Testing of transformer
THERE ARE FIVE TYPES OF
TESTING
 OPEN CIRCUIT TEST ON TRANSFORMER
 Short Circuit Test on Transformer
 LOAD TEST ON SINGLE PHASE TRANSFORMER
 SUMPNER'S TEST
 POLARITY TEST
OPEN CIRCUIT TEST ON TRANSFORMER
One of the winding is connected to the supply at rated
voltage,while the other winding is kept open circuited(HV).
A voltmeter, wattmeter, and an ammeter are connected in(LV)
winding.
 The voltage at rated frequency is applied to that LV side with the
help of a variac of variable ratio auto transformer .
 The HV side of the transformer is kept open. Now with the
help of variac, applied voltage gets slowly increased until the
voltmeter gives reading equal to the rated voltage of the LV
side.
 After reaching at rated LV side voltage, all three instruments
reading (Voltmeter, Ammeter and Wattmeter readings) are
recorded.
 The ammeter reading gives the no load current Ie. As no load
current Ie is quite small compared to rated current of the
transformer, the voltage drops due to this current that can be
taken as negligible.
 Since, voltmeter reading V1 can be considered equal to
secondary induced voltage of the transformer, the input power
during test is indicated by watt-meter reading.
 As the transformer is open circuited, there is no output, hence
the input power here consists of core losses in transformer and
copper loss in transformer during no load condition.
Short Circuit Test on Transformer
 The connection diagram for short circuit test on transformer is
shown in the figure. A voltmeter, wattmeter, and an ammeter
are connected in HV side of the transformer as shown.
 The voltage at rated frequency is applied to that HV side with
the help of a variac of variable ratio auto transformer.
 The LV side of the transformer is short circuited. Now with the
help of variac applied voltage is slowly increased until the
ammeter gives reading equal to the rated current of the HV
side.
 After reaching at rated current of HV side, all three
instruments reading (Voltmeter, Ammeter and Watt-meter
readings) are recorded.
 The ammeter reading gives the primary equivalent of full load
current IL.
 As the voltage applied for full load current in short circuit test
on transformer is quite small compared to the rated primary
voltage of the transformer, the core losses in transformer can
be taken as negligible here.
 The input power during test is indicated by watt-meter reading.
As the transformer is short circuited, there is no output; hence
the input power here consists of copper losses in transformer.
 Therefore it is seen that the short circuit test on transformer is
used to determine copper loss in transformer at full load and
parameters of approximate equivalent circuit of transformer.
LOAD TEST ON SINGLE PHASE
TRANSFORMER
Load test on single phase Transformer aim to
draw the efficiency and regulation characteristics
of single phase transformer.
 Each of the terminals of primary as well as secondary
winding of a transformer is alternately positive and
negative with respect to each other.
 It is essential to know the relative polarities at any
instant of the primary and secondary terminals for
making correct connections under the following type
of operation of the transformer.
CHARACTERISTICS CURVES OF SINGLE
PHASE TRANSFORMER
SUMPNER'S TEST
 Sumpner's test or back to back test can be employed
only when two identical transformers are available.
 Both transformers are connected to supply such that
one transformer is loaded on another.
 Primaries of the two identical transformers are
connected in parallel across a supply.
 Secondary are connected in series such that emf's of
them are opposite to each other.
 Another low voltage supply is connected in series with
secondary to get the readings, as shown in the circuit
diagram shown below.
T1 and T2 are identical transformers.
Secondary of them are connected in voltage
opposition.
as transformers are identical. In this case, as
per superposition theorem, no current flows
through secondary.
Thus input power measured by wattmeter W1
is equal to iron losses of both transformers.
i.e. iron loss per transformer Pi = W1/2.
A small voltage v2 is injected into secondary
with the help of a low voltage transformer.
the voltage v2 is adjusted so that, the rated
current i2 flows through the secondary. in this
case, both primaries and secondary carry rated
current.
thus short circuit test is simulated and
wattmeter w2 shows total full load copper
losses of both transformers.
i.e. copper loss per transformer pcu = w2/2.
From above test results,the full load efficiency
of each transformer can be given as-
POLARITY TEST
Polarity in electrical terms refers to the Positive or
Negative conductors within a d.c. circuit, or to the
Line and Neutral conductor within an a.c. circuit.
the resultant voltage appearing across a voltmeter
will be the sum of the high and low voltage
windings.
This is useful when connecting single phase
transformers in parallel for three phase operations.
 Polarity is a term used only with single phase
transformers.
Let A1 and A2 denotes the ends of the primary
winding.
Let a1 and a2 denotes the ends of the
secondary winding.
Ends A1and a1 are joined and a voltmeter is
connected across A2and a2.
Single phase supply is given to A1 and A2.
If the direction of the induced emf in primary
(Ep) and that of the secondary (Es) is the same.
The voltmeter will read the difference of
emf(Ep ~ Es).
If the windings are wound in the opposite
direction on the magnetic core,Ep and Es will
be in the opposite direction.
The voltmeter will read Ep+Es.in this case, the
polarity is know as additive.
Generally,the polarity used is subtractive.
THANKYOU

Más contenido relacionado

La actualidad más candente

Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerHarshit Khandelwal
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of TransformersGirin Chutia
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.Geetesh Verma
 
Calculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlabCalculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlabMafaz Ahmed
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 
Measurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuitMeasurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuitRaveendranath Macherla
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformersjibinjoy1988
 
Open circuit and Short circuit Test Presentaion
Open circuit and Short circuit Test PresentaionOpen circuit and Short circuit Test Presentaion
Open circuit and Short circuit Test PresentaionLalitGoyal27
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformersjibinjoy1988
 
Single phase Transformer
Single phase Transformer  Single phase Transformer
Single phase Transformer johny renoald
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...Jobin Abraham
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerRaveendranath Macherla
 
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...Prasant Kumar
 
Transformer: Open Circuit and Short Circuit Test
Transformer: Open Circuit and Short Circuit TestTransformer: Open Circuit and Short Circuit Test
Transformer: Open Circuit and Short Circuit TestRidwanul Hoque
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 
Autotransformer
AutotransformerAutotransformer
Autotransformerpapusahu
 

La actualidad más candente (20)

Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformer
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of Transformers
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Testing of Transformer (AREVA)
Testing of Transformer (AREVA)Testing of Transformer (AREVA)
Testing of Transformer (AREVA)
 
Calculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlabCalculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlab
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 
Measurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuitMeasurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuit
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformers
 
Open circuit and Short circuit Test Presentaion
Open circuit and Short circuit Test PresentaionOpen circuit and Short circuit Test Presentaion
Open circuit and Short circuit Test Presentaion
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformers
 
Single phase Transformer
Single phase Transformer  Single phase Transformer
Single phase Transformer
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformer
 
ALL DAY EFFICIENCY
ALL DAY EFFICIENCYALL DAY EFFICIENCY
ALL DAY EFFICIENCY
 
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
 
Transformer: Open Circuit and Short Circuit Test
Transformer: Open Circuit and Short Circuit TestTransformer: Open Circuit and Short Circuit Test
Transformer: Open Circuit and Short Circuit Test
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
Autotransformer
AutotransformerAutotransformer
Autotransformer
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 

Similar a Transformer 2

Transformer Course Lab.pdf
Transformer Course Lab.pdfTransformer Course Lab.pdf
Transformer Course Lab.pdfsmuftah
 
transformers.ppt
transformers.ppttransformers.ppt
transformers.pptjamla1
 
Lecture-2_EEE-105-1.pdf
Lecture-2_EEE-105-1.pdfLecture-2_EEE-105-1.pdf
Lecture-2_EEE-105-1.pdfNaorinHalim
 
potentiometer II.pptx
potentiometer II.pptxpotentiometer II.pptx
potentiometer II.pptxtadi1padma
 
three_phase_transformers-1p protection concept.pdf
three_phase_transformers-1p protection concept.pdfthree_phase_transformers-1p protection concept.pdf
three_phase_transformers-1p protection concept.pdfkanimol143me
 
Transformer by vinay chawla
Transformer by vinay chawlaTransformer by vinay chawla
Transformer by vinay chawlavinaychawla28
 
Ac machines-lab-manual
Ac machines-lab-manualAc machines-lab-manual
Ac machines-lab-manualRao Umar
 
Power converter lab manual by chaturvedula
Power converter lab manual by chaturvedulaPower converter lab manual by chaturvedula
Power converter lab manual by chaturvedulaKumarChaturvedula
 
Testing of power_transformers_kt_80_gb_2
Testing of power_transformers_kt_80_gb_2Testing of power_transformers_kt_80_gb_2
Testing of power_transformers_kt_80_gb_2koperundeviG
 
EMI_U_III_PPT_pptx (1).pptx
EMI_U_III_PPT_pptx (1).pptxEMI_U_III_PPT_pptx (1).pptx
EMI_U_III_PPT_pptx (1).pptxsameed4
 

Similar a Transformer 2 (20)

Notes
NotesNotes
Notes
 
Akshay kumar
Akshay kumarAkshay kumar
Akshay kumar
 
Transformer_theory.pptx
Transformer_theory.pptxTransformer_theory.pptx
Transformer_theory.pptx
 
Transformer
TransformerTransformer
Transformer
 
Transformer Course Lab.pdf
Transformer Course Lab.pdfTransformer Course Lab.pdf
Transformer Course Lab.pdf
 
transformers.ppt
transformers.ppttransformers.ppt
transformers.ppt
 
Lecture-2_EEE-105-1.pdf
Lecture-2_EEE-105-1.pdfLecture-2_EEE-105-1.pdf
Lecture-2_EEE-105-1.pdf
 
potentiometer II.pptx
potentiometer II.pptxpotentiometer II.pptx
potentiometer II.pptx
 
Inverter
InverterInverter
Inverter
 
three_phase_transformers-1p protection concept.pdf
three_phase_transformers-1p protection concept.pdfthree_phase_transformers-1p protection concept.pdf
three_phase_transformers-1p protection concept.pdf
 
Transformer by vinay chawla
Transformer by vinay chawlaTransformer by vinay chawla
Transformer by vinay chawla
 
Ac machines-lab-manual
Ac machines-lab-manualAc machines-lab-manual
Ac machines-lab-manual
 
Em manual 1
Em manual 1Em manual 1
Em manual 1
 
Power converter lab manual by chaturvedula
Power converter lab manual by chaturvedulaPower converter lab manual by chaturvedula
Power converter lab manual by chaturvedula
 
Transformer
TransformerTransformer
Transformer
 
sodapdf-converted.pptx
sodapdf-converted.pptxsodapdf-converted.pptx
sodapdf-converted.pptx
 
Chapter 7 transformers
Chapter 7 transformersChapter 7 transformers
Chapter 7 transformers
 
Testing of power_transformers_kt_80_gb_2
Testing of power_transformers_kt_80_gb_2Testing of power_transformers_kt_80_gb_2
Testing of power_transformers_kt_80_gb_2
 
Shazab
ShazabShazab
Shazab
 
EMI_U_III_PPT_pptx (1).pptx
EMI_U_III_PPT_pptx (1).pptxEMI_U_III_PPT_pptx (1).pptx
EMI_U_III_PPT_pptx (1).pptx
 

Último

Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESNarmatha D
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 

Último (20)

Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIES
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 

Transformer 2

  • 1. Testing of transformer THERE ARE FIVE TYPES OF TESTING  OPEN CIRCUIT TEST ON TRANSFORMER  Short Circuit Test on Transformer  LOAD TEST ON SINGLE PHASE TRANSFORMER  SUMPNER'S TEST  POLARITY TEST
  • 2. OPEN CIRCUIT TEST ON TRANSFORMER One of the winding is connected to the supply at rated voltage,while the other winding is kept open circuited(HV). A voltmeter, wattmeter, and an ammeter are connected in(LV) winding.  The voltage at rated frequency is applied to that LV side with the help of a variac of variable ratio auto transformer .
  • 3.
  • 4.  The HV side of the transformer is kept open. Now with the help of variac, applied voltage gets slowly increased until the voltmeter gives reading equal to the rated voltage of the LV side.  After reaching at rated LV side voltage, all three instruments reading (Voltmeter, Ammeter and Wattmeter readings) are recorded.  The ammeter reading gives the no load current Ie. As no load current Ie is quite small compared to rated current of the transformer, the voltage drops due to this current that can be taken as negligible.  Since, voltmeter reading V1 can be considered equal to secondary induced voltage of the transformer, the input power during test is indicated by watt-meter reading.  As the transformer is open circuited, there is no output, hence the input power here consists of core losses in transformer and copper loss in transformer during no load condition.
  • 5. Short Circuit Test on Transformer  The connection diagram for short circuit test on transformer is shown in the figure. A voltmeter, wattmeter, and an ammeter are connected in HV side of the transformer as shown.  The voltage at rated frequency is applied to that HV side with the help of a variac of variable ratio auto transformer.  The LV side of the transformer is short circuited. Now with the help of variac applied voltage is slowly increased until the ammeter gives reading equal to the rated current of the HV side.  After reaching at rated current of HV side, all three instruments reading (Voltmeter, Ammeter and Watt-meter readings) are recorded.
  • 6.
  • 7.  The ammeter reading gives the primary equivalent of full load current IL.  As the voltage applied for full load current in short circuit test on transformer is quite small compared to the rated primary voltage of the transformer, the core losses in transformer can be taken as negligible here.  The input power during test is indicated by watt-meter reading. As the transformer is short circuited, there is no output; hence the input power here consists of copper losses in transformer.  Therefore it is seen that the short circuit test on transformer is used to determine copper loss in transformer at full load and parameters of approximate equivalent circuit of transformer.
  • 8. LOAD TEST ON SINGLE PHASE TRANSFORMER Load test on single phase Transformer aim to draw the efficiency and regulation characteristics of single phase transformer.  Each of the terminals of primary as well as secondary winding of a transformer is alternately positive and negative with respect to each other.  It is essential to know the relative polarities at any instant of the primary and secondary terminals for making correct connections under the following type of operation of the transformer.
  • 9.
  • 10. CHARACTERISTICS CURVES OF SINGLE PHASE TRANSFORMER
  • 11. SUMPNER'S TEST  Sumpner's test or back to back test can be employed only when two identical transformers are available.  Both transformers are connected to supply such that one transformer is loaded on another.  Primaries of the two identical transformers are connected in parallel across a supply.  Secondary are connected in series such that emf's of them are opposite to each other.  Another low voltage supply is connected in series with secondary to get the readings, as shown in the circuit diagram shown below.
  • 12.
  • 13. T1 and T2 are identical transformers. Secondary of them are connected in voltage opposition. as transformers are identical. In this case, as per superposition theorem, no current flows through secondary. Thus input power measured by wattmeter W1 is equal to iron losses of both transformers. i.e. iron loss per transformer Pi = W1/2.
  • 14. A small voltage v2 is injected into secondary with the help of a low voltage transformer. the voltage v2 is adjusted so that, the rated current i2 flows through the secondary. in this case, both primaries and secondary carry rated current. thus short circuit test is simulated and wattmeter w2 shows total full load copper losses of both transformers. i.e. copper loss per transformer pcu = w2/2.
  • 15. From above test results,the full load efficiency of each transformer can be given as-
  • 16. POLARITY TEST Polarity in electrical terms refers to the Positive or Negative conductors within a d.c. circuit, or to the Line and Neutral conductor within an a.c. circuit. the resultant voltage appearing across a voltmeter will be the sum of the high and low voltage windings. This is useful when connecting single phase transformers in parallel for three phase operations.
  • 17.  Polarity is a term used only with single phase transformers.
  • 18. Let A1 and A2 denotes the ends of the primary winding. Let a1 and a2 denotes the ends of the secondary winding. Ends A1and a1 are joined and a voltmeter is connected across A2and a2. Single phase supply is given to A1 and A2. If the direction of the induced emf in primary (Ep) and that of the secondary (Es) is the same.
  • 19. The voltmeter will read the difference of emf(Ep ~ Es). If the windings are wound in the opposite direction on the magnetic core,Ep and Es will be in the opposite direction. The voltmeter will read Ep+Es.in this case, the polarity is know as additive. Generally,the polarity used is subtractive. THANKYOU