Wall Tile 25×40CM
● LIM SHIEH CHERN ● LOW SIEW MOI ● NG YEE JIE ●
1
Team Members
Low Siew Moi
2821945
Lim Shieh Chern
2821959
Ng Yee Jie
2821942
2
The Company
• Amazon Ceramics Industries
AboutUs
A local ceramic
tiles
manufacturers,
manufacturing
floor tiles, wall
tiles,
homogenous
tiles etc.
Origin
Founded in 1985.
Headquarter in
Senawang,
Negeri Sembilan,
Malaysian
Mission
To be a reputable
manufacturer
and supplier of
innovative and
quality products
at affordable
price in the
building material
industry
3
The Products
20cm x 25cm Wall Tiles
MARVE
25cm x 33cm Wall Tiles
ASTON
4
New Product – 25cm x 40cm
Wall Tiles
EleganceAmaze series
Sphere
Blossom
Wave
5
Project Plan
Project
Objectives
Project
Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
6
Assumptions
Organization Cultural Dimension
• ACI is a more result oriented with relative well motivated organization.
However management with strong autonomy power to control the
financial and moderate risk taker.
External10. Open-System focusInternal
Ends9. Means-ends orientationMeans
High8. Conflict toleranceLow
Other7. Reward criteriaPerformance
High6. Risk toleranceLow
Tight5. ControlLoose
Interdependent4. Unity IntegrationIndependent
People3. People focusTask
Group2. Team emphasisIndividual
Organization1. Member IdentityJob
External10. Open-System focusInternal
Ends9. Means-ends orientationMeans
High8. Conflict toleranceLow
Other7. Reward criteriaPerformance
High6. Risk toleranceLow
Tight5. ControlLoose
Interdependent4. Unity IntegrationIndependent
People3. People focusTask
Group2. Team emphasisIndividual
Organization1. Member IdentityJob
Source: Cultural Dimensions of an Organization Supportive of Project Management (Gary & Larson. p. 73). 7
Project Outline
• Proposing a new size of ceramic wall tiles (WT) for FY09/01 – 25x40cm
Increase
Profit
Attractive
Selling Price
New Product
Strategy
•Gross Profit deteriorated from
20% in FY04/05 to only 14%
presently
•Can improve average gross profit
from 14% in FY08/09 to 20% in
FY09/01, 26% in FY12/13
•25x40cm sells range from
RM25.00 to RM35.00 compared
to common sizes at around
RM11.00 square meters
•To penetrate into urban and middle-
income market, mid range housing
project markets and export markets
•Increase the product mix since
phasing out WT20x20 cm size in
FY07/08
8
Increase Profit
• Financial forecasting
– A potential grow of demand for WT 25x40 in market from 2% in FY09/10 to 80% in
FY12/13
– A margin grow for ACI from 20% in FY09/10 to 26% in FY12/13
F INANC IAL ANAL Y S IS
Actual
FY07/08
Actual
FY08/09
Budget
FY09/10
Forecast
FY10/11
Forecast
FY11/12
Forecast
FY12/13
Des cription
Wall Tiles
Sizes (cm)
Sales Vol
(%)
a. 20x20 % 2% 0% 0% 0% 0% 0%
b. 20x25 % 88% 88% 77% 58% 38% 28%
c. 25x33 % 10% 12% 22% 32% 41% 41%
d. 25x40 % 0% 0% 2% 11% 22% 30%
Total % 100% 100% 100% 100% 100% 100%
Sales Vol
(M2)
a. 20x20 M2 57,057 - - - - -
b. 20x25 M2 2,393,677 2,424,905 2,142,000 1,610,000 1,031,250 781,000
c. 25x33 M2 266,266 340,095 613,200 893,200 1,122,000 1,138,500
d. 25x40 M2 - - 44,800 296,800 596,750 830,500
Total M2 2,717,000 2,765,000 2,800,000 2,800,000 2,750,000 2,750,000
Production C apacity M2 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000
B alance C apacity M2 283,000 235,000 200,000 200,000 250,000 250,000
G ros s Profit Margin
Unit Selling Price (a, b, c & d) RM/M2 11.74 11.33 12.57 13.36 14.18 15.23
Unit Cost of Sales (a, b, c & d) RM/M2 9.83 9.79 10.02 10.42 10.91 11.34
Unit Gross Profit (GP) (a, b, c & d) RM/M2 1.91 1.54 2.55 2.94 3.27 3.89
Wall Tiles GP Margin (a, b, c & d) RM/M2 16% 14% 20% 22% 23% 26%
9
Please refer to Appendix A for further details
Attractive Selling Price
• Market Survey
– Pippo is the only local manufacturer producing 25x40cm wall tiles with one
imported brand, “UCI”, from Thailand
Size (cm) Importer/ Manufacturer/
Trader
Country Type of Material Brand Retailer Price/M2
20x30 KimHin Malaysia Ceramic Matt & Glossy Kimgress RM22.00 - RM28.00
20x40 Venus Malaysia Ceramic Matt & Glossy Venus RM18.00 - RM30.00
25x40 Pippo & Imported Malaysia, Ceramic Matt & Glossy PP & UCI RM25.00 - RM35.00
Thailand
25x45 Guocera Malaysia Ceramic High Glossy Guocera RM40.00 - RM45.00
25x50 Roman Indonesia Ceramic Red Body Roman RM28.00 - RM32.00
30x40 KimHin, Johan, WH &
Sixny
Malaysia, Ceramic Various RM35.00 - RM38.00
China
30x45 Huawei China Ceramic Rectified UNO RM28.00 - RM32.00
30x50 Roman Indonesia Ceramic Red Body Roman RM30.00 - RM35.00
30x60 MML, Guocera, WH, Niro,
Alpha,
Malaysia,
China,
Porcelain (Soluble Salt) &
Full Body
Various RM25.00 - RM35.00
Venue, Seacera,
Imported
Veitnam
10
WBS
• Work Breakdown Structure in Outline Form
1 Marketing Survey
2 Confirm Tiles Designs
3 Factory Product Developmet
4 Confirm Product Costing
5 New Product Marketing Plan
6 Equipments & Machinery - Ready
7 SIRIM Certification & Product Specifiaction
8 Sales & Administration System
9 Warehouse Control System
10 Liaise With Event Management Co
11 A&P Agency Management
12 Puchasing Raw Materials & Equipments
13 Actual Product Production
14 HQ Showroom Decoration
15 Waiting for Exhibition & Rectification
16 New Product Launching Ready
Summary
Tasks
11
Please refer to Appendix B for further details
Project Network Diagram
• The project network diagram is presented separately.
Please refer to Appendix C for further details
12
PERT
Scheduled Project Duration TS 105 days
Critical Path Duration TE 101 days
Standard Deviation 5.35
Probability Z 0.75
Probability % Z% 77%
Milestone (Critical Path) Weighted
Average
Optimistic Expected Pessimistic [(b-a)/6]2
Marketing Survey 13.17 7 14 16 2.25
Factory Product Development 33 22 33 44 13.44
Liaise With Event Management Co 25.17 13 27 30 8.03
Actual Product Production 25.83 17 27 30 4.69
New Product Launching - Ready 3.83 2 4 5 0.25
101 61 105 125
13Please refer to Appendix D for further details
Project Stakeholders
Internal Customers Suppliers Customers Regulatory
1. Top Management 1. Raw Material - Glaze &
Surface
1. Houseowners 1. SIRIM
2. Account 2. Raw Material - Clay & Body 2. Dealers / Retailers 2. DOE
3. Engineering 3. Raw Material - Additive 3. Distributors 3. Bomba
4. Warehouse 4. Packaging - Carton Boxes 4. Interior Designers
5. Purchasing 5. Packaging - Pallet & Others 5. Architects
6. Human Resource 6. Event Management Co. 6. Developers
7. Production 7. A&P Agency 7. Contractors
8. Lab 8. Machineries and Equipments 8. Sub-Contractors
9. Design 9. Utility Co. - Energy 9. Importers
10. QA 10. Bankers 10. Commission Agents
11. Customer Service
12. Marketing
14
Project Plan
Project
Objectives
Project Outline
Business need
to be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
15
Assumptions
Business Need to be Met
Contribute more than 40% gross
profit margin for FY09/10 so that
can achieve overall budgeted
gross profit margin of 20%
Production volume at 2% of total
product portfolio for FY09/10
Produce 90% of 1st grade quality
output and maintain 3% of reject
in order to market effectively
16
Define the Project
• Project Priority Matrix
17
Define the Project
• Communication Plan
What information Target audience When?
Method of
Communication
Provider
Bi-weekly meeting Status Report
(include Decision Action List)
Directors, General
Manager, Project
Manager
Bi-weekly Email Innovation Manager
Marketing Survey Analysis Report
All project team
member
Bi-weekly Presentation & Email Marketing Manager
Tiles Design Proposal
All project team
member
Bi-weekly Presentation & Email Designer
NPD Marketing Plan
Directors, General
Manager, Project
Manager
2 weeks after
project
commenced
Presentation & Email Marketing Manager
Production feasibility report
All project team
member
Bi-weekly Presentation & Email Production Manager
Marketing Communication Status
All project team
member
B-weekly after
Marketing Plan
approved
Email
Marketing Manager &
Customer Service
Manager
Launch event Status
All project team
member
Bi-weekly after
Marketing Plan
approved
Presentation & Email
Marketing Manager &
Innovation Manager
Top 6 High Risk Events - Severity & Risk
Value
All project team
member
Weekly Meeting
New Product
Committee
Deliverables Tracking Plan
All project team
member
Weekly Meeting
New Product
Committee 18
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
19
Assumptions
Project Objectives
• To launch 4 series of WT25x40cm concept tiles officially to the
market for coming MALBEX 2010 (Malaysia building materials
exhibition) scheduled on 20 to 24 January 2010
20
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
21
Assumptions
Budget
• Total budget allocated based on the past historical data
of new product launch. No additional human resource
cost incur where UCI utilized existing employees
WT25x40
RM493K
Mould
Press
Punches
Conveyor
Belt
System
Packing
Machine
Corrugate
Carton
Box
Brou-
chures
Display
Rack
Exhibition
Booth &
Event
RM20K
4%
RM32K
6%
RM150K
30%
RM65K
13%
RM6K
1%
RM40K
8%
RM80K
16%
RM100K
20%
Supports - RM226K (56%)Input - RM267K (54%)
WT25x40
RM493K
Mould
Press
Punches
Conveyor
Belt
System
Packing
Machine
Corrugate
Carton
Box
Brou-
chures
Display
Rack
Exhibition
Booth &
Event
RM20K
4%
RM32K
6%
RM150K
30%
RM65K
13%
RM6K
1%
RM40K
8%
RM80K
16%
RM100K
20%
Supports - RM226K (56%)Input - RM267K (54%)
22
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
23
Assumptions
Directives
•Examine production capability of existing machineriesEngineering
•Confirm the feasibility and characteristics of new size based on
the tiles dimension, strength and manufacturing efficiency
aspects
Production
•Forecast for product cost at below RM11.00 per square meter is
possibleAccount
•Do marketing survey to find out more about the size especially
contemporary seek-after designs, color scheme, trends, popular
installation layout, etc
Marketing
•Getting the product certified by SIRIM QAS Sdn Bhd for the
Product Certification LicenseQA
24
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
25
Assumptions
Assumptions
• NPC assumes that the current scenario will not change
until post launching period
Product life cycle of this
size will continue for
another 5 years
No resignation of any key
personnel from respective
departments
Existing export customers
and domestic stockiest
especially those situated
in urban areas will accept
and buy this new product
26
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
27
Assumptions
Constraints
Not able to produce higher definition of printout due to its
outdated printing machine
Only one showroom in head office and has difficulties
entertaining architects, IDs, developers, and contractors in
the other 2 urban areas
Very limited warehouse space to keep stocks and longer
stocks holding is expected from this size.
28
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
29
Assumptions
Deliverables
All the four series of tiles produced must pass the internal quality standard with QA and NPC
accepted
The tiles must be properly installed on a few mock up showrooms to examine the finishes before
official launching
For each series, a minimum one batch of 5,000 square meters stocks must be available for sales
5,000 copies of brochures must be ready and company web site must be updated on 20 Jan 2010
The SIRIM certification must be obtained
Invitation cards must be sent out one month before MALBEX 2010 to all domestic dealers,
oversea customers, and project customers
Sales plans and promotional offer packages must be ready
Decorated exhibition booth ready with routine marketing personnel on duty, LCD multimedia
presentation, mini showroom, souvenirs, and light refreshment must be ready
30
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
31
Assumptions
Acceptance Criteria
• The utmost acceptance criteria is
Product Quality
• Finishes
• Textures
• Fine printout
• Straight dimension
• Minimum shade
variation
32
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
33
Assumptions
Key Risk
• NPC is concerned with the grading of product quality
• Outputs that are less than 90% of 1st grade salvaged from
production are not tolerable
• Risk in encountering prolonged inventory turnover
• ACI may not have strong cash flow position to hold on to
the slow moving stocks as well as limited warehouse
space available
34
Risk Identification
Project
WT25x40
Marketin
g
Research
Account
Testing
Producti
on
Logistic Design
Budgetin
g
Product
costing -
P & L
Inventory
Raw
material
Utility -
Gas/ Elec
Machiner
ary
Event
Set-up
Engineeri
ng
Deliverab
les
Purchasi
ng
QA
Post
Launche
d
35
Risk Assessment
Risk Event Likelihood
A
Impact
B
Detection Difficulty
C
Severity
A x B =
Risk Value
A x B x C =
Purchasing Department
Raw Material Price Increase 4 2 1 8 8
Missed Material Supply Deliveries 2 4 1 8 8
Production Department
Missed 90% 1st Grade Quality 2 5 1 10 10
Energy Costs - Electricity & Natural Gas 5 4 1 20 20
Resign of Key Production Personnel 3 3 4 9 36
Marketing Department
Poor Pricing & Design Survey Accuracy Result 2 4 5 8 40
Engineering Department
Equipments Breakdown - Minor 2 3 4 6 24
Equipments Not Function to Productivity Target 2 5 2 10 20
36
Key Assessment Level: 1 – Very Low, 2 – Low, 3 – Moderate, 4 – High, 5 – Very High
Please refer to Appendix E for further details
Risk Assessment (cont.)
Risk Event
Likelihood
A
Impact
B
Detection Difficulty
C
Severity
A x B =
Risk Value
A x B x C =
Warehouse Department
Poor Stocks Management due to Loose Pallets Orders 4 3 3 12 36
Account Department
Not Able to Achieve Minimum Product Costing Target 2 5 2 10 20
Design Department
Tile Designs Not Suitable for Mass Production 3 4 4 12 48
QA Department
Miss Deadline to Receive SIRIM Certification 3 3 2 9 18
Deliverables
All Four Series of Tiles Fail Internal Quality Standard 2 5 1 10 10
Sirim Certificate Not Ready before Exhibition 3 3 4 9 36
Post Launched Performance
Slow Sales & Low Inventory Turnover 3 4 3 12 36
Unanticipated After Sales Quality Complaint 2 4 4 8 32 37
Risk Response Matrix and
Contingency Plan
Risk Event Response Contigency Plan Trigger
Who Is
Responsible
Production Department
Missed 90% 1st Grade Quality Reduce
Improve the product
specification
Not solve during trial run
production 4/11/09 Plant Mgr
Resign of Key Production Personnel Reduce
Draw out successor
planning
Immediately after appoint
process engineer Plant Mgr
Marketing Department
Poor Pricing & Design Survey Accuracy
Result Reduce
Outsource professional
research co.
Market survey results not align
with key accounts feedbacks Marketing Mgr
Design Department
Tile Designs Not Suitable for Mass
Production Reduce
Spare two extra designs
series
Failed requirement on trail run
production Design Mgr
QA Department
Miss Deadline to Receive SIRIM
Certification
Reduce /
Retain
Apply temporary certificate
or pending approval
When appointment with SIRIM
auditors can't be made between
17/12/09 to 5/1/10 QA Mgr
Post Launched Performance
Slow Sales & Low Inventory Turnover Reduce
To introduce 30x40cm &
20x40cm
Poor pass 1 year sales
performance Marketing Mgr
38
Please refer to Appendix F for further details
Top Risks
Energy Costs - Electricity
& Natural Gas
20 20 Retain Adjust Product Price
List
Price Increase before
production date
-
Poor Workers' Working
Attitudes
16 48 Reduce Incentive Scheme for
the two group
experience operators
When supervisor can't
produce the desired
quality & quantity targets
Plant Mgr
Poor Pricing & Design
Survey Accuracy Result
8 40 Reduce Outsource
professional research
co.
Market survey results not
align with key accounts
feedbacks
Marketing Mgr
Outdated Machinery
Technology
12 12 Avoid Focus on designs that
existing machineries
are capable
When machinery
performance not
consistent
Engineering
Mgr
Poor Stocks Management
due to Loose Pallets
Orders
12 36 Reduce Standby plan for loose
pallet warehouse
space
When loose stocks
discrepency more than 3%
from quaterly stocks
checking
Warehouse Mgr
Tile Designs Not Suitable
for Mass Production
12 48 Reduce Spare two extra
designs series
Failed requirement on trail
run production
Design Mgr
Sirim Certificate Not
Ready before Exhibition
9 36 Reduce /
Retain
Apply temporary
certificate or pending
approval
When appointment with
SIRIM auditors can't be
made between 17/12/09 to
5/1/10
QA Mgr
Slow Sales & Low
Inventory Turnover
12 36 Reduce To introduce 30x40cm
& 20x40cm
Poor pass 1 year sales
performance
Marketing Mgr
Who Is
Responsible
Severity Risk ValueRisk Event Response Contigency Plan Trigger
39
Change Request Log
Date Rec'd Date Submit
58
Change brochure to
leaflet & improved color A&P Agency No. 1112/14/2009 12/30/2009 Same Submit
Better printout
& glossy
Comments
NPC Requested Change Status Report - Open Items
Date
RC# Description
Reference
Document
Amount Status
40
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
41
Assumptions
Equipment & Facility
Requirements
New mould and
punches for the size
of 25x40 cm tiles
Internally modify the
conveyor belt system
to hold heavier tiles
Mechanically modify
the selection and
packing machine.
42
Machinery Requirements Study
Size (cm) Press
Cavity
Press
Speed
No of Press
/ Minute
No of Tiles
/ Minute
Conveyo
r System
Upgrade
Print
Machine
Upgrade
Kiln
Capacity
New
Selection &
Packing
Machine
Capex Economi
c of
scale
20x30 5 Fast 20 100 No
Change
No No No No
20x40 3 Medium 15 45 Modified Option No Modified Small
25x40 3 Medium 15 45 Modified Option No Modified Small
25x45 3 Medium 15 45 Modified Option No Modified Small
25x50 2 Medium 15 30 Modified Option No Modified Small
30x40 2 Medium 15 30 Modified Option No Modified Small
30x45 2 Slow 12 24 Modified Option No, but
slow
Modified Medium No
30x50 2 Very Slow 10 20 New Yes Yes Modified High No
30x60 2 Very Slow 10 20 New Yes Yes Yes High No
Yes, but
not
Fair, but
not
Yes, but
mkt
unpopula
Yes, but
not
Yes,
most
Yes, but
mkt
43
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
44
Assumptions
New Product Committee
Department Designation Name Report To
Marketing / Team LeaderBusiness Dev Manager Mr. Lim Shieh ChernMarketing Manager
Account Asst Account Manager Ms. Choo PP Financial Controller
Engineering M&E Engineer Mr. Khor LH General Manager
Warehouse Warehouse Supervisor Mr. Ng Yee Jie Warehouse Manager
Purchasing Purchasing Executive Mr. Peter Low Puchasing Manager
Human Resource HR Manager Pn. Salmiah General Manager
Production Production Manager Mr. Lee KG Plant Manager
Production Process Engineer Mr. Hew AP Production Manager
Lab Lab Manager Pn. Zubaidah Plant Manager
Design Design Manager En. Iskandar Marketing Manager
QA QA Manager En. Shafiz General Manager
Customer Service Administration Manager Ms. Julie Siow Marketing Manager
Marketing Marketing Executive Ms. Low Siew Moi Business Dev Manager
Knowledge Attitude Others
- Necessary experience and
knowledge/technical skills critical for
project completion
- Problem-solving ability
- Ambition, initiative and
energy
- Credibility
- Availability to commit this
project
- Political connections
45
Project Reward
• Reward system to motivate project team members to
deliver distinctive result
(source: Raymond J. Stone. P436 )
Reward
Financial
(Monetary)
Non-Financial
(Non-Monetary)
Direct
- Base pay
- Incentive
- Allowance
Indirect
- Insurance
- Company car
- Holiday
Job
- Advacement
- Increase job
responsibility
Environment
- Career security
- Opportunity for
learning and
46
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements &
Evaluation
Resources
Allocation
47
Assumptions
Staffing – Responsible Matrix
1st 2nd 3rd Duration Res-ponsible
Mar-
keting
Design Account
Engi-
neering
Pro-
duction
QA
Customer
Service
Ware-
house
Pur-
chasing
Cost
(RM'00)
Date
Incur
Marketing Survey 14 Marketing 0
Check current Market
Pricing
14 R S
Check Popular Designs 14 R S
Check Current Market
Scenario
14 R S S
Confirm Tiles Designs 7 Design 0
Select designs from
suppliers
3 R S
Select designs from
oversea files
2 R S
Meeting among NPC for
Decision
2 S R S S S S S S
Confirm Product Costing 3 Account 0
Raw material costing from
Lab Dept
2 R S
Packing, Transport &
Admin costing from mgt
account
1 R S S S S
New Product Marketing Plan 11 Marketing 0
Discuss Marketing Plan &
Strategy
8 R S S
Formulate R, P & E Pricing
Scheme
3 R S S
48Please refer to Appendix G for further details
Project Plan
Project
Objectives
Project Outline
Business need to
be met Constraints
Directives
Deliverables
Acceptance
Criteria
Key Risk
Staffing
Equipment &
Facility
RequirementsBudget
Performance
Measurements
& Evaluation
Resources
Allocation
49
Assumptions
Project Measurements and
Control
• Scenario:
50
When
• 30th October
2009
What Happen
• The project team
evaluates and
notices that raw
material costing
worth RM50,000
in total has not
been included
• The unplanned of
RM11,000 will be
incurred in the
month end of
November 2009
(above) and the
remaining
RM39,000 in the
month end of
December 2009
Result
• NPC required to
work out the
new budget
baselines in
order to seek for
approval from
management.
Project Measurements and
Control
• Earned Value Management (EVM)
(RM)
Accumulated
Planned
Value (PV)
Accumulated
Actual Cost
(AC)
Accumulated
Earned Value (EV)
Cost Variance (CV)
= EV-AC
Schedule Value (SV)
= EV-PV
Cost Performance
Index (CPI) = EV/AC
Schedule
Performance Index
(SPI) = EV/PV
PV AC EV CV SV CPI SPI
1-Sep 0 0 0 0 0
7-Sep 0 0 0 0 0
14-Sep 0 0 0 0 0
21-Sep 0 215000 0 -215000 0 0
28-Sep 267000 215000 267000 52000 0 124 100
5-Oct 267000 267000 267000 0 0 100 100
12-Oct 267000 267000 267000 0 0 100 100
19-Oct 267000 267000 267000 0 0 100 100
26-Oct 267000 267000 267000 0 0 100 100
2-Nov 267000 267000 267000 0 0 100 100
9-Nov 267000 267000 267000 0 0 100 100
16-Nov 267000 267000 267000 0 0 100 100
23-Nov 267000 267000 267000 0 0 100 100
30-Nov 267000 278000 267000 -11000 0 96 100
Comments
Date: 30th Oct
- Spend RM11K
extra against budget
- Amount of
RM215K been
spend earlier as
planned
CPI at 4%, under
performanced with extra
11% spend
Work completion as
planned
Proposed
rectification if
required
Date: 30th Oct
Rework the budget
in more details to
avoid unplanned
cost incur
Required to monitor the
unplanned cost, if
necessary required to
replan or request
Management budget
required to avoid over
spent from budget
allocated 51
Project Measurements and
Control
• Earned Value Management (EVM)
– New Budget Allocation
52
WT25x40
RM543K
Mould
Press
Punches
Conveyor
Belt
System
Packing
Machine
Corrugate
Carton
Box
Brou-
chures
Display
Rack
Exhibition
Booth &
Event
RM20K
4%
RM32K
6%
RM150K
28%
RM65K
12%
RM6K
1%
RM40K
7%
RM80K
15%
RM100K
18%
Supports - RM226K (42%)Input - RM267K (49%)
Raw
Materials
RM50K
9%
Unplanned – RM50K (9%)
Project Measurements and
Control
• Cost/Schedule Graph
53
Project Measurements and
Control
• Baselines and scope change
54
• Monthly Status Report
55
Project Name: ACI New 25x40cm Wall Tiles
Project Manager: Lim Shieh Chern
Status as of: 30th October 2009
Status Summary: The project is on schedule. Seeking approval from management to
approve unplanned raw material costs worth RM50,000. RM11,000 will be incurred in
next month.
Explanations: The project team had not taken into consideration some other factors
during the initial planning of raw materials. A detailed calculation indicates that an
additional allocation of RM 50,000 is needed. The allocation will be staggered over 2
months: RM 11,000 in November and RM 39,000 in December. The approval of this
additional budget is crucial in order for the project to be carried out on schedule. Slight
delay in the arrival of raw material will cause great impact to the manufacturing process
and impede the entire workflow and allocation of the company’s resource.
Total cost of approved changes: RM50,000. The amount is attributed to purchasing raw
materials
Projected cost at completion: EAC is estimated to be RM543,000. This represents an
overrun of RM50,000, given a CPI of 0.91
Conclusion
• ACI Will allocate 2% of its existing production capacity for
production
• The capital expenditure is small at RM493,000 with
anticipated extra reserve of RM50,000
• For FY09/10 unit selling price is budgeted at 25% lower or
$18.75 Square Meters compare to current market price
• The key risks are identified and scrutinized the severity.
Contingency plans are in place to handle the unforeseen
circumstances
• NPC strongly recommends the new ceramic wall tiles 25x40
cm to be approved
56

More Related Content

What's hot

PDMA Process StageGate
PDMA Process StageGatePDMA Process StageGate
PDMA Process StageGateDeepSmarts
 
OpenERP - Project Methodology
OpenERP - Project MethodologyOpenERP - Project Methodology
OpenERP - Project MethodologyOdoo
 
Applying the Stage Gate Model for the Manufacturing Arena
Applying the Stage Gate Model for the Manufacturing ArenaApplying the Stage Gate Model for the Manufacturing Arena
Applying the Stage Gate Model for the Manufacturing Arenampaciorek
 
New Product Introduction - Launching Success!
New Product Introduction - Launching Success! New Product Introduction - Launching Success!
New Product Introduction - Launching Success! Product Realization Group
 
Project Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileProject Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileKnowit_TM
 
Phase gate, 5 s lean manufacturing
Phase gate, 5 s lean manufacturingPhase gate, 5 s lean manufacturing
Phase gate, 5 s lean manufacturingUdo Dittmar
 
Stage gate framework
Stage gate frameworkStage gate framework
Stage gate frameworkjongminshi
 
Stage gate process in IT product development
Stage gate process in IT product developmentStage gate process in IT product development
Stage gate process in IT product developmentPrzemek Berendt
 
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2Tim Kasse
 
Process Guidelines V2
Process Guidelines V2Process Guidelines V2
Process Guidelines V2Imaginea
 
Pros & cons of phase gate by akhilesh nawade
Pros & cons of phase gate   by akhilesh nawadePros & cons of phase gate   by akhilesh nawade
Pros & cons of phase gate by akhilesh nawadeakhilesh7486
 
Teq diligent - Corporate Presentation
Teq diligent - Corporate PresentationTeq diligent - Corporate Presentation
Teq diligent - Corporate PresentationTeq Diligent
 
Product Development Process Diagram
Product Development Process Diagram Product Development Process Diagram
Product Development Process Diagram Demand Metric
 
Knowledge sharing for QA teams
Knowledge sharing for QA teamsKnowledge sharing for QA teams
Knowledge sharing for QA teamsZbyszek Mockun
 
Innovation day 2013 2.3 rudy van raemdonck (verhaert) - rapid prototyping o...
Innovation day 2013   2.3 rudy van raemdonck (verhaert) - rapid prototyping o...Innovation day 2013   2.3 rudy van raemdonck (verhaert) - rapid prototyping o...
Innovation day 2013 2.3 rudy van raemdonck (verhaert) - rapid prototyping o...Verhaert Masters in Innovation
 

What's hot (20)

PDMA Process StageGate
PDMA Process StageGatePDMA Process StageGate
PDMA Process StageGate
 
OpenERP - Project Methodology
OpenERP - Project MethodologyOpenERP - Project Methodology
OpenERP - Project Methodology
 
Innovation Team Plan
Innovation Team PlanInnovation Team Plan
Innovation Team Plan
 
Applying the Stage Gate Model for the Manufacturing Arena
Applying the Stage Gate Model for the Manufacturing ArenaApplying the Stage Gate Model for the Manufacturing Arena
Applying the Stage Gate Model for the Manufacturing Arena
 
New Product Introduction - Launching Success!
New Product Introduction - Launching Success! New Product Introduction - Launching Success!
New Product Introduction - Launching Success!
 
IT NPI Process
IT NPI ProcessIT NPI Process
IT NPI Process
 
Project Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileProject Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and Agile
 
Phase gate, 5 s lean manufacturing
Phase gate, 5 s lean manufacturingPhase gate, 5 s lean manufacturing
Phase gate, 5 s lean manufacturing
 
Stage gate framework
Stage gate frameworkStage gate framework
Stage gate framework
 
Stage gate process in IT product development
Stage gate process in IT product developmentStage gate process in IT product development
Stage gate process in IT product development
 
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
 
Agile and Stage-Gate - Getting it Right
Agile and Stage-Gate - Getting it RightAgile and Stage-Gate - Getting it Right
Agile and Stage-Gate - Getting it Right
 
Process Guidelines V2
Process Guidelines V2Process Guidelines V2
Process Guidelines V2
 
Pros & cons of phase gate by akhilesh nawade
Pros & cons of phase gate   by akhilesh nawadePros & cons of phase gate   by akhilesh nawade
Pros & cons of phase gate by akhilesh nawade
 
RamkumarMV15
RamkumarMV15RamkumarMV15
RamkumarMV15
 
Teq diligent - Corporate Presentation
Teq diligent - Corporate PresentationTeq diligent - Corporate Presentation
Teq diligent - Corporate Presentation
 
Vol. VII Quality Gates
Vol. VII Quality GatesVol. VII Quality Gates
Vol. VII Quality Gates
 
Product Development Process Diagram
Product Development Process Diagram Product Development Process Diagram
Product Development Process Diagram
 
Knowledge sharing for QA teams
Knowledge sharing for QA teamsKnowledge sharing for QA teams
Knowledge sharing for QA teams
 
Innovation day 2013 2.3 rudy van raemdonck (verhaert) - rapid prototyping o...
Innovation day 2013   2.3 rudy van raemdonck (verhaert) - rapid prototyping o...Innovation day 2013   2.3 rudy van raemdonck (verhaert) - rapid prototyping o...
Innovation day 2013 2.3 rudy van raemdonck (verhaert) - rapid prototyping o...
 

Viewers also liked

Bangkok Mega Bridge Project Management 2007
Bangkok Mega Bridge Project Management 2007Bangkok Mega Bridge Project Management 2007
Bangkok Mega Bridge Project Management 2007Mook NP
 
Report on launching of new product
Report on launching of new productReport on launching of new product
Report on launching of new productFaiza Javaid
 
Project Estro_LinkedIn
Project Estro_LinkedInProject Estro_LinkedIn
Project Estro_LinkedInSamuel Sutanto
 
Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)Sikander Sardar
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
Product Management 101: #1 How To Create Products Customer Love.
Product Management 101: #1 How To Create Products Customer Love.Product Management 101: #1 How To Create Products Customer Love.
Product Management 101: #1 How To Create Products Customer Love.Jean-Yves SIMON
 
Successful Implementation Of Customer Lifecycle Management And Crosssell
Successful Implementation Of Customer Lifecycle Management And CrosssellSuccessful Implementation Of Customer Lifecycle Management And Crosssell
Successful Implementation Of Customer Lifecycle Management And CrosssellAnand Nigam
 
Chern's Case Study
Chern's Case StudyChern's Case Study
Chern's Case StudyKyle Walkley
 
product and brand management project on smartphone & Amazon
product and brand management  project on smartphone & Amazonproduct and brand management  project on smartphone & Amazon
product and brand management project on smartphone & AmazonTanmoy Roy
 
Amazon-Fresh-Project-Report (1)
Amazon-Fresh-Project-Report (1)Amazon-Fresh-Project-Report (1)
Amazon-Fresh-Project-Report (1)Dhiraj Gurnani
 
Cross-Sell and Upsell Strategies in the Channel
Cross-Sell and Upsell Strategies in the ChannelCross-Sell and Upsell Strategies in the Channel
Cross-Sell and Upsell Strategies in the ChanneleCoast
 
E-Commerce Project Management
E-Commerce Project ManagementE-Commerce Project Management
E-Commerce Project ManagementJanette Toral
 
E-commerce Project Development
E-commerce Project DevelopmentE-commerce Project Development
E-commerce Project DevelopmentAmin Chowdhury
 
toy manufacturers project report.
toy manufacturers project report.toy manufacturers project report.
toy manufacturers project report.Hagi Sahib
 
Retail management project
Retail management projectRetail management project
Retail management projectDeepika Agrawal
 
Restaurant project
Restaurant projectRestaurant project
Restaurant projectArun Kabra
 
New product development process
New product development processNew product development process
New product development processkdore
 

Viewers also liked (20)

Bangkok Mega Bridge Project Management 2007
Bangkok Mega Bridge Project Management 2007Bangkok Mega Bridge Project Management 2007
Bangkok Mega Bridge Project Management 2007
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Report on launching of new product
Report on launching of new productReport on launching of new product
Report on launching of new product
 
Project Estro_LinkedIn
Project Estro_LinkedInProject Estro_LinkedIn
Project Estro_LinkedIn
 
Chpt03 defining the project
Chpt03 defining the projectChpt03 defining the project
Chpt03 defining the project
 
Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)Pakistan Grand Prix (Project Management)
Pakistan Grand Prix (Project Management)
 
Snapchat Project
Snapchat ProjectSnapchat Project
Snapchat Project
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
Product Management 101: #1 How To Create Products Customer Love.
Product Management 101: #1 How To Create Products Customer Love.Product Management 101: #1 How To Create Products Customer Love.
Product Management 101: #1 How To Create Products Customer Love.
 
Successful Implementation Of Customer Lifecycle Management And Crosssell
Successful Implementation Of Customer Lifecycle Management And CrosssellSuccessful Implementation Of Customer Lifecycle Management And Crosssell
Successful Implementation Of Customer Lifecycle Management And Crosssell
 
Chern's Case Study
Chern's Case StudyChern's Case Study
Chern's Case Study
 
product and brand management project on smartphone & Amazon
product and brand management  project on smartphone & Amazonproduct and brand management  project on smartphone & Amazon
product and brand management project on smartphone & Amazon
 
Amazon-Fresh-Project-Report (1)
Amazon-Fresh-Project-Report (1)Amazon-Fresh-Project-Report (1)
Amazon-Fresh-Project-Report (1)
 
Cross-Sell and Upsell Strategies in the Channel
Cross-Sell and Upsell Strategies in the ChannelCross-Sell and Upsell Strategies in the Channel
Cross-Sell and Upsell Strategies in the Channel
 
E-Commerce Project Management
E-Commerce Project ManagementE-Commerce Project Management
E-Commerce Project Management
 
E-commerce Project Development
E-commerce Project DevelopmentE-commerce Project Development
E-commerce Project Development
 
toy manufacturers project report.
toy manufacturers project report.toy manufacturers project report.
toy manufacturers project report.
 
Retail management project
Retail management projectRetail management project
Retail management project
 
Restaurant project
Restaurant projectRestaurant project
Restaurant project
 
New product development process
New product development processNew product development process
New product development process
 

Similar to Project Management: New Product Development for Amazon Ceramic Industries

Genral project report(ppt)
Genral project report(ppt)Genral project report(ppt)
Genral project report(ppt)Raj Amrutiya
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalYee Len Wan
 
Business plan of plastic brick
Business plan of plastic brickBusiness plan of plastic brick
Business plan of plastic brickSHIVAMSHARMA1271
 
Study to construct a new pvc coated fabric manufacturing plant
Study to construct a new pvc coated fabric manufacturing plantStudy to construct a new pvc coated fabric manufacturing plant
Study to construct a new pvc coated fabric manufacturing plantRakhi Pal
 
Iron Cast and Machined Components Case study
Iron Cast and Machined Components Case studyIron Cast and Machined Components Case study
Iron Cast and Machined Components Case studyDragon Sourcing
 
Wear Plate Sourcing Project Case Study by Dragon Sourcing
Wear Plate Sourcing Project Case Study by Dragon SourcingWear Plate Sourcing Project Case Study by Dragon Sourcing
Wear Plate Sourcing Project Case Study by Dragon SourcingJohn William
 
Artificial Grass Carpet Case Study
Artificial Grass Carpet Case StudyArtificial Grass Carpet Case Study
Artificial Grass Carpet Case StudyJohn William
 
Ready mix concrete batching plant - business plan
Ready mix concrete batching plant - business planReady mix concrete batching plant - business plan
Ready mix concrete batching plant - business planRami Taleb
 
ADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHES
ADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHESADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHES
ADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHESiQHub
 
Green roof put nature on top
Green roof   put nature on topGreen roof   put nature on top
Green roof put nature on topYen LE
 
LiteonMobile India Profile
LiteonMobile India Profile LiteonMobile India Profile
LiteonMobile India Profile rmaniva
 
Presentation-Q1-update-27.10.22.pdf
Presentation-Q1-update-27.10.22.pdfPresentation-Q1-update-27.10.22.pdf
Presentation-Q1-update-27.10.22.pdfPeterWesterlund7
 
Agile & Lean in Construction: a brilliantly compelling & inspiring case study
Agile & Lean in Construction: a brilliantly compelling & inspiring case studyAgile & Lean in Construction: a brilliantly compelling & inspiring case study
Agile & Lean in Construction: a brilliantly compelling & inspiring case studyagileoutsideIT
 

Similar to Project Management: New Product Development for Amazon Ceramic Industries (20)

Genral project report(ppt)
Genral project report(ppt)Genral project report(ppt)
Genral project report(ppt)
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisal
 
Business plan of plastic brick
Business plan of plastic brickBusiness plan of plastic brick
Business plan of plastic brick
 
Innovation technique in construction
Innovation technique in constructionInnovation technique in construction
Innovation technique in construction
 
Study to construct a new pvc coated fabric manufacturing plant
Study to construct a new pvc coated fabric manufacturing plantStudy to construct a new pvc coated fabric manufacturing plant
Study to construct a new pvc coated fabric manufacturing plant
 
Iron Cast and Machined Components Case study
Iron Cast and Machined Components Case studyIron Cast and Machined Components Case study
Iron Cast and Machined Components Case study
 
Horizon 2020 SME Instrument - Societal Challenge 5
Horizon 2020 SME Instrument - Societal Challenge 5Horizon 2020 SME Instrument - Societal Challenge 5
Horizon 2020 SME Instrument - Societal Challenge 5
 
Asq int lss
Asq int lssAsq int lss
Asq int lss
 
Zzzzzankita
ZzzzzankitaZzzzzankita
Zzzzzankita
 
Wear Plate Sourcing Project Case Study by Dragon Sourcing
Wear Plate Sourcing Project Case Study by Dragon SourcingWear Plate Sourcing Project Case Study by Dragon Sourcing
Wear Plate Sourcing Project Case Study by Dragon Sourcing
 
Artificial Grass Carpet Case Study
Artificial Grass Carpet Case StudyArtificial Grass Carpet Case Study
Artificial Grass Carpet Case Study
 
Eaga red 1711-02
Eaga red 1711-02Eaga red 1711-02
Eaga red 1711-02
 
Manufacturing Competitiveness Enhancement Program
Manufacturing Competitiveness Enhancement ProgramManufacturing Competitiveness Enhancement Program
Manufacturing Competitiveness Enhancement Program
 
Ready mix concrete batching plant - business plan
Ready mix concrete batching plant - business planReady mix concrete batching plant - business plan
Ready mix concrete batching plant - business plan
 
ADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHES
ADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHESADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHES
ADDRESSING THE CHALLENGES OF RECYCLING IN THE EU THROUGH INNOVATIVE APPROACHES
 
New venture analysis
New venture analysisNew venture analysis
New venture analysis
 
Green roof put nature on top
Green roof   put nature on topGreen roof   put nature on top
Green roof put nature on top
 
LiteonMobile India Profile
LiteonMobile India Profile LiteonMobile India Profile
LiteonMobile India Profile
 
Presentation-Q1-update-27.10.22.pdf
Presentation-Q1-update-27.10.22.pdfPresentation-Q1-update-27.10.22.pdf
Presentation-Q1-update-27.10.22.pdf
 
Agile & Lean in Construction: a brilliantly compelling & inspiring case study
Agile & Lean in Construction: a brilliantly compelling & inspiring case studyAgile & Lean in Construction: a brilliantly compelling & inspiring case study
Agile & Lean in Construction: a brilliantly compelling & inspiring case study
 

More from Yee Jie NG

Value Creation Concept and Approach for VC
Value Creation Concept and Approach for VCValue Creation Concept and Approach for VC
Value Creation Concept and Approach for VCYee Jie NG
 
My Career Portfolio
My Career PortfolioMy Career Portfolio
My Career PortfolioYee Jie NG
 
Smart Connected Hotel Vision Deck
Smart Connected Hotel Vision DeckSmart Connected Hotel Vision Deck
Smart Connected Hotel Vision DeckYee Jie NG
 
Machine learning Mindmap
Machine learning MindmapMachine learning Mindmap
Machine learning MindmapYee Jie NG
 
Digital marketing handbook
Digital marketing handbookDigital marketing handbook
Digital marketing handbookYee Jie NG
 
Product manager 90 days plan
Product manager 90 days planProduct manager 90 days plan
Product manager 90 days planYee Jie NG
 
Design thinking for cloud billing issue
Design thinking for cloud billing issueDesign thinking for cloud billing issue
Design thinking for cloud billing issueYee Jie NG
 
Healthcare Landscape and Connected Health Trend of Singapore
Healthcare Landscape and Connected Health Trend of SingaporeHealthcare Landscape and Connected Health Trend of Singapore
Healthcare Landscape and Connected Health Trend of SingaporeYee Jie NG
 
LEAD Certificate - Corporate Innovation
LEAD Certificate - Corporate InnovationLEAD Certificate - Corporate Innovation
LEAD Certificate - Corporate InnovationYee Jie NG
 
IoT @ Home Infographic
IoT @ Home InfographicIoT @ Home Infographic
IoT @ Home InfographicYee Jie NG
 
MIC Cyberjaya FY12 Annual Report
MIC Cyberjaya FY12 Annual Report   MIC Cyberjaya FY12 Annual Report
MIC Cyberjaya FY12 Annual Report Yee Jie NG
 
Strategic Marketing: A Case Study of Starbucks
Strategic Marketing: A Case Study of StarbucksStrategic Marketing: A Case Study of Starbucks
Strategic Marketing: A Case Study of StarbucksYee Jie NG
 
Scenario and Strategic Planning: A Case Study of Eli Lily & Co.
Scenario and Strategic Planning: A Case Study of Eli Lily & Co.Scenario and Strategic Planning: A Case Study of Eli Lily & Co.
Scenario and Strategic Planning: A Case Study of Eli Lily & Co.Yee Jie NG
 
Marketing: A Case Study of Cialis
Marketing: A Case Study of CialisMarketing: A Case Study of Cialis
Marketing: A Case Study of CialisYee Jie NG
 
Competitive Analysis in Pharmaceutical Industry
Competitive Analysis in Pharmaceutical IndustryCompetitive Analysis in Pharmaceutical Industry
Competitive Analysis in Pharmaceutical IndustryYee Jie NG
 
Change Agent Strategies: Emotion of Change
Change Agent Strategies: Emotion of ChangeChange Agent Strategies: Emotion of Change
Change Agent Strategies: Emotion of ChangeYee Jie NG
 

More from Yee Jie NG (17)

Value Creation Concept and Approach for VC
Value Creation Concept and Approach for VCValue Creation Concept and Approach for VC
Value Creation Concept and Approach for VC
 
My Career Portfolio
My Career PortfolioMy Career Portfolio
My Career Portfolio
 
Smart Connected Hotel Vision Deck
Smart Connected Hotel Vision DeckSmart Connected Hotel Vision Deck
Smart Connected Hotel Vision Deck
 
Machine learning Mindmap
Machine learning MindmapMachine learning Mindmap
Machine learning Mindmap
 
Digital marketing handbook
Digital marketing handbookDigital marketing handbook
Digital marketing handbook
 
Product manager 90 days plan
Product manager 90 days planProduct manager 90 days plan
Product manager 90 days plan
 
Design thinking for cloud billing issue
Design thinking for cloud billing issueDesign thinking for cloud billing issue
Design thinking for cloud billing issue
 
Healthcare Landscape and Connected Health Trend of Singapore
Healthcare Landscape and Connected Health Trend of SingaporeHealthcare Landscape and Connected Health Trend of Singapore
Healthcare Landscape and Connected Health Trend of Singapore
 
LEAD Certificate - Corporate Innovation
LEAD Certificate - Corporate InnovationLEAD Certificate - Corporate Innovation
LEAD Certificate - Corporate Innovation
 
IoT @ Home Infographic
IoT @ Home InfographicIoT @ Home Infographic
IoT @ Home Infographic
 
Rhythm.SG
Rhythm.SGRhythm.SG
Rhythm.SG
 
MIC Cyberjaya FY12 Annual Report
MIC Cyberjaya FY12 Annual Report   MIC Cyberjaya FY12 Annual Report
MIC Cyberjaya FY12 Annual Report
 
Strategic Marketing: A Case Study of Starbucks
Strategic Marketing: A Case Study of StarbucksStrategic Marketing: A Case Study of Starbucks
Strategic Marketing: A Case Study of Starbucks
 
Scenario and Strategic Planning: A Case Study of Eli Lily & Co.
Scenario and Strategic Planning: A Case Study of Eli Lily & Co.Scenario and Strategic Planning: A Case Study of Eli Lily & Co.
Scenario and Strategic Planning: A Case Study of Eli Lily & Co.
 
Marketing: A Case Study of Cialis
Marketing: A Case Study of CialisMarketing: A Case Study of Cialis
Marketing: A Case Study of Cialis
 
Competitive Analysis in Pharmaceutical Industry
Competitive Analysis in Pharmaceutical IndustryCompetitive Analysis in Pharmaceutical Industry
Competitive Analysis in Pharmaceutical Industry
 
Change Agent Strategies: Emotion of Change
Change Agent Strategies: Emotion of ChangeChange Agent Strategies: Emotion of Change
Change Agent Strategies: Emotion of Change
 

Project Management: New Product Development for Amazon Ceramic Industries

  • 1. New Product Development for Wall Tile 25×40CM ● LIM SHIEH CHERN ● LOW SIEW MOI ● NG YEE JIE ● 1
  • 2. Team Members Low Siew Moi 2821945 Lim Shieh Chern 2821959 Ng Yee Jie 2821942 2
  • 3. The Company • Amazon Ceramics Industries AboutUs A local ceramic tiles manufacturers, manufacturing floor tiles, wall tiles, homogenous tiles etc. Origin Founded in 1985. Headquarter in Senawang, Negeri Sembilan, Malaysian Mission To be a reputable manufacturer and supplier of innovative and quality products at affordable price in the building material industry 3
  • 4. The Products 20cm x 25cm Wall Tiles MARVE 25cm x 33cm Wall Tiles ASTON 4
  • 5. New Product – 25cm x 40cm Wall Tiles EleganceAmaze series Sphere Blossom Wave 5
  • 6. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 6 Assumptions
  • 7. Organization Cultural Dimension • ACI is a more result oriented with relative well motivated organization. However management with strong autonomy power to control the financial and moderate risk taker. External10. Open-System focusInternal Ends9. Means-ends orientationMeans High8. Conflict toleranceLow Other7. Reward criteriaPerformance High6. Risk toleranceLow Tight5. ControlLoose Interdependent4. Unity IntegrationIndependent People3. People focusTask Group2. Team emphasisIndividual Organization1. Member IdentityJob External10. Open-System focusInternal Ends9. Means-ends orientationMeans High8. Conflict toleranceLow Other7. Reward criteriaPerformance High6. Risk toleranceLow Tight5. ControlLoose Interdependent4. Unity IntegrationIndependent People3. People focusTask Group2. Team emphasisIndividual Organization1. Member IdentityJob Source: Cultural Dimensions of an Organization Supportive of Project Management (Gary & Larson. p. 73). 7
  • 8. Project Outline • Proposing a new size of ceramic wall tiles (WT) for FY09/01 – 25x40cm Increase Profit Attractive Selling Price New Product Strategy •Gross Profit deteriorated from 20% in FY04/05 to only 14% presently •Can improve average gross profit from 14% in FY08/09 to 20% in FY09/01, 26% in FY12/13 •25x40cm sells range from RM25.00 to RM35.00 compared to common sizes at around RM11.00 square meters •To penetrate into urban and middle- income market, mid range housing project markets and export markets •Increase the product mix since phasing out WT20x20 cm size in FY07/08 8
  • 9. Increase Profit • Financial forecasting – A potential grow of demand for WT 25x40 in market from 2% in FY09/10 to 80% in FY12/13 – A margin grow for ACI from 20% in FY09/10 to 26% in FY12/13 F INANC IAL ANAL Y S IS Actual FY07/08 Actual FY08/09 Budget FY09/10 Forecast FY10/11 Forecast FY11/12 Forecast FY12/13 Des cription Wall Tiles Sizes (cm) Sales Vol (%) a. 20x20 % 2% 0% 0% 0% 0% 0% b. 20x25 % 88% 88% 77% 58% 38% 28% c. 25x33 % 10% 12% 22% 32% 41% 41% d. 25x40 % 0% 0% 2% 11% 22% 30% Total % 100% 100% 100% 100% 100% 100% Sales Vol (M2) a. 20x20 M2 57,057 - - - - - b. 20x25 M2 2,393,677 2,424,905 2,142,000 1,610,000 1,031,250 781,000 c. 25x33 M2 266,266 340,095 613,200 893,200 1,122,000 1,138,500 d. 25x40 M2 - - 44,800 296,800 596,750 830,500 Total M2 2,717,000 2,765,000 2,800,000 2,800,000 2,750,000 2,750,000 Production C apacity M2 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 B alance C apacity M2 283,000 235,000 200,000 200,000 250,000 250,000 G ros s Profit Margin Unit Selling Price (a, b, c & d) RM/M2 11.74 11.33 12.57 13.36 14.18 15.23 Unit Cost of Sales (a, b, c & d) RM/M2 9.83 9.79 10.02 10.42 10.91 11.34 Unit Gross Profit (GP) (a, b, c & d) RM/M2 1.91 1.54 2.55 2.94 3.27 3.89 Wall Tiles GP Margin (a, b, c & d) RM/M2 16% 14% 20% 22% 23% 26% 9 Please refer to Appendix A for further details
  • 10. Attractive Selling Price • Market Survey – Pippo is the only local manufacturer producing 25x40cm wall tiles with one imported brand, “UCI”, from Thailand Size (cm) Importer/ Manufacturer/ Trader Country Type of Material Brand Retailer Price/M2 20x30 KimHin Malaysia Ceramic Matt & Glossy Kimgress RM22.00 - RM28.00 20x40 Venus Malaysia Ceramic Matt & Glossy Venus RM18.00 - RM30.00 25x40 Pippo & Imported Malaysia, Ceramic Matt & Glossy PP & UCI RM25.00 - RM35.00 Thailand 25x45 Guocera Malaysia Ceramic High Glossy Guocera RM40.00 - RM45.00 25x50 Roman Indonesia Ceramic Red Body Roman RM28.00 - RM32.00 30x40 KimHin, Johan, WH & Sixny Malaysia, Ceramic Various RM35.00 - RM38.00 China 30x45 Huawei China Ceramic Rectified UNO RM28.00 - RM32.00 30x50 Roman Indonesia Ceramic Red Body Roman RM30.00 - RM35.00 30x60 MML, Guocera, WH, Niro, Alpha, Malaysia, China, Porcelain (Soluble Salt) & Full Body Various RM25.00 - RM35.00 Venue, Seacera, Imported Veitnam 10
  • 11. WBS • Work Breakdown Structure in Outline Form 1 Marketing Survey 2 Confirm Tiles Designs 3 Factory Product Developmet 4 Confirm Product Costing 5 New Product Marketing Plan 6 Equipments & Machinery - Ready 7 SIRIM Certification & Product Specifiaction 8 Sales & Administration System 9 Warehouse Control System 10 Liaise With Event Management Co 11 A&P Agency Management 12 Puchasing Raw Materials & Equipments 13 Actual Product Production 14 HQ Showroom Decoration 15 Waiting for Exhibition & Rectification 16 New Product Launching Ready Summary Tasks 11 Please refer to Appendix B for further details
  • 12. Project Network Diagram • The project network diagram is presented separately. Please refer to Appendix C for further details 12
  • 13. PERT Scheduled Project Duration TS 105 days Critical Path Duration TE 101 days Standard Deviation 5.35 Probability Z 0.75 Probability % Z% 77% Milestone (Critical Path) Weighted Average Optimistic Expected Pessimistic [(b-a)/6]2 Marketing Survey 13.17 7 14 16 2.25 Factory Product Development 33 22 33 44 13.44 Liaise With Event Management Co 25.17 13 27 30 8.03 Actual Product Production 25.83 17 27 30 4.69 New Product Launching - Ready 3.83 2 4 5 0.25 101 61 105 125 13Please refer to Appendix D for further details
  • 14. Project Stakeholders Internal Customers Suppliers Customers Regulatory 1. Top Management 1. Raw Material - Glaze & Surface 1. Houseowners 1. SIRIM 2. Account 2. Raw Material - Clay & Body 2. Dealers / Retailers 2. DOE 3. Engineering 3. Raw Material - Additive 3. Distributors 3. Bomba 4. Warehouse 4. Packaging - Carton Boxes 4. Interior Designers 5. Purchasing 5. Packaging - Pallet & Others 5. Architects 6. Human Resource 6. Event Management Co. 6. Developers 7. Production 7. A&P Agency 7. Contractors 8. Lab 8. Machineries and Equipments 8. Sub-Contractors 9. Design 9. Utility Co. - Energy 9. Importers 10. QA 10. Bankers 10. Commission Agents 11. Customer Service 12. Marketing 14
  • 15. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 15 Assumptions
  • 16. Business Need to be Met Contribute more than 40% gross profit margin for FY09/10 so that can achieve overall budgeted gross profit margin of 20% Production volume at 2% of total product portfolio for FY09/10 Produce 90% of 1st grade quality output and maintain 3% of reject in order to market effectively 16
  • 17. Define the Project • Project Priority Matrix 17
  • 18. Define the Project • Communication Plan What information Target audience When? Method of Communication Provider Bi-weekly meeting Status Report (include Decision Action List) Directors, General Manager, Project Manager Bi-weekly Email Innovation Manager Marketing Survey Analysis Report All project team member Bi-weekly Presentation & Email Marketing Manager Tiles Design Proposal All project team member Bi-weekly Presentation & Email Designer NPD Marketing Plan Directors, General Manager, Project Manager 2 weeks after project commenced Presentation & Email Marketing Manager Production feasibility report All project team member Bi-weekly Presentation & Email Production Manager Marketing Communication Status All project team member B-weekly after Marketing Plan approved Email Marketing Manager & Customer Service Manager Launch event Status All project team member Bi-weekly after Marketing Plan approved Presentation & Email Marketing Manager & Innovation Manager Top 6 High Risk Events - Severity & Risk Value All project team member Weekly Meeting New Product Committee Deliverables Tracking Plan All project team member Weekly Meeting New Product Committee 18
  • 19. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 19 Assumptions
  • 20. Project Objectives • To launch 4 series of WT25x40cm concept tiles officially to the market for coming MALBEX 2010 (Malaysia building materials exhibition) scheduled on 20 to 24 January 2010 20
  • 21. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 21 Assumptions
  • 22. Budget • Total budget allocated based on the past historical data of new product launch. No additional human resource cost incur where UCI utilized existing employees WT25x40 RM493K Mould Press Punches Conveyor Belt System Packing Machine Corrugate Carton Box Brou- chures Display Rack Exhibition Booth & Event RM20K 4% RM32K 6% RM150K 30% RM65K 13% RM6K 1% RM40K 8% RM80K 16% RM100K 20% Supports - RM226K (56%)Input - RM267K (54%) WT25x40 RM493K Mould Press Punches Conveyor Belt System Packing Machine Corrugate Carton Box Brou- chures Display Rack Exhibition Booth & Event RM20K 4% RM32K 6% RM150K 30% RM65K 13% RM6K 1% RM40K 8% RM80K 16% RM100K 20% Supports - RM226K (56%)Input - RM267K (54%) 22
  • 23. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 23 Assumptions
  • 24. Directives •Examine production capability of existing machineriesEngineering •Confirm the feasibility and characteristics of new size based on the tiles dimension, strength and manufacturing efficiency aspects Production •Forecast for product cost at below RM11.00 per square meter is possibleAccount •Do marketing survey to find out more about the size especially contemporary seek-after designs, color scheme, trends, popular installation layout, etc Marketing •Getting the product certified by SIRIM QAS Sdn Bhd for the Product Certification LicenseQA 24
  • 25. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 25 Assumptions
  • 26. Assumptions • NPC assumes that the current scenario will not change until post launching period Product life cycle of this size will continue for another 5 years No resignation of any key personnel from respective departments Existing export customers and domestic stockiest especially those situated in urban areas will accept and buy this new product 26
  • 27. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 27 Assumptions
  • 28. Constraints Not able to produce higher definition of printout due to its outdated printing machine Only one showroom in head office and has difficulties entertaining architects, IDs, developers, and contractors in the other 2 urban areas Very limited warehouse space to keep stocks and longer stocks holding is expected from this size. 28
  • 29. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 29 Assumptions
  • 30. Deliverables All the four series of tiles produced must pass the internal quality standard with QA and NPC accepted The tiles must be properly installed on a few mock up showrooms to examine the finishes before official launching For each series, a minimum one batch of 5,000 square meters stocks must be available for sales 5,000 copies of brochures must be ready and company web site must be updated on 20 Jan 2010 The SIRIM certification must be obtained Invitation cards must be sent out one month before MALBEX 2010 to all domestic dealers, oversea customers, and project customers Sales plans and promotional offer packages must be ready Decorated exhibition booth ready with routine marketing personnel on duty, LCD multimedia presentation, mini showroom, souvenirs, and light refreshment must be ready 30
  • 31. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 31 Assumptions
  • 32. Acceptance Criteria • The utmost acceptance criteria is Product Quality • Finishes • Textures • Fine printout • Straight dimension • Minimum shade variation 32
  • 33. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 33 Assumptions
  • 34. Key Risk • NPC is concerned with the grading of product quality • Outputs that are less than 90% of 1st grade salvaged from production are not tolerable • Risk in encountering prolonged inventory turnover • ACI may not have strong cash flow position to hold on to the slow moving stocks as well as limited warehouse space available 34
  • 35. Risk Identification Project WT25x40 Marketin g Research Account Testing Producti on Logistic Design Budgetin g Product costing - P & L Inventory Raw material Utility - Gas/ Elec Machiner ary Event Set-up Engineeri ng Deliverab les Purchasi ng QA Post Launche d 35
  • 36. Risk Assessment Risk Event Likelihood A Impact B Detection Difficulty C Severity A x B = Risk Value A x B x C = Purchasing Department Raw Material Price Increase 4 2 1 8 8 Missed Material Supply Deliveries 2 4 1 8 8 Production Department Missed 90% 1st Grade Quality 2 5 1 10 10 Energy Costs - Electricity & Natural Gas 5 4 1 20 20 Resign of Key Production Personnel 3 3 4 9 36 Marketing Department Poor Pricing & Design Survey Accuracy Result 2 4 5 8 40 Engineering Department Equipments Breakdown - Minor 2 3 4 6 24 Equipments Not Function to Productivity Target 2 5 2 10 20 36 Key Assessment Level: 1 – Very Low, 2 – Low, 3 – Moderate, 4 – High, 5 – Very High Please refer to Appendix E for further details
  • 37. Risk Assessment (cont.) Risk Event Likelihood A Impact B Detection Difficulty C Severity A x B = Risk Value A x B x C = Warehouse Department Poor Stocks Management due to Loose Pallets Orders 4 3 3 12 36 Account Department Not Able to Achieve Minimum Product Costing Target 2 5 2 10 20 Design Department Tile Designs Not Suitable for Mass Production 3 4 4 12 48 QA Department Miss Deadline to Receive SIRIM Certification 3 3 2 9 18 Deliverables All Four Series of Tiles Fail Internal Quality Standard 2 5 1 10 10 Sirim Certificate Not Ready before Exhibition 3 3 4 9 36 Post Launched Performance Slow Sales & Low Inventory Turnover 3 4 3 12 36 Unanticipated After Sales Quality Complaint 2 4 4 8 32 37
  • 38. Risk Response Matrix and Contingency Plan Risk Event Response Contigency Plan Trigger Who Is Responsible Production Department Missed 90% 1st Grade Quality Reduce Improve the product specification Not solve during trial run production 4/11/09 Plant Mgr Resign of Key Production Personnel Reduce Draw out successor planning Immediately after appoint process engineer Plant Mgr Marketing Department Poor Pricing & Design Survey Accuracy Result Reduce Outsource professional research co. Market survey results not align with key accounts feedbacks Marketing Mgr Design Department Tile Designs Not Suitable for Mass Production Reduce Spare two extra designs series Failed requirement on trail run production Design Mgr QA Department Miss Deadline to Receive SIRIM Certification Reduce / Retain Apply temporary certificate or pending approval When appointment with SIRIM auditors can't be made between 17/12/09 to 5/1/10 QA Mgr Post Launched Performance Slow Sales & Low Inventory Turnover Reduce To introduce 30x40cm & 20x40cm Poor pass 1 year sales performance Marketing Mgr 38 Please refer to Appendix F for further details
  • 39. Top Risks Energy Costs - Electricity & Natural Gas 20 20 Retain Adjust Product Price List Price Increase before production date - Poor Workers' Working Attitudes 16 48 Reduce Incentive Scheme for the two group experience operators When supervisor can't produce the desired quality & quantity targets Plant Mgr Poor Pricing & Design Survey Accuracy Result 8 40 Reduce Outsource professional research co. Market survey results not align with key accounts feedbacks Marketing Mgr Outdated Machinery Technology 12 12 Avoid Focus on designs that existing machineries are capable When machinery performance not consistent Engineering Mgr Poor Stocks Management due to Loose Pallets Orders 12 36 Reduce Standby plan for loose pallet warehouse space When loose stocks discrepency more than 3% from quaterly stocks checking Warehouse Mgr Tile Designs Not Suitable for Mass Production 12 48 Reduce Spare two extra designs series Failed requirement on trail run production Design Mgr Sirim Certificate Not Ready before Exhibition 9 36 Reduce / Retain Apply temporary certificate or pending approval When appointment with SIRIM auditors can't be made between 17/12/09 to 5/1/10 QA Mgr Slow Sales & Low Inventory Turnover 12 36 Reduce To introduce 30x40cm & 20x40cm Poor pass 1 year sales performance Marketing Mgr Who Is Responsible Severity Risk ValueRisk Event Response Contigency Plan Trigger 39
  • 40. Change Request Log Date Rec'd Date Submit 58 Change brochure to leaflet & improved color A&P Agency No. 1112/14/2009 12/30/2009 Same Submit Better printout & glossy Comments NPC Requested Change Status Report - Open Items Date RC# Description Reference Document Amount Status 40
  • 41. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 41 Assumptions
  • 42. Equipment & Facility Requirements New mould and punches for the size of 25x40 cm tiles Internally modify the conveyor belt system to hold heavier tiles Mechanically modify the selection and packing machine. 42
  • 43. Machinery Requirements Study Size (cm) Press Cavity Press Speed No of Press / Minute No of Tiles / Minute Conveyo r System Upgrade Print Machine Upgrade Kiln Capacity New Selection & Packing Machine Capex Economi c of scale 20x30 5 Fast 20 100 No Change No No No No 20x40 3 Medium 15 45 Modified Option No Modified Small 25x40 3 Medium 15 45 Modified Option No Modified Small 25x45 3 Medium 15 45 Modified Option No Modified Small 25x50 2 Medium 15 30 Modified Option No Modified Small 30x40 2 Medium 15 30 Modified Option No Modified Small 30x45 2 Slow 12 24 Modified Option No, but slow Modified Medium No 30x50 2 Very Slow 10 20 New Yes Yes Modified High No 30x60 2 Very Slow 10 20 New Yes Yes Yes High No Yes, but not Fair, but not Yes, but mkt unpopula Yes, but not Yes, most Yes, but mkt 43
  • 44. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 44 Assumptions
  • 45. New Product Committee Department Designation Name Report To Marketing / Team LeaderBusiness Dev Manager Mr. Lim Shieh ChernMarketing Manager Account Asst Account Manager Ms. Choo PP Financial Controller Engineering M&E Engineer Mr. Khor LH General Manager Warehouse Warehouse Supervisor Mr. Ng Yee Jie Warehouse Manager Purchasing Purchasing Executive Mr. Peter Low Puchasing Manager Human Resource HR Manager Pn. Salmiah General Manager Production Production Manager Mr. Lee KG Plant Manager Production Process Engineer Mr. Hew AP Production Manager Lab Lab Manager Pn. Zubaidah Plant Manager Design Design Manager En. Iskandar Marketing Manager QA QA Manager En. Shafiz General Manager Customer Service Administration Manager Ms. Julie Siow Marketing Manager Marketing Marketing Executive Ms. Low Siew Moi Business Dev Manager Knowledge Attitude Others - Necessary experience and knowledge/technical skills critical for project completion - Problem-solving ability - Ambition, initiative and energy - Credibility - Availability to commit this project - Political connections 45
  • 46. Project Reward • Reward system to motivate project team members to deliver distinctive result (source: Raymond J. Stone. P436 ) Reward Financial (Monetary) Non-Financial (Non-Monetary) Direct - Base pay - Incentive - Allowance Indirect - Insurance - Company car - Holiday Job - Advacement - Increase job responsibility Environment - Career security - Opportunity for learning and 46
  • 47. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 47 Assumptions
  • 48. Staffing – Responsible Matrix 1st 2nd 3rd Duration Res-ponsible Mar- keting Design Account Engi- neering Pro- duction QA Customer Service Ware- house Pur- chasing Cost (RM'00) Date Incur Marketing Survey 14 Marketing 0 Check current Market Pricing 14 R S Check Popular Designs 14 R S Check Current Market Scenario 14 R S S Confirm Tiles Designs 7 Design 0 Select designs from suppliers 3 R S Select designs from oversea files 2 R S Meeting among NPC for Decision 2 S R S S S S S S Confirm Product Costing 3 Account 0 Raw material costing from Lab Dept 2 R S Packing, Transport & Admin costing from mgt account 1 R S S S S New Product Marketing Plan 11 Marketing 0 Discuss Marketing Plan & Strategy 8 R S S Formulate R, P & E Pricing Scheme 3 R S S 48Please refer to Appendix G for further details
  • 49. Project Plan Project Objectives Project Outline Business need to be met Constraints Directives Deliverables Acceptance Criteria Key Risk Staffing Equipment & Facility RequirementsBudget Performance Measurements & Evaluation Resources Allocation 49 Assumptions
  • 50. Project Measurements and Control • Scenario: 50 When • 30th October 2009 What Happen • The project team evaluates and notices that raw material costing worth RM50,000 in total has not been included • The unplanned of RM11,000 will be incurred in the month end of November 2009 (above) and the remaining RM39,000 in the month end of December 2009 Result • NPC required to work out the new budget baselines in order to seek for approval from management.
  • 51. Project Measurements and Control • Earned Value Management (EVM) (RM) Accumulated Planned Value (PV) Accumulated Actual Cost (AC) Accumulated Earned Value (EV) Cost Variance (CV) = EV-AC Schedule Value (SV) = EV-PV Cost Performance Index (CPI) = EV/AC Schedule Performance Index (SPI) = EV/PV PV AC EV CV SV CPI SPI 1-Sep 0 0 0 0 0 7-Sep 0 0 0 0 0 14-Sep 0 0 0 0 0 21-Sep 0 215000 0 -215000 0 0 28-Sep 267000 215000 267000 52000 0 124 100 5-Oct 267000 267000 267000 0 0 100 100 12-Oct 267000 267000 267000 0 0 100 100 19-Oct 267000 267000 267000 0 0 100 100 26-Oct 267000 267000 267000 0 0 100 100 2-Nov 267000 267000 267000 0 0 100 100 9-Nov 267000 267000 267000 0 0 100 100 16-Nov 267000 267000 267000 0 0 100 100 23-Nov 267000 267000 267000 0 0 100 100 30-Nov 267000 278000 267000 -11000 0 96 100 Comments Date: 30th Oct - Spend RM11K extra against budget - Amount of RM215K been spend earlier as planned CPI at 4%, under performanced with extra 11% spend Work completion as planned Proposed rectification if required Date: 30th Oct Rework the budget in more details to avoid unplanned cost incur Required to monitor the unplanned cost, if necessary required to replan or request Management budget required to avoid over spent from budget allocated 51
  • 52. Project Measurements and Control • Earned Value Management (EVM) – New Budget Allocation 52 WT25x40 RM543K Mould Press Punches Conveyor Belt System Packing Machine Corrugate Carton Box Brou- chures Display Rack Exhibition Booth & Event RM20K 4% RM32K 6% RM150K 28% RM65K 12% RM6K 1% RM40K 7% RM80K 15% RM100K 18% Supports - RM226K (42%)Input - RM267K (49%) Raw Materials RM50K 9% Unplanned – RM50K (9%)
  • 53. Project Measurements and Control • Cost/Schedule Graph 53
  • 54. Project Measurements and Control • Baselines and scope change 54
  • 55. • Monthly Status Report 55 Project Name: ACI New 25x40cm Wall Tiles Project Manager: Lim Shieh Chern Status as of: 30th October 2009 Status Summary: The project is on schedule. Seeking approval from management to approve unplanned raw material costs worth RM50,000. RM11,000 will be incurred in next month. Explanations: The project team had not taken into consideration some other factors during the initial planning of raw materials. A detailed calculation indicates that an additional allocation of RM 50,000 is needed. The allocation will be staggered over 2 months: RM 11,000 in November and RM 39,000 in December. The approval of this additional budget is crucial in order for the project to be carried out on schedule. Slight delay in the arrival of raw material will cause great impact to the manufacturing process and impede the entire workflow and allocation of the company’s resource. Total cost of approved changes: RM50,000. The amount is attributed to purchasing raw materials Projected cost at completion: EAC is estimated to be RM543,000. This represents an overrun of RM50,000, given a CPI of 0.91
  • 56. Conclusion • ACI Will allocate 2% of its existing production capacity for production • The capital expenditure is small at RM493,000 with anticipated extra reserve of RM50,000 • For FY09/10 unit selling price is budgeted at 25% lower or $18.75 Square Meters compare to current market price • The key risks are identified and scrutinized the severity. Contingency plans are in place to handle the unforeseen circumstances • NPC strongly recommends the new ceramic wall tiles 25x40 cm to be approved 56

Editor's Notes

  1. Project Implications
  2. Must meet WT25/40 to produce more than 90% of 1st grade Must enhance and optimize to launch the product before MALBEX 2010 It is acceptable and within tolerance level to utilize the budget allocated
  3. During this period, many architects, Interior designers, developers, contractors, dealers, and overseas visitors can visit our booth and get to know our new concepts tiles and tremendous business opportunities are definitely. ACI is ready to take orders from all the targeted customer segments and have sufficient goods available for minimum order of 200 square meters.
  4. Although, it will not pose major risk but may cause some hiccups
  5. Key Assessment Level 1 – Very Low 2 – Low 3 – Moderate 4 – High 5 – Very High