The document outlines guidelines for customers to change their power supply from R-Infra to Tata Power, including filling out an application form and providing documents like proof of ownership/identity and latest energy bills. It provides the application processing fees and lists the Tata Power centers where customers can submit applications along with operating hours and addresses. The notes section provides additional information on tariffs, billing units, exemption certificates, and contact details.
Food processing presentation for bsc agriculture hons
Guidelines Tata Power changeover supply R-Infra
1. Given below are the guidelines for availing changeover of Power Supply from R-Infra to Tata Power :
1. Power Supply Application Form (PSAF) needs to be filled up and submitted to any of 1. Power Supply Application Form (PSAF) needs to be filled up and submitted to any of
the Tata Power Centers as listed in Annexure-1. the Tata Power Centers as listed in Annexure-1.
(Forms are available at all centres mentioned in Annexure-1). (Forms are available at all centres mentioned in Annexure-1).
2. The application form to be accompanied by : 2. The application form to be accompanied by :
a) Proof of Ownership or Occupation of Premises - As per Annexure-2 a) Proof of Ownership or Occupation of Premises - As per Annexure-2
b) Proof of Identity - As per Annexure-3 b) Proof of Identity (Authorised Signatory) - As per Annexure-3
c) Photocopy of latest paid R-Infra energy bills (front & back side) c) Photocopy of latest paid R-Infra energy bills (front & back side)
d) Power Supply Agreement (PSA) for sanctioned load of 50 KW / 63KVA & above
(refer PSA Format)
e) Photocopy of PAN Card of Organization
Category Rate Rs. Per KW / KVA
Sanctioned Load / Contract Demand
Residential 200/- (Two Hundred)
LT Industries 500/- (Five Hundred)
LT Commercial / Temporary supply 1000/- (One Thousand)
HT Industrial 1200/- (One Thousand Two Hundred)
HT Commercial / Temporary supply 1500/- (One Thousand Five Hundred)
NOTES :
a) Tata Power approved tariff along with applicable wheeling charges are attached herewith for f) Power Supply Application Form (PSAF) for Power Supply for Common services (example -
ready reference (Ref. Annexure - 4). Lift, Staircase, Compound, Garden, Water Pump, Gymnasium etc. in Societies is to be accompained by
b) Units billed shall be computed on energy consumed + wheeling losses as prescribed by MERC = Society Registration / Society PAN Card Copy
from time to time (Ref. Annexure - 4). Eg. meter showing consumption of 100 Units, Billing = Written application on society letter head with sign and stamp
Units shall be 109.90 Units for LT Consumers. = of Latest paid R-Infra energy bill (front and back) along with payment proof.
Photo Copy
c) In case an entire society wishes to changeover then individual (PSAF) forms for every Flat / = Proof of Identity of Authorised Signatory.
Gala / Unit Owner along with documents mentioned in point 2 above need to be submitted. g) To avail Electricity Duty exemption kindly provide Electricity Duty exemption eligibility certificate
d) It is recommended that the document may be submitted completed in all respects at least along with the necessary documents from relevant authority in favour of Tata Power.
7 (seven) working days prior to next meter reading date as mentioned in Reliance Energy bill. h) Please do provide your Mobile Number & Email Address to enable us to send you instant SMS &
e) Applicant may issue single cheque for combined amount of Security Deposit and Application Emails regarding your application status & processing, billing details and such value added services.
processing charges for each application. Cheques to be drawn in favour of “The Tata Power Company Limited”. Please be assured that the same will not be shared with any other entity or be used adversely.
i) Photocopies of the documents to be submitted along with the application should be self attested.