DR. A.G. JEETOO HOSPITAL
UPGRADE


      CASE STUDY
       APRIL 2011
THE REDEVELOPMENT
OF DR. A.G. JEETOO HOSPITAL,
   PORT LOUIS, MAURITIUS
ASSESSMENT CRITERIA
Team Experience and Resources

Key Persons – named individuals – 15 yrs experience
      Team Leader
      Design Architect
      Hospital Planner
      Structural Civil Engineer
      Mechanical and Electrical Specialist
      Quantity Surveyor
      Equipment Specialist


Methodology
SCHEDULE OF ACCOMMODATION

 Accident & Emergency –        1158m2
 Outpatients –                 4 054m2
 General Nursing Units –       8 861m2
 Specialized Nursing Units –   1 314m2
 Clinical Services –           3 805m2
 Support Services –            2 796m2
 Establishment –               2 179m2
 Staff Facilities –               865m2
 Circulation –                 2 505m2
 Total Gross Area -            27 553m2
BED ALLOCATION
Medical           112 Beds
Surgery           100 Beds
Orthopaedic        50 Beds
Paediatrics        55 Beds
Nursery/Neo-natal 18 Beds
Gynaecology        25 Beds
Ante-natal         25 Beds
Post-natal         25 Beds
Labour Ward        10 Beds
Psychiatric        30 Beds
Cardiac            30 Beds
Day Ward           12 Beds
Haemodialysis      20 Beds
ICU                20 Beds
High Care          18 Beds
Total            550 Beds
                             13
EXISTING HOSPITAL

Main Entrance            Pharmacy and Records
EXISTING HOSPITAL

Theatres and ICU      Central Space
METHODOLOGY
                            CONSULTANCY SERVICES FOR THE UPGRADING OF THE DR. A.G. JEETOO HOSPITAL

Interrogate Schedule




                                                                                                                                                                                                                      HOSPITAL PLANNER
                                                                                                                   DESIGN ARCHITECT


                                                                                                                                      DESIGN ARCHITECT




                                                                                                                                                                                        STRUCTURAL CIVIL
                                                                                                                                                                        PUBLIC HEALTH
                                                                                                     TEAM LEADER




                                                                                                                                                         ELECTRICAL /
                                                                                                                                                         MECHANICAL
Assess existing buildings




                                                                                                                                                                                                           SURVEYOR
                                NO.             METHODOLOGY - PRE-CONTRACT




                                                                                                                                                                                                           QUANTITY
                                                                                                                                                                        ENGINEER
                                                                                                                   FGG

                                                                                                                                      J&A
Establish Design            1
                            1.1
                                      BRIEF
                                      Accept Brief from the Client.
                                      Analyze brief and evaluate in terms of timescale,
                                                                                                      x
                            1.2

Principles                  1.3
                            1.4
                                      phasing, financial limits.
                                      Analyze schedules of accommodation.
                                      Check whether budget provision is realistic
                                                                                                      x
                                                                                                      x
                                                                                                      x
                                                                                                                        x
                                                                                                                        x
                                                                                                                                           x
                                                                                                                                           x
                                                                                                                                                             x              x             x                  x

                                                                                                                                                                                                             x
                                                                                                                                                                                                                        x
                                                                                                                                                                                                                        x

                                      Report to Client on concerns, comments, and advise on
                            1.5

Agree Standards             1.6
                                      how to proceed.
                                      Agree on reporting procedure.
                                                                                                      x
                                                                                                      x

                            2         SURVEY
                                      Obtain all record drawings of existing buildings,

Prepare Masterplan          2.1
                                      structures, and site.
                                      Obtain from Client information on ownership and any
                                      lessor and lessees of the site, and any known
                                                                                                                                           x                 x              x             x


                            2.2
                                      easements, encroachments, rights of way, rights of

Establish Operational       2.3
                                      support, and other relevant matters.
                                      Obtain existing topographical survey, review, and
                                      identify any further survey required.
                                                                                                      x                                    x

                                                                                                                                           x                                              x


Policies                    2.4

                            2.5
                                      Obtain existing geotechnical survey, review and identify
                                      any further survey required.
                                      Verify accuracy of records, survey as necessary, and
                                                                                                                                                                                          x

                                      prepare site plan of the existing hospital.                                                          x                 x              x             x
                                      Obtain records of underground and overhead services,

Prepare Specifications      2.6
                            2.7
                                      and validate on site.
                                      Evaluate existing site electrical reticulation.
                                      Report to Client on any further surveys or investigations
                                                                                                                                                             x
                                                                                                                                                                            x             x


                            2.8
                                      required.                                                       x                                    x                 x              x             x

Prepare Documentation       2.9
                                      Inspect existing buildings and evaluate in terms of
                                      practicality for re-use. Consider flexibility of space, fire
                                      safety, sound insulation, natural light and ventilation.        x                                    x                 x              x             x
                                      Inspect existing buildings structural and physical
                            2.10
                                      condition.                                                      x                                    x                                              x                  x
                                      Inspect existing buildings mechanical services, in terms
                            2.11      of condition, conformity with current standards, and
                                      potential for being upgraded.                                                                                          x
DESIGN PRINCIPLES

Forming the basis of the Design

   Facilitate delivery of first class medical service.
   Use appropriate technology, and viable resources.
   Services which are essential to welfare of the seriously
   endangered patient are grouped together in close proximity.
   Needs of the patient are paramount.
   Efficient use of staff.
   Maximum use of natural light and ventilation.
   Circulation should be horizontal, and minimise the reliance
   on lifts.
   Different categories of circulation should be separated.
   Systems should be environmentally friendly, low energy
   reliant and low maintenance.
   Construction must be capable of implementation while the
   hospital is fully operational.
ENVIRONMENTAL PRINCIPLES

Conservation of Historic Buildings
Maintenance of existing trees.
Encouragement of indigenous vegetation.
Sustainable building materials and methods.
Utilisation of local resources.
Low Maintenance.
Low energy consumption.
Alternative energy sources.
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION                              o DR A.G.JEETOO HOSPITAL UPGRADE                                                           o APRIL 2010


                                                                                                             M O N S I E U R        S T R E E T

                                                                                                                                                          FIELD MESS
                                                                                                                                                          SERVANTS MESS                 COMPOUNDING
                                                                                         SUB                       GENERATOR         STAFF PARKING
                                                                                               LINEN                                 22 CARS                                            METHADONE


                                                                                         WORKSHOP




                                                                           S T R E E T
                                                                                                               STORES
                                                                                                                                                            GARDEN
                                                                                         ELECTRICAL                                                                                 PROPOSED
                                                                                                                                SERVICE      SPEECH                                 METHADONE CLINIC
                                                                                                              STORES            YARD




                                                                                                                                                                                                       S T R E E T
                                                                                                                                                                PHYSIO

                                                                                                             CATERING




                                                                           P O I V R E
                                                                                                                                              PHYSICAL
                                                                                                                               PARKING                                                     STAFF
                                                                                                 DAY                                                                                PARA   PARKING
                                                                                                                               21 CARS
S T R E E T




                                                                                                 WARD                                         SOCIAL                                MESS   20 CARS




                                                                                                                                                                                                       C O U R C Y
                                                                                                          CARDIAC
                                                                                                          OPD
                                                                                                                                                         GARDEN                         SPARE
                                                                           D E


                                                                                         PLANT
                           L A   P E R O U S S E     S T R E E T
                                                                                           RAMP
                                            INCINERATOR
D E S R O C H E S




                                  CHEST




                                                                                                                                                                                                       D E
                    LABORATORY
                                  CLINIC                               RADIOLOGY                               MEDICAL         ORTHOPAED                                  MEDICAL      PAEDIATRIC
                                                                                                               RECORDS         OPD                   PHARMACY             OPD          OPD

                                                                                                                        H O S P I T A L    S T R E E T
                                           PUBLIC         EMERGENCY
                                           PARKING
                                           24 CARS        DROP-OFF
                                                                                SAMU                   ACCIDENT
                                                                                                       EMERGENCY               UNSORTED      SURGICAL           O&G                   SHARED
                                                                                                                               OPD           OPD                OPD                   OPD




                       PARKING                                                             BUSES                                 TAXIS                            PARKING
                                                          MAIN
                                                          ENTRANCE      V O L C Y                P O U G N E T       S T R E E T




                                                                   GROUND FLOOR PLAN
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010




          EAST ELEVATION




            SECTION J - J                     SECTION B - B
PREMIER PRESENTATION                         o DR A.G.JEETOO HOSPITAL UPGRADE                                                          o APRIL 2010


                                                                                                          M O N S I E U R       S T R E E T


                                                                                                                  SERVICE
                                                                                                                                    PARKING20




                                                                           S T R E E T
                                                                                                                  ENTRANCE                           POST NATAL
                                                                                                                                    CARS




                                                                                                                           SERVICEYARD




                                                                           P O I V R E
                                                                                                                                                          “H” BLOCK




                                                                                                                                                                                          S T R E E T
                                                                                                                                                                                PARKING
                                                                                                                             PARKING
                                                                                                                             21 CARS                                            16 CARS


                                                                           D E
S T R E E T




                                                                                                                                                                                          C O U R C Y
                                                                                                                                                                      STAFF ENTRANCE
                      L A   P E R O U S S E   S T R E E T
D E S R O C H E S




                                                                                             PLANT




                                                                                                                                                                                          D E
                                                                                                                                                                              MORTUARY


                                                                                                                 PARKING     122 CARS



                                                                ENTRANCE
                                          PARKING
                                          24 CARS
                                                                EXIT                                                                                                            PLANT




                                                                                                                  TAXIS
                                                                                                                                                PARKING
                                                     MAIN                                BUSES
                                                     ENTRANCE          V O L C Y                 P O U G N E T   S T R E E T




                                                            BASEMENT PLAN
PREMIER PRESENTATION                              o DR A.G.JEETOO HOSPITAL UPGRADE                                                           o APRIL 2010


                                                                                                             M O N S I E U R        S T R E E T

                                                                                                                                                          FIELD MESS
                                                                                                                                                          SERVANTS MESS                 COMPOUNDING
                                                                                         SUB                       GENERATOR         STAFF PARKING
                                                                                               LINEN                                 22 CARS                                            METHADONE


                                                                                         WORKSHOP




                                                                           S T R E E T
                                                                                                               STORES
                                                                                                                                                            GARDEN
                                                                                         ELECTRICAL                                                                                 PROPOSED
                                                                                                                                SERVICE      SPEECH                                 METHADONE CLINIC
                                                                                                              STORES            YARD




                                                                                                                                                                                                       S T R E E T
                                                                                                                                                                PHYSIO

                                                                                                             CATERING




                                                                           P O I V R E
                                                                                                                                              PHYSICAL
                                                                                                                               PARKING                                                     STAFF
                                                                                                 DAY                                                                                PARA   PARKING
                                                                                                                               21 CARS
S T R E E T




                                                                                                 WARD                                         SOCIAL                                MESS   20 CARS




                                                                                                                                                                                                       C O U R C Y
                                                                                                          CARDIAC
                                                                                                          OPD
                                                                                                                                                         GARDEN                         SPARE
                                                                           D E


                                                                                         PLANT
                           L A   P E R O U S S E     S T R E E T
                                                                                           RAMP
                                            INCINERATOR
D E S R O C H E S




                                  CHEST




                                                                                                                                                                                                       D E
                    LABORATORY
                                  CLINIC                               RADIOLOGY                               MEDICAL         ORTHOPAED                                  MEDICAL      PAEDIATRIC
                                                                                                               RECORDS         OPD                   PHARMACY             OPD          OPD

                                                                                                                        H O S P I T A L    S T R E E T
                                           PUBLIC         EMERGENCY
                                           PARKING
                                           24 CARS        DROP-OFF
                                                                                SAMU                   ACCIDENT
                                                                                                       EMERGENCY               UNSORTED      SURGICAL           O&G                   SHARED
                                                                                                                               OPD           OPD                OPD                   OPD




                       PARKING                                                             BUSES                                 TAXIS                            PARKING
                                                          MAIN
                                                          ENTRANCE      V O L C Y                P O U G N E T       S T R E E T




                                                                   GROUND FLOOR PLAN
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION                      o DR A.G.JEETOO HOSPITAL UPGRADE                                                o APRIL 2010


                                                                                                       M O N S I E U R          S T R E E T




                                                                                                   ADMIN




                                                                     S T R E E T
                                                                                       UPPER
                                                                                                   MEZZ
                                                                                                             UPPER




                                                                                                                                                             S T R E E T
                                                                                                             UPPER




                                                                     P O I V R E
                                                                                        M1
S T R E E T




                                                                                        ADMINISTRATION




                                                                                                                                                             C O U R C Y
                                                                     D E

                       L A   P E R O U S S E   S T R E E T
D E S R O C H E S




                                                                                                                              F




                                                                                                                                                             D E
                                                                                        Q3
                                                             PLANT                                            M2              RECORDS
                                                                                        C.S.S.D.
                                                             ROOM                                             FINANCE         LIBRARY




                                                                                                                        M1
                                                                                   POLICE /        M4                   IT.
                                                                                   STAFF REST      GENERAL
                                                                                                                        M3
                                                                                   ROOMS                                PERSONNEL




                                                              V O L C Y              P O U G N E T         S T R E E T




                                                             MEZZANINE PLAN
PREMIER PRESENTATION                         o DR A.G.JEETOO HOSPITAL UPGRADE                                                       o APRIL 2010


                                                                                                          M O N S I E U R     S T R E E T




                                                                       S T R E E T
                                                                                            UPPER
                                                                                                           UPPER
                                                                                                                                                                       DOCTORS
                                                                                                                                       HEALTH                          MESS




                                                                                                                                                                                   S T R E E T
                                                                                                                                                       DOCTORS MESS
                                                                                                           UPPER




                                                                       P O I V R E
                                                                                                                                                                       PARAMED
                                                                                                                                        HEALTH                         MESS
                                                                                            ORTHOPAEDIC
                                                                                            WARD
S T R E E T




                                                                                                                                                                                   C O U R C Y
                                                                       D E
                                                                                                                                                                           SPARE

                           L A   P E R O U S S E   S T R E E T


                                  CHEST
D E S R O C H E S




                                                                                                                                                                                   D E
                    LABORATORY
                                  CLINIC                                                                           LABOUR WARD              SURGICAL                   SURGICAL
                                                                                     O.T.                          10 BED                   25 BED                     25 BED




                                                                                     ICU 24 BED
                                                                                     HIGHCARE 18 BED                        NURSERY         SURGICAL                  SURGICAL
                                                                                                                            NICU            25 BED                    25 BED




                                                                 V O L C Y              P O U G N E T       S T R E E T




                                                                 FIRST FLOOR PLAN
PREMIER PRESENTATION                      o DR A.G.JEETOO HOSPITAL UPGRADE                                                       o APRIL 2010



                                                                                                        M O N S I E U R   S T R E E T




                                                                         S T R E E T




                                                                                                                                                                            S T R E E T
                                                                         P O I V R E
S T R E E T




                                                                                                                                                                            C O U R C Y
                                                                                                   ROOF
                                                                         D E

                       L A   P E R O U S S E   S T R E E T
D E S R O C H E S




                                                                                                                                        L5a                 L1c




                                                                                                                                                                            D E
                                                                                                           L5b
                                                                                                           ANTE NATAL WARD              GYNAE WARD          MEDICAL WARD
                                                             A/C                                           25 BED                       25 BED              28 BED
                                                             PLANTROOM




                                                                                        E                  L5d                           L1c                 L1c
                                                                                        DIALYSIS UNIT      POST NATAL WARD               MEDICAL WARD        MEDICAL WARD
                                                                                                           25 BED                        28 BED              28 BED




                                                               V O L C Y               P O U G N E T      S T R E E T




                                                              SECOND FLOOR PLAN
PREMIER PRESENTATION                     o DR A.G.JEETOO HOSPITAL UPGRADE                                                            o APRIL 2010



                                                                                                       M O N S I E U R      S T R E E T




                                                                    S T R E E T




                                                                                                                                                                                 S T R E E T
                                                                    P O I V R E
S T R E E T




                                                                                                                                                                                 C O U R C Y
                                                                    D E


                       L A   P E R O U S S E   S T R E E T
D E S R O C H E S




                                                                                                                                          L1c                 L6a




                                                                                                                                                                                 D E
                                                                                                          L4a
                                                                   ROOF                                   PAEDIATRIC WARD                 MEDICAL WARD        PSYCHIATRIC WARD
                                                                                                          25 COT                          28 BED              15 BED
                                                                                         LABORATORY



                                                                                  ROOF                      L4b                            J3                 L6b
                                                                                          PAEDIATRIC        PAEDIATRIC WARD                CARDIAC WARD       PSYCHIATRIC WARD
                                                                                          PLAY AREA         30 BED                         30 BED             15 BED




                                                              V O L C Y              P O U G N E T       S T R E E T




                                                             THIRD FLOOR PLAN
PREMIER PRESENTATION     o DR A.G.JEETOO HOSPITAL UPGRADE           o APRIL 2010


               WARD VENTILATION

       External air quality is poor. Filtered fresh air supply to
       all Wards.

       Air supply into each ward with ceiling fans to assist
       circulation.

       Natural air movement into corridor assisted by
       extraction at each end.

       Extract duct at each end of corridor, with secondary
       extraction via bathrooms into extract shaft,
       discharging at roof level.
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010




          WEST ELEVATION




           SECTION F - F
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION   o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010
PREMIER PRESENTATION          o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010


      ENVIRONMENTAL PRINCIPLES

              Hot water produced by a combination of solar
              water heaters and heat recovery from the
              chillers. Expected annual savings of 85,000
              kWhr saved which can be quantified with an
              associated reduction of carbon dioxide
              emission if this was to be heated by LPG gas of
              17,000 kg




  3/24/2011
PREMIER PRESENTATION     o DR A.G.JEETOO HOSPITAL UPGRADE   o APRIL 2010


    ENVIRONMENTAL PRINCIPLES
  Maximization of daylight through the
  atrium with an estimated annual
  savings of 31,000 kWhr which can be
  quantified with an associated
  reduction of carbon dioxide emission if
  this was to be provided by artificial
  lighting of 16,120 kg

  Maximization of daylight in typical
  wards though openings with an
  estimated annual savings of 48,442
  kWhr which can be quantified with an
  associated reduction of carbon dioxide
  emission if this was to be provided by
  artificial lighting of 25,190 kg
PREMIER PRESENTATION    o DR A.G.JEETOO HOSPITAL UPGRADE          o APRIL 2010


    ENVIRONMENTAL PRINCIPLES

       Filtered fresh air supply to all areas departments of
       the hospital

       Use of energy efficient light fittings and Optimization
       of Energy consumption by using complex Building
       Controls systems

       Equipment using Ozone friendly refrigerants

       Re-use of existing buildings and restoration of historic
       buildings.
PROGRAM


Start of Construction - October 2009
Phase 1 Completion - January 2011
Phase 2 Completion - October 2011
Phase 3 Completion - February 2012
Service Buildings - April 2011
Refurbish Existing – February 2012
Final Completion - February 2012
PROFESSIONAL TEAM

FGG Architects
Team Leader / Architect
J & A Architects
Architect (Mauritius)
Pholela Health
Equipment Specialist
Pro-Design
Mechanical & Electrical
Ocal Ltd
Quantity Surveyor
Gibb
Civil & Structural



Client - Ministry of Health & Quality of Life - Government of Mauritius
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE
SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE

Más contenido relacionado

Destacado

Hospital sector 39
Hospital sector 39Hospital sector 39
Hospital sector 39Shyam Singh
 
Healthcare public design Selected hospital design
Healthcare public design   Selected hospital designHealthcare public design   Selected hospital design
Healthcare public design Selected hospital designSiniša Prvanov
 
Kohinoor Hospital the Sustainable Hospital
Kohinoor Hospital the Sustainable HospitalKohinoor Hospital the Sustainable Hospital
Kohinoor Hospital the Sustainable HospitalRajat Katarne
 
Rural housing in india
Rural housing in indiaRural housing in india
Rural housing in indiakumaresan2704
 
Architectural case study of IIM ahemdabad by louis i khan
Architectural case study of IIM ahemdabad by louis i khanArchitectural case study of IIM ahemdabad by louis i khan
Architectural case study of IIM ahemdabad by louis i khanRajat Katarne
 
Final hospital planning and layout ppt
Final hospital planning and layout pptFinal hospital planning and layout ppt
Final hospital planning and layout pptSandeep Singh
 
Belapur Incremental housing - A case study
Belapur Incremental housing - A case studyBelapur Incremental housing - A case study
Belapur Incremental housing - A case studyRithika Ravishankar
 

Destacado (9)

250 375 bed model hospital
250 375 bed model hospital250 375 bed model hospital
250 375 bed model hospital
 
Hospital sector 39
Hospital sector 39Hospital sector 39
Hospital sector 39
 
Planning hospital service
Planning hospital servicePlanning hospital service
Planning hospital service
 
Healthcare public design Selected hospital design
Healthcare public design   Selected hospital designHealthcare public design   Selected hospital design
Healthcare public design Selected hospital design
 
Kohinoor Hospital the Sustainable Hospital
Kohinoor Hospital the Sustainable HospitalKohinoor Hospital the Sustainable Hospital
Kohinoor Hospital the Sustainable Hospital
 
Rural housing in india
Rural housing in indiaRural housing in india
Rural housing in india
 
Architectural case study of IIM ahemdabad by louis i khan
Architectural case study of IIM ahemdabad by louis i khanArchitectural case study of IIM ahemdabad by louis i khan
Architectural case study of IIM ahemdabad by louis i khan
 
Final hospital planning and layout ppt
Final hospital planning and layout pptFinal hospital planning and layout ppt
Final hospital planning and layout ppt
 
Belapur Incremental housing - A case study
Belapur Incremental housing - A case studyBelapur Incremental housing - A case study
Belapur Incremental housing - A case study
 

Más de SA FHE

Order of Magnitude Estimator for Public Hospitals
Order of Magnitude Estimator for Public HospitalsOrder of Magnitude Estimator for Public Hospitals
Order of Magnitude Estimator for Public HospitalsSA FHE
 
Wi ebe 2014 call for nominations
Wi ebe 2014 call for nominationsWi ebe 2014 call for nominations
Wi ebe 2014 call for nominationsSA FHE
 
2014 07 31 iuss presentation ceasa
2014 07 31 iuss presentation ceasa2014 07 31 iuss presentation ceasa
2014 07 31 iuss presentation ceasaSA FHE
 
Phg cape town tour jul aug 2014
Phg cape town tour jul aug 2014Phg cape town tour jul aug 2014
Phg cape town tour jul aug 2014SA FHE
 
Phg provisional programme 9 jun 2014
Phg provisional programme   9 jun 2014Phg provisional programme   9 jun 2014
Phg provisional programme 9 jun 2014SA FHE
 
Safhe newsletter 2.1
Safhe newsletter 2.1Safhe newsletter 2.1
Safhe newsletter 2.1SA FHE
 
Presentation for safhe april 2014 handout
Presentation for safhe april 2014 handoutPresentation for safhe april 2014 handout
Presentation for safhe april 2014 handoutSA FHE
 
Uia 2014 durban uia phg competition brief c
Uia 2014 durban uia phg competition brief cUia 2014 durban uia phg competition brief c
Uia 2014 durban uia phg competition brief cSA FHE
 
Uia 2014 durban_uia_phg_competition_brief
Uia 2014 durban_uia_phg_competition_briefUia 2014 durban_uia_phg_competition_brief
Uia 2014 durban_uia_phg_competition_briefSA FHE
 
Overview of the Healthcare Technology Management Programme offered by the Uni...
Overview of the Healthcare Technology Management Programme offered by the Uni...Overview of the Healthcare Technology Management Programme offered by the Uni...
Overview of the Healthcare Technology Management Programme offered by the Uni...SA FHE
 
Sans healthcare watch
Sans healthcare watchSans healthcare watch
Sans healthcare watchSA FHE
 
SAFHE Newsletter 2 September 2013
SAFHE Newsletter 2 September 2013SAFHE Newsletter 2 September 2013
SAFHE Newsletter 2 September 2013SA FHE
 
Health facility design for infection control
Health facility design for infection controlHealth facility design for infection control
Health facility design for infection controlSA FHE
 
Am solar presentation hospital-engineers 2013
Am solar presentation   hospital-engineers 2013Am solar presentation   hospital-engineers 2013
Am solar presentation hospital-engineers 2013SA FHE
 
Engineers powerpoint presentation. june 2013
Engineers powerpoint presentation. june 2013Engineers powerpoint presentation. june 2013
Engineers powerpoint presentation. june 2013SA FHE
 
SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...
SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...
SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...SA FHE
 
SAFHE/CEASA 2011 - Clarity Amid Confusion
SAFHE/CEASA 2011 - Clarity Amid ConfusionSAFHE/CEASA 2011 - Clarity Amid Confusion
SAFHE/CEASA 2011 - Clarity Amid ConfusionSA FHE
 
SAFHE/CEASA2011 - Hospital Design in Southern Africa
SAFHE/CEASA2011 - Hospital Design in Southern AfricaSAFHE/CEASA2011 - Hospital Design in Southern Africa
SAFHE/CEASA2011 - Hospital Design in Southern AfricaSA FHE
 
SAFHE/CEASA 2011 - Airborne disinfection methods
SAFHE/CEASA 2011 - Airborne disinfection methodsSAFHE/CEASA 2011 - Airborne disinfection methods
SAFHE/CEASA 2011 - Airborne disinfection methodsSA FHE
 

Más de SA FHE (19)

Order of Magnitude Estimator for Public Hospitals
Order of Magnitude Estimator for Public HospitalsOrder of Magnitude Estimator for Public Hospitals
Order of Magnitude Estimator for Public Hospitals
 
Wi ebe 2014 call for nominations
Wi ebe 2014 call for nominationsWi ebe 2014 call for nominations
Wi ebe 2014 call for nominations
 
2014 07 31 iuss presentation ceasa
2014 07 31 iuss presentation ceasa2014 07 31 iuss presentation ceasa
2014 07 31 iuss presentation ceasa
 
Phg cape town tour jul aug 2014
Phg cape town tour jul aug 2014Phg cape town tour jul aug 2014
Phg cape town tour jul aug 2014
 
Phg provisional programme 9 jun 2014
Phg provisional programme   9 jun 2014Phg provisional programme   9 jun 2014
Phg provisional programme 9 jun 2014
 
Safhe newsletter 2.1
Safhe newsletter 2.1Safhe newsletter 2.1
Safhe newsletter 2.1
 
Presentation for safhe april 2014 handout
Presentation for safhe april 2014 handoutPresentation for safhe april 2014 handout
Presentation for safhe april 2014 handout
 
Uia 2014 durban uia phg competition brief c
Uia 2014 durban uia phg competition brief cUia 2014 durban uia phg competition brief c
Uia 2014 durban uia phg competition brief c
 
Uia 2014 durban_uia_phg_competition_brief
Uia 2014 durban_uia_phg_competition_briefUia 2014 durban_uia_phg_competition_brief
Uia 2014 durban_uia_phg_competition_brief
 
Overview of the Healthcare Technology Management Programme offered by the Uni...
Overview of the Healthcare Technology Management Programme offered by the Uni...Overview of the Healthcare Technology Management Programme offered by the Uni...
Overview of the Healthcare Technology Management Programme offered by the Uni...
 
Sans healthcare watch
Sans healthcare watchSans healthcare watch
Sans healthcare watch
 
SAFHE Newsletter 2 September 2013
SAFHE Newsletter 2 September 2013SAFHE Newsletter 2 September 2013
SAFHE Newsletter 2 September 2013
 
Health facility design for infection control
Health facility design for infection controlHealth facility design for infection control
Health facility design for infection control
 
Am solar presentation hospital-engineers 2013
Am solar presentation   hospital-engineers 2013Am solar presentation   hospital-engineers 2013
Am solar presentation hospital-engineers 2013
 
Engineers powerpoint presentation. june 2013
Engineers powerpoint presentation. june 2013Engineers powerpoint presentation. june 2013
Engineers powerpoint presentation. june 2013
 
SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...
SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...
SAFHE/CEASA 2011 - Open Building for Healthcare Facilities: Lessons from the ...
 
SAFHE/CEASA 2011 - Clarity Amid Confusion
SAFHE/CEASA 2011 - Clarity Amid ConfusionSAFHE/CEASA 2011 - Clarity Amid Confusion
SAFHE/CEASA 2011 - Clarity Amid Confusion
 
SAFHE/CEASA2011 - Hospital Design in Southern Africa
SAFHE/CEASA2011 - Hospital Design in Southern AfricaSAFHE/CEASA2011 - Hospital Design in Southern Africa
SAFHE/CEASA2011 - Hospital Design in Southern Africa
 
SAFHE/CEASA 2011 - Airborne disinfection methods
SAFHE/CEASA 2011 - Airborne disinfection methodsSAFHE/CEASA 2011 - Airborne disinfection methods
SAFHE/CEASA 2011 - Airborne disinfection methods
 

Último

Informed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptxInformed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptxSasikiranMarri
 
Case Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptxCase Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptxNiranjan Chavan
 
Giftedness: Understanding Everyday Neurobiology for Self-Knowledge
Giftedness: Understanding Everyday Neurobiology for Self-KnowledgeGiftedness: Understanding Everyday Neurobiology for Self-Knowledge
Giftedness: Understanding Everyday Neurobiology for Self-Knowledgeassessoriafabianodea
 
Culture and Health Disorders Social change.pptx
Culture and Health Disorders Social change.pptxCulture and Health Disorders Social change.pptx
Culture and Health Disorders Social change.pptxDr. Dheeraj Kumar
 
PULMONARY EDEMA AND ITS MANAGEMENT.pdf
PULMONARY EDEMA AND  ITS  MANAGEMENT.pdfPULMONARY EDEMA AND  ITS  MANAGEMENT.pdf
PULMONARY EDEMA AND ITS MANAGEMENT.pdfDolisha Warbi
 
PNEUMOTHORAX AND ITS MANAGEMENTS.pdf
PNEUMOTHORAX   AND  ITS  MANAGEMENTS.pdfPNEUMOTHORAX   AND  ITS  MANAGEMENTS.pdf
PNEUMOTHORAX AND ITS MANAGEMENTS.pdfDolisha Warbi
 
LUNG TUMORS AND ITS CLASSIFICATIONS.pdf
LUNG TUMORS AND ITS  CLASSIFICATIONS.pdfLUNG TUMORS AND ITS  CLASSIFICATIONS.pdf
LUNG TUMORS AND ITS CLASSIFICATIONS.pdfDolisha Warbi
 
SYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptx
SYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptxSYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptx
SYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptxdrashraf369
 
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdfLippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdfSreeja Cherukuru
 
MedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdf
MedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdfMedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdf
MedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdfSasikiranMarri
 
Glomerular Filtration and determinants of glomerular filtration .pptx
Glomerular Filtration and  determinants of glomerular filtration .pptxGlomerular Filtration and  determinants of glomerular filtration .pptx
Glomerular Filtration and determinants of glomerular filtration .pptxDr.Nusrat Tariq
 
Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...
Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...
Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...MehranMouzam
 
epilepsy and status epilepticus for undergraduate.pptx
epilepsy and status epilepticus  for undergraduate.pptxepilepsy and status epilepticus  for undergraduate.pptx
epilepsy and status epilepticus for undergraduate.pptxMohamed Rizk Khodair
 
Radiation Dosimetry Parameters and Isodose Curves.pptx
Radiation Dosimetry Parameters and Isodose Curves.pptxRadiation Dosimetry Parameters and Isodose Curves.pptx
Radiation Dosimetry Parameters and Isodose Curves.pptxDr. Dheeraj Kumar
 
April 2024 ONCOLOGY CARTOON by DR KANHU CHARAN PATRO
April 2024 ONCOLOGY CARTOON by  DR KANHU CHARAN PATROApril 2024 ONCOLOGY CARTOON by  DR KANHU CHARAN PATRO
April 2024 ONCOLOGY CARTOON by DR KANHU CHARAN PATROKanhu Charan
 
maternal mortality and its causes and how to reduce maternal mortality
maternal mortality and its causes and how to reduce maternal mortalitymaternal mortality and its causes and how to reduce maternal mortality
maternal mortality and its causes and how to reduce maternal mortalityhardikdabas3
 
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara RajendranMusic Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara RajendranTara Rajendran
 
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptx
COVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptxCOVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptx
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptxBibekananda shah
 
systemic bacteriology (7)............pptx
systemic bacteriology (7)............pptxsystemic bacteriology (7)............pptx
systemic bacteriology (7)............pptxEyobAlemu11
 

Último (20)

Informed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptxInformed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptx
 
Case Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptxCase Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptx
 
Giftedness: Understanding Everyday Neurobiology for Self-Knowledge
Giftedness: Understanding Everyday Neurobiology for Self-KnowledgeGiftedness: Understanding Everyday Neurobiology for Self-Knowledge
Giftedness: Understanding Everyday Neurobiology for Self-Knowledge
 
Culture and Health Disorders Social change.pptx
Culture and Health Disorders Social change.pptxCulture and Health Disorders Social change.pptx
Culture and Health Disorders Social change.pptx
 
PULMONARY EDEMA AND ITS MANAGEMENT.pdf
PULMONARY EDEMA AND  ITS  MANAGEMENT.pdfPULMONARY EDEMA AND  ITS  MANAGEMENT.pdf
PULMONARY EDEMA AND ITS MANAGEMENT.pdf
 
PNEUMOTHORAX AND ITS MANAGEMENTS.pdf
PNEUMOTHORAX   AND  ITS  MANAGEMENTS.pdfPNEUMOTHORAX   AND  ITS  MANAGEMENTS.pdf
PNEUMOTHORAX AND ITS MANAGEMENTS.pdf
 
LUNG TUMORS AND ITS CLASSIFICATIONS.pdf
LUNG TUMORS AND ITS  CLASSIFICATIONS.pdfLUNG TUMORS AND ITS  CLASSIFICATIONS.pdf
LUNG TUMORS AND ITS CLASSIFICATIONS.pdf
 
Epilepsy
EpilepsyEpilepsy
Epilepsy
 
SYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptx
SYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptxSYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptx
SYNDESMOTIC INJURY- ANATOMICAL REPAIR.pptx
 
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdfLippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
 
MedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdf
MedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdfMedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdf
MedDRA-A-Comprehensive-Guide-to-Standardized-Medical-Terminology.pdf
 
Glomerular Filtration and determinants of glomerular filtration .pptx
Glomerular Filtration and  determinants of glomerular filtration .pptxGlomerular Filtration and  determinants of glomerular filtration .pptx
Glomerular Filtration and determinants of glomerular filtration .pptx
 
Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...
Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...
Study on the Impact of FOCUS-PDCA Management Model on the Disinfection Qualit...
 
epilepsy and status epilepticus for undergraduate.pptx
epilepsy and status epilepticus  for undergraduate.pptxepilepsy and status epilepticus  for undergraduate.pptx
epilepsy and status epilepticus for undergraduate.pptx
 
Radiation Dosimetry Parameters and Isodose Curves.pptx
Radiation Dosimetry Parameters and Isodose Curves.pptxRadiation Dosimetry Parameters and Isodose Curves.pptx
Radiation Dosimetry Parameters and Isodose Curves.pptx
 
April 2024 ONCOLOGY CARTOON by DR KANHU CHARAN PATRO
April 2024 ONCOLOGY CARTOON by  DR KANHU CHARAN PATROApril 2024 ONCOLOGY CARTOON by  DR KANHU CHARAN PATRO
April 2024 ONCOLOGY CARTOON by DR KANHU CHARAN PATRO
 
maternal mortality and its causes and how to reduce maternal mortality
maternal mortality and its causes and how to reduce maternal mortalitymaternal mortality and its causes and how to reduce maternal mortality
maternal mortality and its causes and how to reduce maternal mortality
 
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara RajendranMusic Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
 
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptx
COVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptxCOVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptx
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptx
 
systemic bacteriology (7)............pptx
systemic bacteriology (7)............pptxsystemic bacteriology (7)............pptx
systemic bacteriology (7)............pptx
 

SAFHE/CEASA 2011 - DR. A.G. JEETOO HOSPITAL UPGRADE

  • 1. DR. A.G. JEETOO HOSPITAL UPGRADE CASE STUDY APRIL 2011
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10. THE REDEVELOPMENT OF DR. A.G. JEETOO HOSPITAL, PORT LOUIS, MAURITIUS
  • 11. ASSESSMENT CRITERIA Team Experience and Resources Key Persons – named individuals – 15 yrs experience Team Leader Design Architect Hospital Planner Structural Civil Engineer Mechanical and Electrical Specialist Quantity Surveyor Equipment Specialist Methodology
  • 12. SCHEDULE OF ACCOMMODATION Accident & Emergency – 1158m2 Outpatients – 4 054m2 General Nursing Units – 8 861m2 Specialized Nursing Units – 1 314m2 Clinical Services – 3 805m2 Support Services – 2 796m2 Establishment – 2 179m2 Staff Facilities – 865m2 Circulation – 2 505m2 Total Gross Area - 27 553m2
  • 13. BED ALLOCATION Medical 112 Beds Surgery 100 Beds Orthopaedic 50 Beds Paediatrics 55 Beds Nursery/Neo-natal 18 Beds Gynaecology 25 Beds Ante-natal 25 Beds Post-natal 25 Beds Labour Ward 10 Beds Psychiatric 30 Beds Cardiac 30 Beds Day Ward 12 Beds Haemodialysis 20 Beds ICU 20 Beds High Care 18 Beds Total 550 Beds 13
  • 14. EXISTING HOSPITAL Main Entrance Pharmacy and Records
  • 15. EXISTING HOSPITAL Theatres and ICU Central Space
  • 16. METHODOLOGY CONSULTANCY SERVICES FOR THE UPGRADING OF THE DR. A.G. JEETOO HOSPITAL Interrogate Schedule HOSPITAL PLANNER DESIGN ARCHITECT DESIGN ARCHITECT STRUCTURAL CIVIL PUBLIC HEALTH TEAM LEADER ELECTRICAL / MECHANICAL Assess existing buildings SURVEYOR NO. METHODOLOGY - PRE-CONTRACT QUANTITY ENGINEER FGG J&A Establish Design 1 1.1 BRIEF Accept Brief from the Client. Analyze brief and evaluate in terms of timescale, x 1.2 Principles 1.3 1.4 phasing, financial limits. Analyze schedules of accommodation. Check whether budget provision is realistic x x x x x x x x x x x x x x Report to Client on concerns, comments, and advise on 1.5 Agree Standards 1.6 how to proceed. Agree on reporting procedure. x x 2 SURVEY Obtain all record drawings of existing buildings, Prepare Masterplan 2.1 structures, and site. Obtain from Client information on ownership and any lessor and lessees of the site, and any known x x x x 2.2 easements, encroachments, rights of way, rights of Establish Operational 2.3 support, and other relevant matters. Obtain existing topographical survey, review, and identify any further survey required. x x x x Policies 2.4 2.5 Obtain existing geotechnical survey, review and identify any further survey required. Verify accuracy of records, survey as necessary, and x prepare site plan of the existing hospital. x x x x Obtain records of underground and overhead services, Prepare Specifications 2.6 2.7 and validate on site. Evaluate existing site electrical reticulation. Report to Client on any further surveys or investigations x x x 2.8 required. x x x x x Prepare Documentation 2.9 Inspect existing buildings and evaluate in terms of practicality for re-use. Consider flexibility of space, fire safety, sound insulation, natural light and ventilation. x x x x x Inspect existing buildings structural and physical 2.10 condition. x x x x Inspect existing buildings mechanical services, in terms 2.11 of condition, conformity with current standards, and potential for being upgraded. x
  • 17. DESIGN PRINCIPLES Forming the basis of the Design Facilitate delivery of first class medical service. Use appropriate technology, and viable resources. Services which are essential to welfare of the seriously endangered patient are grouped together in close proximity. Needs of the patient are paramount. Efficient use of staff. Maximum use of natural light and ventilation. Circulation should be horizontal, and minimise the reliance on lifts. Different categories of circulation should be separated. Systems should be environmentally friendly, low energy reliant and low maintenance. Construction must be capable of implementation while the hospital is fully operational.
  • 18. ENVIRONMENTAL PRINCIPLES Conservation of Historic Buildings Maintenance of existing trees. Encouragement of indigenous vegetation. Sustainable building materials and methods. Utilisation of local resources. Low Maintenance. Low energy consumption. Alternative energy sources.
  • 19. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 20. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T FIELD MESS SERVANTS MESS COMPOUNDING SUB GENERATOR STAFF PARKING LINEN 22 CARS METHADONE WORKSHOP S T R E E T STORES GARDEN ELECTRICAL PROPOSED SERVICE SPEECH METHADONE CLINIC STORES YARD S T R E E T PHYSIO CATERING P O I V R E PHYSICAL PARKING STAFF DAY PARA PARKING 21 CARS S T R E E T WARD SOCIAL MESS 20 CARS C O U R C Y CARDIAC OPD GARDEN SPARE D E PLANT L A P E R O U S S E S T R E E T RAMP INCINERATOR D E S R O C H E S CHEST D E LABORATORY CLINIC RADIOLOGY MEDICAL ORTHOPAED MEDICAL PAEDIATRIC RECORDS OPD PHARMACY OPD OPD H O S P I T A L S T R E E T PUBLIC EMERGENCY PARKING 24 CARS DROP-OFF SAMU ACCIDENT EMERGENCY UNSORTED SURGICAL O&G SHARED OPD OPD OPD OPD PARKING BUSES TAXIS PARKING MAIN ENTRANCE V O L C Y P O U G N E T S T R E E T GROUND FLOOR PLAN
  • 21. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 22. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 EAST ELEVATION SECTION J - J SECTION B - B
  • 23. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T SERVICE PARKING20 S T R E E T ENTRANCE POST NATAL CARS SERVICEYARD P O I V R E “H” BLOCK S T R E E T PARKING PARKING 21 CARS 16 CARS D E S T R E E T C O U R C Y STAFF ENTRANCE L A P E R O U S S E S T R E E T D E S R O C H E S PLANT D E MORTUARY PARKING 122 CARS ENTRANCE PARKING 24 CARS EXIT PLANT TAXIS PARKING MAIN BUSES ENTRANCE V O L C Y P O U G N E T S T R E E T BASEMENT PLAN
  • 24. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T FIELD MESS SERVANTS MESS COMPOUNDING SUB GENERATOR STAFF PARKING LINEN 22 CARS METHADONE WORKSHOP S T R E E T STORES GARDEN ELECTRICAL PROPOSED SERVICE SPEECH METHADONE CLINIC STORES YARD S T R E E T PHYSIO CATERING P O I V R E PHYSICAL PARKING STAFF DAY PARA PARKING 21 CARS S T R E E T WARD SOCIAL MESS 20 CARS C O U R C Y CARDIAC OPD GARDEN SPARE D E PLANT L A P E R O U S S E S T R E E T RAMP INCINERATOR D E S R O C H E S CHEST D E LABORATORY CLINIC RADIOLOGY MEDICAL ORTHOPAED MEDICAL PAEDIATRIC RECORDS OPD PHARMACY OPD OPD H O S P I T A L S T R E E T PUBLIC EMERGENCY PARKING 24 CARS DROP-OFF SAMU ACCIDENT EMERGENCY UNSORTED SURGICAL O&G SHARED OPD OPD OPD OPD PARKING BUSES TAXIS PARKING MAIN ENTRANCE V O L C Y P O U G N E T S T R E E T GROUND FLOOR PLAN
  • 25. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 26. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T ADMIN S T R E E T UPPER MEZZ UPPER S T R E E T UPPER P O I V R E M1 S T R E E T ADMINISTRATION C O U R C Y D E L A P E R O U S S E S T R E E T D E S R O C H E S F D E Q3 PLANT M2 RECORDS C.S.S.D. ROOM FINANCE LIBRARY M1 POLICE / M4 IT. STAFF REST GENERAL M3 ROOMS PERSONNEL V O L C Y P O U G N E T S T R E E T MEZZANINE PLAN
  • 27. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T S T R E E T UPPER UPPER DOCTORS HEALTH MESS S T R E E T DOCTORS MESS UPPER P O I V R E PARAMED HEALTH MESS ORTHOPAEDIC WARD S T R E E T C O U R C Y D E SPARE L A P E R O U S S E S T R E E T CHEST D E S R O C H E S D E LABORATORY CLINIC LABOUR WARD SURGICAL SURGICAL O.T. 10 BED 25 BED 25 BED ICU 24 BED HIGHCARE 18 BED NURSERY SURGICAL SURGICAL NICU 25 BED 25 BED V O L C Y P O U G N E T S T R E E T FIRST FLOOR PLAN
  • 28. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T S T R E E T S T R E E T P O I V R E S T R E E T C O U R C Y ROOF D E L A P E R O U S S E S T R E E T D E S R O C H E S L5a L1c D E L5b ANTE NATAL WARD GYNAE WARD MEDICAL WARD A/C 25 BED 25 BED 28 BED PLANTROOM E L5d L1c L1c DIALYSIS UNIT POST NATAL WARD MEDICAL WARD MEDICAL WARD 25 BED 28 BED 28 BED V O L C Y P O U G N E T S T R E E T SECOND FLOOR PLAN
  • 29. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 M O N S I E U R S T R E E T S T R E E T S T R E E T P O I V R E S T R E E T C O U R C Y D E L A P E R O U S S E S T R E E T D E S R O C H E S L1c L6a D E L4a ROOF PAEDIATRIC WARD MEDICAL WARD PSYCHIATRIC WARD 25 COT 28 BED 15 BED LABORATORY ROOF L4b J3 L6b PAEDIATRIC PAEDIATRIC WARD CARDIAC WARD PSYCHIATRIC WARD PLAY AREA 30 BED 30 BED 15 BED V O L C Y P O U G N E T S T R E E T THIRD FLOOR PLAN
  • 30. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 WARD VENTILATION External air quality is poor. Filtered fresh air supply to all Wards. Air supply into each ward with ceiling fans to assist circulation. Natural air movement into corridor assisted by extraction at each end. Extract duct at each end of corridor, with secondary extraction via bathrooms into extract shaft, discharging at roof level.
  • 31. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 32. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 WEST ELEVATION SECTION F - F
  • 33. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 34. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 35. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010
  • 36. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 ENVIRONMENTAL PRINCIPLES Hot water produced by a combination of solar water heaters and heat recovery from the chillers. Expected annual savings of 85,000 kWhr saved which can be quantified with an associated reduction of carbon dioxide emission if this was to be heated by LPG gas of 17,000 kg 3/24/2011
  • 37. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 ENVIRONMENTAL PRINCIPLES Maximization of daylight through the atrium with an estimated annual savings of 31,000 kWhr which can be quantified with an associated reduction of carbon dioxide emission if this was to be provided by artificial lighting of 16,120 kg Maximization of daylight in typical wards though openings with an estimated annual savings of 48,442 kWhr which can be quantified with an associated reduction of carbon dioxide emission if this was to be provided by artificial lighting of 25,190 kg
  • 38. PREMIER PRESENTATION o DR A.G.JEETOO HOSPITAL UPGRADE o APRIL 2010 ENVIRONMENTAL PRINCIPLES Filtered fresh air supply to all areas departments of the hospital Use of energy efficient light fittings and Optimization of Energy consumption by using complex Building Controls systems Equipment using Ozone friendly refrigerants Re-use of existing buildings and restoration of historic buildings.
  • 39. PROGRAM Start of Construction - October 2009 Phase 1 Completion - January 2011 Phase 2 Completion - October 2011 Phase 3 Completion - February 2012 Service Buildings - April 2011 Refurbish Existing – February 2012 Final Completion - February 2012
  • 40. PROFESSIONAL TEAM FGG Architects Team Leader / Architect J & A Architects Architect (Mauritius) Pholela Health Equipment Specialist Pro-Design Mechanical & Electrical Ocal Ltd Quantity Surveyor Gibb Civil & Structural Client - Ministry of Health & Quality of Life - Government of Mauritius