SlideShare a Scribd company logo
1 of 13
Download to read offline
PILE CAP
INTRODUCTION
Pile caps are thick reinforced concrete mat which rest on top of
the concrete or timber piles (driven or bored and cast-in-situ) to
provide stability to the foundation. The main objective of constructing
the pile caps is to distribute the load of column(s), which is generally
huge for large constructions, to the under lying piles. A similar type of
foundation to the pile caps are Raft Foundation. In case of Raft, which is
a thick and wide spread RCC slab directly resting at the base of
foundation, loads from columns get directly transported to the soil
strata through the Raft. Raft can only be used for stable hard soil layer
capable to carry huge load without failure. Otherwise Pile and Pile caps
are generally used.
FUNCTION OF PILE CAP
1. To distribute a single load coming from the column to the piles
equally.
2. To laterally stabilize the pile thus increasing the overall
efficiency of the pile group
3. To provide the necessary combined resistance stresses set up
by the super structure and/or the ground movement.
Typical arrangements of piles in pile groups:
Typical shape of pile caps for different number of
piles:
MAIN FEATURES OF PILE CAPS
 Minimum grade of concrete that can be used in construction
of piles and pile caps is M25. A complete pile cap can be
casted monolithically in case of smaller pile like for 2-3 piles.
For larger pile caps than those casting is done in layers.
 Reinforcement bars of columns are embedded into the pile
caps up to their development lengths.
 After casting is done pile caps are cured for 28 days and the
shuttering is removed. The adjacent soil is compacted and
leveled using compactor.
 When number of piles in a group is too high, pile caps are
constructed in the form of raft instead of constructing small
pile caps.
Reinforcement caging for a pile cap with 7 piles underneath
PILE CAP CONSTRUCTION AFTER PILES ARE
COMPLETE:
 After the completion of DMC piling, the piles are kept for 28
days for curing and the reinforcement bars of the piles are
kept well above the ground level so that they can be easily
traced later.
 The surveyor determines the level up to which the soil is to
be excavated to construct pile caps.
 The soil is excavated according to that predetermined level
and the upper portions of the piles are then chipped off with
ordinary hammer and jack-hammer. The necessity of this
chipping off of the upper portions of the piles is to get well
compacted concrete piles beneath the pile caps. If the pile
heads were not chipped off, there may have some voids
present in piles below the caps leaving them of little
strength.
The upper portion of piles after excavation up to desired level
Chipping off of the upper ends of the piles
 As per design and detailing, the depth of the pile caps are
assured and reinforcement is provided. Sufficient clear cover
is provided using concrete cubes of required dimension,
passing them through the steel bars in definite intervals.
 The form work is then completed and concreting is done
monolithically or in layers depending upon the size, depth
and reinforcement density of the pile caps.
BATCHING
PLANT
PROJECT SITE
TCS (TATA CONSULTANCY SERVICE) IT-SEZ PARK
DLF, NEWTOWN, RAJARHAT, KOLKATA,
WESTBENGAL
JOINT VENTURE PROJECT OF L&T AND SPCL
INTRODUCTION
A batching plant is a mechanical system that efficiently mixes and
prepares concrete of desired strength and quality. Cement, coarse
aggregates, sand, water are mixed according to design specifications,
fly ash, admixtures etc are added if required. The whole process is done
mechanically.
Schematic diagram of a concrete batching plant.
Types of batching plant
On the basis of amount of concrete prepared by the plant in unit
time the plants are classified. At the project site the plant in work was
CP30 or Concrete Plant 30. It means that the plant can ideally produce
30 m3
concrete in an hour. There is also CP60 type of plants that are
usually used. It produces 60 m3
concrete in an hour, or 1 m3
concrete in
a minute. So these are also called M1 plants.
COMMON PARTS OF A BTACHING PLANT
 CEMENT SILO: These store the cement. There is usually
more than one silo used for a plant to store different kinds
of cements. These are large cylindrical structure with
tapered bottom end connected to the screw conveyor.
 SCREW CONVEYOR: this is used to carry the cement from
the silo to the pan mixer.
 HOPPER: this is where the front end loader dumps the
aggregates.
 BELT CONVEYEOR: this carries the aggregates from hopper
to the aggregates bin.
 AGGREGATE STORAGE BIN: These are the conical bins that
temporarily store the aggregates, both coarse and fine and
supply them to the skip bucket.
 PNEUMATIC CYLINDER AND DISCHARGE GATE: These are
attached with computerized censors and discharge exact
amount of aggregate into the skip bucket as per mix design
specification.
 SKIP BUCKET: it carries the aggregate from storage bin to
the pan mixer.
SKIP BUCKET AND DISCHARGE GATES
 PAN MIXER: this is where the concrete is prepared by
mixing all its ingredients. And when the concrete is ready
they discharge the ready concrete into the transit mixer.
 ADMIXTUER CHAMBER: admixtures are stored here and
those are conveyed to the pan mixers.
ADMIXTURE CHAMBER
 CEMENT FEEDING PUMP: these are used to feed the silo
with cement from the cement storage rooms.
 DUST COLLECTOR: this is a chamber that, through a pipe
and pump, collects the harmful cement dust from the
storage room.
DUST COLLECTOR
 CONTROL ROOM: this is, from where the whole procedure
is controlled. Computer software is made by the plant
manufactures that also controls the concrete preparation
process. If in case there is any problem the procedures can
be controlled manually too.
SOFTWARE AIDED CONTRLON
 WATER VAT: this is a vat located near the plant from where
required amount of water is supplied to the pan mixer
through a pump.
FLOW CHART: BATCING PLANT OPERATION
CONCLUSION TO THE PORJECT
At the project site the plant was aided by one 180kVA and
one 125kVA power generators. Naphtha-base “sikamant-3008NS”
admixtures were being used. For concrete of higher strength (higher
grade than M50) PC-base admixtures are used. The mixing arms inside
the pan mixer are powered by 30Hp motor. Correction shits were
prepared on daily basis to check deviation in strength of concrete due
to variable moisture content of sand.

More Related Content

What's hot

Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundation
AmiRul AFiq
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
Sagar Shah
 

What's hot (20)

Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Building construction notes pdf
Building construction notes pdfBuilding construction notes pdf
Building construction notes pdf
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
 
Base isolation of structures
Base isolation of structures Base isolation of structures
Base isolation of structures
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONS
 
Foundation & Footings
Foundation & FootingsFoundation & Footings
Foundation & Footings
 
types of Foundations with animated sketches
types of Foundations with animated sketchestypes of Foundations with animated sketches
types of Foundations with animated sketches
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundation
 
Introduction to prestressed concrete structures
Introduction to prestressed concrete structuresIntroduction to prestressed concrete structures
Introduction to prestressed concrete structures
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Foundation ppt
Foundation pptFoundation ppt
Foundation ppt
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Bc open pre fabricated construction system
Bc open pre fabricated construction systemBc open pre fabricated construction system
Bc open pre fabricated construction system
 

Viewers also liked

Room Acoustics
Room AcousticsRoom Acoustics
Room Acoustics
Drew
 
L 16 pilfoundation
L 16 pilfoundationL 16 pilfoundation
L 16 pilfoundation
karna13
 
Motivation theory
Motivation theoryMotivation theory
Motivation theory
A B
 

Viewers also liked (20)

Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile cap
 
Pile design guide (Collected)
Pile design guide (Collected)Pile design guide (Collected)
Pile design guide (Collected)
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pile cap two pile laod 50 t desigh and drawing
Pile cap  two pile laod 50 t  desigh and drawingPile cap  two pile laod 50 t  desigh and drawing
Pile cap two pile laod 50 t desigh and drawing
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Building Construction - Foundation
Building Construction - FoundationBuilding Construction - Foundation
Building Construction - Foundation
 
Room Acoustics
Room AcousticsRoom Acoustics
Room Acoustics
 
Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
 
Illumination
IlluminationIllumination
Illumination
 
Electric power grid
Electric power gridElectric power grid
Electric power grid
 
Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
 
Elevators & Escalators
Elevators & EscalatorsElevators & Escalators
Elevators & Escalators
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
L 16 pilfoundation
L 16 pilfoundationL 16 pilfoundation
L 16 pilfoundation
 
Scaffolding 101
Scaffolding 101Scaffolding 101
Scaffolding 101
 
Motivation theory
Motivation theoryMotivation theory
Motivation theory
 
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
 

Similar to PILE-CAP & Batching plant

Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Prerak Ka.Patel
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
AJAY SHAHU
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
Mylene Delmoro
 

Similar to PILE-CAP & Batching plant (20)

Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
CONCRETE
CONCRETECONCRETE
CONCRETE
 
Concrete
ConcreteConcrete
Concrete
 
Microtunel Construction / Secant Pile
Microtunel Construction / Secant PileMicrotunel Construction / Secant Pile
Microtunel Construction / Secant Pile
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
READY MIX CONCRETE
READY MIX CONCRETEREADY MIX CONCRETE
READY MIX CONCRETE
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipment
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Ready Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B M
Ready Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B MReady Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B M
Ready Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B M
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
3 hayzi.pptx
3 hayzi.pptx3 hayzi.pptx
3 hayzi.pptx
 
Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering)
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 

PILE-CAP & Batching plant

  • 2. INTRODUCTION Pile caps are thick reinforced concrete mat which rest on top of the concrete or timber piles (driven or bored and cast-in-situ) to provide stability to the foundation. The main objective of constructing the pile caps is to distribute the load of column(s), which is generally huge for large constructions, to the under lying piles. A similar type of foundation to the pile caps are Raft Foundation. In case of Raft, which is a thick and wide spread RCC slab directly resting at the base of foundation, loads from columns get directly transported to the soil strata through the Raft. Raft can only be used for stable hard soil layer capable to carry huge load without failure. Otherwise Pile and Pile caps are generally used. FUNCTION OF PILE CAP 1. To distribute a single load coming from the column to the piles equally. 2. To laterally stabilize the pile thus increasing the overall efficiency of the pile group 3. To provide the necessary combined resistance stresses set up by the super structure and/or the ground movement.
  • 3. Typical arrangements of piles in pile groups: Typical shape of pile caps for different number of piles:
  • 4. MAIN FEATURES OF PILE CAPS  Minimum grade of concrete that can be used in construction of piles and pile caps is M25. A complete pile cap can be casted monolithically in case of smaller pile like for 2-3 piles. For larger pile caps than those casting is done in layers.  Reinforcement bars of columns are embedded into the pile caps up to their development lengths.  After casting is done pile caps are cured for 28 days and the shuttering is removed. The adjacent soil is compacted and leveled using compactor.  When number of piles in a group is too high, pile caps are constructed in the form of raft instead of constructing small pile caps. Reinforcement caging for a pile cap with 7 piles underneath
  • 5. PILE CAP CONSTRUCTION AFTER PILES ARE COMPLETE:  After the completion of DMC piling, the piles are kept for 28 days for curing and the reinforcement bars of the piles are kept well above the ground level so that they can be easily traced later.  The surveyor determines the level up to which the soil is to be excavated to construct pile caps.  The soil is excavated according to that predetermined level and the upper portions of the piles are then chipped off with ordinary hammer and jack-hammer. The necessity of this chipping off of the upper portions of the piles is to get well compacted concrete piles beneath the pile caps. If the pile heads were not chipped off, there may have some voids present in piles below the caps leaving them of little strength. The upper portion of piles after excavation up to desired level
  • 6. Chipping off of the upper ends of the piles  As per design and detailing, the depth of the pile caps are assured and reinforcement is provided. Sufficient clear cover is provided using concrete cubes of required dimension, passing them through the steel bars in definite intervals.  The form work is then completed and concreting is done monolithically or in layers depending upon the size, depth and reinforcement density of the pile caps.
  • 7. BATCHING PLANT PROJECT SITE TCS (TATA CONSULTANCY SERVICE) IT-SEZ PARK DLF, NEWTOWN, RAJARHAT, KOLKATA, WESTBENGAL JOINT VENTURE PROJECT OF L&T AND SPCL
  • 8. INTRODUCTION A batching plant is a mechanical system that efficiently mixes and prepares concrete of desired strength and quality. Cement, coarse aggregates, sand, water are mixed according to design specifications, fly ash, admixtures etc are added if required. The whole process is done mechanically. Schematic diagram of a concrete batching plant.
  • 9. Types of batching plant On the basis of amount of concrete prepared by the plant in unit time the plants are classified. At the project site the plant in work was CP30 or Concrete Plant 30. It means that the plant can ideally produce 30 m3 concrete in an hour. There is also CP60 type of plants that are usually used. It produces 60 m3 concrete in an hour, or 1 m3 concrete in a minute. So these are also called M1 plants. COMMON PARTS OF A BTACHING PLANT  CEMENT SILO: These store the cement. There is usually more than one silo used for a plant to store different kinds of cements. These are large cylindrical structure with tapered bottom end connected to the screw conveyor.  SCREW CONVEYOR: this is used to carry the cement from the silo to the pan mixer.  HOPPER: this is where the front end loader dumps the aggregates.  BELT CONVEYEOR: this carries the aggregates from hopper to the aggregates bin.  AGGREGATE STORAGE BIN: These are the conical bins that temporarily store the aggregates, both coarse and fine and supply them to the skip bucket.  PNEUMATIC CYLINDER AND DISCHARGE GATE: These are attached with computerized censors and discharge exact amount of aggregate into the skip bucket as per mix design specification.
  • 10.  SKIP BUCKET: it carries the aggregate from storage bin to the pan mixer. SKIP BUCKET AND DISCHARGE GATES  PAN MIXER: this is where the concrete is prepared by mixing all its ingredients. And when the concrete is ready they discharge the ready concrete into the transit mixer.  ADMIXTUER CHAMBER: admixtures are stored here and those are conveyed to the pan mixers. ADMIXTURE CHAMBER
  • 11.  CEMENT FEEDING PUMP: these are used to feed the silo with cement from the cement storage rooms.  DUST COLLECTOR: this is a chamber that, through a pipe and pump, collects the harmful cement dust from the storage room. DUST COLLECTOR  CONTROL ROOM: this is, from where the whole procedure is controlled. Computer software is made by the plant manufactures that also controls the concrete preparation process. If in case there is any problem the procedures can be controlled manually too. SOFTWARE AIDED CONTRLON  WATER VAT: this is a vat located near the plant from where required amount of water is supplied to the pan mixer through a pump.
  • 12. FLOW CHART: BATCING PLANT OPERATION
  • 13. CONCLUSION TO THE PORJECT At the project site the plant was aided by one 180kVA and one 125kVA power generators. Naphtha-base “sikamant-3008NS” admixtures were being used. For concrete of higher strength (higher grade than M50) PC-base admixtures are used. The mixing arms inside the pan mixer are powered by 30Hp motor. Correction shits were prepared on daily basis to check deviation in strength of concrete due to variable moisture content of sand.