Overview
• The New Solar Guidelines
• The New Wind Guidelines
• Drawbacks
• Conclusion
2
The New Solar Guidelines
• New guidelines for the Tariff Based Competitive Bidding Process for Procurement of Power from Grid
Connected Solar PV Power Projects were published on 3rd August 2017 (the “New Solar Guidelines”)
• Objectives
- Further promote competitive bidding
- Facilitate transparency and fairness
- Provide a framework for an Intermediary Procurer as an aggregator for the sale and purchase of
power
- Standardization, uniformity and a risk sharing framework, encouraging investment and
increasing bankability and profitability
3
The New Solar Guidelines
• The New Solar Guidelines are issued pursuant to section 63 of the Electricity Act for procuring long
term electricity from solar projects of 5MW and above
• Defined Terms
- “Appropriate Commission” means:
- the State Electricity Regulatory Commission where the Distribution Licensee is located
- Where there are more than one Distribution Licensees, it is the Central State Electricity
Regulatory Authority
- “Authorized Representative” means, where the PPA signing agency and the agency tendering
the project are different, the agency tendering the project
- “Distribution Licensee” means a DISCOM
- “End Procurer” means a Distribution Licensee
4
The New Solar Guidelines
• Defined Terms
- “Intermediary Procurer” means a trading entity that aggregates the solar power purchased by
different Solar Power Generators, selling it to a Distribution Licensee
- “Procurer” means a Distribution Licensee, Authorized Representative or an Intermediary
Procurer
- “PSA” means a power sale agreement between the the Intermediary Procurer and the End
Procurer
- “PPA” means a power purchase agreement between the Intermediary Procurer and the Solar
Power Generator
- “Solar Power Generator” means the generator
- “Standard Bidding Documents” include the model Request for Selection, the PPA and the PSA
5
The New Solar Guidelines
• Bid Documentation
- Standard form in accordance with the New Guidelines and the Standard Bidding Documents
- Deviations must be approved by the Appropriate Commission
- Standard Bidding Documents have not yet been published? Conflict?
- Procurement of Clearances
- Lease agreement, cleared by relevant authority
- End Procurer clearance of the draft Standard Bidding Documents
- (If applicable) clearance by the Solar Power Park Developer, with a draft Implementation
Agreement consistent with the Standard Bidding Documents
6
The New Solar Guidelines
• Bid Structure
- Package of a minimum 50MW (subject to exceptions) and bidder to quote for entire package
- Selection of fixed tariff or escalating tariff (cannot be more than the tariff for grid connected
solar projects notified by the Appropriate Commission)
- Possibility of VGF based bidding offered by the Procurer to the Solar Power Generator
• Eligible Bidders
- Procurers may set minimum technical criteria depending on the effect it would have on the pool
of eligible bidders
- Financial criteria (Net Worth of at least 20 per cent of the CERC Benchmark Capital Cost)
- Additional liquidity tests (including annual turnover, bank references)
7
The New Solar Guidelines
• Eligible Bidders
- Successful bidder must ensure shareholding in SPV remains at least at 51 per cent until one year
from the Commercial Operation Date
- Post COD, the developer can exit, creating a secondary market and releasing capital
• The PPA
- Longer terms at lower tariffs (but tariffs keep dropping) and not less than 25 years
- Capacity Utilization Factor (“CUF”) (the ratio of actual output to maximum possible output)
- If below minimum CUF, penalty for shortfall (for all potential costs of the Procurer, subject to a
[minimum] of 25% if the cost of the shortfall calculated at PPA tariff (Clause 5.2.1(a))
- Excess of the maximum CUF specified can be sold to third parties subject to right of first refusal
- If Procurer purchases excess, then it will be at 75% of the PPA tariff
8
The New Solar Guidelines
• Payment Security
- Scenario 1 (Direct Procurement)
• Procurer to provide Solar Power Generator with an revolving Letter of Credit for not less
than one months’ average billings
• Payment Security Fund to provide at least 3 months’ billings
• Procurer may also choose to provide a State Government Guarantee, providing adequate
security for energy charges and termination compensation if any
• Condition that recourse is first made to the Letter of Credit and the Payment Security
Fund
9
The New Solar Guidelines
- Scenario 2 (Intermediary Procurer to Solar Power Generator)
• Intermediary Procurer to provide Solar Power Generator with
- A revolving letter of credit for not less than one months’ average billings
- Payment Security Fund to provide at least 3 months’ billings
• End Procurer to Intermediary Procurer (back-to-back)
- Payment Security from End Procurer to Intermediary Procurer
- Revolving letter of credit for not less than on months’ average billings and
- State Government Guarantee for energy charges and termination compensation if
any
- Payment Security Fund
10
The New Solar Guidelines
• Off-take Constraints (Transmission Infrastructure not built)
- Compensation?
• 19% of CUF or committed CUF, whichever is lower – generation loss
• Any compensation from grid builder offset amounts owed by End Procurer?
• Off-take Constraints (Temporary Grid Unavailability)
- Compensation?
• Generation loss formula (average generation x unavailability) or
• Generation compensation at PPA tariff for the generation loss
11
The New Solar Guidelines
• Events of Default
- Solar Power Generator Event of Default
• PPA damages and forfeiture of bank guarantee (limitation of liability and consequential
loss?)
• Lender right of substitution (step-in)
• If no step-in, then the Procurer may terminate and acquire the asset at 90 per cent of the
debt due, or failing which, the Lenders may exercise their security
- Procurer Event of Default
• Novation to a third party procurer with consent of Solar Power Generator
• Solar Power Generator may terminate, triggering debt due and 150 per cent of adjusted
equity
12
The New Solar Guidelines
• Events of Default
- Procurer Event of Default
• Pay the Solar Power Generator damages equal to 6 months of revenue, or the balance of
the amount due under the PPA and keep the project assets
• Procurer takes the risk for failure of STU or CTU to build out the transmission line
• Change in Law
- Compensation to put the suffering party in the position it would have been otherwise
• Includes change in taxes having a direct effect on the project
• Exclude tax on corporate income or withholding tax on income or dividend
13
The New Solar Guidelines
• Bank Guarantees
- Solar Power Generator shall provide the following bank guarantees
• Earnest Money Deposit of 2% of the project cost
• Performance Bank Guarantee of between 4 and 5% of the project cost
• Financial Close
- Within 7 months from the date of execution of the PPA or Performance Bank Guarantee is lost
• This will be challenging
• Land acquisition and other conditions precedent? Extensions possible
• Better to have land acquisition as a pre-condition to bid?
14
The New Solar Guidelines
• Commissioning Schedule
- 13 months from date of execution of PPA
- 15 months for projects over 250 MW
• What happens if Financial Close does not happen for 7 months?
• Delay liquidated damages?
• Extension for delay in handing over land up to one year
• Transmission Connectivity
- Who constructs the transmission line and what happens if it’s delayed or terminated?
- Who pays to have it built?
15
The New Solar Guidelines
• Transmission Connectivity
- Where project site is not specified by the Procurer, it’s up to the Solar Power Generator to
connect with the CTU or the STU
- If the site is not a solar project park, the Procurer may specify that the Solar Power Generator be
responsible for building out connectivity and arranging access
- Is this realistic given the short Commissioning Schedules?
- Only sensible for a Solar Power Generator to develop in an existing solar power park?
• Disputes
- Disputes over tariff (CERC)
- Other disputes, arbitration under the Arbitration Act
16
The New Wind Guidelines
• New guidelines for the Tariff Based Competitive Bidding Process for Procurement of Power from Grid
Connected Wind Power Projects were published on 6th December 2017 (the “New Wind Guidelines”)
- New Wind Guidelines broadly similar to the New Solar Guidelines
- Similar defined terms, bid documentation and bid structure
• Bid Submission
- Identification of 100 per cent of land acquisition at time of bid and acquisition of all the land
within 7 months
- Different from the New Solar Guidelines
• Availability of 25 per cent of land at bid initiation, possession of 90 per cent within one
month of the signing of the PPA, with the balance 10 per cent within 2 months thereafter)
- Why different?
17
The New Wind Guidelines
• The PPA
- Broadly similar to the New Solar Guidelines, term not less than 25 years
- Capacity Utilization Factor (“CUF”) slightly different
- Declared annual CUF shall be no less than 22%
- Similar compensation provisions for failure to meet CUF
• Payment Security
- Similar to the New Solar Guidelines
• Force Majeure
- In accordance with industry standards
18
The New Wind Guidelines
• Off-take Constraints (Transmission Infrastructure not built)
- The provisions in the New Solar Guidelines appear to be absent – why?
- Surely, the same risks arise?
• Off-take Constraints (Grid Unavailability)
- Compensation?
• Generation loss formula (average generation x unavailability) or
• Generation compensation at PPA tariff for the generation loss
- Similar to the New Solar Guidelines
19
The New Wind Guidelines
• Events of Default
- Broadly same as under the New Solar Guidelines
• Change in Law
- Broadly same as under the New Solar Guidelines
• Bank Guarantees
- Wind Power Generator shall provide the following bank guarantees
• Earnest Money Deposit of 2% of the project cost
• Performance Bank Guarantee not more than 5% of the project cost
20
The New Wind Guidelines
• Financial Close
- Within 7 months from the date of execution of the PPA or Performance Bank Guarantee is lost
- Force majeure extension and discretionary extensions for other reasons?
• Commissioning Schedule
- 18 months from the date of execution of the PPA
• Eligible Bidders
- Similar to the New Solar Guidelines - Procurers may set minimum technical criteria depending
on the effect it would have on the pool of eligible bidders
- Financial criteria (Net Worth of at least 20 per cent of the capital costs of the project)
- Additional liquidity tests (including annual turnover, bank references)
21
The New Wind Guidelines
• Transmission Connectivity
- Obligation on the Wind Power Generator
- Broadly similar to the New Solar Guidelines
• Arbitration
- Same as the New Solar Guidelines
22
Drawbacks
• Payment Security
- One months revolving letter of credit?
- Off-set by potential termination payments?
• Payment Security Fund
- How will it be funded?
- Condition precedent to Financial Close
- Lender security over the account
• Transmission line risk?
• Timelines realistic?
23
Conclusion
• Generally, the payment security approved in the New Solar Guidelines has not been seen in PPAs signed
by the DISCOMS in the past, which is a step forward
• Specific references to State Government Guarantees for Procurer’s off-take obligations is encouraging
• Clarification of termination payments to cover debt an encouraging step forward to bankability
24
Contact
BANGALORE DELHI
101, 1st Floor, “Embassy Classic” 2nd Floor, Block D, The Mira
#11, Vittal Mallya Road Mathura Road, Ishwar Nagar
Bangalore, 560 001 New Delhi 110 065
T: +91 80 4072 6600 T: +91 120 472 8100
E: bangalore@induslaw.com E: delhi@induslaw.com
HYDERABAD MUMBAI
204, Ashoka Capitol 1002A, 10th Floor, Tower 2, Indiabulls Financial Center
Road No.2, Banjara Hills Senapati Bapat Marg, Lower Parel (W)
Hyderabad, 500 034 Mumbai, 400 013
T: +91 40 4026 4624 T: +91 22 4920 7200
E: hyderabad@induslaw.com E: mumbai@induslaw.com
DISCLAIMER
This presentation is for information purposes only. Nothing contained herein is, purports to be, or is intended as legal advice and you should
seek legal advice before you act on any information or view expressed herein.
Although we have endeavored to accurately reflect the subject matter of this presentation, we make no representation or warranty, express or
implied, in any manner whatsoever in connection with its contents.
No recipient of this presentation should construe it as an attempt to solicit business in any manner whatsoever.
25

More Related Content

What's hot

Contracts for difference
Contracts for differenceContracts for difference
Contracts for differenceGeoff White
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluationChirag Jain
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Gensol Engineering Limited
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economicsChirag Jain
 
200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALA200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALATahnoon Elahi
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreementChirag Jain
 
Session 21 preparation of techno commercial report
Session 21   preparation of techno commercial reportSession 21   preparation of techno commercial report
Session 21 preparation of techno commercial reportChirag Jain
 
Session 01 Introduction to the course
Session 01   Introduction to the courseSession 01   Introduction to the course
Session 01 Introduction to the courseChirag Jain
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Amitava Nag
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Gensol Engineering Limited
 
POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)Munira Abubakari
 
Incentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based IncentivesIncentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based IncentivesHIMADRI BANERJI
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmDNVGLEnergy
 
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?madhavanvee
 

What's hot (20)

Contracts for difference
Contracts for differenceContracts for difference
Contracts for difference
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluation
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economics
 
200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALA200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALA
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Abt meter
Abt meterAbt meter
Abt meter
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
Session 21 preparation of techno commercial report
Session 21   preparation of techno commercial reportSession 21   preparation of techno commercial report
Session 21 preparation of techno commercial report
 
Session 01 Introduction to the course
Session 01   Introduction to the courseSession 01   Introduction to the course
Session 01 Introduction to the course
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
Potential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passedPotential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passed
 
POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)
 
Incentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based IncentivesIncentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based Incentives
 
Power Market regulation
Power Market regulationPower Market regulation
Power Market regulation
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
 
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
 

Similar to India's New Guidelines for Solar & Wind Projects: A New Bankable Model?

Newjersey solar pres
Newjersey solar presNewjersey solar pres
Newjersey solar presmarzan
 
Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...
   Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...   Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...
Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...Dr. Oliver Massmann
 
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerRf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerPratap Malempati
 
Solar Energy Forum
Solar Energy ForumSolar Energy Forum
Solar Energy ForumEddie Egger
 
MARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTORMARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTORRanbir Ghosh
 
Summary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarSummary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarPratap Malempati
 
coned-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdfconed-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdfJose Morales
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNAIPPAI
 
Solar PV Net meetering explained
Solar PV Net meetering explainedSolar PV Net meetering explained
Solar PV Net meetering explainedAndy Varoshiotis
 
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...prashantkumarchinama
 
Sbi rooftop program
Sbi rooftop programSbi rooftop program
Sbi rooftop programJay Ranvir
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxsonu1811
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access MaharashtraJay Ranvir
 
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"seleven
 
Mcc tariff models dr harish ahuja
Mcc tariff models dr harish ahujaMcc tariff models dr harish ahuja
Mcc tariff models dr harish ahujamcci175
 
Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Dr. Oliver Massmann
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesSaurabh Mehta
 
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...Dr. Oliver Massmann
 

Similar to India's New Guidelines for Solar & Wind Projects: A New Bankable Model? (20)

Newjersey solar pres
Newjersey solar presNewjersey solar pres
Newjersey solar pres
 
Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...
   Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...   Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...
Lawyer in Vietnam Dr. Oliver Massmann Solar Power Investments - Latest upd...
 
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerRf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
 
Solar Energy Forum
Solar Energy ForumSolar Energy Forum
Solar Energy Forum
 
MARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTORMARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTOR
 
Summary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarSummary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind Solar
 
coned-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdfconed-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdf
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
 
Solar PV Net meetering explained
Solar PV Net meetering explainedSolar PV Net meetering explained
Solar PV Net meetering explained
 
CfDs in Albania
CfDs in AlbaniaCfDs in Albania
CfDs in Albania
 
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
 
Debt Financing Options for C&I Rooftop Solar PV
Debt Financing Options for C&I Rooftop Solar PVDebt Financing Options for C&I Rooftop Solar PV
Debt Financing Options for C&I Rooftop Solar PV
 
Sbi rooftop program
Sbi rooftop programSbi rooftop program
Sbi rooftop program
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptx
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access Maharashtra
 
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
 
Mcc tariff models dr harish ahuja
Mcc tariff models dr harish ahujaMcc tariff models dr harish ahuja
Mcc tariff models dr harish ahuja
 
Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
 

More from Ran Chakrabarti

Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)
Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)
Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)Ran Chakrabarti
 
Merger Control Regime & M&A in India
Merger Control Regime & M&A in IndiaMerger Control Regime & M&A in India
Merger Control Regime & M&A in IndiaRan Chakrabarti
 
Doing Business in India | Warsaw | Poland | 24 April 2018
Doing Business in India | Warsaw | Poland | 24 April 2018Doing Business in India | Warsaw | Poland | 24 April 2018
Doing Business in India | Warsaw | Poland | 24 April 2018Ran Chakrabarti
 
Do the Risks Outweigh the Rewards?
Do the Risks Outweigh the Rewards?Do the Risks Outweigh the Rewards?
Do the Risks Outweigh the Rewards?Ran Chakrabarti
 
Cross Border Insolvency - Key Issues
Cross Border Insolvency - Key IssuesCross Border Insolvency - Key Issues
Cross Border Insolvency - Key IssuesRan Chakrabarti
 
Projects & Project Financing in india
Projects & Project Financing in indiaProjects & Project Financing in india
Projects & Project Financing in indiaRan Chakrabarti
 

More from Ran Chakrabarti (6)

Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)
Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)
Legal issues in infrastructure: Risk Allocation & Mitigation (July 2017)
 
Merger Control Regime & M&A in India
Merger Control Regime & M&A in IndiaMerger Control Regime & M&A in India
Merger Control Regime & M&A in India
 
Doing Business in India | Warsaw | Poland | 24 April 2018
Doing Business in India | Warsaw | Poland | 24 April 2018Doing Business in India | Warsaw | Poland | 24 April 2018
Doing Business in India | Warsaw | Poland | 24 April 2018
 
Do the Risks Outweigh the Rewards?
Do the Risks Outweigh the Rewards?Do the Risks Outweigh the Rewards?
Do the Risks Outweigh the Rewards?
 
Cross Border Insolvency - Key Issues
Cross Border Insolvency - Key IssuesCross Border Insolvency - Key Issues
Cross Border Insolvency - Key Issues
 
Projects & Project Financing in india
Projects & Project Financing in indiaProjects & Project Financing in india
Projects & Project Financing in india
 

Recently uploaded

Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfWhy Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfMilind Agarwal
 
一比一原版旧金山州立大学毕业证学位证书
 一比一原版旧金山州立大学毕业证学位证书 一比一原版旧金山州立大学毕业证学位证书
一比一原版旧金山州立大学毕业证学位证书SS A
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm2020000445musaib
 
如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书Fir L
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书Fir sss
 
Cleades Robinson's Commitment to Service
Cleades Robinson's Commitment to ServiceCleades Robinson's Commitment to Service
Cleades Robinson's Commitment to ServiceCleades Robinson
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...James Watkins, III JD CFP®
 
如何办理(Lincoln文凭证书)林肯大学毕业证学位证书
如何办理(Lincoln文凭证书)林肯大学毕业证学位证书如何办理(Lincoln文凭证书)林肯大学毕业证学位证书
如何办理(Lincoln文凭证书)林肯大学毕业证学位证书Fs Las
 
如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书Fir L
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》o8wvnojp
 
Understanding Social Media Bullying: Legal Implications and Challenges
Understanding Social Media Bullying: Legal Implications and ChallengesUnderstanding Social Media Bullying: Legal Implications and Challenges
Understanding Social Media Bullying: Legal Implications and ChallengesFinlaw Associates
 
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceanilsa9823
 
一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书E LSS
 
Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126Oishi8
 
Introduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionIntroduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionAnuragMishra811030
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 

Recently uploaded (20)

Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfWhy Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
 
Old Income Tax Regime Vs New Income Tax Regime
Old  Income Tax Regime Vs  New Income Tax   RegimeOld  Income Tax Regime Vs  New Income Tax   Regime
Old Income Tax Regime Vs New Income Tax Regime
 
一比一原版旧金山州立大学毕业证学位证书
 一比一原版旧金山州立大学毕业证学位证书 一比一原版旧金山州立大学毕业证学位证书
一比一原版旧金山州立大学毕业证学位证书
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm
 
如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书
 
Cleades Robinson's Commitment to Service
Cleades Robinson's Commitment to ServiceCleades Robinson's Commitment to Service
Cleades Robinson's Commitment to Service
 
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...
 
如何办理(Lincoln文凭证书)林肯大学毕业证学位证书
如何办理(Lincoln文凭证书)林肯大学毕业证学位证书如何办理(Lincoln文凭证书)林肯大学毕业证学位证书
如何办理(Lincoln文凭证书)林肯大学毕业证学位证书
 
如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
 
Understanding Social Media Bullying: Legal Implications and Challenges
Understanding Social Media Bullying: Legal Implications and ChallengesUnderstanding Social Media Bullying: Legal Implications and Challenges
Understanding Social Media Bullying: Legal Implications and Challenges
 
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
 
一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书
 
Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126
 
Introduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionIntroduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusion
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 

India's New Guidelines for Solar & Wind Projects: A New Bankable Model?

  • 1. The New Competitive Bidding Guidelines: Addressing DISCOM Offtake & PPA Risks? Ran Chakrabarti Partner 17 January 2018
  • 2. Overview • The New Solar Guidelines • The New Wind Guidelines • Drawbacks • Conclusion 2
  • 3. The New Solar Guidelines • New guidelines for the Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects were published on 3rd August 2017 (the “New Solar Guidelines”) • Objectives - Further promote competitive bidding - Facilitate transparency and fairness - Provide a framework for an Intermediary Procurer as an aggregator for the sale and purchase of power - Standardization, uniformity and a risk sharing framework, encouraging investment and increasing bankability and profitability 3
  • 4. The New Solar Guidelines • The New Solar Guidelines are issued pursuant to section 63 of the Electricity Act for procuring long term electricity from solar projects of 5MW and above • Defined Terms - “Appropriate Commission” means: - the State Electricity Regulatory Commission where the Distribution Licensee is located - Where there are more than one Distribution Licensees, it is the Central State Electricity Regulatory Authority - “Authorized Representative” means, where the PPA signing agency and the agency tendering the project are different, the agency tendering the project - “Distribution Licensee” means a DISCOM - “End Procurer” means a Distribution Licensee 4
  • 5. The New Solar Guidelines • Defined Terms - “Intermediary Procurer” means a trading entity that aggregates the solar power purchased by different Solar Power Generators, selling it to a Distribution Licensee - “Procurer” means a Distribution Licensee, Authorized Representative or an Intermediary Procurer - “PSA” means a power sale agreement between the the Intermediary Procurer and the End Procurer - “PPA” means a power purchase agreement between the Intermediary Procurer and the Solar Power Generator - “Solar Power Generator” means the generator - “Standard Bidding Documents” include the model Request for Selection, the PPA and the PSA 5
  • 6. The New Solar Guidelines • Bid Documentation - Standard form in accordance with the New Guidelines and the Standard Bidding Documents - Deviations must be approved by the Appropriate Commission - Standard Bidding Documents have not yet been published? Conflict? - Procurement of Clearances - Lease agreement, cleared by relevant authority - End Procurer clearance of the draft Standard Bidding Documents - (If applicable) clearance by the Solar Power Park Developer, with a draft Implementation Agreement consistent with the Standard Bidding Documents 6
  • 7. The New Solar Guidelines • Bid Structure - Package of a minimum 50MW (subject to exceptions) and bidder to quote for entire package - Selection of fixed tariff or escalating tariff (cannot be more than the tariff for grid connected solar projects notified by the Appropriate Commission) - Possibility of VGF based bidding offered by the Procurer to the Solar Power Generator • Eligible Bidders - Procurers may set minimum technical criteria depending on the effect it would have on the pool of eligible bidders - Financial criteria (Net Worth of at least 20 per cent of the CERC Benchmark Capital Cost) - Additional liquidity tests (including annual turnover, bank references) 7
  • 8. The New Solar Guidelines • Eligible Bidders - Successful bidder must ensure shareholding in SPV remains at least at 51 per cent until one year from the Commercial Operation Date - Post COD, the developer can exit, creating a secondary market and releasing capital • The PPA - Longer terms at lower tariffs (but tariffs keep dropping) and not less than 25 years - Capacity Utilization Factor (“CUF”) (the ratio of actual output to maximum possible output) - If below minimum CUF, penalty for shortfall (for all potential costs of the Procurer, subject to a [minimum] of 25% if the cost of the shortfall calculated at PPA tariff (Clause 5.2.1(a)) - Excess of the maximum CUF specified can be sold to third parties subject to right of first refusal - If Procurer purchases excess, then it will be at 75% of the PPA tariff 8
  • 9. The New Solar Guidelines • Payment Security - Scenario 1 (Direct Procurement) • Procurer to provide Solar Power Generator with an revolving Letter of Credit for not less than one months’ average billings • Payment Security Fund to provide at least 3 months’ billings • Procurer may also choose to provide a State Government Guarantee, providing adequate security for energy charges and termination compensation if any • Condition that recourse is first made to the Letter of Credit and the Payment Security Fund 9
  • 10. The New Solar Guidelines - Scenario 2 (Intermediary Procurer to Solar Power Generator) • Intermediary Procurer to provide Solar Power Generator with - A revolving letter of credit for not less than one months’ average billings - Payment Security Fund to provide at least 3 months’ billings • End Procurer to Intermediary Procurer (back-to-back) - Payment Security from End Procurer to Intermediary Procurer - Revolving letter of credit for not less than on months’ average billings and - State Government Guarantee for energy charges and termination compensation if any - Payment Security Fund 10
  • 11. The New Solar Guidelines • Off-take Constraints (Transmission Infrastructure not built) - Compensation? • 19% of CUF or committed CUF, whichever is lower – generation loss • Any compensation from grid builder offset amounts owed by End Procurer? • Off-take Constraints (Temporary Grid Unavailability) - Compensation? • Generation loss formula (average generation x unavailability) or • Generation compensation at PPA tariff for the generation loss 11
  • 12. The New Solar Guidelines • Events of Default - Solar Power Generator Event of Default • PPA damages and forfeiture of bank guarantee (limitation of liability and consequential loss?) • Lender right of substitution (step-in) • If no step-in, then the Procurer may terminate and acquire the asset at 90 per cent of the debt due, or failing which, the Lenders may exercise their security - Procurer Event of Default • Novation to a third party procurer with consent of Solar Power Generator • Solar Power Generator may terminate, triggering debt due and 150 per cent of adjusted equity 12
  • 13. The New Solar Guidelines • Events of Default - Procurer Event of Default • Pay the Solar Power Generator damages equal to 6 months of revenue, or the balance of the amount due under the PPA and keep the project assets • Procurer takes the risk for failure of STU or CTU to build out the transmission line • Change in Law - Compensation to put the suffering party in the position it would have been otherwise • Includes change in taxes having a direct effect on the project • Exclude tax on corporate income or withholding tax on income or dividend 13
  • 14. The New Solar Guidelines • Bank Guarantees - Solar Power Generator shall provide the following bank guarantees • Earnest Money Deposit of 2% of the project cost • Performance Bank Guarantee of between 4 and 5% of the project cost • Financial Close - Within 7 months from the date of execution of the PPA or Performance Bank Guarantee is lost • This will be challenging • Land acquisition and other conditions precedent? Extensions possible • Better to have land acquisition as a pre-condition to bid? 14
  • 15. The New Solar Guidelines • Commissioning Schedule - 13 months from date of execution of PPA - 15 months for projects over 250 MW • What happens if Financial Close does not happen for 7 months? • Delay liquidated damages? • Extension for delay in handing over land up to one year • Transmission Connectivity - Who constructs the transmission line and what happens if it’s delayed or terminated? - Who pays to have it built? 15
  • 16. The New Solar Guidelines • Transmission Connectivity - Where project site is not specified by the Procurer, it’s up to the Solar Power Generator to connect with the CTU or the STU - If the site is not a solar project park, the Procurer may specify that the Solar Power Generator be responsible for building out connectivity and arranging access - Is this realistic given the short Commissioning Schedules? - Only sensible for a Solar Power Generator to develop in an existing solar power park? • Disputes - Disputes over tariff (CERC) - Other disputes, arbitration under the Arbitration Act 16
  • 17. The New Wind Guidelines • New guidelines for the Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Wind Power Projects were published on 6th December 2017 (the “New Wind Guidelines”) - New Wind Guidelines broadly similar to the New Solar Guidelines - Similar defined terms, bid documentation and bid structure • Bid Submission - Identification of 100 per cent of land acquisition at time of bid and acquisition of all the land within 7 months - Different from the New Solar Guidelines • Availability of 25 per cent of land at bid initiation, possession of 90 per cent within one month of the signing of the PPA, with the balance 10 per cent within 2 months thereafter) - Why different? 17
  • 18. The New Wind Guidelines • The PPA - Broadly similar to the New Solar Guidelines, term not less than 25 years - Capacity Utilization Factor (“CUF”) slightly different - Declared annual CUF shall be no less than 22% - Similar compensation provisions for failure to meet CUF • Payment Security - Similar to the New Solar Guidelines • Force Majeure - In accordance with industry standards 18
  • 19. The New Wind Guidelines • Off-take Constraints (Transmission Infrastructure not built) - The provisions in the New Solar Guidelines appear to be absent – why? - Surely, the same risks arise? • Off-take Constraints (Grid Unavailability) - Compensation? • Generation loss formula (average generation x unavailability) or • Generation compensation at PPA tariff for the generation loss - Similar to the New Solar Guidelines 19
  • 20. The New Wind Guidelines • Events of Default - Broadly same as under the New Solar Guidelines • Change in Law - Broadly same as under the New Solar Guidelines • Bank Guarantees - Wind Power Generator shall provide the following bank guarantees • Earnest Money Deposit of 2% of the project cost • Performance Bank Guarantee not more than 5% of the project cost 20
  • 21. The New Wind Guidelines • Financial Close - Within 7 months from the date of execution of the PPA or Performance Bank Guarantee is lost - Force majeure extension and discretionary extensions for other reasons? • Commissioning Schedule - 18 months from the date of execution of the PPA • Eligible Bidders - Similar to the New Solar Guidelines - Procurers may set minimum technical criteria depending on the effect it would have on the pool of eligible bidders - Financial criteria (Net Worth of at least 20 per cent of the capital costs of the project) - Additional liquidity tests (including annual turnover, bank references) 21
  • 22. The New Wind Guidelines • Transmission Connectivity - Obligation on the Wind Power Generator - Broadly similar to the New Solar Guidelines • Arbitration - Same as the New Solar Guidelines 22
  • 23. Drawbacks • Payment Security - One months revolving letter of credit? - Off-set by potential termination payments? • Payment Security Fund - How will it be funded? - Condition precedent to Financial Close - Lender security over the account • Transmission line risk? • Timelines realistic? 23
  • 24. Conclusion • Generally, the payment security approved in the New Solar Guidelines has not been seen in PPAs signed by the DISCOMS in the past, which is a step forward • Specific references to State Government Guarantees for Procurer’s off-take obligations is encouraging • Clarification of termination payments to cover debt an encouraging step forward to bankability 24
  • 25. Contact BANGALORE DELHI 101, 1st Floor, “Embassy Classic” 2nd Floor, Block D, The Mira #11, Vittal Mallya Road Mathura Road, Ishwar Nagar Bangalore, 560 001 New Delhi 110 065 T: +91 80 4072 6600 T: +91 120 472 8100 E: bangalore@induslaw.com E: delhi@induslaw.com HYDERABAD MUMBAI 204, Ashoka Capitol 1002A, 10th Floor, Tower 2, Indiabulls Financial Center Road No.2, Banjara Hills Senapati Bapat Marg, Lower Parel (W) Hyderabad, 500 034 Mumbai, 400 013 T: +91 40 4026 4624 T: +91 22 4920 7200 E: hyderabad@induslaw.com E: mumbai@induslaw.com DISCLAIMER This presentation is for information purposes only. Nothing contained herein is, purports to be, or is intended as legal advice and you should seek legal advice before you act on any information or view expressed herein. Although we have endeavored to accurately reflect the subject matter of this presentation, we make no representation or warranty, express or implied, in any manner whatsoever in connection with its contents. No recipient of this presentation should construe it as an attempt to solicit business in any manner whatsoever. 25