro-chemical Based Processes.pptxUNIT-3 -Chemical and Electro-chemical Based Processes.pptx
UNIT-3 -Chemical and Electro-chemical Based Processes.pptxRaja P
 
UNIT 5 -Recent Trends in Non-Traditional Machining Processes.pptx
UNIT 5  -Recent Trends in Non-Traditional Machining Processes.pptxUNIT 5  -Recent Trends in Non-Traditional Machining Processes.pptx
UNIT 5 -Recent Trends in Non-Traditional Machining Processes.pptxRaja P
 
UNIT 4 -Advanced Nano finishing Processes.pptx
UNIT 4  -Advanced Nano finishing Processes.pptxUNIT 4  -Advanced Nano finishing Processes.pptx
UNIT 4 -Advanced Nano finishing Processes.pptxRaja P
 
UNIT-II Linear and Angular Measurements.pptx
UNIT-II Linear and Angular Measurements.pptxUNIT-II Linear and Angular Measurements.pptx
UNIT-II Linear and Angular Measurements.pptxRaja P
 
UNIT-V Advances in Metrology.pptx
UNIT-V Advances in Metrology.pptxUNIT-V Advances in Metrology.pptx
UNIT-V Advances in Metrology.pptxRaja P
 
UNIT-III Form Measurement.pptx
UNIT-III Form Measurement.pptxUNIT-III Form Measurement.pptx
UNIT-III Form Measurement.pptxRaja P
 
Unit-IV Measurement of Mechanical Parameters.ppt
Unit-IV Measurement of Mechanical Parameters.pptUnit-IV Measurement of Mechanical Parameters.ppt
Unit-IV Measurement of Mechanical Parameters.pptRaja P
 
UNIT- I Basics of Metrology.pptx
UNIT- I Basics of Metrology.pptxUNIT- I Basics of Metrology.pptx
UNIT- I Basics of Metrology.pptxRaja P
 
Ultrasonic machining process
Ultrasonic machining processUltrasonic machining process
Ultrasonic machining processRaja P
 
Electrical energy based processes
Electrical energy based processesElectrical energy based processes
Electrical energy based processesRaja P
 
Advanced manufacturing process
Advanced manufacturing processAdvanced manufacturing process
Advanced manufacturing processRaja P
 
Alternative energy sources
Alternative energy sourcesAlternative energy sources
Alternative energy sourcesRaja P
 
Steering, brakes and suspension systems
Steering, brakes and suspension systemsSteering, brakes and suspension systems
Steering, brakes and suspension systemsRaja P
 
Transmission systems
Transmission systemsTransmission systems
Transmission systemsRaja P
 
Engine auxiliary systems
Engine auxiliary systemsEngine auxiliary systems
Engine auxiliary systemsRaja P
 
Automobile Engineering
Automobile EngineeringAutomobile Engineering
Automobile EngineeringRaja P
 
Process planning and cost estimation
Process planning and cost estimationProcess planning and cost estimation
Process planning and cost estimationRaja P
 
Milling operations
Milling operationsMilling operations
Milling operationsRaja P
 

Más de Raja P (20)

UNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptx
UNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptxUNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptx
UNIT-2 -THERMAL AND ELECTRICAL ENERGY BASED PROCESSES.pptx
 
UNIT-1-Introduction_to_Unconventional_Machining_Processes.pptx
UNIT-1-Introduction_to_Unconventional_Machining_Processes.pptxUNIT-1-Introduction_to_Unconventional_Machining_Processes.pptx
UNIT-1-Introduction_to_Unconventional_Machining_Processes.pptx
 
UNIT-3 -Chemical and Electro-chemical Based Processes.pptx
UNIT-3 -Chemical and Electro-chemical Based Processes.pptxUNIT-3 -Chemical and Electro-chemical Based Processes.pptx
UNIT-3 -Chemical and Electro-chemical Based Processes.pptx
 
UNIT 5 -Recent Trends in Non-Traditional Machining Processes.pptx
UNIT 5  -Recent Trends in Non-Traditional Machining Processes.pptxUNIT 5  -Recent Trends in Non-Traditional Machining Processes.pptx
UNIT 5 -Recent Trends in Non-Traditional Machining Processes.pptx
 
UNIT 4 -Advanced Nano finishing Processes.pptx
UNIT 4  -Advanced Nano finishing Processes.pptxUNIT 4  -Advanced Nano finishing Processes.pptx
UNIT 4 -Advanced Nano finishing Processes.pptx
 
UNIT-II Linear and Angular Measurements.pptx
UNIT-II Linear and Angular Measurements.pptxUNIT-II Linear and Angular Measurements.pptx
UNIT-II Linear and Angular Measurements.pptx
 
UNIT-V Advances in Metrology.pptx
UNIT-V Advances in Metrology.pptxUNIT-V Advances in Metrology.pptx
UNIT-V Advances in Metrology.pptx
 
UNIT-III Form Measurement.pptx
UNIT-III Form Measurement.pptxUNIT-III Form Measurement.pptx
UNIT-III Form Measurement.pptx
 
Unit-IV Measurement of Mechanical Parameters.ppt
Unit-IV Measurement of Mechanical Parameters.pptUnit-IV Measurement of Mechanical Parameters.ppt
Unit-IV Measurement of Mechanical Parameters.ppt
 
UNIT- I Basics of Metrology.pptx
UNIT- I Basics of Metrology.pptxUNIT- I Basics of Metrology.pptx
UNIT- I Basics of Metrology.pptx
 
Ultrasonic machining process
Ultrasonic machining processUltrasonic machining process
Ultrasonic machining process
 
Electrical energy based processes
Electrical energy based processesElectrical energy based processes
Electrical energy based processes
 
Advanced manufacturing process
Advanced manufacturing processAdvanced manufacturing process
Advanced manufacturing process
 
Alternative energy sources
Alternative energy sourcesAlternative energy sources
Alternative energy sources
 
Steering, brakes and suspension systems
Steering, brakes and suspension systemsSteering, brakes and suspension systems
Steering, brakes and suspension systems
 
Transmission systems
Transmission systemsTransmission systems
Transmission systems
 
Engine auxiliary systems
Engine auxiliary systemsEngine auxiliary systems
Engine auxiliary systems
 
Automobile Engineering
Automobile EngineeringAutomobile Engineering
Automobile Engineering
 
Process planning and cost estimation
Process planning and cost estimationProcess planning and cost estimation
Process planning and cost estimation
 
Milling operations
Milling operationsMilling operations
Milling operations
 

Último

cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabusViolet Violet
 
IT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptxIT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptxSAJITHABANUS
 
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...Amil baba
 
Engineering Mechanics Chapter 5 Equilibrium of a Rigid Body
Engineering Mechanics  Chapter 5  Equilibrium of a Rigid BodyEngineering Mechanics  Chapter 5  Equilibrium of a Rigid Body
Engineering Mechanics Chapter 5 Equilibrium of a Rigid BodyAhmadHajasad2
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 
A Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationA Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationMohsinKhanA
 
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfSummer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfNaveenVerma126
 
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Apollo Techno Industries Pvt Ltd
 
Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...sahb78428
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptxSaiGouthamSunkara
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Projectreemakb03
 
The relationship between iot and communication technology
The relationship between iot and communication technologyThe relationship between iot and communication technology
The relationship between iot and communication technologyabdulkadirmukarram03
 
Basic Principle of Electrochemical Sensor
Basic Principle of  Electrochemical SensorBasic Principle of  Electrochemical Sensor
Basic Principle of Electrochemical SensorTanvir Moin
 
Modelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsModelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsYusuf Yıldız
 
Graphics Primitives and CG Display Devices
Graphics Primitives and CG Display DevicesGraphics Primitives and CG Display Devices
Graphics Primitives and CG Display DevicesDIPIKA83
 
Power System electrical and electronics .pptx
Power System electrical and electronics .pptxPower System electrical and electronics .pptx
Power System electrical and electronics .pptxMUKULKUMAR210
 
Nodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptxNodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptxwendy cai
 
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxUNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxrealme6igamerr
 

Último (20)

cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabus
 
IT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptxIT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptx
 
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
 
Présentation IIRB 2024 Marine Cordonnier.pdf
Présentation IIRB 2024 Marine Cordonnier.pdfPrésentation IIRB 2024 Marine Cordonnier.pdf
Présentation IIRB 2024 Marine Cordonnier.pdf
 
Engineering Mechanics Chapter 5 Equilibrium of a Rigid Body
Engineering Mechanics  Chapter 5  Equilibrium of a Rigid BodyEngineering Mechanics  Chapter 5  Equilibrium of a Rigid Body
Engineering Mechanics Chapter 5 Equilibrium of a Rigid Body
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
A Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationA Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software Simulation
 
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfSummer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
 
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
 
Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptx
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Project
 
The relationship between iot and communication technology
The relationship between iot and communication technologyThe relationship between iot and communication technology
The relationship between iot and communication technology
 
Basic Principle of Electrochemical Sensor
Basic Principle of  Electrochemical SensorBasic Principle of  Electrochemical Sensor
Basic Principle of Electrochemical Sensor
 
Modelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsModelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovations
 
Graphics Primitives and CG Display Devices
Graphics Primitives and CG Display DevicesGraphics Primitives and CG Display Devices
Graphics Primitives and CG Display Devices
 
Power System electrical and electronics .pptx
Power System electrical and electronics .pptxPower System electrical and electronics .pptx
Power System electrical and electronics .pptx
 
Lecture 2 .pdf
Lecture 2                           .pdfLecture 2                           .pdf
Lecture 2 .pdf
 
Nodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptxNodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptx
 
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxUNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
 

Process planning activities

  • 2. Introduction: • Setting process parameters, work holding devices, inspection/quality assurance methods, economics of process planning. Process parameters calculation: • Cutting speed, feed rate, depth of cut. Cutting speed: • Surface cutting speed or surface speed, relative speed b/w tool and w/p. • Tool or w/p or both may be moving during cutting.(mpm).
  • 3. Factors affecting the selection of cutting speed:
  • 6. Cutting speeds for different combinations of operation and material
  • 7. Cutting speed ranges for different combinations of work piece and tool material
  • 11. Spindle speeds and stroke speeds: • Turning, boring, milling, drilling-spindle speeds. • Shaping, planning, slotting-stroke speeds. Calculation of spindle speeds/no of strokes:
  • 13. Feed and feed rate Feed: • Distance through which tool advances into w/p during 1 revolution of the w/p or the cutter. Feed rate: • Speed at which the cutting tool penetrates the w/p. Unit: • mm/min of spindle revolution. Factors affecting feed rate: • W/p material, capacity of m/c tool, cutting tool, cutting fluid application, surface finish, operation type, nature of cut.
  • 14. Feed rates for turning and boring in mm/rev for HSS and carbide tool materials
  • 15. Feed rates for drilling in mm/rev for HSS and carbide tool drills
  • 16. Feed rates for milling in mm/tooth for HSS and carbide cutters
  • 17. Feed rates for shaping and planning: • 0.05-0.75-shaping. • 0.5-3.0-planning. Feed rates for grinding: • Cross feed surface grinding-1.0-1.5mm/pass. • Feed rate cylindrical grinding-1.0-1.5mm/pass. Depth of cut: • Thickness of the layer of metal removed in one cut or pass, direction perpendicular to the machined surface(mm). • Particular operation/c material, surface finish reqd,tool used.
  • 19. Machining time calculations: • Selecting speed, feed rate, depth of cut. Selection of jigs and fixtures: • Work holding device as jig or fixture. • Communicate to tool engg, design and drawings. Work holding device: Position and hold workpiece, precise, mfg operations. Types of work holding devices General work holding devices: • Vices, clamps, abutments, chucks, collets, centres, mandrels, face plates. Specialist work holding devices: • Jigs, fixtures. Jigs: Clamps the m/c table, align the bushes of jig with spindle. Fixtures:Clamps the m/c table, clamps the w/p during machining,welding,inspection or assembly.
  • 21. Elements of jigs and fixtures
  • 22. Principles of jigs and fixtures design factors influencing jigs and fixtures design
  • 27. General factors in workholder design and selection
  • 28. Reasons for using jigs and fixtures • Reduces marking, measuring and setting of w/p. • Automatic exact position of workpiece and tool. • Reduces production cycle time, increases production capacity. • Interchangeability of production parts. • Speed, feed, depth of cut. • Clamp rigidity of w/p. • Comfort operation. • Settings eliminated. • Reduces cost and defects.
  • 29. Types of jigs-Drill, Boring. Drill jig: • Drilling, reaming, tapping, chamfering, spot facing, counter sinking. Different types of drilling jigs: • Template, plate, open type, swinging leaf type, box type, solid type, pot type, index, multistation, universal. Boring jig: • Bore holes that is too large to drill or made on odd size. Types of fixtures: • Designed specifically operation ,carried out properly for w/p. Different types of fixtures operation: • Turning, milling, grinding, broaching, boring/drilling, tapping, welding, assembling. Construction of fixtures: • Plate, angle plate, vice-jaw, indexing.
  • 30. Standard parts for jigs and fixtures: • Mechanical fasteners, locating and supporting devices, indexing pins, drill bushes, hand knobs, handles. Selection of quality assurance methods: • Dimensional and geometric tolerances, surface finish specifications, inspection criteria, quality engineer, QA tools. • Balance b/w quality, avoid increase of time & mfg costs. Tasks: • Inspection locations, testing methods, evaluation and identification of corrective action, influences processes, equipment, tools and mfg parameters. Quality definition: • Totality of features and characteristics of a product or service, that bear on its ability to satisfy stated and implied needs of the customer. TQM definition: • Management approach of an organisation, centered on quality, participation of all its members and aiming longterm success through
  • 31. Customer satisfaction and benefits to all members of the organisation and to society. Principles/concepts of TQM
  • 33. Basic quality strategies: • Detection strategy, prevention strategy. Detection strategy: • Non-conformance is detected, various inspection methods, process is adjusted.
  • 34. Prevention strategy: • Non-conformance is minimized/eliminated.
  • 35. Seven statistical tools of quality:(Q-7)
  • 36. Statistical quality control: • Employing inspection methodologies from statistical sampling theory to conformance requirements. • Inspected samples of batch in statistical interferences, conclusions for whole batch. Two methods of SQC: • Statistical process control, Acceptance sampling. Assignable and chance causes of variations: • Two objects exactly alike, degree of inherent variability. Four sources of variations: • Processes, materials, operations, miscellaneous factors. • Miscellaneous- heat, light, humidity. Assignable causes of variations: Larger in magnitude and easily traced and detected. Reasons • Differences among machines, materials, processes, overtime, relationship to one another.
  • 37. • Analyzing data, identify and eliminate remedial actions. Chance or random or common causes of variations: • Inevitable in any process, difficult to trace and control, best conditions of production, random manner. • Human variability from one operation cycle to next by raw materials, fluctuations, lack of skills. • Process operating under stable system of chance causes said to be statistical control. Control charts: • Graph that displays data taken over time and variations of this data. Uses • Process is statistically or not,variability,capability of production,variation,effect of process change. Types • Control charts for variables, attributes.
  • 39. Control charts for variables: • Quality characteristics measured and expressed in specific units of measurements. Types: • Average,range,standard deviation charts. • Average charts-monitor centering. • Range charts-dispersion. • Standard deviation-variation. Control charts for attributes: • Attribute refers quality characteristics conform specifications or not conform specifications. • Monitors the number of defects or fraction defect rate present in sample. Types: • P-chart: Rejected fraction non-conforming to specifications. • np chart: Number of non-confirming items.
  • 40. • C chart:Number of non-conformities. • U chart:Number of non-conformities per unit.
  • 41. Process capability: • Output of an in-control process to specify limits by capability indices. • Compares customer specification limits or voice of the process. Definition: • Minimum spread of specific measurement variation include 99.7% of measurements from given process. • 99.7% area (-3σ to 3σ),process capability=6σ(natural tolerance). Purpose: • Inherent capable of specified tolerance limits. • Failing to meet specifications. Process capability indices(Measures of process capability): Process capability index Cp • Process potential performance of natural process to spread specified. Used in product design phase and pilot production phase. Cp = Total specification tolerance/process capability Cp =USL-LSL/6σ
  • 42. • USL=Upper specification limit, LSL=Lower specification limit, USL-LSL=Tolerance, σ=population standard deviation,6σ=Process capability Cp =Capability index. Interpretation of Cp : • Cp >1= Process variation meeting the specifications.(better quality, improves process capability) • Cp˂1= Process variation not meeting the specifications. • Cp = 1 process just meeting the specifications. Process capability index Cpk: • Location of process. • Pilot production phase and routine production phase. • Cpk = min{USL-Mean/3σ,Mean-LSL/3σ}. • Interpretation of Cpk: Cpk=or˂ than Cp, Cpk >1-process confirm specifications, Cpk ˂ 1- process not conform specifications.
  • 43. • Cpk = 1-process just conform specifications, Cp=Cpk-process centered. Inspection and measurement: • Objective-Product quality is maintained. • Aims-Conforming and non-conforming product,mfg variations, discover inefficiency. Stages(Locations) Inspection of incoming materials(Preproduction inspection or input inspection): • Inspecting and checking the raw materials and parts that supplied before stock or mfg. • Inspection at suppliers end. Inspection of production process(Inspection during production or process inspection): • Production process going on, work centres at critical production points. • Prevent wastage of time and money, defective units, delays.
  • 44. Inspection of finished goods(Post-production inspection or output inspection): • Finished goods inspected and carried before marketing, poor quality rejected. Methods of inspection: • 100% inspection. • Sampling inspection. 100% inspection: • Specifications or standards and acceptance or rejection of parts. Sampling inspection: • Avoid more cost, satisfactory random sample, piece by piece inspection. • Statistical methods-Quality, reliable. Types of inspection: • Inspection of variables, inspection of attributes. • Qualitative characteristics-attributes.
  • 46. Measurement instruments: Based on quality of component employed. Characteristics: Dimensions, physical properties-quantified. Functionality, appearance-qualified, counted, checked. Measurement instruments for variable inspection:
  • 48. Measurement instruments used for attributes inspection:
  • 50. Selecting measuring instruments(factors considered for selecting measuring instruments):
  • 51. Set of documents required for process planning(information required for process planning):
  • 53. Economics of process planning: • Cost estimating, cost accounting, cost types, cost components, calculation and manufacturing of product. • Material type,mfg process, product volume, make or buy, design. • Classification of costs, elements of costs, total cost of product. Break even analysis: • Cost-volume-profit analysis studies the inter-relationship among firm sales, costs, operating profit, output levels. • Fixed costs, variable costs, prices, sales mix. • Effect of changes in volume on profit. • Cost and revenues are equal-break even point. Aims of Break even analysis: • Profit level of o/p, cost and revenues, fixed budgeted sales, make or buy decision, product mix, promotion mix, plant expansion decisions, equipment replacement decisions, margin of safety, profit, business enterprises, facility locations.
  • 54. Break-even point: • Sales level at which the total revenues and total costs are equal. • No profit-No loss point. • Sells above BEP-profit, Sells below BEP-loss. • Changes fixed cost, variable cost, selling price. Determination of break-even point: Algebraic method, graphical method. Algebraic method: Break even point in terms of physical units: • FC=fixed cost, • VC=variable cost, • TVC=total variable cost, • TC=total costs, • TR=total revenue • Q=sales volume
  • 55. • SP= selling price per unit • Total costs = fixed cost + variable cost Total costs=FC+(VC×Q) • Total revenue=Selling price/unit × quantity sold TR=SP×Q BEP,Total costs=Total revenue TC=TR FC+(VC×Q)=SP×Q QBEP=FC/(SP-VC) Break even quantity= Fixed costs/(Selling price per unit- Variable cost per unit) • Break-even point in terms of sales value Break even sales(BEP in Rs)=Fixed costs/1-(variable cost per unit/selling price per unit) BEP in rupees=FC/(1-(VC/SP)
  • 56. Contribution • C=SP-VC • Companion value of revenue product sale covers fixed costs with remainder takes profit. • Contribution ratio=contribution/selling price • Contribution ratio=selling price-variable cost/selling price P/V ratio(profit-volume ratio) p/v ratio=contribution/sales The graphical method(break even chart):
  • 57. Margin of safety: • Difference between the existing level of output and the level of output at BEP. • Margin of safety(in %)=sales-sales at BEP/sales×100. • > MOS- > Profit • <MOS- > incurring losses