3. What is you Supply for cement for all the centres?
4. What is cost per ton to all the centers?NoidaGreaterNoidaGhaziabadNew DelhiSupplyKush khera2903103302401850Raas840960980890580Andhei-Dewari790810830740520Demand20015060020002900<br /> <br />These are the demand and suppy of shree cement from the three plants kush khera, Raas , Andheri.<br /> <br /> Software<br /> Software used to determine the transportation problem is Tora.<br />Facet of the data i.e Demand & Supply of cement per day per ton are:-<br />NoidaGreaterNoidaGhaziabadNew DelhiSupplyKush khera2903103306299207112000240-1143031751850000185001850Raas84097155-63520000200960127000-12701500015041529015748023000230980890-17145-952500580Andhei-Dewari79081041529055562537000370830-1143051244515000150740-171451016000520Demand48260127000020015240127000015035560127000060066675127000020002900<br /> <br /> <br />20 x x x<br />50 50 120 120<br />50 50 20 x<br />-112395025908000<br /> 500 500 500 500 <br />398780025273000 <br /> 50 150 150 150<br />29413201524000 50 150 150 x<br />294132027178000<br /> 840 960 980 x<br />169100528638500 <br /> 840 960 x x<br />78486027178000 <br /> 840 x x x<br />Therfore the initial basic feasible solution for the above mentioned transportation problem is mentioned below<br />240*1850 +840*200 + 960*150 +980*230 +830*370 +740*150 = Rs.13,99,500.<br />After putting these values which are rupees per day per ton <br />into tora we came into the result that the minimum cost of transporting cement from one ware house to supply depot is Rs.13,99,500<br /> <br /> <br /> <br /> <br /> <br /> Conclusion<br /> The entire case discusses about the cost incurred for the transportation of the goods from the source location to the destination location of SHREE CEMENT LTD. The objective of the project is to seek whether the cost incurred on the transportation is minimum or not. With the data provided by the company we were able to analyze on transportation model of SHREE CEMENT LTD is having the minimum transportation cost for transporting the goods. In the end it can be concluded that the solution that we have derived is best feasible solution, incurring the minimum cost on the transportation for moving goods from source to destination.<br />. <br /> Bibliography<br /> <br />www.shreecement.com<br />www.wikipedia.com<br />Operation Research by J.K.Sharma<br />................………………………END…………....……………............<br />