Earned Value Management Project Analysis

Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Próximo SlideShare
7.4 Forecasting Techniques
7.4 Forecasting Techniques
Cargando en…3
×

Eche un vistazo a continuación

1 de 6 Anuncio

Más Contenido Relacionado

Similares a Earned Value Management Project Analysis (20)

Anuncio

Más reciente (20)

Earned Value Management Project Analysis

  1. 1. SIMPLE SAMPLE MEMORANDUM ROGER H. MANDEL Rmandel@PramsCo.com Mobile #: 858-735-2038 Date: 30 April 2018 To: Program Management Subj.: EARNED VALUE PROJECT MANAGEMENT ANALYSIS REPORT, Data through 31 March 2018 1. Summary Status: a. Data indicates the performance changes, as shown on Figure #1, from 31 January 2017 to 31 March 2018 as follows: i. Percent scheduled to be completed at 68.02% ii. Percent complete 46.76%, about 22% behind schedule iii. Percent Spent of Budget at 64.39%, about 17.63% cost overrun iv. Percent spent of Latest Revised Estimate at 54.71% Figure #1 - 2,000,000 4,000,000 6,000,000 8,000,000 10,000,000 12,000,000 14,000,000 16,000,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 SIMPLE SAMPLE Budget $13.9M Planned $9.48M Schedule Variance $2.98M Cost Variance in $2.45M SAMPLE Page 1
  2. 2. SIMPLE SAMPLE 2. Trends, as shown on Figure #2: a. With 15 months of data: i. Schedule performance changed from 69.3% to 68.6%. Cumulative SPI 0.686. ii. Cost performance changed from 75.2% to 72.6%. Cumulative CPI 0.726. iii. Schedule and Cost Performance has a negative trend as shown on Figure #2 below. Figure #2 0.400 0.500 0.600 0.700 0.800 0.900 1.000 1.100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 CPI 0.726 SPI 0.686 SIMPLE SAMPLE Cumulative 3. Projections: a. The analyst projects a significant cost overrun due to the negative trends in cost performance. The Vendors Estimate at Completion (EAC) changed from a cost overrun of about $1.97 million to now more like $2.45 million over the current performance measurement baseline of $13.9 million. b. The significant trend data indicates a poor schedule performance cumulative to date at about 68.6%. That calculated for every 100 hours planned the progress is at 68.6 hours. The SPI is 0.686. c. The cumulative cost performance to date is at 72.6%. That calculated for every $100 dollars expended the contractor earns (accomplishes) $72.6 dollars’ worth of work. The CPI is 0.726. SAMPLE Page 2
  3. 3. SIMPLE SAMPLE 4. Choice and Rationale: a. The worst-case projection for the scheduled completion date, for these efforts, will be missed by about 13 months. Scheduled completion date is stated as January 2019. Completion is projected to be March 2020. 5. Major Areas of Concern as shown on Figure #3: a. The behind schedule is shown as be being greater than 3 months and is projected to grow to, worst case at, 13 months. With only 15 months of data, the contractor is behind schedule by greater than 3 months, as show of Figure #3. b. Cost variance grew from -$1,970,000 to -$2,450,000. Figure #3 150,000 2,150,000 4,150,000 6,150,000 8,150,000 10,150,000 12,150,000 SIMPLE SAMPLE SV In Time Greater than 3 months 6. Exhibit as shown on Figure # 4: a. Analyst’s (Worst Case) Estimated Cost at Completion is $23.3 M. b. Contractor’s Estimated Cost at Completion at $16.4 M. c. Budget at $13.9 M. d. Planned performance to date is $9.48 M. e. Expended to date is $9.95 M. f. Earned to date is $6.5 M. g. Currently at least 3+ months behind schedule. SAMPLE Page 3
  4. 4. SIMPLE SAMPLE h. Cost overrun to date is $2.45 M. Figure #4 Program: As of: 31-Mar-2018 Planned Earned Expended SV CV Budget Vendor's EAC $9,480,000 $6,500,000 $8,950,000 ($2,980,000) ($2,450,000) $13,900,000 $16,350,000 Percent Complete Work Remaining Cumulative CPI 6 Month Moving Average 3 Month Moving Average Independent Projection Worst Case Completed 15 Reporting Periods 0.726 0.771 0.608 0.304 Independent $10,189,231 $9,592,363 $12,164,384 $24,342,105 Projection $19,139,231 $18,542,363 $21,114,384 $33,292,105 Worst Case 2.19% 3 MMA Current Work Remaining 4.38% 3.74% 53.24% Independent Projected Completion Date 29-Mar-2020 31-Jan-2019 $24,342,105 $16,942,105 $33,292,105 Best Case $19,139,231 Most likely $26,215,668 Worst Case $33,292,105 Independent EAC Project Cost Overrun Projection of Average Earning Per Month for Remaining Work Percent Complete Cost of Work Remaining To Complete Performance Index 46.76% Independent EAC $7,400,000 Contract Completion Date Independent Total Estimated Cost to Go Dollars as StatedSIMPLE SAMPLE Copy to: The Essential EVM Formulas Acronyms: AC: Actual Cost (ACWP means Actual Cost of Work Performed). The cost for the work performed. ACWP: Actual Cost of Work Performed. BAC: Budgeted at Completion, also Authorized Budget also Total Planned Value. BCWP: Budget Cost for Work Performed. Completed (accomplished) budgeted work. BCWS: Budget Cost for Work Scheduled. The cost for the work performed. CPI: Cost Performance Index. Earned divided by Expended. CV: Cost Variance. The mathematical difference between Earned and Expended. EAC: Estimate at Completion SAMPLE Page 4
  5. 5. SIMPLE SAMPLE EV: Earned Value (BCWP means Budgeted Cost for Work Performed) also Accomplished Work ETC: Estimate to Complete. The estimated cost to complete all budgeted work. IEAC: Independent Estimate at Completion. Independent projected cost at the completion of all budgeted work. PV: Planned Value (BCWS means Budgeted Cost for Work Scheduled) SV: Schedule Variance. The mathematical difference between Earned and Planned. SPI: Schedule Performance Index. Earned divided by Planned. TCPI: To Complete Performance Index. The cost efficiency factor to complete budgeted work or to complete all work at the EAC value. WR: Work Remaining. The difference between the budgeted value and work accomplished. Formulas: Cost Performance Index (CPI): CPI = EV / AC Cost Variance (CV): CV = EV - AC Cost Variance % (CV %): CV% = 100 x (CV / EV) Estimate at Completion (EAC): ACWP cumulative + (Work Remaining / The Average Projected Cost Performance Index for work remaining) Independent Estimate at Complete (IEAC): IEAC calculations are based on the use of a Performance Index and should be so stated: IEAC = AC cumulative + (BAC - EV cumulative)/ Performance Index IEAC = AC + (BAC - EV) / CPI current IEAC = AC + (BAC - EV) / SPI current IEAC = AC + (BAC - EV) / (SPI * CPI) IEAC = AC + (BAC - EV) / ((SPI * .20) + (CPI * .80)) IEAC = AC + (BAC - EV) / CPI cumulative x (x equals the cumulative of the last x periods) IEAC = AC + (BAC - EV) / Projected Average CPI to completion Percent Complete: Percent Complete = 100 x (EV cumulative / BAC) Percent Spent: Percent Spent = 100 x (AC cumulative / BAC (or EAC)) Schedule Variance (SV): SV = EV - PV Schedule Variance % (SV %): SV% = 100 x (SV / PV) Schedule Performance Index (SPI): SPI = EV / PV To Complete Performance Index (TCPI): TCPI to EAC = Work Remaining / Cost Remaining TCPI EAC: = (BAC - EV) / (EAC – AC) Variance at Complete (VAC): VAC = BAC – EAC Variance at Complete % (VAC %): VAC % = 100 x (VAC / BAC) Work Remaining: BAC - BCWP SAMPLE Page 5
  6. 6. SIMPLE SAMPLE EV: Earned Value (BCWP means Budgeted Cost for Work Performed) also Accomplished Work ETC: Estimate to Complete. The estimated cost to complete all budgeted work. IEAC: Independent Estimate at Completion. Independent projected cost at the completion of all budgeted work. PV: Planned Value (BCWS means Budgeted Cost for Work Scheduled) SV: Schedule Variance. The mathematical difference between Earned and Planned. SPI: Schedule Performance Index. Earned divided by Planned. TCPI: To Complete Performance Index. The cost efficiency factor to complete budgeted work or to complete all work at the EAC value. WR: Work Remaining. The difference between the budgeted value and work accomplished. Formulas: Cost Performance Index (CPI): CPI = EV / AC Cost Variance (CV): CV = EV - AC Cost Variance % (CV %): CV% = 100 x (CV / EV) Estimate at Completion (EAC): ACWP cumulative + (Work Remaining / The Average Projected Cost Performance Index for work remaining) Independent Estimate at Complete (IEAC): IEAC calculations are based on the use of a Performance Index and should be so stated: IEAC = AC cumulative + (BAC - EV cumulative)/ Performance Index IEAC = AC + (BAC - EV) / CPI current IEAC = AC + (BAC - EV) / SPI current IEAC = AC + (BAC - EV) / (SPI * CPI) IEAC = AC + (BAC - EV) / ((SPI * .20) + (CPI * .80)) IEAC = AC + (BAC - EV) / CPI cumulative x (x equals the cumulative of the last x periods) IEAC = AC + (BAC - EV) / Projected Average CPI to completion Percent Complete: Percent Complete = 100 x (EV cumulative / BAC) Percent Spent: Percent Spent = 100 x (AC cumulative / BAC (or EAC)) Schedule Variance (SV): SV = EV - PV Schedule Variance % (SV %): SV% = 100 x (SV / PV) Schedule Performance Index (SPI): SPI = EV / PV To Complete Performance Index (TCPI): TCPI to EAC = Work Remaining / Cost Remaining TCPI EAC: = (BAC - EV) / (EAC – AC) Variance at Complete (VAC): VAC = BAC – EAC Variance at Complete % (VAC %): VAC % = 100 x (VAC / BAC) Work Remaining: BAC - BCWP SAMPLE Page 5

×