MINISTRY OF EDUCATION OF YOUTHS
AND SPORTS
INSTITUTE OF TECHNOLOGY OF CAMBODIA
DEPARTMENT OF INDUSTRIALAND MECHANICAL
FINAL YEAR THESIS
Tittle: Designing, Installation and Testing of VRF System
Students : TITH Sopheara and VENG Socheat
Specialty : Mechanical engineering
Advisor : Mr. KHOUN Rithymean
Academic Year : 2016- 2017
1
Contents
I. General Introduction
II. Definition
III. Panasonic VRF system
IV. Load calculation
V. Selection
VI. VRF system installation
VII. Testing and Commissioning
VIII.Conclusion
2
I. General Introduction
 Presentation of Internship
•From: 20 February to 20 May 2017
•Company: Comin Khmere
•Position : MVAC trainee
•Project: TK Royal One (Cambodia)
3
II. Definition
4
What is VRF systems?
• Variable refrigerant flow vary the flow of refrigerant to
indoor units based on demand. There are 2 types of VRF
system, heat pump and heat recovery system.
What is VRF Heat pump ?
• VRF heat pump provide heating or cooling but not
simultaneous heating and cooling
5
II. Definition
What is VRF heat recovery?
• VRF heat recovery can operate simultaneous in
heating or cooling mode.
6
II. Definition
Variable refrigerant flow (VRF) is an air-conditioning system
configuration where there is one outdoor unit and multiple
indoor units.
III. Panasonic VRF System
7
III. Panasonic VRF System
1. Outdoor unit
The outdoor unit of VRF
system, sometimes called the
outside unit or condenser.
8
(Carin, 2016)
III. Panasonic VRF System
DC twin rotary compressor:
The component of compressor are:
1. Electric motor
2. Compression mechanism
3. Accumulator
The compressor is the heart of the
refrigeration cycle.
9
(Bhatia, 2014)
III.Panasonic VRF System
a. 2-WAY Mini-FSV LE1 Series
 Use for cooling or heating mode only
Capacity range from 4HP to 6HP
COP: 4.21 in case of 4 HP
 Cooling operation possible up to 46 °C
And low as -20 °C for heating mode
 Max connectable 9 units with length 150m
10
(Hiong, 2016-2017)
III.Panasonic VRF System
b. 2-WAY FSV-EX ME2 Series
 Use for cooling or heating mode only
 Capacity range from 8HP to 80HP
 Operation temperature as high as 52°C
for cooling and as low as -20 °C for
heating mode
 Max connectable 64 units with max
length 1,000m
11
(Hiong, 2016-2017)
III.Panasonic VRF System
c. 3-WAY FSV MF2 Series
 Using for simultaneous heating and cooling
 Capacity range from 8HP to 42HP
 Temperature operation as high as 46°C for
cooling and as low as -20 for heating
 Max connectable 52 units with pipe length
up to 500m
12
(Hiong, 2016-2017)
III.Panasonic VRF System
2. Indoor unit
There are many types of indoor units such as:
• F2 type : Cooling Capacity 2.2kW to 16kW
• M1 type : Cooling Capacity 2.2kW up to 5.6kW
• Z1 type : Cooling Capacity 2.2kW to 7.3kW
• E2 type : Cooling Capacity 18kW to 28kW
13
III.Panasonic VRF System
2. Indoor unit
• E1 type : Cooling Capacity 7.3kW to 28kW
• U1 type : 4-way cassette, Cooling Capacity 2.2kW to 16kW
• Y2 type : 4-way mini cassette, Cooling Capacity 2.2kW to 5.6kW
• L1 type : 2-way cassette, Cooling Capacity 2.2kW to 7.3kW
• D1 type : 1-way cassette, Cooling Capacity 2.8kW to 7.3kW
• P1 type : Floor standing, Cooling Capacity 2.2kW to 7.3kW
14
IV.Load Calculation
 Feature of the Building TK Royal One
15http://www.cambodiancondos.com/condo-developments/tk-royal-one/
IV. Load Calculation
1. Estimate Method
Q = S . R
• Q: Total heat load [Btu.h-1]or [W]
• S: room area [m2]
• R: The rate of cooling [Btu.h-1.m-2]
Calculation total heating load for TKR1 “ Reception
room’’ which has S = 62.4 m2
• R = 900 Btu.h-1.m-2
Thus, Q = 56160 Btu.h−1 =16.45kW
16
Another room calculate by Estimate method
Items Type of Room
AREA Ratio Cooling Capacity
m² Btu/h.m2 kW Btu/h
1 Conference Hall 265.45 1200 93.36 318540
2 Break Room 49.07 750 10.78 36802
3 Coffee Shop 73.6 1300 28.04 95680
4 Financial Office 98.14 850 24.48 83419
5 Hall 35.5 700 7.28 24850
6 Office 56.5 850 14.07 48025
7 Meeting Room 31.95 900 8.40 28755
8 Service Counter 36.8 1300 14.02 47840
9 Shop 87.7 800 20.56 70160
10 Toilet 38 500 5.56 19000
17
IV. Load Calculation
2. Manual Method
The Manual Method is the method used to calculate the cooling load
of the building space with minimum errors.
Total heating load:
QT = QS + QL [W]
oTotal sensitive loads
QS = QStr+ QSRm+QSRv+QSoc+QSecl+QSequip
oTotal latent loads
QL= QLr+ QLoc+QLequip
18
IV.Load Calculation
Calculation heating load for TKR1 “ Reception Area’’
oTotal sensitive loads
QS = 14445.26 W
oTotal latent loads
QL = 1197.58W
Total heating load:
QT= 14445.26 W + 1197.58W = 15642.84 W = 15.64 kW
19
IV.Load Calculation
Verify the cooling capacity coefficient R [Btu/h.m2]:
• Manul method: R= 53367Btu.h−1 / 62.4 m2 = 855 Btu.h−1
• Estimate method: R = 900 Btu.h−1
From the calculation above by manual method, we see that
error of cooling rate approximate 5 % compared to
estimation method
20
V. Selection
1. Selection indoor unit
The total cooling load required is 109.8 kW
21(Hiong, 2016-2017)
V. Selection
The characteristic of outdoor unit model U-40ME2R8
are:
• Cooling capacity 113 kW
• Using with power supply 400/415 V/3-phase/50 Hz
• Electrical rating for cooling option: 57.3 A
• Refrigerant amount at shipment: 22.0 kg
• Air flowrate: 48600 m3 h-1
22
V. Selection
2. Selection indoor unit
 For Conference Hall of TKR1:
The requirement of cooling load is 93.36 kW.
Catalogue of model mid static duct E1 type chosen that
Its cooling capacity from 7.3 kW to 28 kW.
E1 type is a kind of saving energy, the power input
45% less (compared to H1 type)
4 of S-224ME1E5 were chosen: Cooling capacity 4 ×
22.4kW = 89.6kW
23
V. Selection
24
(Hiong, 2016-2017)
VI.VRF System Installation
1. Air duct installation
25
2. Indoor unit installation
VI.VRF System Installation
3. Copper pipe installation
26
VI.VRF System Installation
4. Drainage water pipe installation
27
VI.VRF System Installation
5. Outdoor unit installation
28
VII. Testing and Commissioning
Before we start operation VRF, we have to:
1. Test refrigerant pipe
2. Adding refrigerant
3. Check at main power on
4. Testing and commissioning
29
30
1. Test refrigerant pipe
a. Check for any leakage in the
refrigerant piping
b. Perform vacuum drying to
remove all moisture
• Keeping the valve of the outdoor
unit closed
• If the specified amount of
refrigerant cannot be charged, fully
open the valves of the outdoor unit
at liquid and gas sides, operate the
air conditioner in COOL mode
31
2. Adding refrigerant
Check on the outdoor unit
Check on the setting indoor unit
32
3. Check at main power on
a. Check ON the rotary switches of
outdoor unit
b. Check ON the setting indoor unit
• Incoming supply for outdoor phrase sequence for 3 phases,
Incoming Voltage (380~415V).
• Incoming voltage for Indoor 220~240V and ensure power supply all
Indoor unit is turn "ON".
• Once all the setting is set and check, then start addressing the system
by short-circuit pin CN-30
33
4. Testing and commissioning
34
 Start addressing the system by short-circuit pin CN-30
Laptop - Window 7 professional – 32
or 64 bits operation system
 Normal USB Printer
Wire
 Panasonic Flash Writer – 8F000900210 / Part Code – 6233214375
 To be purchase from Panasonic
(Oudom, 2017)
35
a. Indoor fan speed and temperature.
OUTDOOR Screen
INDOOR Screen
b. Outdoor Compressor temperature,
Gas temperature and etc.
 After the result have to be printed out by manufacture and to be attached in
Testing and Commissioning form for VRF recording.
(Oudom, 2017)
VIII. Conclusion
• The calculation cooling load by estimation and manual
seem a litter bit difference value. The selection of the
systems that suitable for reception area and conference
hall is outdoor unit model U-40ME2R8 which maximum
cooling capacity is 113 kW.
• To get the best result of VRF system, we have to
understand about plan and condition for installation of
indoor unit, outdoor unit, air duct, copper pipe, and
drainage water pipe.
• VRF testing and commissioning is a part which we use
the method statement to carry on indoor unit, outdoor unit
operation after installation.
36
Thank You For Your
Attention !
Q & A
37
Thank you for your
attention!!!
Question?

Más contenido relacionado

La actualidad más candente

Cooling Systems - Chiller Technologies
Cooling Systems - Chiller TechnologiesCooling Systems - Chiller Technologies
Cooling Systems - Chiller TechnologiesHusain Baqer
 
Heating Ventilation & Air Conditioning (HVAC)
Heating Ventilation & Air Conditioning (HVAC)Heating Ventilation & Air Conditioning (HVAC)
Heating Ventilation & Air Conditioning (HVAC)Joshua Joel
 
Air Conditioning Systems in Refrigeration and Air Conditioning
Air Conditioning Systems in Refrigeration and Air ConditioningAir Conditioning Systems in Refrigeration and Air Conditioning
Air Conditioning Systems in Refrigeration and Air ConditioningAjaypalsinh Barad
 
Hvac introduction-Basics of HVAC
Hvac introduction-Basics of HVACHvac introduction-Basics of HVAC
Hvac introduction-Basics of HVACMDSALEKINNEWAZ
 
Basics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaBasics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaJitendra Jha
 
HVAC - by Anoushka Aggarwal
HVAC - by Anoushka AggarwalHVAC - by Anoushka Aggarwal
HVAC - by Anoushka AggarwalANOUSHKAAggarwal
 
Hvac presentation for beginers
Hvac presentation for beginersHvac presentation for beginers
Hvac presentation for beginersguestf11b52
 
Air Conditioning & Hvac Systems
Air Conditioning & Hvac SystemsAir Conditioning & Hvac Systems
Air Conditioning & Hvac SystemsGAURAV. H .TANDON
 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systemsmichaeljmack
 
Control system for HVAC
Control system for HVACControl system for HVAC
Control system for HVACfarooq husain
 
S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)no suhaila
 
Introduction to VRF
Introduction to VRF Introduction to VRF
Introduction to VRF John Chavez
 
Centralized ac system
Centralized ac systemCentralized ac system
Centralized ac systemFebin Siby
 
Chilled water piping basics
Chilled water piping basicsChilled water piping basics
Chilled water piping basicsAp Naseem
 
Air Condtioning Systems HVAC
Air Condtioning Systems HVACAir Condtioning Systems HVAC
Air Condtioning Systems HVACPrashanth Dommeti
 
Underground car parking ventilation system
Underground car parking ventilation systemUnderground car parking ventilation system
Underground car parking ventilation systemMohamed Hashish
 

La actualidad más candente (20)

HVAC introduction
HVAC introductionHVAC introduction
HVAC introduction
 
Cooling Systems - Chiller Technologies
Cooling Systems - Chiller TechnologiesCooling Systems - Chiller Technologies
Cooling Systems - Chiller Technologies
 
Heating Ventilation & Air Conditioning (HVAC)
Heating Ventilation & Air Conditioning (HVAC)Heating Ventilation & Air Conditioning (HVAC)
Heating Ventilation & Air Conditioning (HVAC)
 
Air Conditioning Systems in Refrigeration and Air Conditioning
Air Conditioning Systems in Refrigeration and Air ConditioningAir Conditioning Systems in Refrigeration and Air Conditioning
Air Conditioning Systems in Refrigeration and Air Conditioning
 
Hvac introduction-Basics of HVAC
Hvac introduction-Basics of HVACHvac introduction-Basics of HVAC
Hvac introduction-Basics of HVAC
 
Basics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaBasics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra Jha
 
HVAC - by Anoushka Aggarwal
HVAC - by Anoushka AggarwalHVAC - by Anoushka Aggarwal
HVAC - by Anoushka Aggarwal
 
Hvac presentation for beginers
Hvac presentation for beginersHvac presentation for beginers
Hvac presentation for beginers
 
HVAC Fundamentals
HVAC  FundamentalsHVAC  Fundamentals
HVAC Fundamentals
 
Air Conditioning & Hvac Systems
Air Conditioning & Hvac SystemsAir Conditioning & Hvac Systems
Air Conditioning & Hvac Systems
 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systems
 
Hvac complete final
Hvac complete finalHvac complete final
Hvac complete final
 
Control system for HVAC
Control system for HVACControl system for HVAC
Control system for HVAC
 
S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)
 
Introduction to VRF
Introduction to VRF Introduction to VRF
Introduction to VRF
 
Centralized ac system
Centralized ac systemCentralized ac system
Centralized ac system
 
Chilled water piping basics
Chilled water piping basicsChilled water piping basics
Chilled water piping basics
 
Air Condtioning Systems HVAC
Air Condtioning Systems HVACAir Condtioning Systems HVAC
Air Condtioning Systems HVAC
 
CHILLER PLANT MANAGER
CHILLER PLANT MANAGERCHILLER PLANT MANAGER
CHILLER PLANT MANAGER
 
Underground car parking ventilation system
Underground car parking ventilation systemUnderground car parking ventilation system
Underground car parking ventilation system
 

Similar a Design, Installation and Testing of the VRF System

PRESENTATION AIRWELL VRF 2014 GB
PRESENTATION  AIRWELL VRF 2014 GBPRESENTATION  AIRWELL VRF 2014 GB
PRESENTATION AIRWELL VRF 2014 GBArjang Ahmadi
 
Catalog Biến tần Frenic-HVAC (Fuji Electric)
Catalog Biến tần Frenic-HVAC (Fuji Electric)Catalog Biến tần Frenic-HVAC (Fuji Electric)
Catalog Biến tần Frenic-HVAC (Fuji Electric)Beeteco
 
Fuji tu dong hoa catalog frenic-hvac-dienhathe.org
Fuji tu dong hoa catalog frenic-hvac-dienhathe.orgFuji tu dong hoa catalog frenic-hvac-dienhathe.org
Fuji tu dong hoa catalog frenic-hvac-dienhathe.orgDien Ha The
 
[ME-20249]Complex Engineering RAC file.pdf
[ME-20249]Complex Engineering RAC file.pdf[ME-20249]Complex Engineering RAC file.pdf
[ME-20249]Complex Engineering RAC file.pdfSHAHFAISALHAMEED
 
Experimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancementExperimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancementeSAT Journals
 
Experimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancementExperimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancementeSAT Journals
 
IRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFD
IRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFDIRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFD
IRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFDIRJET Journal
 
Crac precision climate_control_units_for_data_centres
Crac precision climate_control_units_for_data_centresCrac precision climate_control_units_for_data_centres
Crac precision climate_control_units_for_data_centresEeu SC
 
IRJET- Air Conditioning Ceiling Fan by using Thermoelectric Module
IRJET- Air Conditioning Ceiling Fan by using Thermoelectric ModuleIRJET- Air Conditioning Ceiling Fan by using Thermoelectric Module
IRJET- Air Conditioning Ceiling Fan by using Thermoelectric ModuleIRJET Journal
 
High Efficiency Solutions EEV & Monitoring Systems
High Efficiency Solutions  EEV & Monitoring SystemsHigh Efficiency Solutions  EEV & Monitoring Systems
High Efficiency Solutions EEV & Monitoring SystemsCAREL Industries S.p.A
 
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiencyInlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiencyH.Ikeuchi & Co.,Ltd
 
AETEG Presentation.pptx
AETEG Presentation.pptxAETEG Presentation.pptx
AETEG Presentation.pptxTamarana Kumar
 
Technical specification EEE
Technical specification EEETechnical specification EEE
Technical specification EEEAmit Kumar
 
Training Seminar - Standards, Heat Tracing Options & Application Optimization...
Training Seminar - Standards, Heat Tracing Options & Application Optimization...Training Seminar - Standards, Heat Tracing Options & Application Optimization...
Training Seminar - Standards, Heat Tracing Options & Application Optimization...Thorne & Derrick International
 
Rittal - Re-Cooling - Chiller Ürünleri
Rittal - Re-Cooling - Chiller ÜrünleriRittal - Re-Cooling - Chiller Ürünleri
Rittal - Re-Cooling - Chiller Ürünlerierdinc klima
 
Eta a series reflow oven
Eta a series reflow ovenEta a series reflow oven
Eta a series reflow ovenMark Tung
 
Eta a series reflow oven
Eta a series reflow ovenEta a series reflow oven
Eta a series reflow ovenMark Tung
 
Hecu – high energy efficiency solution for condensing units fitted with DC co...
Hecu – high energy efficiency solution for condensing units fitted with DC co...Hecu – high energy efficiency solution for condensing units fitted with DC co...
Hecu – high energy efficiency solution for condensing units fitted with DC co...CAREL Industries S.p.A
 

Similar a Design, Installation and Testing of the VRF System (20)

PRESENTATION AIRWELL VRF 2014 GB
PRESENTATION  AIRWELL VRF 2014 GBPRESENTATION  AIRWELL VRF 2014 GB
PRESENTATION AIRWELL VRF 2014 GB
 
Frenic hvac catalog
Frenic hvac catalogFrenic hvac catalog
Frenic hvac catalog
 
Design HVAC System for Hospital
Design HVAC System for Hospital Design HVAC System for Hospital
Design HVAC System for Hospital
 
Catalog Biến tần Frenic-HVAC (Fuji Electric)
Catalog Biến tần Frenic-HVAC (Fuji Electric)Catalog Biến tần Frenic-HVAC (Fuji Electric)
Catalog Biến tần Frenic-HVAC (Fuji Electric)
 
Fuji tu dong hoa catalog frenic-hvac-dienhathe.org
Fuji tu dong hoa catalog frenic-hvac-dienhathe.orgFuji tu dong hoa catalog frenic-hvac-dienhathe.org
Fuji tu dong hoa catalog frenic-hvac-dienhathe.org
 
[ME-20249]Complex Engineering RAC file.pdf
[ME-20249]Complex Engineering RAC file.pdf[ME-20249]Complex Engineering RAC file.pdf
[ME-20249]Complex Engineering RAC file.pdf
 
Experimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancementExperimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancement
 
Experimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancementExperimentation on heat pipe and cfd analysis for performance enhancement
Experimentation on heat pipe and cfd analysis for performance enhancement
 
IRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFD
IRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFDIRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFD
IRJET- Enhancement of COP of Vapor Compression Refrigeration Cycle using CFD
 
Crac precision climate_control_units_for_data_centres
Crac precision climate_control_units_for_data_centresCrac precision climate_control_units_for_data_centres
Crac precision climate_control_units_for_data_centres
 
IRJET- Air Conditioning Ceiling Fan by using Thermoelectric Module
IRJET- Air Conditioning Ceiling Fan by using Thermoelectric ModuleIRJET- Air Conditioning Ceiling Fan by using Thermoelectric Module
IRJET- Air Conditioning Ceiling Fan by using Thermoelectric Module
 
High Efficiency Solutions EEV & Monitoring Systems
High Efficiency Solutions  EEV & Monitoring SystemsHigh Efficiency Solutions  EEV & Monitoring Systems
High Efficiency Solutions EEV & Monitoring Systems
 
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiencyInlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
 
AETEG Presentation.pptx
AETEG Presentation.pptxAETEG Presentation.pptx
AETEG Presentation.pptx
 
Technical specification EEE
Technical specification EEETechnical specification EEE
Technical specification EEE
 
Training Seminar - Standards, Heat Tracing Options & Application Optimization...
Training Seminar - Standards, Heat Tracing Options & Application Optimization...Training Seminar - Standards, Heat Tracing Options & Application Optimization...
Training Seminar - Standards, Heat Tracing Options & Application Optimization...
 
Rittal - Re-Cooling - Chiller Ürünleri
Rittal - Re-Cooling - Chiller ÜrünleriRittal - Re-Cooling - Chiller Ürünleri
Rittal - Re-Cooling - Chiller Ürünleri
 
Eta a series reflow oven
Eta a series reflow ovenEta a series reflow oven
Eta a series reflow oven
 
Eta a series reflow oven
Eta a series reflow ovenEta a series reflow oven
Eta a series reflow oven
 
Hecu – high energy efficiency solution for condensing units fitted with DC co...
Hecu – high energy efficiency solution for condensing units fitted with DC co...Hecu – high energy efficiency solution for condensing units fitted with DC co...
Hecu – high energy efficiency solution for condensing units fitted with DC co...
 

Último

NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESNarmatha D
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 

Último (20)

NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIES
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 

Design, Installation and Testing of the VRF System

  • 1. MINISTRY OF EDUCATION OF YOUTHS AND SPORTS INSTITUTE OF TECHNOLOGY OF CAMBODIA DEPARTMENT OF INDUSTRIALAND MECHANICAL FINAL YEAR THESIS Tittle: Designing, Installation and Testing of VRF System Students : TITH Sopheara and VENG Socheat Specialty : Mechanical engineering Advisor : Mr. KHOUN Rithymean Academic Year : 2016- 2017 1
  • 2. Contents I. General Introduction II. Definition III. Panasonic VRF system IV. Load calculation V. Selection VI. VRF system installation VII. Testing and Commissioning VIII.Conclusion 2
  • 3. I. General Introduction  Presentation of Internship •From: 20 February to 20 May 2017 •Company: Comin Khmere •Position : MVAC trainee •Project: TK Royal One (Cambodia) 3
  • 4. II. Definition 4 What is VRF systems? • Variable refrigerant flow vary the flow of refrigerant to indoor units based on demand. There are 2 types of VRF system, heat pump and heat recovery system.
  • 5. What is VRF Heat pump ? • VRF heat pump provide heating or cooling but not simultaneous heating and cooling 5 II. Definition
  • 6. What is VRF heat recovery? • VRF heat recovery can operate simultaneous in heating or cooling mode. 6 II. Definition
  • 7. Variable refrigerant flow (VRF) is an air-conditioning system configuration where there is one outdoor unit and multiple indoor units. III. Panasonic VRF System 7
  • 8. III. Panasonic VRF System 1. Outdoor unit The outdoor unit of VRF system, sometimes called the outside unit or condenser. 8 (Carin, 2016)
  • 9. III. Panasonic VRF System DC twin rotary compressor: The component of compressor are: 1. Electric motor 2. Compression mechanism 3. Accumulator The compressor is the heart of the refrigeration cycle. 9 (Bhatia, 2014)
  • 10. III.Panasonic VRF System a. 2-WAY Mini-FSV LE1 Series  Use for cooling or heating mode only Capacity range from 4HP to 6HP COP: 4.21 in case of 4 HP  Cooling operation possible up to 46 °C And low as -20 °C for heating mode  Max connectable 9 units with length 150m 10 (Hiong, 2016-2017)
  • 11. III.Panasonic VRF System b. 2-WAY FSV-EX ME2 Series  Use for cooling or heating mode only  Capacity range from 8HP to 80HP  Operation temperature as high as 52°C for cooling and as low as -20 °C for heating mode  Max connectable 64 units with max length 1,000m 11 (Hiong, 2016-2017)
  • 12. III.Panasonic VRF System c. 3-WAY FSV MF2 Series  Using for simultaneous heating and cooling  Capacity range from 8HP to 42HP  Temperature operation as high as 46°C for cooling and as low as -20 for heating  Max connectable 52 units with pipe length up to 500m 12 (Hiong, 2016-2017)
  • 13. III.Panasonic VRF System 2. Indoor unit There are many types of indoor units such as: • F2 type : Cooling Capacity 2.2kW to 16kW • M1 type : Cooling Capacity 2.2kW up to 5.6kW • Z1 type : Cooling Capacity 2.2kW to 7.3kW • E2 type : Cooling Capacity 18kW to 28kW 13
  • 14. III.Panasonic VRF System 2. Indoor unit • E1 type : Cooling Capacity 7.3kW to 28kW • U1 type : 4-way cassette, Cooling Capacity 2.2kW to 16kW • Y2 type : 4-way mini cassette, Cooling Capacity 2.2kW to 5.6kW • L1 type : 2-way cassette, Cooling Capacity 2.2kW to 7.3kW • D1 type : 1-way cassette, Cooling Capacity 2.8kW to 7.3kW • P1 type : Floor standing, Cooling Capacity 2.2kW to 7.3kW 14
  • 15. IV.Load Calculation  Feature of the Building TK Royal One 15http://www.cambodiancondos.com/condo-developments/tk-royal-one/
  • 16. IV. Load Calculation 1. Estimate Method Q = S . R • Q: Total heat load [Btu.h-1]or [W] • S: room area [m2] • R: The rate of cooling [Btu.h-1.m-2] Calculation total heating load for TKR1 “ Reception room’’ which has S = 62.4 m2 • R = 900 Btu.h-1.m-2 Thus, Q = 56160 Btu.h−1 =16.45kW 16
  • 17. Another room calculate by Estimate method Items Type of Room AREA Ratio Cooling Capacity m² Btu/h.m2 kW Btu/h 1 Conference Hall 265.45 1200 93.36 318540 2 Break Room 49.07 750 10.78 36802 3 Coffee Shop 73.6 1300 28.04 95680 4 Financial Office 98.14 850 24.48 83419 5 Hall 35.5 700 7.28 24850 6 Office 56.5 850 14.07 48025 7 Meeting Room 31.95 900 8.40 28755 8 Service Counter 36.8 1300 14.02 47840 9 Shop 87.7 800 20.56 70160 10 Toilet 38 500 5.56 19000 17
  • 18. IV. Load Calculation 2. Manual Method The Manual Method is the method used to calculate the cooling load of the building space with minimum errors. Total heating load: QT = QS + QL [W] oTotal sensitive loads QS = QStr+ QSRm+QSRv+QSoc+QSecl+QSequip oTotal latent loads QL= QLr+ QLoc+QLequip 18
  • 19. IV.Load Calculation Calculation heating load for TKR1 “ Reception Area’’ oTotal sensitive loads QS = 14445.26 W oTotal latent loads QL = 1197.58W Total heating load: QT= 14445.26 W + 1197.58W = 15642.84 W = 15.64 kW 19
  • 20. IV.Load Calculation Verify the cooling capacity coefficient R [Btu/h.m2]: • Manul method: R= 53367Btu.h−1 / 62.4 m2 = 855 Btu.h−1 • Estimate method: R = 900 Btu.h−1 From the calculation above by manual method, we see that error of cooling rate approximate 5 % compared to estimation method 20
  • 21. V. Selection 1. Selection indoor unit The total cooling load required is 109.8 kW 21(Hiong, 2016-2017)
  • 22. V. Selection The characteristic of outdoor unit model U-40ME2R8 are: • Cooling capacity 113 kW • Using with power supply 400/415 V/3-phase/50 Hz • Electrical rating for cooling option: 57.3 A • Refrigerant amount at shipment: 22.0 kg • Air flowrate: 48600 m3 h-1 22
  • 23. V. Selection 2. Selection indoor unit  For Conference Hall of TKR1: The requirement of cooling load is 93.36 kW. Catalogue of model mid static duct E1 type chosen that Its cooling capacity from 7.3 kW to 28 kW. E1 type is a kind of saving energy, the power input 45% less (compared to H1 type) 4 of S-224ME1E5 were chosen: Cooling capacity 4 × 22.4kW = 89.6kW 23
  • 25. VI.VRF System Installation 1. Air duct installation 25 2. Indoor unit installation
  • 26. VI.VRF System Installation 3. Copper pipe installation 26
  • 27. VI.VRF System Installation 4. Drainage water pipe installation 27
  • 28. VI.VRF System Installation 5. Outdoor unit installation 28
  • 29. VII. Testing and Commissioning Before we start operation VRF, we have to: 1. Test refrigerant pipe 2. Adding refrigerant 3. Check at main power on 4. Testing and commissioning 29
  • 30. 30 1. Test refrigerant pipe a. Check for any leakage in the refrigerant piping b. Perform vacuum drying to remove all moisture
  • 31. • Keeping the valve of the outdoor unit closed • If the specified amount of refrigerant cannot be charged, fully open the valves of the outdoor unit at liquid and gas sides, operate the air conditioner in COOL mode 31 2. Adding refrigerant
  • 32. Check on the outdoor unit Check on the setting indoor unit 32 3. Check at main power on a. Check ON the rotary switches of outdoor unit b. Check ON the setting indoor unit
  • 33. • Incoming supply for outdoor phrase sequence for 3 phases, Incoming Voltage (380~415V). • Incoming voltage for Indoor 220~240V and ensure power supply all Indoor unit is turn "ON". • Once all the setting is set and check, then start addressing the system by short-circuit pin CN-30 33 4. Testing and commissioning
  • 34. 34  Start addressing the system by short-circuit pin CN-30 Laptop - Window 7 professional – 32 or 64 bits operation system  Normal USB Printer Wire  Panasonic Flash Writer – 8F000900210 / Part Code – 6233214375  To be purchase from Panasonic (Oudom, 2017)
  • 35. 35 a. Indoor fan speed and temperature. OUTDOOR Screen INDOOR Screen b. Outdoor Compressor temperature, Gas temperature and etc.  After the result have to be printed out by manufacture and to be attached in Testing and Commissioning form for VRF recording. (Oudom, 2017)
  • 36. VIII. Conclusion • The calculation cooling load by estimation and manual seem a litter bit difference value. The selection of the systems that suitable for reception area and conference hall is outdoor unit model U-40ME2R8 which maximum cooling capacity is 113 kW. • To get the best result of VRF system, we have to understand about plan and condition for installation of indoor unit, outdoor unit, air duct, copper pipe, and drainage water pipe. • VRF testing and commissioning is a part which we use the method statement to carry on indoor unit, outdoor unit operation after installation. 36
  • 37. Thank You For Your Attention ! Q & A 37 Thank you for your attention!!! Question?