May-22 1 RA BILL 5 LACK 500000 193097.04 323339.65 516436.69 0 2108811.68
Jun-22 2 RA BILL 12 LACK 1200000 546016.95 440194.85 986211.8 -213788
Jul-22 3 RA BILL 12 LACK 1200000 1231570.05 256965.23 1488535.28 0
Aug-22 4 RA BILL 12 LACK 1200000 1321427.1 44591.65 1366018.75 0
Sep-22 5 RA BILL 15 LACK 1500000 1383948.29 128429.89 1512378.18 0
Oct-22 6 RA BILL 24.40 LACK 2361290 2102182.8 264003.23 2366186.03 0
Nov-22 7 RA BILL 25 LACK 2500000 1785069 241731.12 2026800.12 -473200 5056406.37
Dec-22 8 RA BILL 25 LACK 2500000 2069089.27 77327.76 2146417.03 -353583 3778232.54
Jan-23 9 RA BILL 25 LACK 2446233 2449708.32 0 2449708.32 0
Feb-23 10 RA BILL 22 LACK 2200000 2121671.88 96209.54 2217881.42 0
Mar-23 11 RA BILL 25 LACK 2500000 0 0
TOTAL 202.40 LACK 20107523 15203780.7 1872792.92 17076573.62 -1040571 10943450.59