Se ha denunciado esta presentación.
Se está descargando tu SlideShare. ×

Earned value management

Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Anuncio
Próximo SlideShare
Earned value management
Earned value management
Cargando en…3
×

Eche un vistazo a continuación

1 de 22 Anuncio

Earned value management

Descargar para leer sin conexión

Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of the project management triangle:

Scope
Schedule, and
Costs

In a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.

Early EVM research showed that the areas of planning and control are significantly impacted by its use; and similarly, using the methodology improves both scope definition as well as the analysis of overall project performance. More recent research studies have shown that the principles of EVM are positive predictors of project success.[1] Popularity of EVM has grown in recent years beyond government contracting, in which sector its importance continues to rise[2] (e.g., recent new DFARS rules[3]), in part because EVM can also surface in and help substantiate contract disputes.[4]

Essential features of any EVM implementation include

a project plan that identifies work to be accomplished,
a valuation of planned work, called Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS), and
pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work, called Earned Value (EV) or Budgeted Cost of Work Performed (BCWP).

EVM implementations for large or complex projects include many more features, such as indicators and forecasts of cost performance (over budget or under budget) and schedule performance (behind schedule or ahead of schedule). However, the most basic requirement of an EVM system is that it quantifies progress using PV and EV

Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of the project management triangle:

Scope
Schedule, and
Costs

In a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.

Early EVM research showed that the areas of planning and control are significantly impacted by its use; and similarly, using the methodology improves both scope definition as well as the analysis of overall project performance. More recent research studies have shown that the principles of EVM are positive predictors of project success.[1] Popularity of EVM has grown in recent years beyond government contracting, in which sector its importance continues to rise[2] (e.g., recent new DFARS rules[3]), in part because EVM can also surface in and help substantiate contract disputes.[4]

Essential features of any EVM implementation include

a project plan that identifies work to be accomplished,
a valuation of planned work, called Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS), and
pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work, called Earned Value (EV) or Budgeted Cost of Work Performed (BCWP).

EVM implementations for large or complex projects include many more features, such as indicators and forecasts of cost performance (over budget or under budget) and schedule performance (behind schedule or ahead of schedule). However, the most basic requirement of an EVM system is that it quantifies progress using PV and EV

Anuncio
Anuncio

Más Contenido Relacionado

Presentaciones para usted (20)

A los espectadores también les gustó (20)

Anuncio

Similares a Earned value management (20)

Anuncio

Más reciente (20)

Earned value management

  1. 1. EARNED VALUE MANAGEMENT ASHIF A R ashifmsd@gmail.com Ph No. - 9745350127
  2. 2. INTRODUCTION • Project management technique for measuring project progress in an objective manner. • Combine measurements of scope, schedule, and cost in a single integrated system. • Provides an early warning of performance problems. • Improve • the definition of project scope, • prevent scope creep, • communicate objective progress to stakeholders, • keep the project team focused on achieving progress.
  3. 3. Elements of Project Control • Creation of a Baseline Schedule • Measurement of Performance • Effective Corrective Actions
  4. 4. Project Monitoring
  5. 5. Project Monitoring • Planning and scheduling play an important role in project management • But without monitoring the project, chances of completing the project on schedule is difficult • Two parameters are monitored • Cost • Time • The following graph shows the Time-cost relationship for a project
  6. 6. Project Monitoring Cost Cost over-run with schedule Time Time over-run Ideal Curve This graph shows Project Progress
  7. 7. Concepts of Earned Value
  8. 8. Concept of Earned Value • Consider the following example: • Wall construction Wall is divided into 4 sections For 4-sections - 100 man-hours are required Hence if 2-sections are completed, (2/4) × 100 = 50 man-hours • We say that 50 man-hours have been EARNED • The actual man-hours spent to construct these two sections can be more than or less than the EarnedValue of man-hours
  9. 9. Concept of Earned Value • Wall construction If 4 sections cost Rs. 1000/- then the cost of constructing 2 sections = Rs. 500/- We say that Rs. 500/- is the EARNED value of money The actual cost incurred in constructing these two sections can be more than or less than the Earned Value of money It is important to note that Earned Value is based on the Actual quantities installed or Actual quantity of work done Hence output is considered in the Earned Value concept
  10. 10. Concept of Earned Value • Calculation of Earned Value • Earned Value of man-hours or money for an activity can be calculated as follows:
  11. 11. Components of Earned Value
  12. 12. Components of Earned value Analysis • Budgeted Cost ofWork Scheduled (BCWS) • It is the budgeted cost of work scheduled to be performed • It is also called the Planned Value (PV) • It tells how much work have been completed
  13. 13. Components of Earned value Analysis • Budgeted Cost ofWork Performed (BCWP) • It is the budgeted cost of work actually performed • The Earned Value for the work actually completed • It tells how much work is actually completed
  14. 14. Components of Earned value Analysis • Actual Cost ofWork Performed (ACWP) • It is the amount actually spent on the work completed • This could be more or less than the Earned Value
  15. 15. Components of Earned value Analysis • Scheduled Variance (SC) • It compares work completed vs work planned • It helps to identify whether the project is ahead or behind schedule • Negative value indicated that the project is behind schedule
  16. 16. Components of Earned value Analysis • Scheduled Performance Index (SPI) • It helps to identify whether the project is ahead or behind schedule • Less than 1 indicates that the project is behind schedule • It can be used to forecast how long it will take for the project to complete
  17. 17. Components of Earned value Analysis • Cost Variance (CV) • It compares what was planned to be spent on the work completed vs. what was actually spent • It helps to identify whether the project is ahead or behind schedule • Negative value indicates that the project is over budget
  18. 18. Components of Earned value Analysis • Cost Performance Index (CPI) • It helps to identify weather the project is above or below budget • Less than 1 means the project is over budget • It can be utilised to forecast how much amount will be required to complete the project
  19. 19. Components of Earned value Analysis • Budget at Completion (BAC) • It is the amount that was originally budgeted to complete the project
  20. 20. Components of Earned value Analysis • Estimate at Completion (EAC) • It is the estimated amount required to complete the project
  21. 21. Components of Earned value Analysis http://www.iceincusa.com/16CSP/content/4_ev/gifs/image1.gif (17.01.2007)

×