Welcome to ….
NEC4 : The good, the bad & the ugly.
Part 1 : Contract strategy changes
Presenter :
Jon Broome
jon@leadingedgeprojects.co.uk www.jonbroome.com
+44 (0) 07970 428 929
setting | projects
up for | success
leading edge
projects consulting ltd
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Objectives
For both Part 1 and Part 2 :
 To identify and review the changes made as well as
highlighting changes that have not been made.
 To express an opinion on what is good (most of the changes);
bad (really ‘could do better') & ugly (the few clangers they have dropped).
 Part 1 focusses on “the contract strategy changes”
e.g. new members of the family, main & secondary options, including
dispute clauses.
 Part 2 focusses on “changes to the Engineering &
Construction Contract (ECC)” with attention on the payment,
programme, early warning and compensation event clauses.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Agenda for Part 1
1. A very little bit about me
2. Quick Overview of NEC’s original objectives
3. Objectives for the fourth edition.
4. Two changes in terminology
5. New members of the family
6. Changes to the main payment options
7. Changes to the ‘W’ dispute options
8. Changes to secondary options
9. Some other changes across the family.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
A very little bit about me & NEC.
 Genuine NEC Geek.
 Involvement in NEC goes back 20+ years
 Contributions to 2nd & 3rd editions of full
Engineering & Construction Contract (ECC)
acknowledged.
 Authored top selling ‘NEC3 : A User’s Guide’
 Led development of NEC3 Professional Services
Short Contract with other members of C&P SIG.
 Co-authored bi’s on-line NEC3&4® Academy
NEC3® & NEC4® are registered trademarks of ICE Publishing
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Clients have / do
include …
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
NEC’s 3 original objectives
Stimulus to Good
project Management
Clarity
& Simplicity Flexibility
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Flexibility
Purpose : to promote easy selection of ‘best fit’
contracting strategy for Package’s circumstances
 Whole family of interlocking contracts for works,
goods & services.
 Similar structure & terminology across whole family
to promote ease of learning and ‘back to back’ness
for process integration and contractual cover.
 Modular structure within each ‘long’ contract, so
that can rapidly assemble ‘best fit’ commercial
arrangement without expensive legal input.
 Any extent of Contractor design in ECC; can alter
testing requirements etc.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Clarity & Simplicity
Purpose : to promote ease of understanding at ‘doer’ level &
so reduce disputes due to misunderstanding or omissions
 Simple & common structure across whole family leads to
ease of finding way around any contract
 Flow charting to ensure logic : hints at process of project
management
 Shorter sentence length & use of bullet points
 Less subjectivity: preciser definitions; roles &
responsibilities; risk allocation & rules for assessing the
quantum of compensation events(claims & variations).
 ECC is about a third of the length of traditional contracts
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Stimulus to good project management
Purpose : Range of contractual mechanisms and incentives to
promote collaborative project management, thereby increasing
predictability of time, cost & quality being delivered.
For example :
 Strong emphasis on detailed updated agreed programme
 Early warning of issues and process for resolution
 More defined criteria & process for rapid resolution of time & cost
affects of compensation events
 All actions have a timescale attached to them often with a
sanctions / stimulus if not done
 Separate & more defined Roles & Responsibilities within contract,
especially ECC : Project Manager, Supervisor, Adjudicator.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Objectives for the 4th edition
 inspire increased use of NEC in new
markets and sectors.
 support new approaches to procurement
which improve contract management
 provide greater stimulus to good project
management.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Context of
comments
 Very easy to criticise what others have done.
 So put any negative comments in context :
o most of what has changed is for the GOOD.
o NEC3 is already a good contract.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Two changes in terminology
These apply across the family :
 ‘Employer’ becomes ‘Client’ as more commonly
accepted across sectors
 Works / Service / Goods Information all
become ‘Scope’ : avoids need for generic
statements when subcontracting.
Both are ‘GOOD’ changes.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
 Engineering and Construction Contract (ECC)
 Engineering and Construction Subcontract (ECS)
 Engineering and Construction Short Contract (ECSC)
 Engineering and Construction Short Subcontract (ECSS)
 Professional Service Contract (PSC)
 Professional Service Short Contract (PSSC)
 Professional Service Subcontract (PSS) - NEW
 Term Service Contract (TSC)
 Term Service Short Contract (TSSC)
 Term Service Subcontract (TSS) - NEW
 Design, Build and Operate Contract (DBOC) - NEW
 Supply Contract (SC)
 Supply Short Contract (SSC)
 Dispute Resolution Service Contract (DSRC) - NEWLY NAMED
 Framework Contract (FC) and
 Alliancing Contract (consultative) - NEW.
The NEC4 family of contracts :
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changes to the Family
 The GOOD : Two new subcontracts – the PSS
and TSS – as reduces the need to amend main
contracts.
 The Could do Better : Subcontracts for
compatible short versions of these contracts.
 The GOOD : the DBO contract as :
o saves having to have an extra over-arching
agreement which ties D, B & O together.
o encourages use of a Finance+DBO contract
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Alliance Contractual Framework
Sub
Consultants
Principal
Consultants
Sub
Contractors
Principal
Contractors
Sub
Suppliers
Principal
Suppliers
Client
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
3 forms of Alliance :
Simple Alliance
 Enacted under NEC 3 & 4 through option X12.
 Re-named ‘Multiparty Collaboration’ option where:
o set of X12 add-on clauses to individual contracts;
o covers Core Group, Partnering Information and KPI’s
against which positive only incentives can be set;
o high level extra clauses for early warnings, joint
timetable (programme) & a compensation event for
changes to the Partnering Information.
o easiest to put in place as only upside for ‘Partners’.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
3 forms of Alliance :
Pure / Australian Alliance
 NEW Alliancing Contract (Consultative) where :
o one multi-party contract
o very similar in structure to other members of family
o covers joint down-side liabilities
o all ‘Partners’ sign the same contract at the same
time, which is hard – technically & legally - to make
happen
o allows for two stage engagement with Stage One
being on a cost-plus basis e.g. development of
Scope & Prices
o also hardest form of alliance to get one party out.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
3 forms of Alliance :
Traditional Alliance
 Where all alliance members have traditional works and
service contracts.
 Usually cost-based, but not always e.g. where most
costs incurred in a factory; more fit for purpose /
circumstance individual contractual relationship vs. one size fits all.
 Over-arching alliance contract ties fortunes to result of
overall project, whether good & bad.
 Easier to add members as individual Scope reaches
maturity and easier to get rid of if under-performing
e.g. can get out of Alliance but keep works contract.
 No NEC4 traditional alliancing contract.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changes to the main payment options
 Professional Service Contract (PSC) has lost
‘option G : Term Contract’.
 Often a Client want a consultant to provide a base level
of service for a period of time, with the ability to
instruct additional Tasks for minor projects as & when
required without having to put new contract in place.
 NEC publishers say use Term Service Contract
(TSC), but you need an Affected Property, insurance is
different etc. so would need to do multitude of tweaks.
 Far easier to update NEC3 PSC Option G to be
compatible with NEC4 PSC.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changes to the ‘W’ Dispute options
 W1 and W2 are in NEC3 and for Adjudication. W2 is for the
UK and W1 for the rest of the world.
 In NEC4, both options now have Senior Representatives
before you get to Adjudication. In W1 it is mandatory,
whereas in W2 it can’t be and isn’t.
 New to NEC4, is W3 : The Dispute Avoidance Board
o who are 1 or 3 experienced people who keep in touch
with the contract;
o if a potential dispute arises, they try to help resolve it,
then make recommendation;
o Parties have to refer a dispute to it before going onto
adjudication, so is not compliant with Construction Acts.
BUT could have easily tweaked it, as W4, to be UK
compliant.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
? Questions so far ?
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changes to the ‘X’ Clauses.
 ‘X8 : Undertakings to the Client or Others’ : Previously
no X8 in ECC, but ‘Collateral Warranties’ in PSC. Like that :
o broadens scope of what is covered i.e. not just CW’s
o is now in ECC and TSC .
 New ‘X9 : Transfer of rights’ in ECC for material
developed for contact as per NEC3 PSC.
 New ‘X10 : Information Modelling’ replaces ’Employer’s
Agent’ in NEC3 PSC as :
o NEC4 PSC now has a Service Manager.
o allows for broader application than BIM
o Guidance Notes on BIM for NEC3 were vapid and BIM
Protocol is a contractual car crash waiting to happen.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changed ‘X15 : Contractor’s design’
 ECC always allowed for any extent of Contractor design,
but previous X15 only limited Contractor’s liability down
to ‘reasonable skill and care’ and correction of Defects .
 New X15 does above and
o covers Professional Indemnity insurance
o changes wording to that which insurance industry
comfortable with
o changes burden of proof onto Client
o covers IP ownership of material
o period for retention of material.
 Would have liked to have seen similar X provisions in
ECSC & ECSS to make into an ‘intermediate’ contract for
simple design.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changes to the ‘X’ Clauses.
 Inclusion of ‘X22 : Early Contractor
Involvement’ and ‘Y(UK)1 : Project Bank
Account’ from consultative documents / separate
addendums.
 New ‘X21 : Whole life cost’ where Contractor
may propose an idea which reduces wlc and gets a
share of wlc savings … but would like to have
o seen proportions stated in CD,
o whole life value (benefit/wlc) clause
o what happens if PM/Client steals ’similar’ idea ?
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Changes to the ‘X’ Clauses.
 No change to ‘X1 : Price adjustment for inflation’. When
used, an almost universal amendment is to set periods when
the adjustment made e.g. annually, not when an indices
changes.
 ‘X4 : Ultimate Holding Company Guarantee’ has
changed from ‘Parent Company Guarantee’. The UHC could
be an offshore hard to get to company. Better to have one
you can get to.
 ‘X18 : Limitation of Liability’ still contains a ‘total liability’
cap which has four types of damages or negative incentives
as ‘excluded matters’. So not really a ‘total liability’ !
 ‘X22 : Early Contractor Involvement’ doesn’t have
specific termination provisions if the Client does not proceed
from Stage 1 to 2 with same Contractor.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Some other changes across the family
 A Schedule of Cost Components for all ‘long’ forms,
although have reservations for calculating People
costs under PSC
 Schedule includes Subcontractor costs.
 Tidying up of Subcontractor definition to exclude
labour only / agency staff.
 NEC4 Section 8 is now ‘Liabilities and Insurance’ vs
‘Risks and Insurance’.
 Not so sure about listing out “Client’s liabilities”
and then “Contractor’s liabilities”. What happens if
an event is in neither or could be in both ?
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
To finish on a GOOD note x3
In ‘long’ forms, really like :
 greater emphasis on Contractor putting forward
proposals e.g. wlc’s, value engineering and acceleration
 the prod to use cloud-based NEC communication
systems as almost hard-wire in contractually compliant
responses and make it evident who is operating the
contract & who isn’t – see ECC clause 13.2;
 that, when not accepting a communication, the Project
Manager or equivalent has to not just state contractual
reason for not accepting, but also give “sufficient detail
to enable the Contractor to correct the matter” - see
ECC clause 13.4
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Summary of Part 1
 mainly GOOD
 COULD DO BETTER’s are mainly
tweaks which have not been done,
except for not having a Traditional
Alliance Contract
 No real UGLIES yet, although getting
rid of option G : Term Contract of
the PSC comes close.
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
? Final Questions ?
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Next week
Focus on provisions within ECC for
 Payment
 Programme
 Early warnings
 Compensation events
… but similar provisions in all ‘long’ forms.
APOLOGIES
©
2017
+44(0)7970 428 929
jon@leadingedgeprojects.co.uk
www.jonbroome.com
Link to raise questions for Part 2 :
Changes to the Engineering &
Construction Contract (ECC)
http://bit.ly/2mqHPI6
This presentation was delivered
at an APM webinar
To find out more about
upcoming webinars please visit
our website
www.apm.org.uk/events

Más contenido relacionado

La actualidad más candente

NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...Association for Project Management
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
NEC4 Project Manager Accreditation Post-training Arrangement
NEC4 Project Manager Accreditation Post-training ArrangementNEC4 Project Manager Accreditation Post-training Arrangement
NEC4 Project Manager Accreditation Post-training ArrangementLetty Ma
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 

La actualidad más candente (20)

NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
NEC Engineering and Construction Short Contract (ECSC) webinar
NEC Engineering and Construction Short Contract (ECSC) webinarNEC Engineering and Construction Short Contract (ECSC) webinar
NEC Engineering and Construction Short Contract (ECSC) webinar
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
NEC4 Project Manager Accreditation Post-training Arrangement
NEC4 Project Manager Accreditation Post-training ArrangementNEC4 Project Manager Accreditation Post-training Arrangement
NEC4 Project Manager Accreditation Post-training Arrangement
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 

Similar a NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webinar, 14 November 2017

What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...Association for Project Management
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...Association for Project Management
 
[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...
[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...
[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...SirionLabs
 
Increase Limits Option Article copy (2)
Increase Limits Option Article copy (2)Increase Limits Option Article copy (2)
Increase Limits Option Article copy (2)Matthew Copus
 
The importance of using contracts in seo
The importance of using contracts in seoThe importance of using contracts in seo
The importance of using contracts in seoramone_johnny
 
SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...
SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...
SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...SirionLabs
 
The Communication Management Plan ( Cmp )
The Communication Management Plan ( Cmp )The Communication Management Plan ( Cmp )
The Communication Management Plan ( Cmp )Serena Brown
 
Corporate Contracts Case Studies
Corporate Contracts Case StudiesCorporate Contracts Case Studies
Corporate Contracts Case StudiesBrad Simpson
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 
Neojurix contract management
Neojurix contract managementNeojurix contract management
Neojurix contract managementNehaa Satalkar
 
IFRS 15 is coming: prepare now
IFRS 15 is coming: prepare nowIFRS 15 is coming: prepare now
IFRS 15 is coming: prepare nowQuantiQ Technology
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017Browne Jacobson LLP
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfTarigTaha3
 

Similar a NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webinar, 14 November 2017 (20)

What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 
[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...
[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...
[SirionLabs Webinar] Faster Contracts, Better Contracts: Eliminating the Fric...
 
Practitioner class 3: Contract strategy
Practitioner class 3: Contract strategyPractitioner class 3: Contract strategy
Practitioner class 3: Contract strategy
 
Increase Limits Option Article copy (2)
Increase Limits Option Article copy (2)Increase Limits Option Article copy (2)
Increase Limits Option Article copy (2)
 
Agile contracting- APM Contracts and Procurement SIG, July 2016
Agile contracting- APM Contracts and Procurement SIG, July 2016Agile contracting- APM Contracts and Procurement SIG, July 2016
Agile contracting- APM Contracts and Procurement SIG, July 2016
 
The importance of using contracts in seo
The importance of using contracts in seoThe importance of using contracts in seo
The importance of using contracts in seo
 
SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...
SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...
SirionLabs Webinar Featuring Forrester - Why Modern Contract Management is a ...
 
The Communication Management Plan ( Cmp )
The Communication Management Plan ( Cmp )The Communication Management Plan ( Cmp )
The Communication Management Plan ( Cmp )
 
Corporate Contracts Case Studies
Corporate Contracts Case StudiesCorporate Contracts Case Studies
Corporate Contracts Case Studies
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Neojurix contract management
Neojurix contract managementNeojurix contract management
Neojurix contract management
 
IFRS 15 is coming: prepare now
IFRS 15 is coming: prepare nowIFRS 15 is coming: prepare now
IFRS 15 is coming: prepare now
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Agile contracts
Agile contractsAgile contracts
Agile contracts
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
 
BIM and IPD
BIM and IPDBIM and IPD
BIM and IPD
 
Bkozlowski wpa
Bkozlowski wpaBkozlowski wpa
Bkozlowski wpa
 

Más de Association for Project Management

Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...
Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...
Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...Association for Project Management
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakAssociation for Project Management
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Association for Project Management
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Association for Project Management
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Association for Project Management
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...Association for Project Management
 
APM Wessex Branch: Soft Skills Training for Project Management – harder than ...
APM Wessex Branch: Soft Skills Training for Project Management – harder than ...APM Wessex Branch: Soft Skills Training for Project Management – harder than ...
APM Wessex Branch: Soft Skills Training for Project Management – harder than ...Association for Project Management
 
Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Association for Project Management
 
Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...
Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...
Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...Association for Project Management
 
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Association for Project Management
 
Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...
Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...
Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...Association for Project Management
 

Más de Association for Project Management (20)

Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...
Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...
Programme of the Year Winner: La Autoridad para Reconstruccion con Cambios (A...
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peak
 
Demystifying digital accessibility webinar
Demystifying digital accessibility webinarDemystifying digital accessibility webinar
Demystifying digital accessibility webinar
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...
 
Burnout_ Prevention Intervention Recovery.pdf
Burnout_ Prevention Intervention  Recovery.pdfBurnout_ Prevention Intervention  Recovery.pdf
Burnout_ Prevention Intervention Recovery.pdf
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...
 
Risk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threatRisk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threat
 
Time-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA LeadersTime-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA Leaders
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
 
Including mental health support in project delivery
Including mental health support in project deliveryIncluding mental health support in project delivery
Including mental health support in project delivery
 
Sustainability in Project Management – what you need to know
Sustainability in Project Management – what you need to knowSustainability in Project Management – what you need to know
Sustainability in Project Management – what you need to know
 
APM Wessex Branch: Soft Skills Training for Project Management – harder than ...
APM Wessex Branch: Soft Skills Training for Project Management – harder than ...APM Wessex Branch: Soft Skills Training for Project Management – harder than ...
APM Wessex Branch: Soft Skills Training for Project Management – harder than ...
 
Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Steve Maclaren - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
 
Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...
Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...
Martin Paver - APM Scotland Branch Conference 2023: Net Zero Nation and Susta...
 
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
 
Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...
Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...
Dr Karen Thompson - APM Scotland Branch Conference 2023: Net Zero Nation and ...
 

Último

Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024Stephan Koning
 
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)tazeenaila12
 
MoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor PresentationMoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor Presentationbaron83
 
Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...
Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...
Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...IMARC Group
 
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfTalent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfCharles Cotter, PhD
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Lviv Startup Club
 
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...AustraliaChapterIIBA
 
Upgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsUpgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsIntellect Design Arena Ltd
 
To Create Your Own Wig Online To Create Your Own Wig Online
To Create Your Own Wig Online  To Create Your Own Wig OnlineTo Create Your Own Wig Online  To Create Your Own Wig Online
To Create Your Own Wig Online To Create Your Own Wig Onlinelng ths
 
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...Khaled Al Awadi
 
Project Brief & Information Architecture Report
Project Brief & Information Architecture ReportProject Brief & Information Architecture Report
Project Brief & Information Architecture Reportamberjiles31
 
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...TalentView
 
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGUNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGlokeshwarmaha
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsWristbands Ireland
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access
 
Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..dlewis191
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyHanna Klim
 
Lecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toLecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toumarfarooquejamali32
 
Entrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsEntrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsP&CO
 
Live-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarLive-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarNathanielSchmuck
 

Último (20)

Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
 
MoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor PresentationMoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor Presentation
 
Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...
Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...
Boat Trailers Market PPT: Growth, Outlook, Demand, Keyplayer Analysis and Opp...
 
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfTalent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)
 
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
 
Upgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsUpgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking Applications
 
To Create Your Own Wig Online To Create Your Own Wig Online
To Create Your Own Wig Online  To Create Your Own Wig OnlineTo Create Your Own Wig Online  To Create Your Own Wig Online
To Create Your Own Wig Online To Create Your Own Wig Online
 
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
 
Project Brief & Information Architecture Report
Project Brief & Information Architecture ReportProject Brief & Information Architecture Report
Project Brief & Information Architecture Report
 
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
 
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGUNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and Festivals
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024
 
Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agency
 
Lecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toLecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb to
 
Entrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsEntrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizations
 
Live-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarLive-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry Webinar
 

NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webinar, 14 November 2017

  • 1. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Welcome to …. NEC4 : The good, the bad & the ugly. Part 1 : Contract strategy changes Presenter : Jon Broome jon@leadingedgeprojects.co.uk www.jonbroome.com +44 (0) 07970 428 929 setting | projects up for | success leading edge projects consulting ltd
  • 2. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Objectives For both Part 1 and Part 2 :  To identify and review the changes made as well as highlighting changes that have not been made.  To express an opinion on what is good (most of the changes); bad (really ‘could do better') & ugly (the few clangers they have dropped).  Part 1 focusses on “the contract strategy changes” e.g. new members of the family, main & secondary options, including dispute clauses.  Part 2 focusses on “changes to the Engineering & Construction Contract (ECC)” with attention on the payment, programme, early warning and compensation event clauses.
  • 3. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Agenda for Part 1 1. A very little bit about me 2. Quick Overview of NEC’s original objectives 3. Objectives for the fourth edition. 4. Two changes in terminology 5. New members of the family 6. Changes to the main payment options 7. Changes to the ‘W’ dispute options 8. Changes to secondary options 9. Some other changes across the family.
  • 4. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com A very little bit about me & NEC.  Genuine NEC Geek.  Involvement in NEC goes back 20+ years  Contributions to 2nd & 3rd editions of full Engineering & Construction Contract (ECC) acknowledged.  Authored top selling ‘NEC3 : A User’s Guide’  Led development of NEC3 Professional Services Short Contract with other members of C&P SIG.  Co-authored bi’s on-line NEC3&4® Academy NEC3® & NEC4® are registered trademarks of ICE Publishing
  • 6. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com NEC’s 3 original objectives Stimulus to Good project Management Clarity & Simplicity Flexibility
  • 7. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Flexibility Purpose : to promote easy selection of ‘best fit’ contracting strategy for Package’s circumstances  Whole family of interlocking contracts for works, goods & services.  Similar structure & terminology across whole family to promote ease of learning and ‘back to back’ness for process integration and contractual cover.  Modular structure within each ‘long’ contract, so that can rapidly assemble ‘best fit’ commercial arrangement without expensive legal input.  Any extent of Contractor design in ECC; can alter testing requirements etc.
  • 8. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Clarity & Simplicity Purpose : to promote ease of understanding at ‘doer’ level & so reduce disputes due to misunderstanding or omissions  Simple & common structure across whole family leads to ease of finding way around any contract  Flow charting to ensure logic : hints at process of project management  Shorter sentence length & use of bullet points  Less subjectivity: preciser definitions; roles & responsibilities; risk allocation & rules for assessing the quantum of compensation events(claims & variations).  ECC is about a third of the length of traditional contracts
  • 9. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Stimulus to good project management Purpose : Range of contractual mechanisms and incentives to promote collaborative project management, thereby increasing predictability of time, cost & quality being delivered. For example :  Strong emphasis on detailed updated agreed programme  Early warning of issues and process for resolution  More defined criteria & process for rapid resolution of time & cost affects of compensation events  All actions have a timescale attached to them often with a sanctions / stimulus if not done  Separate & more defined Roles & Responsibilities within contract, especially ECC : Project Manager, Supervisor, Adjudicator.
  • 10. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Objectives for the 4th edition  inspire increased use of NEC in new markets and sectors.  support new approaches to procurement which improve contract management  provide greater stimulus to good project management.
  • 11. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Context of comments  Very easy to criticise what others have done.  So put any negative comments in context : o most of what has changed is for the GOOD. o NEC3 is already a good contract.
  • 12. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Two changes in terminology These apply across the family :  ‘Employer’ becomes ‘Client’ as more commonly accepted across sectors  Works / Service / Goods Information all become ‘Scope’ : avoids need for generic statements when subcontracting. Both are ‘GOOD’ changes.
  • 13. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com  Engineering and Construction Contract (ECC)  Engineering and Construction Subcontract (ECS)  Engineering and Construction Short Contract (ECSC)  Engineering and Construction Short Subcontract (ECSS)  Professional Service Contract (PSC)  Professional Service Short Contract (PSSC)  Professional Service Subcontract (PSS) - NEW  Term Service Contract (TSC)  Term Service Short Contract (TSSC)  Term Service Subcontract (TSS) - NEW  Design, Build and Operate Contract (DBOC) - NEW  Supply Contract (SC)  Supply Short Contract (SSC)  Dispute Resolution Service Contract (DSRC) - NEWLY NAMED  Framework Contract (FC) and  Alliancing Contract (consultative) - NEW. The NEC4 family of contracts :
  • 14. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changes to the Family  The GOOD : Two new subcontracts – the PSS and TSS – as reduces the need to amend main contracts.  The Could do Better : Subcontracts for compatible short versions of these contracts.  The GOOD : the DBO contract as : o saves having to have an extra over-arching agreement which ties D, B & O together. o encourages use of a Finance+DBO contract
  • 15. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Alliance Contractual Framework Sub Consultants Principal Consultants Sub Contractors Principal Contractors Sub Suppliers Principal Suppliers Client
  • 16. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com 3 forms of Alliance : Simple Alliance  Enacted under NEC 3 & 4 through option X12.  Re-named ‘Multiparty Collaboration’ option where: o set of X12 add-on clauses to individual contracts; o covers Core Group, Partnering Information and KPI’s against which positive only incentives can be set; o high level extra clauses for early warnings, joint timetable (programme) & a compensation event for changes to the Partnering Information. o easiest to put in place as only upside for ‘Partners’.
  • 17. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com 3 forms of Alliance : Pure / Australian Alliance  NEW Alliancing Contract (Consultative) where : o one multi-party contract o very similar in structure to other members of family o covers joint down-side liabilities o all ‘Partners’ sign the same contract at the same time, which is hard – technically & legally - to make happen o allows for two stage engagement with Stage One being on a cost-plus basis e.g. development of Scope & Prices o also hardest form of alliance to get one party out.
  • 18. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com 3 forms of Alliance : Traditional Alliance  Where all alliance members have traditional works and service contracts.  Usually cost-based, but not always e.g. where most costs incurred in a factory; more fit for purpose / circumstance individual contractual relationship vs. one size fits all.  Over-arching alliance contract ties fortunes to result of overall project, whether good & bad.  Easier to add members as individual Scope reaches maturity and easier to get rid of if under-performing e.g. can get out of Alliance but keep works contract.  No NEC4 traditional alliancing contract.
  • 19. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changes to the main payment options  Professional Service Contract (PSC) has lost ‘option G : Term Contract’.  Often a Client want a consultant to provide a base level of service for a period of time, with the ability to instruct additional Tasks for minor projects as & when required without having to put new contract in place.  NEC publishers say use Term Service Contract (TSC), but you need an Affected Property, insurance is different etc. so would need to do multitude of tweaks.  Far easier to update NEC3 PSC Option G to be compatible with NEC4 PSC.
  • 20. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changes to the ‘W’ Dispute options  W1 and W2 are in NEC3 and for Adjudication. W2 is for the UK and W1 for the rest of the world.  In NEC4, both options now have Senior Representatives before you get to Adjudication. In W1 it is mandatory, whereas in W2 it can’t be and isn’t.  New to NEC4, is W3 : The Dispute Avoidance Board o who are 1 or 3 experienced people who keep in touch with the contract; o if a potential dispute arises, they try to help resolve it, then make recommendation; o Parties have to refer a dispute to it before going onto adjudication, so is not compliant with Construction Acts. BUT could have easily tweaked it, as W4, to be UK compliant.
  • 22. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changes to the ‘X’ Clauses.  ‘X8 : Undertakings to the Client or Others’ : Previously no X8 in ECC, but ‘Collateral Warranties’ in PSC. Like that : o broadens scope of what is covered i.e. not just CW’s o is now in ECC and TSC .  New ‘X9 : Transfer of rights’ in ECC for material developed for contact as per NEC3 PSC.  New ‘X10 : Information Modelling’ replaces ’Employer’s Agent’ in NEC3 PSC as : o NEC4 PSC now has a Service Manager. o allows for broader application than BIM o Guidance Notes on BIM for NEC3 were vapid and BIM Protocol is a contractual car crash waiting to happen.
  • 23. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changed ‘X15 : Contractor’s design’  ECC always allowed for any extent of Contractor design, but previous X15 only limited Contractor’s liability down to ‘reasonable skill and care’ and correction of Defects .  New X15 does above and o covers Professional Indemnity insurance o changes wording to that which insurance industry comfortable with o changes burden of proof onto Client o covers IP ownership of material o period for retention of material.  Would have liked to have seen similar X provisions in ECSC & ECSS to make into an ‘intermediate’ contract for simple design.
  • 24. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changes to the ‘X’ Clauses.  Inclusion of ‘X22 : Early Contractor Involvement’ and ‘Y(UK)1 : Project Bank Account’ from consultative documents / separate addendums.  New ‘X21 : Whole life cost’ where Contractor may propose an idea which reduces wlc and gets a share of wlc savings … but would like to have o seen proportions stated in CD, o whole life value (benefit/wlc) clause o what happens if PM/Client steals ’similar’ idea ?
  • 25. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Changes to the ‘X’ Clauses.  No change to ‘X1 : Price adjustment for inflation’. When used, an almost universal amendment is to set periods when the adjustment made e.g. annually, not when an indices changes.  ‘X4 : Ultimate Holding Company Guarantee’ has changed from ‘Parent Company Guarantee’. The UHC could be an offshore hard to get to company. Better to have one you can get to.  ‘X18 : Limitation of Liability’ still contains a ‘total liability’ cap which has four types of damages or negative incentives as ‘excluded matters’. So not really a ‘total liability’ !  ‘X22 : Early Contractor Involvement’ doesn’t have specific termination provisions if the Client does not proceed from Stage 1 to 2 with same Contractor.
  • 26. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Some other changes across the family  A Schedule of Cost Components for all ‘long’ forms, although have reservations for calculating People costs under PSC  Schedule includes Subcontractor costs.  Tidying up of Subcontractor definition to exclude labour only / agency staff.  NEC4 Section 8 is now ‘Liabilities and Insurance’ vs ‘Risks and Insurance’.  Not so sure about listing out “Client’s liabilities” and then “Contractor’s liabilities”. What happens if an event is in neither or could be in both ?
  • 27. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com To finish on a GOOD note x3 In ‘long’ forms, really like :  greater emphasis on Contractor putting forward proposals e.g. wlc’s, value engineering and acceleration  the prod to use cloud-based NEC communication systems as almost hard-wire in contractually compliant responses and make it evident who is operating the contract & who isn’t – see ECC clause 13.2;  that, when not accepting a communication, the Project Manager or equivalent has to not just state contractual reason for not accepting, but also give “sufficient detail to enable the Contractor to correct the matter” - see ECC clause 13.4
  • 28. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Summary of Part 1  mainly GOOD  COULD DO BETTER’s are mainly tweaks which have not been done, except for not having a Traditional Alliance Contract  No real UGLIES yet, although getting rid of option G : Term Contract of the PSC comes close.
  • 30. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Next week Focus on provisions within ECC for  Payment  Programme  Early warnings  Compensation events … but similar provisions in all ‘long’ forms. APOLOGIES
  • 31. © 2017 +44(0)7970 428 929 jon@leadingedgeprojects.co.uk www.jonbroome.com Link to raise questions for Part 2 : Changes to the Engineering & Construction Contract (ECC) http://bit.ly/2mqHPI6
  • 32. This presentation was delivered at an APM webinar To find out more about upcoming webinars please visit our website www.apm.org.uk/events