Construction management
Introduction
Resource leveling
Resource allocation
Other schedules derived from project schedules
Network crashing and cost-time trade-off
Contents
The scheduling of activities, so that none of the precedence
relationships are violated and none of the resource availabilities
are exceeded, is a difficult task and can result in a number of
combinations of possible early start and late start schedules.
In literature, scheduling problems with limited resources is
classified as large combinatorial problem.
A number of programs based on some rules of thumb (also called
heuristic) have been developed to solve such problems.
These heuristic programs for resource scheduling can be broadly
classified under two categories: (1) Resource leveling and (2)
Resource allocation
Introduction
The resource allocation procedure mainly consists of two activities:
(i) Resource smoothing
(ii) Resource levelling.
Resource Leveling and Resource Smoothing are two resource optimization
techniques. Resource Leveling is performed to balance the demand and
supply of resources. Resource Smoothing is performed to achieve a more
uniform resource utilization over a period of time. Resource Leveling may
change the critical path of the project, whereas Resource Smoothing does
not.
Methods of resource allocation
Resource smoothing
Resource Smoothing: Resource Smoothing is a resource optimization
technique in which the Project Manager adjusts the timing of different
activities so that the requirement for resources does not exceed a certain
pre-defined limit. The objective is to complete the work by the required
date while avoiding peaks resource demand.
The intelligent utilization of floats can smoothen the demand of resources
to the maximum possible extent is called resource Smoothing. In other
words, activities may only be delayed within their free and total float.
The resource smoothing is applied in such a way that the total project
duration remains the same i.e. there is no change in the total duration of
the project. First, the periods of minimum demand for resources are
determined or located and the activities are shifted according to the
availability of float and requirement of resources. Thus the intelligent use
of floats can smoothen the demand to the maximum possible extent. This
type of resource allocation is known as resource smoothing
Resource leveling
Resource Leveling is a resource optimization technique in which the
Project Manager adjusts the start dates and finish dates of different
activities in order to balance the demand for resources vs available supply.
If the demand of a resource is more than its availability, then the only
alternative is to delay the activity having maximum float. This process is
called resource levelling. If there are more than one activities requiring
the same amount of resources, in that case activity having minimum
duration is chosen for resource reallocation. Resource levelling is
adopted in case there is restriction on the availability resources
Resource levelling, Scenario A:
 For example, if there are two task on project network diagram and they are
scheduled on the same time period and both required the same resource,
“X”.
 Task A is on critical path, Task B is on non-critical path which means
which has float.
 Further assume, the task A is high priority task than the task B.
 In this situation, if we perform resource levelling, the project schedule or
critical path may or may not change.
 If the levelling delay within the free or total float the project schedule will
not change otherwise it will get changed.
Resource levelling, Scenario B:
 For example, if both task A and B are on critical path and they are
scheduled on the same time period and required the same resource, “X”.
 If we perform resource leveling in this situation then the project schedule or
critical path will surely get changed.
 It doesn’t matter which task of the two are high-priority than other.
Complete within given time
Complete within given resources
Scheduling is a process for setting in order the various planned activities by fixing the
starting and finishing dates to each part of the work in such a manner that the whole
work should be done in an orderly and systematic way.
For example, a railway map will show a passenger, the route by which he will travel from
one place to another and stations along that route. But the time table will give him the
time element that is the hour when his journey will begin, the time at which the train will
reach at various stations and also the total time that will be required to reach the
destination.
In the same way the planning department will have to frame a time schedule for a
project which will assign definite timings for individual constructional operations
leading to finished product.
SCHEDULING
1) Construction schedule
2) Staff schedule
3) Labor schedule
4) Material schedule
5) Financial schedule
6) Equipment schedule
7) Invoice schedule
8) Estimation of direct and indirect costs
Schedules derived from project schedule
The main objective of network planning is to complete the job within the stipulated
time at minimum cost. At times it becomes necessary to accelerate the completion of
work. This be made possible only by reducing the duration of critical activities. The
duration of critical path can be reduced by the deployment of additional resources e. g
additional labour, shuttering, centering etc., which again increases the cost.
While exploring the possibility of accelerating project completion by arranging additional
critical activities, the following questions require careful consideration.
To what extent the project duration be reduced ?
What is the lowest cost for reducing the project duration to the specified date?
What is the project duration for which the total project cost is the lowest?
Cost time analysis provides answers to these questions. The durations of critical
activities may be reduced in two ways (i) by deploying more resources for early
completion of such activities. (ii) by relaxing the technical specifications for such
activities.
TIME - COST TRADE OFF
If the duration is made longer, cost will be reduced. on the other hand, reducing the
project duration would increase the cost of the project. A decision on this will depend on
whether the commitment of additional resources and expenses is worthwhile.
The Optimum duration will be one which gives the most economic cost for completing
the project. In CPM there are two time cost estimates for each activity:
1. Normal estimate : In normal estimate, highlighting on cost, time being associated
with minimum cost.
2. Crash estimate : In crash estimate emphasis is given to absolute minimum time
required to complete the job. The necessary cost to complete the project with in the
minimum time is provided.
Updating can be defined as planning and programming of the
remaining portion of an activity job, by introducing the latest
information available.
At the end of day of work, the activities of the project must either be
completed, in progress or they may not have started yet.
Some of the activities may not have achieved the required percentage
of progress, which was planned to have achieved on the day of
updating.
Updating
As far as progress is concerned, three possibilities exists:
i) Some or all activities are progressing as per schedule.
ii) Some or all activities are ahead of schedule.
iii) Some or all activities are behind schedule.
If all activities are progressing as per schedule, there is no need for
updating the
network. But, in case of activities are behind schedule, the process of
updating is required to revive the time schedule of various activities on
the arrow diagram. Such revision is known as updating.
Module :-5 project scheduling and resource levelling

More Related Content

What's hot

Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 

What's hot (20)

time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimation
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Bar chart
Bar chartBar chart
Bar chart
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 

Similar to Module :-5 project scheduling and resource levelling

Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
IOSRJMCE
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
melchioreq
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
sslovepk
 

Similar to Module :-5 project scheduling and resource levelling (20)

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
B012440511
B012440511B012440511
B012440511
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 

More from Shree Swami atmanand saraswati inst. of technology, surat

More from Shree Swami atmanand saraswati inst. of technology, surat (20)

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
BCT - Module 5 special work
BCT - Module 5 special workBCT - Module 5 special work
BCT - Module 5 special work
 
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)
 
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :- 8 material management
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 2 project organization
 
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 b remote sensing
 
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 a gps
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 

Recently uploaded

Recently uploaded (20)

COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 

Module :-5 project scheduling and resource levelling

  • 1. PREPARED BY:- Karm Balar Asst. Prof. S.S.A.S.I.T. S.S.A.S.I.T G.T.U SHREE SWAMI ATMANAND SARASWATI INSTITUTE OF TECHNOLOGY, SURAT Construction management
  • 2. Introduction Resource leveling Resource allocation Other schedules derived from project schedules Network crashing and cost-time trade-off Contents
  • 3. The scheduling of activities, so that none of the precedence relationships are violated and none of the resource availabilities are exceeded, is a difficult task and can result in a number of combinations of possible early start and late start schedules. In literature, scheduling problems with limited resources is classified as large combinatorial problem. A number of programs based on some rules of thumb (also called heuristic) have been developed to solve such problems. These heuristic programs for resource scheduling can be broadly classified under two categories: (1) Resource leveling and (2) Resource allocation Introduction
  • 4. The resource allocation procedure mainly consists of two activities: (i) Resource smoothing (ii) Resource levelling. Resource Leveling and Resource Smoothing are two resource optimization techniques. Resource Leveling is performed to balance the demand and supply of resources. Resource Smoothing is performed to achieve a more uniform resource utilization over a period of time. Resource Leveling may change the critical path of the project, whereas Resource Smoothing does not. Methods of resource allocation
  • 5. Resource smoothing Resource Smoothing: Resource Smoothing is a resource optimization technique in which the Project Manager adjusts the timing of different activities so that the requirement for resources does not exceed a certain pre-defined limit. The objective is to complete the work by the required date while avoiding peaks resource demand. The intelligent utilization of floats can smoothen the demand of resources to the maximum possible extent is called resource Smoothing. In other words, activities may only be delayed within their free and total float.
  • 6. The resource smoothing is applied in such a way that the total project duration remains the same i.e. there is no change in the total duration of the project. First, the periods of minimum demand for resources are determined or located and the activities are shifted according to the availability of float and requirement of resources. Thus the intelligent use of floats can smoothen the demand to the maximum possible extent. This type of resource allocation is known as resource smoothing
  • 7. Resource leveling Resource Leveling is a resource optimization technique in which the Project Manager adjusts the start dates and finish dates of different activities in order to balance the demand for resources vs available supply. If the demand of a resource is more than its availability, then the only alternative is to delay the activity having maximum float. This process is called resource levelling. If there are more than one activities requiring the same amount of resources, in that case activity having minimum duration is chosen for resource reallocation. Resource levelling is adopted in case there is restriction on the availability resources
  • 8. Resource levelling, Scenario A:  For example, if there are two task on project network diagram and they are scheduled on the same time period and both required the same resource, “X”.  Task A is on critical path, Task B is on non-critical path which means which has float.  Further assume, the task A is high priority task than the task B.  In this situation, if we perform resource levelling, the project schedule or critical path may or may not change.  If the levelling delay within the free or total float the project schedule will not change otherwise it will get changed. Resource levelling, Scenario B:  For example, if both task A and B are on critical path and they are scheduled on the same time period and required the same resource, “X”.  If we perform resource leveling in this situation then the project schedule or critical path will surely get changed.  It doesn’t matter which task of the two are high-priority than other.
  • 9. Complete within given time Complete within given resources
  • 10. Scheduling is a process for setting in order the various planned activities by fixing the starting and finishing dates to each part of the work in such a manner that the whole work should be done in an orderly and systematic way. For example, a railway map will show a passenger, the route by which he will travel from one place to another and stations along that route. But the time table will give him the time element that is the hour when his journey will begin, the time at which the train will reach at various stations and also the total time that will be required to reach the destination. In the same way the planning department will have to frame a time schedule for a project which will assign definite timings for individual constructional operations leading to finished product. SCHEDULING
  • 11. 1) Construction schedule 2) Staff schedule 3) Labor schedule 4) Material schedule 5) Financial schedule 6) Equipment schedule 7) Invoice schedule 8) Estimation of direct and indirect costs Schedules derived from project schedule
  • 12.
  • 13.
  • 14.
  • 15.
  • 16. The main objective of network planning is to complete the job within the stipulated time at minimum cost. At times it becomes necessary to accelerate the completion of work. This be made possible only by reducing the duration of critical activities. The duration of critical path can be reduced by the deployment of additional resources e. g additional labour, shuttering, centering etc., which again increases the cost. While exploring the possibility of accelerating project completion by arranging additional critical activities, the following questions require careful consideration. To what extent the project duration be reduced ? What is the lowest cost for reducing the project duration to the specified date? What is the project duration for which the total project cost is the lowest? Cost time analysis provides answers to these questions. The durations of critical activities may be reduced in two ways (i) by deploying more resources for early completion of such activities. (ii) by relaxing the technical specifications for such activities. TIME - COST TRADE OFF
  • 17. If the duration is made longer, cost will be reduced. on the other hand, reducing the project duration would increase the cost of the project. A decision on this will depend on whether the commitment of additional resources and expenses is worthwhile. The Optimum duration will be one which gives the most economic cost for completing the project. In CPM there are two time cost estimates for each activity: 1. Normal estimate : In normal estimate, highlighting on cost, time being associated with minimum cost. 2. Crash estimate : In crash estimate emphasis is given to absolute minimum time required to complete the job. The necessary cost to complete the project with in the minimum time is provided.
  • 18. Updating can be defined as planning and programming of the remaining portion of an activity job, by introducing the latest information available. At the end of day of work, the activities of the project must either be completed, in progress or they may not have started yet. Some of the activities may not have achieved the required percentage of progress, which was planned to have achieved on the day of updating. Updating
  • 19. As far as progress is concerned, three possibilities exists: i) Some or all activities are progressing as per schedule. ii) Some or all activities are ahead of schedule. iii) Some or all activities are behind schedule. If all activities are progressing as per schedule, there is no need for updating the network. But, in case of activities are behind schedule, the process of updating is required to revive the time schedule of various activities on the arrow diagram. Such revision is known as updating.