Overview of the Fairhill/MLK green infrastructure ambassador project taking shape in Cleveland. Includes details on project history, improvements, Project Clean Lake, traffic patterns and impacts during construction, and more.
4. • Political subdivision of Ohio
• Created in 1972 by Court Order
– Code of Regulations
– Governed by seven Trustees
• Separate and distinct from the City of
Cleveland and Cuyahoga County
Who We Are…
5. • Sanitary & regional stormwater services to
Cleveland and 61 member communities
– 1 million customers
– 90+ billion gallons treated each year
• Water quality monitoring
• Lake Erie beach monitoring and
maintenance
What We Do…
6. We Own and Operate 3 Wastewater
Treatment Plants
Westerly
Southerly
Easterly
6
7. Northeast Ohio Regional Sewer District
Responsibility
• $3 billion in 25 years
• Combined Sewer
Overflow (CSO) control
• Sewer fees
• Regional flooding
and erosion issues
• Impervious
surface fee
8. Northeast Ohio Regional Sewer District
Responsibility
• Regional flooding
and erosion issues
• Impervious
surface fee
• $3 billion in 25 years
• Combined Sewer
Overflow (CSO) control
• Sewer fees
10. 10 10
Dry Weather Flow
to treatment plant
Additional Conveyance
Capacity Available for
wet-weather
Combined Sewer
Overflow Discharge to
Stream/Lake
What is a Combined Sewer?
16. Consent Decree Requires Northeast
Ohio’s CSO Problem Reduced in 25
Years
98%
Capture
0
1
2
3
4
5
6
7
8
9
Baseline (1970s) Current (2011) Target (2036)
9
4.5
0.494
TypicalYear
CSOVolumeRemaining
(BG)
0 to 4 overflows
in typical year
0 to 80+
overflows in
typical year
17. CSO Consent Decree
25 years of Tunnel Construction
Seven Tunnel Systems
– 21 Miles
– 17’ to 24’ in Diameter
– 100’ to 200’ in Depth
42. Outlet Pipe to
Bioretention Area
Maximum Height
14 feet
Large Stones to Slow
Down Stormwater
Bioretention
Area
Exposed Aggregate
Concrete
Stamped & Stained
Concrete
Standard Concrete Stained Concrete
43. NEORSD will maintain the following:
Maintenance Responsibilities
• New storm sewers and new street inlets
• Bioretention basins (includes storm sewer infrastructure
within the bioretention basins)
• Public plaza (includes facility maintenance, litter control, etc.)
46. Pre Construction Coordination
• Pre Construction Inspection/Photographs
• Coordination with residents for access to property (typically
exterior of the home photographed)
• Residential Notification
• 72-hour notification prior to commencement of work
• Access To Property
• Contractor to coordinate & maintain access to drives, if
crossing is to occur
• Maintained with steel road plate
• Issues and Complaints
• NEORSD Customer Service (216)881-8247 8AM-5PM
47. Maintenance of Traffic
• Tentative Plan (Subject to Change)
based on approval/schedule
• Major Components:
– West bound lane Fairhill Road closed. Detour to be
established around Larchmere Blvd. to MLK Drive.
– No left turn from E. 124th, E. 127th, Kemper Road
and North Moreland Road
– Intersection of MLK and Fairhill channelized to
eastbound Fairhill, left turn only lane, to North MLK
– Pedestrian sidewalk closed along north Fairhill Road
– No street parking allowed
48.
49.
50. Open Cut Construction
• Noise and dust limited to working hours.
Contractor is responsible for maintaining
work zone.
• Partial restoration of road cuts when sewer
work completed.
56. Questions & Answers
Question: Where will bus route #48/#48A go?
How will the public be notified of RTA bus route
and/or bus stop location changes?
RTA service alerts are posted at
http://www.riderta.com
RTA Answerline (216) 621-9500 is also available
to help answer RTA related questions.
57. Questions & Answers
Question: Who do I contact if I have a
question or concern?
NEORSD Customer Service Department
(216) 881-8247 8AM – 5PM
58. Questions & Answers
Question: What impacts should I expect
from construction of the new storm sewers
within the public right-of-way?
Temporary on-street parking limitations.
Temporary lane closures, detours and limits
to left turns onto Fairhill Road westbound.
Temporary driveway access closures.
Pedestrian sidewalk closures/detours.
Construction dust & noise.
59. For more information:
• NEORSD Customer Service (216) 881-8247
• Project Clean Lake official homepage:
www.neorsd.org/cso.php