Publicidad
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Publicidad
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Publicidad
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Sayan  CESC LT Report.pdf
Próximo SlideShare
CESC LTD. TRAINING REPORTCESC LTD. TRAINING REPORT
Cargando en ... 3
1 de 13
Publicidad

Más contenido relacionado

Publicidad

Sayan CESC LT Report.pdf

  1. The Calcutta Electric Supply Corporation Limited (CESC) VOCTIONAL TRAINING REPORT ON LT MAINS (SOUTHERN DISTRICT) Submitted By, Name: SAYAN BASAK B. P. Poddar Institute of Management and Technology University Roll: 11501620025 Date: 18/07/2022 – 23/07/2022
  2. Certificate of Declaration: This is to clarify that Mr. Sayan Basak, engineering trainee (distribution) have successfully completed her training in LT mains under my guidance as a part of the training program for engineering trainee. Date: . Dy. Manager Mains (Southern District)
  3. Introduction Kolkata, being one of the major hubs as far as India’s Industrial and Business scenario is concerned; there is a steady increase in electricity demand in the city. The scorching and sultry weather is also one of the key factors in this regard. Every summer we see a rush ofapplications for new ACs leading to heavy increase in load demand and hence system capacity. Now, CESC has this responsibility of distributing power to the entire population of 3 million in the metropolitan area of Kolkata and Howrah, some portions of North & South 24 Parganas for which it has to maintain a large distribution network. The distribution system is healthy and reliable investments are made on an ongoing basis to maintain the network. In addition to maintenance, CESC is constantly making efforts, inviting new ideas to improve the existing network, starting from Distribution Transformer up to the service end to meet various challenges faced by it on daily basis. Mainly distribution systems are of 2 types, they are- • Primary Distribution system (33KV/11KV or 6KV) • Secondary Distribution system (11KV or 6KV/400V) Mains (Distribution) have two wings - LT and HT. Each of them has many subdivisions. LT department is concerned with the secondary distribution network (11 or 6kV/ 400V) that supplies electricity to domestic, commercial and some industrial consumers. It basically deals with the fault detection, restoration, new meter connection, LT cable joining etc. in LT network.
  4. Day Wise Report: Day 1 Report: On Tuesday 19/07/2022, I reported at around 9 am at Jadavpur office. Asst. Engineer sir Samaresh Gantait referred me to Mr Z. Khan, with him I went the site Survery Park Kolkata. Job Details: Two new service done on the 1462, Survey Park building and also removal of old service under the supervisor Mr Z.Khan. According to the job we have to place a new pole in front of this building. • Firstly, a new pole is installed in front of the building and after that we take connection from the nearest pole. A overhead service is done with 4 core LT AB (Arial Bunch) type cable used for this purpose. One G.I pipes are sunk into holes dug with the help of earth Auger. Job Slip for 49 mtr cable Job Slip for 45 mtr cable
  5. After the pole installation we placed a 1100v underground service for main line of the building. One cable is 49mtr long and another is 45mtr long according to plan. Laying of Service cable: • Applicant’s details from job slip must be verified. • The meter board position and the wall for fixing board must be verified. • Depth of laying cable is 75 cm. • Cable should be laid inside pipes wherever crossing any installation of other agencies and to be adequately protected. • Pre-cut length of cable is laid in trench prepared and within pipes laid for this purpose. New Building where the work is done Pole arrived for installation
  6. • The service cable should be containing a loop in ground below meter board. This cable must enter meter board through a 75mm dia PVC pipe 1.0-meter-long placed vertically below ground. For Joining the Connection: The line was off for 1 hours form the nearby pillar box and the jumper was opened from the other side. Pillar boxes are units from where the distribution takes place i.e. they act as nodes. There are of two types namely Feeder Pillar Box and Distribution Pillar Box. In case of Feeder Pillar Box it is connected to (400 mm2 XLPE 1.1kV grade cable) coming from the L.T end of the transformer. While in a distribution pillar box it may be connected to some other pillar box or an overhead pole via underground cables. As the main work finished, the line was to be normalised but before that they had to check if there is any fault in the line. Meter Board Installation: • The main switch or MCB must be identified. • The board must be at least 1.0 meter verticaly above the floor level. • Earthing Brackets must be provided to all meter boards. • Asbestos millboards are fixed over the rear wall for fre protection. Service Disconnected from Feeder Box New Meter Installed
  7. Day 2 Report: On Wednesday 20/07/2022, I reported at around 9 am at Jadavpur office. Asst. Engineer sir Samaresh Gantait referred me to Mr Z. Khan, with him I went the site Golf Garden Kolkata. Job Details: To install a feeder pillar in Golf Garden 17/D Prince Golam Hossain Shah Rd under the supervisor Mr Z.Khan. Job Slip
  8. According to their service plan feeder pillar was installed over there. Installation of Feeder Pillar Box: • Mainly 6-way pillar box is generally installed there. • This type of Feeder Pillar installed in conjunction with the distribution transformer. New Service Plan
  9. • Here six nos. of cable may be terminated. • Here four nos. of cablese may be terminated. Where to Erect: • Erection requirements for both 4 & 6 way are come. • They are preferably to be erected on footpaths. • Sufficient clearance from building line is maintained for smooth Pedestrian movement. Feeder Pillar Box Earthing: • All pillar boxes body are earthed. • Two nos. 4.5 mtr long and 50m dia C.I pipes are sunk into holes dug with the help of earth Auger. • The holes are 600mm apart and dug 450 mm away from pillar box. • The neutral conductor is earthed only at Feeder box. • Neural earth and body earth must be done on opposite side of the box and separated by one meter.
  10. Day 3 Report: On Friday 22/07/2022, I reported at around 9 am at Jadavpur office. Asst. Engineer sir Samaresh Gantait referred me to Prasanta sir, with him I went the site Nava Nagar Colony. Job Details: Jadavpur O/T No.1 U5—240 sqmm PVC dist. feed sing ACPB 316 U3 found 9R)/ (Red Phase No current).
  11. Fault Type: Distributer Fault. Pillar Box: JADAVPURE O/T T.1.F-1&2. Cable Size: 240 Sqmm. • Service was cut off from two pillar box. The Fault is happened on a linked cable. Another pillar box we see the R phase is missing that means the voltage of a R phase is zero. In case of linked cable, we have to punch the cable to locate the fault. • To perform punch or pin the cable we digging at the middle of the cable length. Lamp test was done to locate different feeders and incomers. • Necessary steps were taken in the pillar box so that underground digging can be done safely to locate the fault. • Several pockets were made in the ground to locate the fault. It was done in the pin test method. Faulty Pillar Box Fault occur on fifth number unit
  12. After cut off the faulty part then that cable was prepared for the join. Using 240- 240 straight joint kit for joining this cable. Finally, after the completed the joint check all the line and then supply was resumed. Pin Test is running Main Faulty Part Cable joining is running Pour the mixture compound in the joint
  13. Conclusion: I have completed my training in LT cell from Jadavpur site under Mr Soumyabrata Mazumder from the period of 18/07/2022 to 23/07/2022. Throughout the training period I learned about new supply lines, Underground distribution cable fault, service fault about pillar box etc. The training was very an important as it helps to gain practical knowledge about the subject which will helped me to gain practical knowledge and experience.
Publicidad