CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 1
UNIT-1
Introduction to
Construction
Management
Learning Outcomes
By the end of this unit the learner will be able to:
 Discuss the key features of the Constructionindustry
 Understand the Role of Construction Supervisor
 Describe the importance of Construction Supervision, Inspecting and Testing
Procedures.
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 2
Unit 1
Introduction to Construction Management
This unit presents a brief introduction to the construction industry. Construction is indeed one of the most
important Industries on earth, dating backing to the beginning of civilisation. The evidence is all around
us, serving as witnesses to the ingenuity of man. Some famous examples include the Pyramids of Egypt,
the Taj Mahal of India, Roman Amphitheatres of Italy, and the Great Wall of China.
Modern construction has evolved from simple manual techniques into a complex maze of highly
mechanised and orchestrated symphonies of activities, requiring billions of dollars in investment and
serving as the second biggest source of employment in the world. Construction involves many field
activities requiring the use of resources such as land, construction materials, labour, equipment and
energy, etc., to achieve a pre-defined objective of raising structures such as roads, buildings, dams and
just about any imaginable structure you will find around you.
Due to limited and very costly resources, construction has to be managed productively and efficiently
using innovation, creativity and sound organisational and economic principles. Properly managed
construction projects result in lower costs, completion of projects on time, and higher-quality structures.
In order to construct a successful organisational model for a successful construction project, it is
important to study and understand the various components that make up a successful model.
Construction activities must be cost-effective, using high-quality materials and performed within a limited
timeframe to achieve quality endproducts.
The face of the construction industry has been changing rapidly in recent times. These advancements in
modern construction methodologies and techniques, along with the emergence of more productive
equipment, mean that industry players must remain on their toes to keep up with the latest construction
technology. In order to remain relevant, companies must adopt new approaches to managing and building
projects. The growth in technology has produced newer and better materials to use, newer techniques of
accomplishing tasks at lower costs and with better time management skills, and newer equipment for
more productive work, etc. Therefore, the human resource capacity must constantly update or upgrade
knowledge and skills.
Market Size and its Importance
The achievements within the construction industry spanning thousands of years and involving a diversity
of civilisations have been immense. Construction has produced different types of infrastructure ranging
from small residential buildings to mega sports complexes and industrial buildings. Unsurprisingly, it
remains one of the largest businesses on the planet, with a market capitalisation of trillions of dollars.
Construction has contributed to most advanced economies of the world through the provision of critical
infrastructures of economic significance, especially in recent times. Investment in construction activities
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 3
contributes a sizeable portion of a country’s GDP, in terms of creating employment opportunities for
workers to earn decent incomes and contribute to the economy.
Some established countries in Asia, such as Hong Kong and South Korea, rode the benefits of construction
to attain their present level of economic success. China and Malaysia are following in their footsteps and
have been investing heavily in mega construction projects for the last 50 years or so. It is a very powerful
tool for development and economic progress.
Features of the Construction Industry
Some of the important features of the construction industry are described below:
Complexity
The modern construction industry is highly mechanised and complex; it involves complex interactions
between a vast array of resources, such as thousands of skilled labourers, equipment such as cranes and
earthmovers, logistics etc., all interconnected in thousands of activities. Activities may overlap
simultaneously or in sequential discrete steps or even randomly – a phenomenon more complex than
anything to be found in ordinary factories or manufacturing contexts.
Uniqueness
One way in which construction differs from other industries is the fact that no two projects are ever alike.
In other words, each project is unique. This uniqueness of each project is defined by the nature of the site
of construction and is also influenced by the weather and the ground conditions at each site location.
The construction supervisor and management team are critical to the success of every construction
project. They are responsible for ensuring that plans and specifications are adhered to and for managing
the limited resources available within the budget and delivering the complete project on time. Since
there is little room for costly mistakes, it is incumbent on the supervisory team to be vigilant to ensure
that mistakes are detected instantly and corrected immediately.
Mobility of Facilities
One major difference between the construction and mainstream manufacturing industries is that
products resulting from construction are stationary, while those resulting from manufacturing tend to be
mobile during value addition. The construction industry requires the movement of resources such as
labour, equipment etc. from one place to another to create products under dynamic and hazardous
working conditions. Manufacturing industries, on the other hand, require products at various stages of the
product life cycle to be moved from one facility to the next for value to be added. Products are
standardised and easy to control, unlike construction where new techniques or modifications to existing
techniques have to be developed to deal with the constantly changing working environment.
Multiplicity of Agencies
Many agencies are involved in construction projects, from the conception of the product through to the
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 4
completion of the project. Each agency is expected to play a specific role in the course of the project life
cycle. These agencies may include governmental agencies, land authorities, planning agencies, the fire
department, and Town and Country Planning Councils, etc. Their roles may differ but, essentially, they
ensure that the project complies with the laws of the land. They carry out inspections and provide
certifications for various activities on site.
Organisation
The owner of the construction project normally advertises the project and invites tenders from
prospective contractors to undertake the project. The contract is awarded to a successful bidder after a
competitive bid process. The winning contractor then engages the services of subcontractors on
contracts to execute various planned activities within a specified timeframe. Subcontractors may also
employ hundreds of skilled workers to work on specialised aspects of the project. During the
construction of larger-scale projects, it is very common to have thousands of employees working on
diverse aspects of the project site. The complexity of large-scale projects necessitates a great deal of
organisation and management of a large group of people who interact with one another in many ways to
produce the final product within a limited timeperiod.
Three groups of people are normally involved in a typical construction project:
These three groups interact in a well-organised way with no particular group having absolute control.
Each group has a set of unique functions to perform at specific moments and their activities may overlap
or occur sequentially. The owner is expected to exercise control of the finance and quality control, the
engineering group ensures structural and aesthetic integrity, while the contractor motivates the
workforce to execute the work professionally and to a very high standard to meet the deadline.
The main categories of activities of a construction project include:
 The owner
 The engineering group comprising managers, architects, structural engineers and civil engineers
etc.
 The construction group consisting of a number of contractors and workers who perform the
actual work.
i. Design and planning
ii. Executing construction work
iii. Supervision and inspection
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 5
Finance
Financial activities involved in construction can be classified into the following categories:
Funding sources include credit facilities, loans and securities. Frequently, the construction industry
experiences cash flow issues due to the blockage of security deposits, earnest-money, and delayed
payment of bills, among many other impediments.
Management
Since most companies’ HQs are far away from the project site, it becomes difficult for the management
to provide direct supervision and control of activities. This gives most projects’ workforces autonomy in
tackling their responsibilities. It is thus essential to have well-trained personnel who will execute their
mandated activities professionally and on time to achieve satisfactorily high-quality products.
Productivity and Labour Quality
Productivity
The construction industry is not as productive as other industries, according to several studies.
Historically, productivity in the construction industry has not been as high as one might have expected
given the large number of people employed in this sector. Two main reasons may account for this low
productivity:
 Supply issues
 Demand issues
Supply is hampered by the immobile nature of projects and the harsh conditions prevailing during the
construction process. With regard to demand issues, one finds that demand for construction products
tends to be seasonal or cyclic, resulting in a highly unpredictable market.
The lack of adequately-trained personnel is the single most important factor in low productivity records.
The availability of well-trained personnel to make wise decisions in executing activities becomes very
important for producing high-quality products. Highly trained human resources are lacking in areas that
1. Investments in fixed assets, such as tools, equipment, machinery, catering and shuttering,etc.
2. Short-term finances, such as earnest-money and security deposits to meet the cash flow
requirements at construction sites
3. Investment in the future through education, training, research, and development of human
resources and technologies
4. Overheads in salaries and establishment of other expenses relating to advertisements and public
relations, legal expenses and other related expenses required for the project torun smoothly
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 6
would substantially improve construction productivity. Areas such as effective information management
systems and design and equipment management are both in dire need of high-quality personnel.
Better productivity might be achieved through systematic planning and management of all aspects of
construction projects using highly trained human resources at all levels as well as the best available
techniques and equipment to produce quality products at lower cost and in shorter durations.
Management and organisation of projects will entail coordination of interactions between the planning,
design and execution stages of projects.
Labour Quality
Labour for construction work mostly depends upon the location of the project site. This means that the
local workforce is normally employed to carry out various aspects of the construction. The quality of the
labour employed will determine the quality of the final product. Workers may improve their skills
through on-the-job learning, by trial and error, or by imitation.
Safety Hazards
A typical construction project is inherently dangerous because of the high propensity for accidents to
occur. The wide range of working conditions involving supported structures, moving equipment and
labour make the site a highly unpredictable environment. Consequently, there is a need to put in place
safety measures to prevent accidents from occurring. Unfortunately, due to the rapidly changing
conditions, it is not sufficient to adopt safety procedures from the static manufacturing environment for
implementation on construction project sites.
Careful and adequate research needs to be conducted to determine the most effective types of safety
procedure to implement on the site because losses resulting from construction accidents may be so
significant that they will even wipe out profits.
Role of Construction Supervisor
The main duty of the construction supervisor is to motivate and coordinate the activities of other
workers to complete the job on time. Supervisors serve as the link between workers and top
management levels of the organisation. They operate at the first line of management. There are three
levels of management: the top-level, the mid-level, and the first-line level.
Top-Level Management
They formulate the objectives and policies of the company.
Mid-Level Management
They are mostly involved in the procurement of materials, labour and equipment management. They
may also be responsible for highly specialised duties such as lift installation and HVAC.
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 7
First-Line Management
This level is usually composed of the construction supervisors. It is the lowest level of management,
taking instructions from the mid-level and reporting back to them during the course of construction.
Responsibilities of the Construction Supervisor
The responsibilities of the construction supervisor include ensuring that all work is of the desired quality,
costs do not overrun the budget due to errors, and the work is completed on time.
Duties of Construction Supervisor
Construction Supervisor and the Phases of Construction Project
The construction supervisor should be familiar with the various phases of the project. The following
phases are normally devised for construction projects:
Project construction sites can be executed by the owner or by a contractor. Construction by the owner is
termed ‘departmental construction’. It requires the owner to form his own company and engage the
services of an engineer and contractor. The second method is to employ the services of contractors. The
contractor-type construction involves both the owner and the contractor appointing their individual
supervisors to oversee the project.
The owner’s supervisor must ensure that all specifications and plans are being followed by undertaking
regular planned or unplanned inspections of activities on the site. His responsibilities include the
following:
i) Ensure that construction is carried out according to the contract drawings andspecifications
ii) Ensure that the contractor follows the agreed schedule
 Instructs workers on what to do
 Motivates workers to accomplish all objectives
 Encourages a spirit of teamwork
 Ensures workers are disciplined
 Deal with all manner of conflicts arising at the worksite
 Promotes a good relationship between the workers and the generalpublic
 Ensures plans and schedules are adhered to by regular inspectionand quality control
 Trains and develops the workforce to meet newchallenges
 Conception of the building based on requirements of the owner oruser
 Determining the feasibility of the project and comparingalternatives
 Preparing detailed designs, drawings, and resource cost estimates
 Translating construction ideas from paper into reality usingresources.
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 8
iii) Ensure that quality standards of materials, processes and workmanship aremaintained
Supervision for the Owner/Consultant
The owner’s supervisor can achieve success in the field by doing the following:
 Submit daily progress reports to the owner’s engineer
 Work with the contractor’s team frequently
 Clarify any aspects of the work that the contractor does not understand or is unsure about
 Demand the highest-quality standards from thecontractor
 Deal discreetly and fairly but resolutely with the contractor’s staff in the field on all aspects of the
work to ensure high-quality work
 Solve problems commensurate with his/her expertise and escalate them to the site engineer
when problems are beyond his/her ability to solve or will require the supervision of more senior
personnel
 Take timely actions to correct deviations from plans
 Report serious problems to the site engineerimmediately
 Use discretion and professionalism when implementing contract specifications but receive
occasional advice from the site’s engineer and work within the limits of his/her responsibility and
authority
 Be tactful or diplomatic when dealing with field staff
 Maintain proper documentation including registers, equipment documents and labour
documents, etc.
 Keep a work order book containing instructions from management to thecontractor
 Request early inspection and approval of completed portions of work to avoiddelays
 Help the engineer to prepare accounts and issue payments to the contractor
 Maintain all contract documents such as drawings and specifications at each phase of theproject
Supervision for the Construction Agency
If the owner decides to secure the services of a construction agency to undertake the project with the
assistance of a construction supervisor, the construction agency must ensure that the structure is
completed on time, at the agreed cost and to the specified quality standard.
Before beginning construction activities, the supervisor for the construction agency should ensure that:
 All drawings are ready, including detailed working drawings
 Detailed bills of quantities are available
 Information on all resources required are available and ready
 Suppliers and workers are ready to begin
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 9
 Execution plans for activities are developed and milestones and completion datesfinalised
 The project manager and his team of engineers have been selected to oversee technical aspects
of the project
For a supervisor to succeed comprehensively with a project, he/she must study and understand all
contract requirements, designs, drawings and specifications and any other relevant documents. He/she
must also study the programme of construction prepared by the project engineer and his team and
devise realistic schedules for activities for each day of the week or a weekly schedule to keep up with the
overall project plan
Sample of a supervisor's schedule for a typical day:
Table 1.1
Supervisor's Schedule for a Typical Day
1. Brick masonry for the superstructure of Building 1 to becontinued
2. Excavation for the foundation of Building 2 to be started today. Labour team to be
organised, instructions to be given to them, necessary tools to beissued
3. Excavation work should he completed by tomorrow evening; make request to the field
engineer to inspect the work tomorrow and approve the foundation so that laying the
concrete bed for the foundation can commence in two days’time
4. Send a requisition to the store to supply cement, to place an order for a supply of sand and
aggregates so that these materials can be delivered to the site by tomorrowevening.
5. Request the project office to supply the working drawings of RCC slab to help estimate
resource requirements
6. Send a note to the accounts department to arrange for the payment of wages to labourers
at the end of the week
7. Submit reports to the project office
The above list of activities is not exhaustive and should be seen as of an indicative nature only.
The supervisor should ensure that the following facilities are available on the site:
i. Site offices, site stores, workshops and canteens, etc. along with the necessary furniture,
ventilation and lighting, etc.
ii. Access to the site, as well as various units such as site office, stores, and workshops, etc.
iii. Adequate parking facilities and unloading platforms for incomingmaterials
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 10
iv. Toilets suitably located - separate toilets for women
v. Adequate supply of water for drinking, washing and constructionoperations
vi. Arrangements for regular cleaning of office, stores, canteen etc
vii. Ensuring adequate safety precautions on site by:
a) Promoting safe stacking of materials
b) Encouraging safe handling of materials
c) Insisting on the use of protective wear such as helmets, gloves, gumboots and goggles
where necessary
d) Providing fencing around excavated trenches
e) Ensuring good housekeeping on site
f) Providing first-aid boxes
g) Employing trained workers and operators
h) Ensuring proper maintenance of equipment
i) Providing training to workers and creating safety awareness amongst them
The supervisor should maintain documents containing thefollowing:
 File containing list of contact details of all persons connected to the project including details of the
owner(s), officials of local authorities, Government officials, suppliers, police department etc.
 Folder for approved drawings andspecifications
 Contract documents
 Construction programme (e.g. in the form of a bar chart)
 Files containing important letters
 Work order book
 Progress chart
 Registers for materials, use of equipment, labouremployed
 Record of tests carried out on materials and works
 A general plan of work showing all work completed each day 
Daily diary containing the following:
 Details of works in progress
 Notes on weather conditions
 Names of visitors
 Number of hours worked
 Details of work carried out by subcontractors, labour contractors,
 Workers employed on work site
 Materials arrived; issued to subcontractors, consumed onworks
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 11
 Equipment details such as hours worked, fuel or power used, repairsand
maintenance output etc.
 Any other relevant details.
Construction Supervision and Inspection and Testing
The supervisor is expected to carry out inspection and testing continuously from the beginning of the
project until its completion.
Inspection
This is carried out in order to check the quality. Construction materials may be inspected to ensure they
meet quality specifications in terms of colour, size and composition. Inspections may be carried out while
work is in progress to ensure that:
i. The correct quantities of materials areused
ii. The sequence specified by the activities schedule plan is beingfollowed
iii. Correct procedures are applied during activities to ensure high-qualitystandards
iv. Final output of activities meets the desired specifications in dimensions andcontents
The right person (at the right time) should be chosen to carry out the inspection in order for the
inspection programme to be successful.
Supervisors are required to perform regular inspections of construction work. For contract jobs, the
owner may ask his engineer to inspect the work to ensure everything is going according to plan and
within budget. Inspections are carried out on materials and can be performed at any stage of the work. If
the contract stipulates that certain phases must be inspected by the engineer, the supervisor must
arrange for this well in advance and record details of the inspection in the work order book. To avoid
remedial work or the rejection of work, the supervisor must be pre-emptive to spot mistakes quite early
and report to the necessary authority to correct them immediately. Such prompt actions will prevent
unnecessary delays due to remedial work or rejection and will avoid extra costs.
Construction Supervisor's Role in Ensuring Progress
The construction supervisor is directly responsible for ensuring that progress is made according to
schedules. It is his/her duty to ensure that progress is consistently maintained by doing the following:
 Studying the construction programme prepared by the project manager or project engineer.
 Preparing detailed programmes to expand on the schedules and preparing schedules for
organising the resources required for the work.
 Having in place a systematic approach to writing daily progressreports.
 Ensuring that all specifications and requirements of the project are beingfollowed.
CONSTRUCTION MANAGEMENT
Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 12
 The supervisor must also regularly check the quality of work and compare it with quality control
specifications to determine whether the project is on the right track or not. He/she should correct
any deviations promptly if he/she is in a position to do so; otherwise, deviations should be
reported to the site engineer immediately for prompt corrective measures to be implemented.
Further Reading:
 Barbara J. Jackson (2016), Construction ManagementJumpStart
 Stephen Emmitt, Christopher A. Gorse (2010), Barry's Introduction to
Construction of Buildings
 Frank Harris, Ronald McCaffer (2020), Modern ConstructionManagement

Recomendados

CSQS ch 1, 2& 3 lec. note.pdf por
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfDejeneTsegaye6
3 vistas72 diapositivas
Essay Construction por
Essay ConstructionEssay Construction
Essay ConstructionCustom Paper Writing Services
9 vistas21 diapositivas
CONSTRUCTION MANAGEMENT por
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTAishwarya Phalke
366 vistas14 diapositivas
SRI AARUTHRAA CONSTRUCTION por
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONVijayfan2
5 vistas5 diapositivas
SRI AARUTHRAA CONSTRUCTION por
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONVijayfan2
9 vistas4 diapositivas
SRI AARUTHRAA CONSTRUCTION por
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONVijayfan2
6 vistas4 diapositivas

Más contenido relacionado

Similar a 1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf

Construction Project Essay por
Construction Project EssayConstruction Project Essay
Construction Project EssayAshley Thomas
3 vistas154 diapositivas
Classification & Construction Type. por
Classification & Construction Type.Classification & Construction Type.
Classification & Construction Type.faizanNoor8
437 vistas10 diapositivas
Risks And Challenges Of Indian Construction Industry por
Risks And Challenges Of Indian Construction IndustryRisks And Challenges Of Indian Construction Industry
Risks And Challenges Of Indian Construction IndustryLaurie Gunlicks
4 vistas40 diapositivas
Reinforce your working domain with leading-edge BIM training and skills to th... por
Reinforce your working domain with leading-edge BIM training and skills to th...Reinforce your working domain with leading-edge BIM training and skills to th...
Reinforce your working domain with leading-edge BIM training and skills to th...nibtedu
21 vistas7 diapositivas
BIM based organizational learning por
BIM based organizational learningBIM based organizational learning
BIM based organizational learningIJRES Journal
281 vistas9 diapositivas
Slow Productivity In Construction Industry por
Slow Productivity In Construction IndustrySlow Productivity In Construction Industry
Slow Productivity In Construction IndustryJessica Anderson
4 vistas44 diapositivas

Similar a 1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf(20)

Classification & Construction Type. por faizanNoor8
Classification & Construction Type.Classification & Construction Type.
Classification & Construction Type.
faizanNoor8437 vistas
Risks And Challenges Of Indian Construction Industry por Laurie Gunlicks
Risks And Challenges Of Indian Construction IndustryRisks And Challenges Of Indian Construction Industry
Risks And Challenges Of Indian Construction Industry
Laurie Gunlicks4 vistas
Reinforce your working domain with leading-edge BIM training and skills to th... por nibtedu
Reinforce your working domain with leading-edge BIM training and skills to th...Reinforce your working domain with leading-edge BIM training and skills to th...
Reinforce your working domain with leading-edge BIM training and skills to th...
nibtedu21 vistas
BIM based organizational learning por IJRES Journal
BIM based organizational learningBIM based organizational learning
BIM based organizational learning
IJRES Journal281 vistas
Slow Productivity In Construction Industry por Jessica Anderson
Slow Productivity In Construction IndustrySlow Productivity In Construction Industry
Slow Productivity In Construction Industry
Jessica Anderson4 vistas
Mechanized Construction- Relevance and Importance in India por JIT KUMAR GUPTA
Mechanized Construction- Relevance and Importance in IndiaMechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in India
JIT KUMAR GUPTA1.1K vistas
Role and Importance of Prefrication in Promoting Sustainable Built Environment por JIT KUMAR GUPTA
Role and Importance of Prefrication in Promoting Sustainable Built EnvironmentRole and Importance of Prefrication in Promoting Sustainable Built Environment
Role and Importance of Prefrication in Promoting Sustainable Built Environment
JIT KUMAR GUPTA76 vistas
Benefits Offsite Production For A Construction Project por Ashley Cornett
Benefits Offsite Production For A Construction ProjectBenefits Offsite Production For A Construction Project
Benefits Offsite Production For A Construction Project
Ashley Cornett2 vistas
Unit 1 basics of construction por SANJEEV Wazir
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
SANJEEV Wazir818 vistas
Lean Construction And The Construction Process por Krystal Ellison
Lean Construction And The Construction ProcessLean Construction And The Construction Process
Lean Construction And The Construction Process
Krystal Ellison4 vistas
Construction project management por Senthil Kannan
Construction project managementConstruction project management
Construction project management
Senthil Kannan3.4K vistas
Constructionprojectmanagement Amit Payal por AMIT PAYAL
Constructionprojectmanagement Amit PayalConstructionprojectmanagement Amit Payal
Constructionprojectmanagement Amit Payal
AMIT PAYAL11 vistas
Economics of project evaluation for reference cpm module2 por ahsanrabbani
Economics of project evaluation for reference cpm module2Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2
ahsanrabbani196 vistas
Construction industry por Shahrukh Niaz
Construction industryConstruction industry
Construction industry
Shahrukh Niaz1.7K vistas
International Journal of Engineering and Science Invention (IJESI) por inventionjournals
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
inventionjournals284 vistas

Más de ahsansaeed78

Dynamics of Structures - A K Chopra - Solutions Manual.pdf por
Dynamics of Structures - A K Chopra - Solutions Manual.pdfDynamics of Structures - A K Chopra - Solutions Manual.pdf
Dynamics of Structures - A K Chopra - Solutions Manual.pdfahsansaeed78
24 vistas536 diapositivas
1661351030Unit 4 1056-V1 Equipment Management.pdf por
1661351030Unit 4 1056-V1 Equipment Management.pdf1661351030Unit 4 1056-V1 Equipment Management.pdf
1661351030Unit 4 1056-V1 Equipment Management.pdfahsansaeed78
3 vistas13 diapositivas
1661351057Unit 5 1057-V1 Material Management.pdf por
1661351057Unit 5 1057-V1 Material Management.pdf1661351057Unit 5 1057-V1 Material Management.pdf
1661351057Unit 5 1057-V1 Material Management.pdfahsansaeed78
2 vistas18 diapositivas
1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select... por
1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select...1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select...
1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select...ahsansaeed78
2 vistas14 diapositivas
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf por
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdfahsansaeed78
3 vistas16 diapositivas
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf por
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdfahsansaeed78
4 vistas12 diapositivas

Más de ahsansaeed78(12)

Dynamics of Structures - A K Chopra - Solutions Manual.pdf por ahsansaeed78
Dynamics of Structures - A K Chopra - Solutions Manual.pdfDynamics of Structures - A K Chopra - Solutions Manual.pdf
Dynamics of Structures - A K Chopra - Solutions Manual.pdf
ahsansaeed7824 vistas
1661351030Unit 4 1056-V1 Equipment Management.pdf por ahsansaeed78
1661351030Unit 4 1056-V1 Equipment Management.pdf1661351030Unit 4 1056-V1 Equipment Management.pdf
1661351030Unit 4 1056-V1 Equipment Management.pdf
ahsansaeed783 vistas
1661351057Unit 5 1057-V1 Material Management.pdf por ahsansaeed78
1661351057Unit 5 1057-V1 Material Management.pdf1661351057Unit 5 1057-V1 Material Management.pdf
1661351057Unit 5 1057-V1 Material Management.pdf
ahsansaeed782 vistas
1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select... por ahsansaeed78
1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select...1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select...
1661351014Unit 2 1053-V1 Preliminary Investigations- Location and Site Select...
ahsansaeed782 vistas
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf por ahsansaeed78
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
ahsansaeed783 vistas
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf por ahsansaeed78
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
ahsansaeed784 vistas
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf por ahsansaeed78
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
ahsansaeed784 vistas
1586001978CONSTRUCTION ASSESSMENT 8.pdf por ahsansaeed78
1586001978CONSTRUCTION ASSESSMENT 8.pdf1586001978CONSTRUCTION ASSESSMENT 8.pdf
1586001978CONSTRUCTION ASSESSMENT 8.pdf
ahsansaeed783 vistas
1586001946CONSTRUCTION ASSESSMENT 7.pdf por ahsansaeed78
1586001946CONSTRUCTION ASSESSMENT 7.pdf1586001946CONSTRUCTION ASSESSMENT 7.pdf
1586001946CONSTRUCTION ASSESSMENT 7.pdf
ahsansaeed782 vistas
1586001946CONSTRUCTION ASSESSMENT 7 (1).pdf por ahsansaeed78
1586001946CONSTRUCTION ASSESSMENT 7 (1).pdf1586001946CONSTRUCTION ASSESSMENT 7 (1).pdf
1586001946CONSTRUCTION ASSESSMENT 7 (1).pdf
ahsansaeed783 vistas
PPTX-Genigraphics-Poster-Template-A0.pptx por ahsansaeed78
PPTX-Genigraphics-Poster-Template-A0.pptxPPTX-Genigraphics-Poster-Template-A0.pptx
PPTX-Genigraphics-Poster-Template-A0.pptx
ahsansaeed7823 vistas
ECS_Expo_Poster_Template.pptx por ahsansaeed78
ECS_Expo_Poster_Template.pptxECS_Expo_Poster_Template.pptx
ECS_Expo_Poster_Template.pptx
ahsansaeed782 vistas

Último

DESIGN OF SPRINGS-UNIT4.pptx por
DESIGN OF SPRINGS-UNIT4.pptxDESIGN OF SPRINGS-UNIT4.pptx
DESIGN OF SPRINGS-UNIT4.pptxgopinathcreddy
19 vistas47 diapositivas
Proposal Presentation.pptx por
Proposal Presentation.pptxProposal Presentation.pptx
Proposal Presentation.pptxkeytonallamon
29 vistas36 diapositivas
Advances in micro milling: From tool fabrication to process outcomes por
Advances in micro milling: From tool fabrication to process outcomesAdvances in micro milling: From tool fabrication to process outcomes
Advances in micro milling: From tool fabrication to process outcomesShivendra Nandan
7 vistas18 diapositivas
sam_software_eng_cv.pdf por
sam_software_eng_cv.pdfsam_software_eng_cv.pdf
sam_software_eng_cv.pdfsammyigbinovia
5 vistas5 diapositivas
MK__Cert.pdf por
MK__Cert.pdfMK__Cert.pdf
MK__Cert.pdfHassan Khan
10 vistas1 diapositiva
Digital Watermarking Of Audio Signals.pptx por
Digital Watermarking Of Audio Signals.pptxDigital Watermarking Of Audio Signals.pptx
Digital Watermarking Of Audio Signals.pptxAyushJaiswal781174
12 vistas25 diapositivas

Último(20)

Proposal Presentation.pptx por keytonallamon
Proposal Presentation.pptxProposal Presentation.pptx
Proposal Presentation.pptx
keytonallamon29 vistas
Advances in micro milling: From tool fabrication to process outcomes por Shivendra Nandan
Advances in micro milling: From tool fabrication to process outcomesAdvances in micro milling: From tool fabrication to process outcomes
Advances in micro milling: From tool fabrication to process outcomes
Shivendra Nandan7 vistas
Introduction to CAD-CAM.pptx por suyogpatil49
Introduction to CAD-CAM.pptxIntroduction to CAD-CAM.pptx
Introduction to CAD-CAM.pptx
suyogpatil495 vistas
_MAKRIADI-FOTEINI_diploma thesis.pptx por fotinimakriadi
_MAKRIADI-FOTEINI_diploma thesis.pptx_MAKRIADI-FOTEINI_diploma thesis.pptx
_MAKRIADI-FOTEINI_diploma thesis.pptx
fotinimakriadi8 vistas
What is Whirling Hygrometer.pdf por IIT KHARAGPUR
What is Whirling Hygrometer.pdfWhat is Whirling Hygrometer.pdf
What is Whirling Hygrometer.pdf
IIT KHARAGPUR 12 vistas
Effect of deep chemical mixing columns on properties of surrounding soft clay... por AltinKaradagli
Effect of deep chemical mixing columns on properties of surrounding soft clay...Effect of deep chemical mixing columns on properties of surrounding soft clay...
Effect of deep chemical mixing columns on properties of surrounding soft clay...
AltinKaradagli6 vistas
fakenews_DBDA_Mar23.pptx por deepmitra8
fakenews_DBDA_Mar23.pptxfakenews_DBDA_Mar23.pptx
fakenews_DBDA_Mar23.pptx
deepmitra814 vistas
zincalume water storage tank design.pdf por 3D LABS
zincalume water storage tank design.pdfzincalume water storage tank design.pdf
zincalume water storage tank design.pdf
3D LABS5 vistas

1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf

  • 1. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 1 UNIT-1 Introduction to Construction Management Learning Outcomes By the end of this unit the learner will be able to:  Discuss the key features of the Constructionindustry  Understand the Role of Construction Supervisor  Describe the importance of Construction Supervision, Inspecting and Testing Procedures.
  • 2. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 2 Unit 1 Introduction to Construction Management This unit presents a brief introduction to the construction industry. Construction is indeed one of the most important Industries on earth, dating backing to the beginning of civilisation. The evidence is all around us, serving as witnesses to the ingenuity of man. Some famous examples include the Pyramids of Egypt, the Taj Mahal of India, Roman Amphitheatres of Italy, and the Great Wall of China. Modern construction has evolved from simple manual techniques into a complex maze of highly mechanised and orchestrated symphonies of activities, requiring billions of dollars in investment and serving as the second biggest source of employment in the world. Construction involves many field activities requiring the use of resources such as land, construction materials, labour, equipment and energy, etc., to achieve a pre-defined objective of raising structures such as roads, buildings, dams and just about any imaginable structure you will find around you. Due to limited and very costly resources, construction has to be managed productively and efficiently using innovation, creativity and sound organisational and economic principles. Properly managed construction projects result in lower costs, completion of projects on time, and higher-quality structures. In order to construct a successful organisational model for a successful construction project, it is important to study and understand the various components that make up a successful model. Construction activities must be cost-effective, using high-quality materials and performed within a limited timeframe to achieve quality endproducts. The face of the construction industry has been changing rapidly in recent times. These advancements in modern construction methodologies and techniques, along with the emergence of more productive equipment, mean that industry players must remain on their toes to keep up with the latest construction technology. In order to remain relevant, companies must adopt new approaches to managing and building projects. The growth in technology has produced newer and better materials to use, newer techniques of accomplishing tasks at lower costs and with better time management skills, and newer equipment for more productive work, etc. Therefore, the human resource capacity must constantly update or upgrade knowledge and skills. Market Size and its Importance The achievements within the construction industry spanning thousands of years and involving a diversity of civilisations have been immense. Construction has produced different types of infrastructure ranging from small residential buildings to mega sports complexes and industrial buildings. Unsurprisingly, it remains one of the largest businesses on the planet, with a market capitalisation of trillions of dollars. Construction has contributed to most advanced economies of the world through the provision of critical infrastructures of economic significance, especially in recent times. Investment in construction activities
  • 3. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 3 contributes a sizeable portion of a country’s GDP, in terms of creating employment opportunities for workers to earn decent incomes and contribute to the economy. Some established countries in Asia, such as Hong Kong and South Korea, rode the benefits of construction to attain their present level of economic success. China and Malaysia are following in their footsteps and have been investing heavily in mega construction projects for the last 50 years or so. It is a very powerful tool for development and economic progress. Features of the Construction Industry Some of the important features of the construction industry are described below: Complexity The modern construction industry is highly mechanised and complex; it involves complex interactions between a vast array of resources, such as thousands of skilled labourers, equipment such as cranes and earthmovers, logistics etc., all interconnected in thousands of activities. Activities may overlap simultaneously or in sequential discrete steps or even randomly – a phenomenon more complex than anything to be found in ordinary factories or manufacturing contexts. Uniqueness One way in which construction differs from other industries is the fact that no two projects are ever alike. In other words, each project is unique. This uniqueness of each project is defined by the nature of the site of construction and is also influenced by the weather and the ground conditions at each site location. The construction supervisor and management team are critical to the success of every construction project. They are responsible for ensuring that plans and specifications are adhered to and for managing the limited resources available within the budget and delivering the complete project on time. Since there is little room for costly mistakes, it is incumbent on the supervisory team to be vigilant to ensure that mistakes are detected instantly and corrected immediately. Mobility of Facilities One major difference between the construction and mainstream manufacturing industries is that products resulting from construction are stationary, while those resulting from manufacturing tend to be mobile during value addition. The construction industry requires the movement of resources such as labour, equipment etc. from one place to another to create products under dynamic and hazardous working conditions. Manufacturing industries, on the other hand, require products at various stages of the product life cycle to be moved from one facility to the next for value to be added. Products are standardised and easy to control, unlike construction where new techniques or modifications to existing techniques have to be developed to deal with the constantly changing working environment. Multiplicity of Agencies Many agencies are involved in construction projects, from the conception of the product through to the
  • 4. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 4 completion of the project. Each agency is expected to play a specific role in the course of the project life cycle. These agencies may include governmental agencies, land authorities, planning agencies, the fire department, and Town and Country Planning Councils, etc. Their roles may differ but, essentially, they ensure that the project complies with the laws of the land. They carry out inspections and provide certifications for various activities on site. Organisation The owner of the construction project normally advertises the project and invites tenders from prospective contractors to undertake the project. The contract is awarded to a successful bidder after a competitive bid process. The winning contractor then engages the services of subcontractors on contracts to execute various planned activities within a specified timeframe. Subcontractors may also employ hundreds of skilled workers to work on specialised aspects of the project. During the construction of larger-scale projects, it is very common to have thousands of employees working on diverse aspects of the project site. The complexity of large-scale projects necessitates a great deal of organisation and management of a large group of people who interact with one another in many ways to produce the final product within a limited timeperiod. Three groups of people are normally involved in a typical construction project: These three groups interact in a well-organised way with no particular group having absolute control. Each group has a set of unique functions to perform at specific moments and their activities may overlap or occur sequentially. The owner is expected to exercise control of the finance and quality control, the engineering group ensures structural and aesthetic integrity, while the contractor motivates the workforce to execute the work professionally and to a very high standard to meet the deadline. The main categories of activities of a construction project include:  The owner  The engineering group comprising managers, architects, structural engineers and civil engineers etc.  The construction group consisting of a number of contractors and workers who perform the actual work. i. Design and planning ii. Executing construction work iii. Supervision and inspection
  • 5. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 5 Finance Financial activities involved in construction can be classified into the following categories: Funding sources include credit facilities, loans and securities. Frequently, the construction industry experiences cash flow issues due to the blockage of security deposits, earnest-money, and delayed payment of bills, among many other impediments. Management Since most companies’ HQs are far away from the project site, it becomes difficult for the management to provide direct supervision and control of activities. This gives most projects’ workforces autonomy in tackling their responsibilities. It is thus essential to have well-trained personnel who will execute their mandated activities professionally and on time to achieve satisfactorily high-quality products. Productivity and Labour Quality Productivity The construction industry is not as productive as other industries, according to several studies. Historically, productivity in the construction industry has not been as high as one might have expected given the large number of people employed in this sector. Two main reasons may account for this low productivity:  Supply issues  Demand issues Supply is hampered by the immobile nature of projects and the harsh conditions prevailing during the construction process. With regard to demand issues, one finds that demand for construction products tends to be seasonal or cyclic, resulting in a highly unpredictable market. The lack of adequately-trained personnel is the single most important factor in low productivity records. The availability of well-trained personnel to make wise decisions in executing activities becomes very important for producing high-quality products. Highly trained human resources are lacking in areas that 1. Investments in fixed assets, such as tools, equipment, machinery, catering and shuttering,etc. 2. Short-term finances, such as earnest-money and security deposits to meet the cash flow requirements at construction sites 3. Investment in the future through education, training, research, and development of human resources and technologies 4. Overheads in salaries and establishment of other expenses relating to advertisements and public relations, legal expenses and other related expenses required for the project torun smoothly
  • 6. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 6 would substantially improve construction productivity. Areas such as effective information management systems and design and equipment management are both in dire need of high-quality personnel. Better productivity might be achieved through systematic planning and management of all aspects of construction projects using highly trained human resources at all levels as well as the best available techniques and equipment to produce quality products at lower cost and in shorter durations. Management and organisation of projects will entail coordination of interactions between the planning, design and execution stages of projects. Labour Quality Labour for construction work mostly depends upon the location of the project site. This means that the local workforce is normally employed to carry out various aspects of the construction. The quality of the labour employed will determine the quality of the final product. Workers may improve their skills through on-the-job learning, by trial and error, or by imitation. Safety Hazards A typical construction project is inherently dangerous because of the high propensity for accidents to occur. The wide range of working conditions involving supported structures, moving equipment and labour make the site a highly unpredictable environment. Consequently, there is a need to put in place safety measures to prevent accidents from occurring. Unfortunately, due to the rapidly changing conditions, it is not sufficient to adopt safety procedures from the static manufacturing environment for implementation on construction project sites. Careful and adequate research needs to be conducted to determine the most effective types of safety procedure to implement on the site because losses resulting from construction accidents may be so significant that they will even wipe out profits. Role of Construction Supervisor The main duty of the construction supervisor is to motivate and coordinate the activities of other workers to complete the job on time. Supervisors serve as the link between workers and top management levels of the organisation. They operate at the first line of management. There are three levels of management: the top-level, the mid-level, and the first-line level. Top-Level Management They formulate the objectives and policies of the company. Mid-Level Management They are mostly involved in the procurement of materials, labour and equipment management. They may also be responsible for highly specialised duties such as lift installation and HVAC.
  • 7. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 7 First-Line Management This level is usually composed of the construction supervisors. It is the lowest level of management, taking instructions from the mid-level and reporting back to them during the course of construction. Responsibilities of the Construction Supervisor The responsibilities of the construction supervisor include ensuring that all work is of the desired quality, costs do not overrun the budget due to errors, and the work is completed on time. Duties of Construction Supervisor Construction Supervisor and the Phases of Construction Project The construction supervisor should be familiar with the various phases of the project. The following phases are normally devised for construction projects: Project construction sites can be executed by the owner or by a contractor. Construction by the owner is termed ‘departmental construction’. It requires the owner to form his own company and engage the services of an engineer and contractor. The second method is to employ the services of contractors. The contractor-type construction involves both the owner and the contractor appointing their individual supervisors to oversee the project. The owner’s supervisor must ensure that all specifications and plans are being followed by undertaking regular planned or unplanned inspections of activities on the site. His responsibilities include the following: i) Ensure that construction is carried out according to the contract drawings andspecifications ii) Ensure that the contractor follows the agreed schedule  Instructs workers on what to do  Motivates workers to accomplish all objectives  Encourages a spirit of teamwork  Ensures workers are disciplined  Deal with all manner of conflicts arising at the worksite  Promotes a good relationship between the workers and the generalpublic  Ensures plans and schedules are adhered to by regular inspectionand quality control  Trains and develops the workforce to meet newchallenges  Conception of the building based on requirements of the owner oruser  Determining the feasibility of the project and comparingalternatives  Preparing detailed designs, drawings, and resource cost estimates  Translating construction ideas from paper into reality usingresources.
  • 8. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 8 iii) Ensure that quality standards of materials, processes and workmanship aremaintained Supervision for the Owner/Consultant The owner’s supervisor can achieve success in the field by doing the following:  Submit daily progress reports to the owner’s engineer  Work with the contractor’s team frequently  Clarify any aspects of the work that the contractor does not understand or is unsure about  Demand the highest-quality standards from thecontractor  Deal discreetly and fairly but resolutely with the contractor’s staff in the field on all aspects of the work to ensure high-quality work  Solve problems commensurate with his/her expertise and escalate them to the site engineer when problems are beyond his/her ability to solve or will require the supervision of more senior personnel  Take timely actions to correct deviations from plans  Report serious problems to the site engineerimmediately  Use discretion and professionalism when implementing contract specifications but receive occasional advice from the site’s engineer and work within the limits of his/her responsibility and authority  Be tactful or diplomatic when dealing with field staff  Maintain proper documentation including registers, equipment documents and labour documents, etc.  Keep a work order book containing instructions from management to thecontractor  Request early inspection and approval of completed portions of work to avoiddelays  Help the engineer to prepare accounts and issue payments to the contractor  Maintain all contract documents such as drawings and specifications at each phase of theproject Supervision for the Construction Agency If the owner decides to secure the services of a construction agency to undertake the project with the assistance of a construction supervisor, the construction agency must ensure that the structure is completed on time, at the agreed cost and to the specified quality standard. Before beginning construction activities, the supervisor for the construction agency should ensure that:  All drawings are ready, including detailed working drawings  Detailed bills of quantities are available  Information on all resources required are available and ready  Suppliers and workers are ready to begin
  • 9. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 9  Execution plans for activities are developed and milestones and completion datesfinalised  The project manager and his team of engineers have been selected to oversee technical aspects of the project For a supervisor to succeed comprehensively with a project, he/she must study and understand all contract requirements, designs, drawings and specifications and any other relevant documents. He/she must also study the programme of construction prepared by the project engineer and his team and devise realistic schedules for activities for each day of the week or a weekly schedule to keep up with the overall project plan Sample of a supervisor's schedule for a typical day: Table 1.1 Supervisor's Schedule for a Typical Day 1. Brick masonry for the superstructure of Building 1 to becontinued 2. Excavation for the foundation of Building 2 to be started today. Labour team to be organised, instructions to be given to them, necessary tools to beissued 3. Excavation work should he completed by tomorrow evening; make request to the field engineer to inspect the work tomorrow and approve the foundation so that laying the concrete bed for the foundation can commence in two days’time 4. Send a requisition to the store to supply cement, to place an order for a supply of sand and aggregates so that these materials can be delivered to the site by tomorrowevening. 5. Request the project office to supply the working drawings of RCC slab to help estimate resource requirements 6. Send a note to the accounts department to arrange for the payment of wages to labourers at the end of the week 7. Submit reports to the project office The above list of activities is not exhaustive and should be seen as of an indicative nature only. The supervisor should ensure that the following facilities are available on the site: i. Site offices, site stores, workshops and canteens, etc. along with the necessary furniture, ventilation and lighting, etc. ii. Access to the site, as well as various units such as site office, stores, and workshops, etc. iii. Adequate parking facilities and unloading platforms for incomingmaterials
  • 10. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 10 iv. Toilets suitably located - separate toilets for women v. Adequate supply of water for drinking, washing and constructionoperations vi. Arrangements for regular cleaning of office, stores, canteen etc vii. Ensuring adequate safety precautions on site by: a) Promoting safe stacking of materials b) Encouraging safe handling of materials c) Insisting on the use of protective wear such as helmets, gloves, gumboots and goggles where necessary d) Providing fencing around excavated trenches e) Ensuring good housekeeping on site f) Providing first-aid boxes g) Employing trained workers and operators h) Ensuring proper maintenance of equipment i) Providing training to workers and creating safety awareness amongst them The supervisor should maintain documents containing thefollowing:  File containing list of contact details of all persons connected to the project including details of the owner(s), officials of local authorities, Government officials, suppliers, police department etc.  Folder for approved drawings andspecifications  Contract documents  Construction programme (e.g. in the form of a bar chart)  Files containing important letters  Work order book  Progress chart  Registers for materials, use of equipment, labouremployed  Record of tests carried out on materials and works  A general plan of work showing all work completed each day  Daily diary containing the following:  Details of works in progress  Notes on weather conditions  Names of visitors  Number of hours worked  Details of work carried out by subcontractors, labour contractors,  Workers employed on work site  Materials arrived; issued to subcontractors, consumed onworks
  • 11. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 11  Equipment details such as hours worked, fuel or power used, repairsand maintenance output etc.  Any other relevant details. Construction Supervision and Inspection and Testing The supervisor is expected to carry out inspection and testing continuously from the beginning of the project until its completion. Inspection This is carried out in order to check the quality. Construction materials may be inspected to ensure they meet quality specifications in terms of colour, size and composition. Inspections may be carried out while work is in progress to ensure that: i. The correct quantities of materials areused ii. The sequence specified by the activities schedule plan is beingfollowed iii. Correct procedures are applied during activities to ensure high-qualitystandards iv. Final output of activities meets the desired specifications in dimensions andcontents The right person (at the right time) should be chosen to carry out the inspection in order for the inspection programme to be successful. Supervisors are required to perform regular inspections of construction work. For contract jobs, the owner may ask his engineer to inspect the work to ensure everything is going according to plan and within budget. Inspections are carried out on materials and can be performed at any stage of the work. If the contract stipulates that certain phases must be inspected by the engineer, the supervisor must arrange for this well in advance and record details of the inspection in the work order book. To avoid remedial work or the rejection of work, the supervisor must be pre-emptive to spot mistakes quite early and report to the necessary authority to correct them immediately. Such prompt actions will prevent unnecessary delays due to remedial work or rejection and will avoid extra costs. Construction Supervisor's Role in Ensuring Progress The construction supervisor is directly responsible for ensuring that progress is made according to schedules. It is his/her duty to ensure that progress is consistently maintained by doing the following:  Studying the construction programme prepared by the project manager or project engineer.  Preparing detailed programmes to expand on the schedules and preparing schedules for organising the resources required for the work.  Having in place a systematic approach to writing daily progressreports.  Ensuring that all specifications and requirements of the project are beingfollowed.
  • 12. CONSTRUCTION MANAGEMENT Copyrights © CPD (Courses for Professional Development). All Rights Reserved. Unit 1050-V1 Page 12  The supervisor must also regularly check the quality of work and compare it with quality control specifications to determine whether the project is on the right track or not. He/she should correct any deviations promptly if he/she is in a position to do so; otherwise, deviations should be reported to the site engineer immediately for prompt corrective measures to be implemented. Further Reading:  Barbara J. Jackson (2016), Construction ManagementJumpStart  Stephen Emmitt, Christopher A. Gorse (2010), Barry's Introduction to Construction of Buildings  Frank Harris, Ronald McCaffer (2020), Modern ConstructionManagement