SlideShare una empresa de Scribd logo
1 de 11
FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY
Fidic Yellow vs Silver
Weero Koster
Partner
Norton Rose LLP
February 2012
General application
• Yellow Book: design/build contract
electrical/mechanical works, including plant supply
and construction works; allocation of risk on basis
of insurability, project management principles and
ability to foresee and mitigate
• Silver Book: fixed-price, date-certain, lump-sum
turn-key contract:
• Little risk of price increase (but higher price) or
delay for Employer
• Shift of risks to Contractor: design and
execution
General risk profile: Shift of risks
• Employer’s Engineer is Employer’s Representative
• Employer’s ‘determinations’
• Setting Out
• (No) Unforeseeable difficulties & verification/
interpretation of Employer data (incl. sub-surface,
hydrological and Employer Requirements)
• General design obligations, design error
Shift of risks, cont’d
• No extension of Time for Completion for:
• exceptionally adverse climatic conditions
(except FM)
• unforeseeable shortages in personnel or goods
by epidemic or government actions
• Errors in Employer’s Requirements
• Setting Out
• Unforeseeable physical conditions
Shift of risks, cont’d
• Employer’s Risk excludes:
• Use of works by Employer,
• Design of works by Employer’s personnel,
• Unforeseeable operation of forces of nature
General risk profile: key
employer issues
• Contractor fully responsible for design and design
coordination (including Employer design)
• Full ground condition risk to Contractor
• Employer to retain influence over project
• Right to Variations
• Limited scope for Contractor claims for
time/money; Contractor will:
• Price these risks, so increase initial Contract
Sum
• Do extensive due diligence to mitigate, leading
to delay in execution
Payment & security: key
employer issues
• Fixed price lump sum payments against schedule
of payments & Performance Certificate
• Long payment period
• No claim for additional time or money for e.g.
Variations/innovations, ‘in country” Force Majeure,
Unforeseen ground conditions, setting out or
discovery of fossils
• Robust security package: advance payment bond,
performance bond, retention of money
• Warranty bond after Taking Over (> 2yrs)
Programme/delay: key
employer issues
• Liquidated Damages for delay (10 – 20 %, > ?)
• Limited rights for extension of Time for Completion
• Suspension by Employer entitles Contractor
extension of time/ costs
Testing and defects,
insurance: key employer
issues
• Suitable testing regime
• Employer technical advisors to set
performance/reliability standards and regime for
testing/ performance guarantee levels
• Liquidated Damages for performance (10 – 20 %,
> ?)
• Defects liability period (1 – 2 yrs): default is 1 yr
• Liability cap, sub-caps and ‘carve-outs’
• Project specific insurance provisions; all insurance
monies go in separate insurance proceeds
account for benefit Employer
Permits, change in law, FM:
key employer issues
• Employer planning, environmental/ Contractor
construction and transport: permit schedule
• Change in law after contract signing/ in force,
EH&S developments
• Exhaustive FM list ?
• Location of FM, “in country” FM: costs in addition
to EOT ?
FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY

Más contenido relacionado

La actualidad más candente

Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 

La actualidad más candente (20)

Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Fidic
FidicFidic
Fidic
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 

Similar a Fidic yellow vs silver

Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013Weero Koster
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Managementbrainquisitive
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
Q1 2021 Financial Report Presentation Slides
Q1 2021 Financial Report Presentation SlidesQ1 2021 Financial Report Presentation Slides
Q1 2021 Financial Report Presentation SlidesTeckResourcesLtd
 
Q1 Financial Report 2022 Conference Call Slides
Q1 Financial Report 2022 Conference Call SlidesQ1 Financial Report 2022 Conference Call Slides
Q1 Financial Report 2022 Conference Call SlidesTeckResourcesLtd
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
Q2 2021 Presentation Slides
Q2 2021 Presentation SlidesQ2 2021 Presentation Slides
Q2 2021 Presentation SlidesTeckResourcesLtd
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Indonesia
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
Q4 2014 conference call presentation
Q4 2014 conference call presentationQ4 2014 conference call presentation
Q4 2014 conference call presentationAdam Martin
 

Similar a Fidic yellow vs silver (20)

Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Design-Build Operate and Finance
Design-Build Operate and FinanceDesign-Build Operate and Finance
Design-Build Operate and Finance
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
Q1 2021 Financial Report Presentation Slides
Q1 2021 Financial Report Presentation SlidesQ1 2021 Financial Report Presentation Slides
Q1 2021 Financial Report Presentation Slides
 
Q1 Financial Report 2022 Conference Call Slides
Q1 Financial Report 2022 Conference Call SlidesQ1 Financial Report 2022 Conference Call Slides
Q1 Financial Report 2022 Conference Call Slides
 
Pmc hitesh
Pmc hiteshPmc hitesh
Pmc hitesh
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Q2 2021 Presentation Slides
Q2 2021 Presentation SlidesQ2 2021 Presentation Slides
Q2 2021 Presentation Slides
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Q4 2014 conference call presentation
Q4 2014 conference call presentationQ4 2014 conference call presentation
Q4 2014 conference call presentation
 

Más de Weero Koster

Nationaal energieakkoord
Nationaal energieakkoordNationaal energieakkoord
Nationaal energieakkoordWeero Koster
 
Energy project finance
Energy project financeEnergy project finance
Energy project financeWeero Koster
 
Warsaw presentation
Warsaw presentationWarsaw presentation
Warsaw presentationWeero Koster
 
Energy opportunities in the netherlands
Energy opportunities in the netherlandsEnergy opportunities in the netherlands
Energy opportunities in the netherlandsWeero Koster
 
Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Weero Koster
 
Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012Weero Koster
 

Más de Weero Koster (6)

Nationaal energieakkoord
Nationaal energieakkoordNationaal energieakkoord
Nationaal energieakkoord
 
Energy project finance
Energy project financeEnergy project finance
Energy project finance
 
Warsaw presentation
Warsaw presentationWarsaw presentation
Warsaw presentation
 
Energy opportunities in the netherlands
Energy opportunities in the netherlandsEnergy opportunities in the netherlands
Energy opportunities in the netherlands
 
Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013
 
Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012
 

Último

Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCRalexsharmaa01
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCRashishs7044
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 

Último (20)

Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 

Fidic yellow vs silver

  • 1. FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY Fidic Yellow vs Silver Weero Koster Partner Norton Rose LLP February 2012
  • 2. General application • Yellow Book: design/build contract electrical/mechanical works, including plant supply and construction works; allocation of risk on basis of insurability, project management principles and ability to foresee and mitigate • Silver Book: fixed-price, date-certain, lump-sum turn-key contract: • Little risk of price increase (but higher price) or delay for Employer • Shift of risks to Contractor: design and execution
  • 3. General risk profile: Shift of risks • Employer’s Engineer is Employer’s Representative • Employer’s ‘determinations’ • Setting Out • (No) Unforeseeable difficulties & verification/ interpretation of Employer data (incl. sub-surface, hydrological and Employer Requirements) • General design obligations, design error
  • 4. Shift of risks, cont’d • No extension of Time for Completion for: • exceptionally adverse climatic conditions (except FM) • unforeseeable shortages in personnel or goods by epidemic or government actions • Errors in Employer’s Requirements • Setting Out • Unforeseeable physical conditions
  • 5. Shift of risks, cont’d • Employer’s Risk excludes: • Use of works by Employer, • Design of works by Employer’s personnel, • Unforeseeable operation of forces of nature
  • 6. General risk profile: key employer issues • Contractor fully responsible for design and design coordination (including Employer design) • Full ground condition risk to Contractor • Employer to retain influence over project • Right to Variations • Limited scope for Contractor claims for time/money; Contractor will: • Price these risks, so increase initial Contract Sum • Do extensive due diligence to mitigate, leading to delay in execution
  • 7. Payment & security: key employer issues • Fixed price lump sum payments against schedule of payments & Performance Certificate • Long payment period • No claim for additional time or money for e.g. Variations/innovations, ‘in country” Force Majeure, Unforeseen ground conditions, setting out or discovery of fossils • Robust security package: advance payment bond, performance bond, retention of money • Warranty bond after Taking Over (> 2yrs)
  • 8. Programme/delay: key employer issues • Liquidated Damages for delay (10 – 20 %, > ?) • Limited rights for extension of Time for Completion • Suspension by Employer entitles Contractor extension of time/ costs
  • 9. Testing and defects, insurance: key employer issues • Suitable testing regime • Employer technical advisors to set performance/reliability standards and regime for testing/ performance guarantee levels • Liquidated Damages for performance (10 – 20 %, > ?) • Defects liability period (1 – 2 yrs): default is 1 yr • Liability cap, sub-caps and ‘carve-outs’ • Project specific insurance provisions; all insurance monies go in separate insurance proceeds account for benefit Employer
  • 10. Permits, change in law, FM: key employer issues • Employer planning, environmental/ Contractor construction and transport: permit schedule • Change in law after contract signing/ in force, EH&S developments • Exhaustive FM list ? • Location of FM, “in country” FM: costs in addition to EOT ?
  • 11. FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY