EQUIPMENT CAPACITIES
CALCULATIONS IN PLANNING
-A.V.REDDY
• Estimates capacity (KW/HP) of machines,
Electric power, Power cost/ton of coal or
OB , For OCs Capacities of shovels
dumper combination, capital required for
Plant and machinery etc, of New
Projects to in corporate in Feasibility
Reports. (FRs)
• Estimates P&M for Revised Feasibility
Reports of projects.
• Estimates P&M requirement of completed
projects and on going projects.
Technology adopted
a) Hand section
b) Mechanised mining
a) Hand Section :
Equipment required :
Haulers (DH,EH), Pumps, Drill M/Cs, Main
mechanical ventilator, Auxiliary fans
connected Electricals
• Gradient (1:3.5 or 1:4) Approx= 57/gradient
• Weight to be pulled
Calculation :
Pull = Pull due to rope(w) + Pull due tubs(W)
(kgs)
Pull due to rope= Resistance against gradient (w)
+ Rope rolling resistance(f)
= w x Gradient (Sin O) + w/10
( w is weight/mtr of rope)
=w/3.5+ w/10 (10% weight of rope)
Pull due to tubs/(man riding cars)
= Resistance against gradient (W) + Rolling
resistance of tubs (F)
= W x Gradient + W/40 (W/20)
where W is the total weight of tubs
= W / 3.5 + W/40 (W/20)
Total Pull = w/3.5+w/10 +W / 3.5 + W/40
(W/20) Kgs
Based on pull, rope is selected.
Breaking load of rope as per IS 1570 =352 KN for
26 mm rope dia
Factor of safety =9
Breaking Load = 350 x1000/9.81 Kgs
=35678 Kgs
Safe load =35678/9
=3964 kgs
HP =Total Pull x speed(mps)/75
KW =Total pull x speed(mps)/102
Peripheral speed of rope= 3.14xN
xD/60x1000 m/sec D is Drum Dia, in mm
N is RPM
Total Length of Installation,L in mtrs. 2200
Max. Lift,H in mtrs 134
Distance between two chairs m 16
Max. Travelling Speed,V m/s 3
Man Riding Capacity,C Nos. 675
Weight of person,Mper
in kgs 80
Weight of Chair,Mchair
in kgs 13
Weight of Rope,Mrope
in kg/m 1.6
Drive&Return wheel Dia,D in mtrs 1.5
Power required to raise mass of persons,Ppers
in W
= C x H x 9.81 x 80/3600 = 675x133.52x9.81x80/3600 =19647 W
Power to overcome Frictions,PFriction
Line Friction,PFriction1
Chair Spacing ,X chair
in mtrs 16
Total Continuous Rope length,LRope
in mtrs
=2 x L + 3.14 x D = 2x 2200 + 3,14x1.5 = 4404.71
Total no. of chairs, X
=L rope / Chair spacing = 4404.71/16 = 275.29
Total no.of persons on one side only,Y =275/2 = 134
PFricion1
= 0.09((Lrope x Mrope) +( Y*Mper) +X * Mchairs)) V = 5304 W
Friction included by vertical&horizontal curve stations,
PFriction2
P Friction C=
K*(Ppers
+PFriction1
)
where K is a constant that increases with angle
of deflection
Angle of Deflection % Value of K
5°To10° 1 0.01
10°To20° 2 0.02
20°To30° 3.5 0.035
30°To40° 5 0.05
Three curve stations are there
Sl.No Horizontal Angle Vertical Angle
1 33° 2.34°
2 37° 2.04°
3 33° 1.00°
At 1st Station,PFrictionCH1
= 0.05 x (19647 +5304) = 1247.57 W
PFrictionCV1
= 0.01 x (19647 +5304) = 249.51
At2nd Station,PFrictionCH2
= 1247.57w
PFrictionCV2
= 249.51W
At3rd Station,PFrictionCH3
= 1247.57W
PFrictionCV3
= 249.51W
Total PFriction2
= 3 * (1247.57+249.51) =4491W
Friction induced by Return sheeve
Wheel,PFriction3
0.02x(Ppers
+PFriction1
+PFriction2
)
0.02x(19647.468+5304.0042+4491.
27)
=588.854844
Therefore ,PFriction
=(5304+4491+588)
= 10384.12904
Total Power at the Driving Wheel,P Ppers
+PFriction
Efficiency of the System 0.76
Therefore,Input Power 39515.25927
Taking5%extra,Required Power will be 41491.02223
Standard Available Power,KW 45
Rope Pull Calculation
Power at Driving Wheel
= 30 KW =30/0.746=40HP
HP=2NT / 4500
So, T=HPX4500 / 2N
= (40*4500*7)/ (2*22*19.1)
= 1499.286054
= 15kN
Power = QxHx Sp.gravity/75x Efficiency HP
= Qx Hx Sp.gravity/102 x Efficiency KW
Q = Ltr/sec
H = Head in mtrs
Sp.gravity = 1.03 gms/cc
one gallon =4.54 Ltrs
Generally GPM of pump is taken
Say 2250 LPM = 2250/4.54 = 495 GPM or
500 GPM
Generally in SCCL mines single, Double,
multistage centrifugal pumps are being
used for pumping water from under
ground to surface.
7.5 HP to 500 HP.
• Depending upon depth and sump capacity
pumps are deployed.
Air Power in KW =
Air Discharge (Cu.m/sec)x water gauge in
mm/ 102
Fan efficiency = Air power in KW / brake
shaft Power in KW
Brake shaft power = Transmission efficiency
x motor efficiency x Measured input power
in KW
Overall efficiency = Air power KW x100/
Measured power in KW
Auxiliary fans of 20 KW is deployed in
galleries where the flow is less than
requirement
High water gauge fans of 90 KW (200 to
500mm water gauge) are deployed in
Road header drivages.
In SCCL mines1 to 3 lakh CFT/min i.e
(3000 to 9000 Cu.m/min) are working with
blade angle 14 to 22 deg
For Adriyala shaft 15000Cu.m/min fan is
required.
Mechanised mining :
To increase the production and safety
mechanised mining is adopted with
following technologies.
a) Long wall :
Shearer is the deciding factor
1 Determine the mining rate, TPH
Assume
Cutting height,H mtrs 3.0
Web depth,D mtrs 1.0
Max. cutting speed,Vs mt/min 12.0
Coal density(solid), T/Cu.m 1.5
TPM= H*D*Vs
* T/min 54
TPH 3240
Drum Dia. mtrs 1.8
Web mtrs 1
Cutting speed, Vs mt/min 12.0
Density of coal (solid) T/m3
1.5
Q(Mining rate in tonnes per hour by one drum) TPH 1944
K is Specific energy consumption factor in HP-hr/Ton
Normally K is 0.5 for hard coal and 0.25-0.35 for soft coal
P(HP) = QK HP 972
There fore, for 3mtr extraction, the other drum requires only
a power of
(3-1.8)*1*12*1.5*0.5 HP 648
But, in practice, both drums will require equal power for bi-
directional
operation
KW 725.112
• (Assumed 1TPH=1KG)
• For 1000 TPH,
• S1 = 1000 Kg.
• S1 - Tension
• gc1 – Gravitational resistance on slack side (weight
component acting along the bottom for chain)
• gc2 - Gravitational resistance on tension side
• RC1 - Frictional resistance on slack side
• RC2 - Frictional resistance on tension side
• gc1 = qc x L x Sinø
• Where qc = Wt. of chain/mt.
• L = Length of chain in mt.
• Ø = Inclination
• RC1 = qc x L x fc x Cosø
• Where qc - Wt. of chain/mt.
• L - Length of chain in mt.
• fc - Frictional co-efficient of
chain with pan
• ~ 0.35 to 0.4 for
soft chain
• ~ 0.45 for shaking
& watering
• S2 = S1 + gc1 + RC1 or S1 + qcL (Sinø + fc
Cosø)
• (S1, S2 are in the opp. Direction)
• S3 > S2 and there will be some loss
• Thus S3 = 1.05 S2
• S4 = S3 – Gc2 + RC2
• Where
• gc2 = (qc x L x Sinø) + (qy x L x Sinø)
• RC2 = (qc x L x fc Cosø) + qy x L x fy x Cosø
• qy = Q/3.6V (Q = TPH, V = Velocity m/s)
• Fy = Frictional co-efficient of material conveyed
• 0.45 to 0.8 for dry soft coal,
• 0.8 for silica, rock etc, normally 0.7
• Now S4 = S3 – gc2 + RC2
• Or S4 = S3 – (qc L Sinø + qy L Sinø) + (qc L fc Cosø +
qy L fy Cosø)
• = S3 + qc L (fc Cosø – Sinø) + qy L (fy Cosø
– Sinø)
• Power (P) = (S4 – S1) KW
• 102
• Motor Power - P/h h = 0.8 to 0.9
Based on shearer capacity AFC,BSL, Gate
Belts, Trunk belts are designed.
The supports are designed by taking load
coming to supports / Sq.m area as per
finite element method.
The connected electricals are designed
basing on the above capacities
Power pack is designed on the design of
support load.
In SCCL Long wall technologies produced 4
to 7 lakhs per annum
BG technology the following equipment is
deployed
a) Jumbo Drills
b) LHDs
c) Hydraulic props
d) Power pack
SDL Low height are deployed in hand
section mines to increase productivity,
safety and decrease in man power
Based on production No. of LHD,SDL are
deployed
For CTX,811 Eimco LHDs annual
production = 50,000 T
For 912 Eimco LHDs = 60,000 T/ annum
For Low height SDLs = 45,000 T/ annum
Connected Electricals like GEBs, HT/LT
switches, transformers are calculated on
the No. of SDLs / LHDs deployed
a) Power to move load horizontally
=2.72 x L x F x (C+46)/1000 kW
b) Power to move empty belt
= 9.81 x F x G x (C+46) x S/1000 kW
c) Power to elevate load
=2.72 x L x H/1000 kW
Total Power P = (a) +( b) +(c)
Taking safety factor as 1.1 to 1.2 Total
power requirement is calculated
C = Centre distance in mtrs
F = Friction factor (0.03)
G = Inertia factor
H = Change in elevation in mtrs
L = Peak load in Tonnes/Hour
S = Belt speed in mtrs/sec
L= B x D x S/1000 Tonnes/Hr
L = Peak load
B =Belt capacity Factor
D = Material density Kg/Cu.m
S = Belt speed in mtrs/sec
• Selection of belt
T = K x P/S kN
P is power required, K = Belt Drive factor
S = speed mtrs/sec
= kN/1 m = kN/m Taking Factor of Safety as
10:1 for PVC F.S 7:1 for steel cordvalue from
table can be used for selection PVC/ Steel cord
Based on coal production, OB removal and
depth of the mine No. of shovels( Coal,
OB), Dumpers, RBH Drills (Coal, OB),
Dozers, Graders,Pumps and water
sprinklers and other common equipment
are calculated
Sl.No Particulars 3cu.mShovel
along with
35T Dumper
1 No. of Annual working days 330
2 No. of duty shifts 3
3 Duration of shift in Hr 8
4 Total No. of Annual shift hrs 7920
5 Annual utilisation of shift hrs 61%
6 Annual working hr 4831.2
7 Shovel bucket capacity (m3) 3
8 Material density - Tes/BCM 2.2
9 Swell Factor 0.732
10 Bucket fill factor 0.905
11 Swell cum fill factor 0.662
12 Material quantity per shovel bucket (T) 4.3722
13 Pay load capacity of dumper (T) 31.5
14 No. of passes per dumper load 7.204
15 No. of passes adopted 7
16 Adopted Pay load capacity of dumper (T) 30.605
17 Bucket cycle time (Minutes) 0.6
18 Loading time per dumper (Minutes) 4.2
19 Spotting time of dumper 0.5
20 Shovel time for loading dumper (Minutes) 4.7
21 Hourly shovel capacity Cum/hr 177.595
22 Factor for travelling positioning etc. 0.85
23 Annual shovel capacity (Cum) 729300
M.Cum 0.73
Sl.No DESCRIPTION 0.5
1 Shovel loading time for dumper ,min 4.70
2 Spotting for unloading ,min 0.5
3 Unloading time ,min 0.6
4 Travelling time ,up ,min 1.20
5 Travelling time, down, min 1.00
6 Dumper cycle time. min 8.00
7 Dumper waiting time 1.40
8 Cycle time adopted 9.40
9 No. of trips per hour 6.382979
10 Dumper utilisation hours 2376
12 No. of trips per annum 15165.96
13 Dumper capacity,Cu.m 14.43182
14 Corrected dumper capacity 14.03093
15 Annual Dumper capacity,M.cum 0.212793
16 Calculated capacity of shovel, M.cum 0.73
17 No.of Dumpers required per shovel 3.524559
18 Rounded no. 4
Assessment of volume of water to be
pumped
Q = A x H x Run off coefficient
A = Catchment area in Sq.m
H = Maximum daily precipitation in m
Run off coefficients
For mined out area = 0.60
Area beyond excavation =0.10
For internal dump area =0.15
Maximum capacity of pump is determined
on operating time 20 Hrs for 10 days i.e
200 Hrs as per CMPDI
In SCCL 20 Hrs for 6 days i.e 120 hrs
Add 10% seepage for attaining total make
up
Peak pumping capacity = /120
No of pumps is determined from above
depend on pump capacity Cu.m/Hr
For coal based on coal & OB No. of Drills is
calculated
Drilling pattern for coal = 5 x 5 x 6/5
Height of bench =5 m
Spacing =5 m
Burden =5 m
Volume of coal exposed/ mtr drilling =30 Cu.m
Annul working hrs =2112
Annual meterage = 42000
Volume of coal exposed by one drill =1.26 M.Cu.m
Drill employed =150mm
For OB 250mm RBH drills are used
Depending on OB removal/ year No. of drills
calculated
Drilling pattern =8 x 8 x 9/8
Volume of OB exposed /mtr of drilling =72 Cu.m
Annual working Hrs =2112
Annual meterage = 40000
Volume of OB exposed M.Cu.m = 2.88
Road Length to be graded, Km 17
Road Width to be graded, Mtr 20
Area to be Graded, Sq.mtrs 340000
Speed of the Grader ,Mtrs / Hr 6100
Blade Length ,Mtrs 4.32
Blade overlap ,Mtrs 0.3
Width of Graded area/each pass ,Mtrs 4.32 SIN 600
3.74
Graded Area/hr,Sq,Mtrs((3.74-0.3)*6100) 20984
No of Hours required /day 16.20
No. of Graders available at GKOC 2
Working hours required / each Grader/Day 8.1
% of utilization on SSH 34
Dozers are 50% of shovel population
Water Sprinklers 28 kL -2 Nos
Common equipment
Cranes 10T to 70/100T
Diesel bouser
Maintenance van
Compact vibrator, Tyre handlers, Front end
loaders, Fire tenders etc, are provided
Power calculations
Connected load = kW
Active load = Connected load x demand factor kW
Demand factor = 0.6 to 0.9
kVA = Active load / Power factor
Power factor = 0.8
No. of annual working hrs = say 3000
Energy consumption/annum = Active load x No.of
hrs/annum
Unit cost =2.80 x kWH
Surcharge @ 0.06Rs/kWH
Maximum demand/ kVA= Rs.250
SURVEY OFF NORMS FOR HEMM
Sl.
Equipment
Existing(CMPDI) Proposed(SCCL)
No. Hours Years Hours Years
1 10 Cu.m Rope Shovel 80000 22 100000 25
2 4.6-5 Cu.m Rope Shovel 36000 12 40000 15
3 5-10 Cu.m Hydraulic Excavators 20000 9 40000 15
4 2.2-3.5 Cu.m Hydraulic Excavators 20000 9 35000 15
5 85 T Rear Dumpers 22000 10 35000 15
6 35 T Rear Dumpers 12000 9 20000 15
7 Water Sprinklers 12000 9 25000 15
8 420&310HP Dozers 14000 9 20000 12
9 250mm RBH Drills 20000 9 35000 15
10 150mm RBH Drills 10000 9 25000 15
11 Motor Graders 10000 9 20000 15
12 Front End Loader 16000 9 25000 15
Basic E&Mcalculations for a coal mining project

More Related Content

What's hot

Bucket wheel excavator
Bucket wheel excavatorBucket wheel excavator
Bucket wheel excavator
VR M
 
Haul road design
Haul road designHaul road design
Haul road design
VR M
 

What's hot (20)

Underground mine
Underground mineUnderground mine
Underground mine
 
Working of dragline
Working of draglineWorking of dragline
Working of dragline
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
 
Mine transportation system
Mine transportation systemMine transportation system
Mine transportation system
 
Mine locomotive ppt (under ground transport system )
Mine locomotive ppt (under ground transport system )Mine locomotive ppt (under ground transport system )
Mine locomotive ppt (under ground transport system )
 
High angle conveying
High angle conveyingHigh angle conveying
High angle conveying
 
Armoured face conveyor
Armoured face conveyorArmoured face conveyor
Armoured face conveyor
 
Auxiliary ventilation
Auxiliary ventilationAuxiliary ventilation
Auxiliary ventilation
 
Bucket wheel excavator
Bucket wheel excavatorBucket wheel excavator
Bucket wheel excavator
 
Road Header and Bolter Miner
Road Header and Bolter MinerRoad Header and Bolter Miner
Road Header and Bolter Miner
 
Ppt mine machinery
Ppt mine machineryPpt mine machinery
Ppt mine machinery
 
Shovel dumper productivity calculation.pptx
Shovel dumper productivity calculation.pptxShovel dumper productivity calculation.pptx
Shovel dumper productivity calculation.pptx
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning Material
 
Mine cars
Mine carsMine cars
Mine cars
 
Side discharge loader
Side discharge loaderSide discharge loader
Side discharge loader
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Haul road design
Haul road designHaul road design
Haul road design
 
Balancing Diagram ppt
Balancing Diagram pptBalancing Diagram ppt
Balancing Diagram ppt
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
 

Viewers also liked

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
SATYANARAYANA I
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
SATYANARAYANA I
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit mining
SATYANARAYANA I
 
Openpit fundamentals
Openpit fundamentalsOpenpit fundamentals
Openpit fundamentals
VR M
 
Calendario tenis competiciones castilla la mancha 2013
Calendario tenis competiciones castilla la mancha 2013Calendario tenis competiciones castilla la mancha 2013
Calendario tenis competiciones castilla la mancha 2013
jgtenisok
 
Jones aleph acqorders
Jones aleph acqordersJones aleph acqorders
Jones aleph acqorders
ENUG
 
Clausura 1ª promoción curso experto community manager cámara de comercio málaga
Clausura 1ª promoción curso experto community manager cámara de comercio málagaClausura 1ª promoción curso experto community manager cámara de comercio málaga
Clausura 1ª promoción curso experto community manager cámara de comercio málaga
Javier Pérez Caro
 
ေႀကးမံု 1-nov-13-km
ေႀကးမံု 1-nov-13-kmေႀကးမံု 1-nov-13-km
ေႀကးမံု 1-nov-13-km
san aye
 

Viewers also liked (20)

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit mining
 
Openpit fundamentals
Openpit fundamentalsOpenpit fundamentals
Openpit fundamentals
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
21 febrero sandino vive 2014
21 febrero sandino vive 201421 febrero sandino vive 2014
21 febrero sandino vive 2014
 
Cloud desktop for byod
Cloud desktop for byodCloud desktop for byod
Cloud desktop for byod
 
Toxic Blue-Green Algae Reminders
Toxic Blue-Green Algae RemindersToxic Blue-Green Algae Reminders
Toxic Blue-Green Algae Reminders
 
Calendario tenis competiciones castilla la mancha 2013
Calendario tenis competiciones castilla la mancha 2013Calendario tenis competiciones castilla la mancha 2013
Calendario tenis competiciones castilla la mancha 2013
 
Jones aleph acqorders
Jones aleph acqordersJones aleph acqorders
Jones aleph acqorders
 
Sainilk Awasiya Mahavidyalaya announces admissions open for BBA.
Sainilk Awasiya Mahavidyalaya announces admissions open for BBA.Sainilk Awasiya Mahavidyalaya announces admissions open for BBA.
Sainilk Awasiya Mahavidyalaya announces admissions open for BBA.
 
Concept02
Concept02Concept02
Concept02
 
Asteroides
AsteroidesAsteroides
Asteroides
 
Clausura 1ª promoción curso experto community manager cámara de comercio málaga
Clausura 1ª promoción curso experto community manager cámara de comercio málagaClausura 1ª promoción curso experto community manager cámara de comercio málaga
Clausura 1ª promoción curso experto community manager cámara de comercio málaga
 
Briviesca a través del tiempo. La judería de Briviesca
Briviesca a través del tiempo. La judería de BriviescaBriviesca a través del tiempo. La judería de Briviesca
Briviesca a través del tiempo. La judería de Briviesca
 
ေႀကးမံု 1-nov-13-km
ေႀကးမံု 1-nov-13-kmေႀကးမံု 1-nov-13-km
ေႀကးမံု 1-nov-13-km
 
H3 o product presentation
H3 o product presentationH3 o product presentation
H3 o product presentation
 
Goldmedia Trendmonitor 2011. Analysen und Prognosen für 2011 in den Bereichen...
Goldmedia Trendmonitor 2011. Analysen und Prognosen für 2011 in den Bereichen...Goldmedia Trendmonitor 2011. Analysen und Prognosen für 2011 in den Bereichen...
Goldmedia Trendmonitor 2011. Analysen und Prognosen für 2011 in den Bereichen...
 
Datasheet vicos Trans data management
Datasheet vicos Trans data managementDatasheet vicos Trans data management
Datasheet vicos Trans data management
 

Similar to Basic E&Mcalculations for a coal mining project

Similar to Basic E&Mcalculations for a coal mining project (20)

project ppt
project pptproject ppt
project ppt
 
gantry crane report
gantry crane reportgantry crane report
gantry crane report
 
Design and development of ridge profile power weeder
Design and development of ridge profile power weederDesign and development of ridge profile power weeder
Design and development of ridge profile power weeder
 
Design of Machine Elements - Unit 4 Procedures
 Design of Machine Elements - Unit 4 Procedures Design of Machine Elements - Unit 4 Procedures
Design of Machine Elements - Unit 4 Procedures
 
trainingonchp-170107190647.pdf
trainingonchp-170107190647.pdftrainingonchp-170107190647.pdf
trainingonchp-170107190647.pdf
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical liner
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentation
 
Design of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 ProcedureDesign of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 Procedure
 
CHP
CHP CHP
CHP
 
Ship design project & presentation 3
Ship design project &  presentation 3Ship design project &  presentation 3
Ship design project & presentation 3
 
Design and analysis of solar support structure and daily tilting mechanism
Design and analysis of solar support structure and daily tilting mechanismDesign and analysis of solar support structure and daily tilting mechanism
Design and analysis of solar support structure and daily tilting mechanism
 
Casement Type Wind Turbine
Casement Type Wind TurbineCasement Type Wind Turbine
Casement Type Wind Turbine
 
project ppt 2 pdf.pdf
project ppt 2 pdf.pdfproject ppt 2 pdf.pdf
project ppt 2 pdf.pdf
 
transmission line
transmission line transmission line
transmission line
 
IRJET- Study on Different Estimation Methods of Propulsion Power for 60 Mts O...
IRJET- Study on Different Estimation Methods of Propulsion Power for 60 Mts O...IRJET- Study on Different Estimation Methods of Propulsion Power for 60 Mts O...
IRJET- Study on Different Estimation Methods of Propulsion Power for 60 Mts O...
 
Design of Synchronous machine.pdf
Design of Synchronous machine.pdfDesign of Synchronous machine.pdf
Design of Synchronous machine.pdf
 
Presentation-for-teachers.pptx
Presentation-for-teachers.pptxPresentation-for-teachers.pptx
Presentation-for-teachers.pptx
 
Basic Theory & Formulae Training Module
Basic Theory & Formulae Training ModuleBasic Theory & Formulae Training Module
Basic Theory & Formulae Training Module
 
Feasibility analysis of offshore wind power plants with DC collection grid
Feasibility analysis of offshore wind power plants with DC collection gridFeasibility analysis of offshore wind power plants with DC collection grid
Feasibility analysis of offshore wind power plants with DC collection grid
 
Bidirectional floating hydro turbine
Bidirectional floating hydro turbineBidirectional floating hydro turbine
Bidirectional floating hydro turbine
 

Recently uploaded

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
amitlee9823
 
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
amitlee9823
 
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
gajnagarg
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdf
tbatkhuu1
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
kumaririma588
 
Abortion Pills in Oman (+918133066128) Cytotec clinic buy Oman Muscat
Abortion Pills in Oman (+918133066128) Cytotec clinic buy Oman MuscatAbortion Pills in Oman (+918133066128) Cytotec clinic buy Oman Muscat
Abortion Pills in Oman (+918133066128) Cytotec clinic buy Oman Muscat
Abortion pills in Kuwait Cytotec pills in Kuwait
 

Recently uploaded (20)

Jordan_Amanda_DMBS202404_PB1_2024-04.pdf
Jordan_Amanda_DMBS202404_PB1_2024-04.pdfJordan_Amanda_DMBS202404_PB1_2024-04.pdf
Jordan_Amanda_DMBS202404_PB1_2024-04.pdf
 
WhatsApp Chat: 📞 8617697112 Call Girl Baran is experienced
WhatsApp Chat: 📞 8617697112 Call Girl Baran is experiencedWhatsApp Chat: 📞 8617697112 Call Girl Baran is experienced
WhatsApp Chat: 📞 8617697112 Call Girl Baran is experienced
 
Q4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentationQ4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentation
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Just Call Vip call girls Nagpur Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Nagpur Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Nagpur Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Nagpur Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
 
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
 
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdf
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
Hingoli ❤CALL GIRL 8617370543 ❤CALL GIRLS IN Hingoli ESCORT SERVICE❤CALL GIRL
Hingoli ❤CALL GIRL 8617370543 ❤CALL GIRLS IN Hingoli ESCORT SERVICE❤CALL GIRLHingoli ❤CALL GIRL 8617370543 ❤CALL GIRLS IN Hingoli ESCORT SERVICE❤CALL GIRL
Hingoli ❤CALL GIRL 8617370543 ❤CALL GIRLS IN Hingoli ESCORT SERVICE❤CALL GIRL
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
 
The hottest UI and UX Design Trends 2024
The hottest UI and UX Design Trends 2024The hottest UI and UX Design Trends 2024
The hottest UI and UX Design Trends 2024
 
Abortion Pills in Oman (+918133066128) Cytotec clinic buy Oman Muscat
Abortion Pills in Oman (+918133066128) Cytotec clinic buy Oman MuscatAbortion Pills in Oman (+918133066128) Cytotec clinic buy Oman Muscat
Abortion Pills in Oman (+918133066128) Cytotec clinic buy Oman Muscat
 
Call Girls Jalgaon Just Call 8617370543Top Class Call Girl Service Available
Call Girls Jalgaon Just Call 8617370543Top Class Call Girl Service AvailableCall Girls Jalgaon Just Call 8617370543Top Class Call Girl Service Available
Call Girls Jalgaon Just Call 8617370543Top Class Call Girl Service Available
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
 

Basic E&Mcalculations for a coal mining project

  • 2. • Estimates capacity (KW/HP) of machines, Electric power, Power cost/ton of coal or OB , For OCs Capacities of shovels dumper combination, capital required for Plant and machinery etc, of New Projects to in corporate in Feasibility Reports. (FRs) • Estimates P&M for Revised Feasibility Reports of projects. • Estimates P&M requirement of completed projects and on going projects.
  • 3. Technology adopted a) Hand section b) Mechanised mining a) Hand Section : Equipment required : Haulers (DH,EH), Pumps, Drill M/Cs, Main mechanical ventilator, Auxiliary fans connected Electricals
  • 4. • Gradient (1:3.5 or 1:4) Approx= 57/gradient • Weight to be pulled Calculation : Pull = Pull due to rope(w) + Pull due tubs(W) (kgs) Pull due to rope= Resistance against gradient (w) + Rope rolling resistance(f) = w x Gradient (Sin O) + w/10 ( w is weight/mtr of rope) =w/3.5+ w/10 (10% weight of rope)
  • 5. Pull due to tubs/(man riding cars) = Resistance against gradient (W) + Rolling resistance of tubs (F) = W x Gradient + W/40 (W/20) where W is the total weight of tubs = W / 3.5 + W/40 (W/20) Total Pull = w/3.5+w/10 +W / 3.5 + W/40 (W/20) Kgs Based on pull, rope is selected. Breaking load of rope as per IS 1570 =352 KN for 26 mm rope dia Factor of safety =9
  • 6. Breaking Load = 350 x1000/9.81 Kgs =35678 Kgs Safe load =35678/9 =3964 kgs HP =Total Pull x speed(mps)/75 KW =Total pull x speed(mps)/102 Peripheral speed of rope= 3.14xN xD/60x1000 m/sec D is Drum Dia, in mm N is RPM
  • 7. Total Length of Installation,L in mtrs. 2200 Max. Lift,H in mtrs 134 Distance between two chairs m 16 Max. Travelling Speed,V m/s 3 Man Riding Capacity,C Nos. 675 Weight of person,Mper in kgs 80 Weight of Chair,Mchair in kgs 13 Weight of Rope,Mrope in kg/m 1.6 Drive&Return wheel Dia,D in mtrs 1.5
  • 8. Power required to raise mass of persons,Ppers in W = C x H x 9.81 x 80/3600 = 675x133.52x9.81x80/3600 =19647 W Power to overcome Frictions,PFriction Line Friction,PFriction1 Chair Spacing ,X chair in mtrs 16 Total Continuous Rope length,LRope in mtrs =2 x L + 3.14 x D = 2x 2200 + 3,14x1.5 = 4404.71 Total no. of chairs, X =L rope / Chair spacing = 4404.71/16 = 275.29 Total no.of persons on one side only,Y =275/2 = 134 PFricion1 = 0.09((Lrope x Mrope) +( Y*Mper) +X * Mchairs)) V = 5304 W
  • 9. Friction included by vertical&horizontal curve stations, PFriction2 P Friction C= K*(Ppers +PFriction1 ) where K is a constant that increases with angle of deflection Angle of Deflection % Value of K 5°To10° 1 0.01 10°To20° 2 0.02 20°To30° 3.5 0.035 30°To40° 5 0.05
  • 10. Three curve stations are there Sl.No Horizontal Angle Vertical Angle 1 33° 2.34° 2 37° 2.04° 3 33° 1.00° At 1st Station,PFrictionCH1 = 0.05 x (19647 +5304) = 1247.57 W PFrictionCV1 = 0.01 x (19647 +5304) = 249.51 At2nd Station,PFrictionCH2 = 1247.57w PFrictionCV2 = 249.51W At3rd Station,PFrictionCH3 = 1247.57W PFrictionCV3 = 249.51W Total PFriction2 = 3 * (1247.57+249.51) =4491W
  • 11. Friction induced by Return sheeve Wheel,PFriction3 0.02x(Ppers +PFriction1 +PFriction2 ) 0.02x(19647.468+5304.0042+4491. 27) =588.854844 Therefore ,PFriction =(5304+4491+588) = 10384.12904 Total Power at the Driving Wheel,P Ppers +PFriction
  • 12. Efficiency of the System 0.76 Therefore,Input Power 39515.25927 Taking5%extra,Required Power will be 41491.02223 Standard Available Power,KW 45 Rope Pull Calculation Power at Driving Wheel = 30 KW =30/0.746=40HP HP=2NT / 4500 So, T=HPX4500 / 2N = (40*4500*7)/ (2*22*19.1) = 1499.286054 = 15kN
  • 13. Power = QxHx Sp.gravity/75x Efficiency HP = Qx Hx Sp.gravity/102 x Efficiency KW Q = Ltr/sec H = Head in mtrs Sp.gravity = 1.03 gms/cc one gallon =4.54 Ltrs Generally GPM of pump is taken Say 2250 LPM = 2250/4.54 = 495 GPM or 500 GPM
  • 14. Generally in SCCL mines single, Double, multistage centrifugal pumps are being used for pumping water from under ground to surface. 7.5 HP to 500 HP. • Depending upon depth and sump capacity pumps are deployed.
  • 15. Air Power in KW = Air Discharge (Cu.m/sec)x water gauge in mm/ 102 Fan efficiency = Air power in KW / brake shaft Power in KW Brake shaft power = Transmission efficiency x motor efficiency x Measured input power in KW Overall efficiency = Air power KW x100/ Measured power in KW
  • 16. Auxiliary fans of 20 KW is deployed in galleries where the flow is less than requirement High water gauge fans of 90 KW (200 to 500mm water gauge) are deployed in Road header drivages. In SCCL mines1 to 3 lakh CFT/min i.e (3000 to 9000 Cu.m/min) are working with blade angle 14 to 22 deg For Adriyala shaft 15000Cu.m/min fan is required.
  • 17. Mechanised mining : To increase the production and safety mechanised mining is adopted with following technologies. a) Long wall : Shearer is the deciding factor
  • 18. 1 Determine the mining rate, TPH Assume Cutting height,H mtrs 3.0 Web depth,D mtrs 1.0 Max. cutting speed,Vs mt/min 12.0 Coal density(solid), T/Cu.m 1.5 TPM= H*D*Vs * T/min 54 TPH 3240
  • 19. Drum Dia. mtrs 1.8 Web mtrs 1 Cutting speed, Vs mt/min 12.0 Density of coal (solid) T/m3 1.5 Q(Mining rate in tonnes per hour by one drum) TPH 1944 K is Specific energy consumption factor in HP-hr/Ton Normally K is 0.5 for hard coal and 0.25-0.35 for soft coal P(HP) = QK HP 972 There fore, for 3mtr extraction, the other drum requires only a power of (3-1.8)*1*12*1.5*0.5 HP 648 But, in practice, both drums will require equal power for bi- directional operation KW 725.112
  • 20. • (Assumed 1TPH=1KG) • For 1000 TPH, • S1 = 1000 Kg. • S1 - Tension • gc1 – Gravitational resistance on slack side (weight component acting along the bottom for chain) • gc2 - Gravitational resistance on tension side • RC1 - Frictional resistance on slack side • RC2 - Frictional resistance on tension side • gc1 = qc x L x Sinø • Where qc = Wt. of chain/mt. • L = Length of chain in mt. • Ø = Inclination
  • 21. • RC1 = qc x L x fc x Cosø • Where qc - Wt. of chain/mt. • L - Length of chain in mt. • fc - Frictional co-efficient of chain with pan • ~ 0.35 to 0.4 for soft chain • ~ 0.45 for shaking & watering • S2 = S1 + gc1 + RC1 or S1 + qcL (Sinø + fc Cosø) • (S1, S2 are in the opp. Direction) • S3 > S2 and there will be some loss • Thus S3 = 1.05 S2 • S4 = S3 – Gc2 + RC2
  • 22. • Where • gc2 = (qc x L x Sinø) + (qy x L x Sinø) • RC2 = (qc x L x fc Cosø) + qy x L x fy x Cosø • qy = Q/3.6V (Q = TPH, V = Velocity m/s) • Fy = Frictional co-efficient of material conveyed • 0.45 to 0.8 for dry soft coal, • 0.8 for silica, rock etc, normally 0.7 • Now S4 = S3 – gc2 + RC2 • Or S4 = S3 – (qc L Sinø + qy L Sinø) + (qc L fc Cosø + qy L fy Cosø) • = S3 + qc L (fc Cosø – Sinø) + qy L (fy Cosø – Sinø) • Power (P) = (S4 – S1) KW • 102 • Motor Power - P/h h = 0.8 to 0.9
  • 23. Based on shearer capacity AFC,BSL, Gate Belts, Trunk belts are designed. The supports are designed by taking load coming to supports / Sq.m area as per finite element method. The connected electricals are designed basing on the above capacities Power pack is designed on the design of support load.
  • 24. In SCCL Long wall technologies produced 4 to 7 lakhs per annum BG technology the following equipment is deployed a) Jumbo Drills b) LHDs c) Hydraulic props d) Power pack SDL Low height are deployed in hand section mines to increase productivity, safety and decrease in man power
  • 25. Based on production No. of LHD,SDL are deployed For CTX,811 Eimco LHDs annual production = 50,000 T For 912 Eimco LHDs = 60,000 T/ annum For Low height SDLs = 45,000 T/ annum Connected Electricals like GEBs, HT/LT switches, transformers are calculated on the No. of SDLs / LHDs deployed
  • 26. a) Power to move load horizontally =2.72 x L x F x (C+46)/1000 kW b) Power to move empty belt = 9.81 x F x G x (C+46) x S/1000 kW c) Power to elevate load =2.72 x L x H/1000 kW Total Power P = (a) +( b) +(c)
  • 27. Taking safety factor as 1.1 to 1.2 Total power requirement is calculated C = Centre distance in mtrs F = Friction factor (0.03) G = Inertia factor H = Change in elevation in mtrs L = Peak load in Tonnes/Hour S = Belt speed in mtrs/sec
  • 28. L= B x D x S/1000 Tonnes/Hr L = Peak load B =Belt capacity Factor D = Material density Kg/Cu.m S = Belt speed in mtrs/sec • Selection of belt T = K x P/S kN P is power required, K = Belt Drive factor S = speed mtrs/sec = kN/1 m = kN/m Taking Factor of Safety as 10:1 for PVC F.S 7:1 for steel cordvalue from table can be used for selection PVC/ Steel cord
  • 29. Based on coal production, OB removal and depth of the mine No. of shovels( Coal, OB), Dumpers, RBH Drills (Coal, OB), Dozers, Graders,Pumps and water sprinklers and other common equipment are calculated
  • 30. Sl.No Particulars 3cu.mShovel along with 35T Dumper 1 No. of Annual working days 330 2 No. of duty shifts 3 3 Duration of shift in Hr 8 4 Total No. of Annual shift hrs 7920 5 Annual utilisation of shift hrs 61%
  • 31. 6 Annual working hr 4831.2 7 Shovel bucket capacity (m3) 3 8 Material density - Tes/BCM 2.2 9 Swell Factor 0.732 10 Bucket fill factor 0.905 11 Swell cum fill factor 0.662
  • 32. 12 Material quantity per shovel bucket (T) 4.3722 13 Pay load capacity of dumper (T) 31.5 14 No. of passes per dumper load 7.204 15 No. of passes adopted 7 16 Adopted Pay load capacity of dumper (T) 30.605 17 Bucket cycle time (Minutes) 0.6
  • 33. 18 Loading time per dumper (Minutes) 4.2 19 Spotting time of dumper 0.5 20 Shovel time for loading dumper (Minutes) 4.7 21 Hourly shovel capacity Cum/hr 177.595 22 Factor for travelling positioning etc. 0.85 23 Annual shovel capacity (Cum) 729300 M.Cum 0.73
  • 34. Sl.No DESCRIPTION 0.5 1 Shovel loading time for dumper ,min 4.70 2 Spotting for unloading ,min 0.5 3 Unloading time ,min 0.6 4 Travelling time ,up ,min 1.20 5 Travelling time, down, min 1.00
  • 35. 6 Dumper cycle time. min 8.00 7 Dumper waiting time 1.40 8 Cycle time adopted 9.40 9 No. of trips per hour 6.382979 10 Dumper utilisation hours 2376 12 No. of trips per annum 15165.96
  • 36. 13 Dumper capacity,Cu.m 14.43182 14 Corrected dumper capacity 14.03093 15 Annual Dumper capacity,M.cum 0.212793 16 Calculated capacity of shovel, M.cum 0.73 17 No.of Dumpers required per shovel 3.524559 18 Rounded no. 4
  • 37. Assessment of volume of water to be pumped Q = A x H x Run off coefficient A = Catchment area in Sq.m H = Maximum daily precipitation in m Run off coefficients For mined out area = 0.60 Area beyond excavation =0.10 For internal dump area =0.15
  • 38. Maximum capacity of pump is determined on operating time 20 Hrs for 10 days i.e 200 Hrs as per CMPDI In SCCL 20 Hrs for 6 days i.e 120 hrs Add 10% seepage for attaining total make up Peak pumping capacity = /120 No of pumps is determined from above depend on pump capacity Cu.m/Hr
  • 39. For coal based on coal & OB No. of Drills is calculated Drilling pattern for coal = 5 x 5 x 6/5 Height of bench =5 m Spacing =5 m Burden =5 m Volume of coal exposed/ mtr drilling =30 Cu.m Annul working hrs =2112 Annual meterage = 42000 Volume of coal exposed by one drill =1.26 M.Cu.m Drill employed =150mm
  • 40. For OB 250mm RBH drills are used Depending on OB removal/ year No. of drills calculated Drilling pattern =8 x 8 x 9/8 Volume of OB exposed /mtr of drilling =72 Cu.m Annual working Hrs =2112 Annual meterage = 40000 Volume of OB exposed M.Cu.m = 2.88
  • 41. Road Length to be graded, Km 17 Road Width to be graded, Mtr 20 Area to be Graded, Sq.mtrs 340000 Speed of the Grader ,Mtrs / Hr 6100 Blade Length ,Mtrs 4.32 Blade overlap ,Mtrs 0.3
  • 42. Width of Graded area/each pass ,Mtrs 4.32 SIN 600 3.74 Graded Area/hr,Sq,Mtrs((3.74-0.3)*6100) 20984 No of Hours required /day 16.20 No. of Graders available at GKOC 2 Working hours required / each Grader/Day 8.1 % of utilization on SSH 34
  • 43. Dozers are 50% of shovel population Water Sprinklers 28 kL -2 Nos Common equipment Cranes 10T to 70/100T Diesel bouser Maintenance van Compact vibrator, Tyre handlers, Front end loaders, Fire tenders etc, are provided
  • 44. Power calculations Connected load = kW Active load = Connected load x demand factor kW Demand factor = 0.6 to 0.9 kVA = Active load / Power factor Power factor = 0.8 No. of annual working hrs = say 3000 Energy consumption/annum = Active load x No.of hrs/annum Unit cost =2.80 x kWH Surcharge @ 0.06Rs/kWH Maximum demand/ kVA= Rs.250
  • 45. SURVEY OFF NORMS FOR HEMM Sl. Equipment Existing(CMPDI) Proposed(SCCL) No. Hours Years Hours Years 1 10 Cu.m Rope Shovel 80000 22 100000 25 2 4.6-5 Cu.m Rope Shovel 36000 12 40000 15 3 5-10 Cu.m Hydraulic Excavators 20000 9 40000 15 4 2.2-3.5 Cu.m Hydraulic Excavators 20000 9 35000 15 5 85 T Rear Dumpers 22000 10 35000 15 6 35 T Rear Dumpers 12000 9 20000 15 7 Water Sprinklers 12000 9 25000 15 8 420&310HP Dozers 14000 9 20000 12 9 250mm RBH Drills 20000 9 35000 15 10 150mm RBH Drills 10000 9 25000 15 11 Motor Graders 10000 9 20000 15 12 Front End Loader 16000 9 25000 15